Achieving Shell’s ‘Goal Zero’ alarm target DYNAMO: PROJECT ALARM ZERO Luciano Centurion June 2019
15

DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

Jan 10, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

Achieving Shell’s ‘Goal Zero’ alarm targetDYNAMO: PROJECT ALARM ZEROLuciano Centurion

June 2019

Page 2: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

1

Luciano Centurion

• Technical Custodian for the EPF Control System at Shell Upstream Argentina

• Based in Sierras Blancas – Neuquen

• Supervised installations of the DCS, SIS, F&G, CCTV and Field RTU’s

• Joined Shell in 2017 with a goal to improve the alarm system in-line with global expectations

Page 3: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

GOAL ZEROAchieving Shell’s Alarm Management Targets

Page 4: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

3

Target Requirements

• Risk Normalization

– When there are nuisance alarms operators tend to shelve them and forget about them

– If a stale alarm doesn’t cause any abnormal situation in the short term, it can be forgotten forever

• Dilemmas

– Operators have to deal with hard decisions when they have too many Alarms to acknowledge

– Encourage people to ask for help when they don’t know what to do

• Care

– I care about the people, the asset and the environment

– From my position, I can collaborate to have no harms, increasing the performance of alarm system

Page 5: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

4

Program Development

• Investigation Phase

– Observe current alarm performance

– Gather alarm history

– Talk to board operators

– Determine a baseline for improvement

– Identify needs

▪ Tools, resources, time, money, etc.

– Identify goals

▪ Alarm rates, standing alarms,responsibilities, informative documents, etc.

Page 6: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

5

Program Development

• Plan Development Phase

– Implement DynAMo® Alarm Suite

– Track Alarm KPI Performance

– Develop Alarm Philosophy

– Rationalize Alarms

– Train Operators

– Drive Continuous Improvement

Page 7: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

6

During the Implementation

• Leverage DynAMo’s reporting and analysis capabilities

• Implement weekly meetings to review alarm behavior

– Input: Operator logbooks, Metrics & Reporting KPI’s, actual process states

– Output: Actions for I&E Supervisor, Operator Lead and/or Site Engineers

• Implement a monthly report

– KPI (alarm rate, top 5 bad actors and standing alarms)

– Monthly performance overviews

– Actions for I&E Supervisor, Operator Lead and/or Site Engineers - with a due date and work-order number

• Develop and implement a process for alarm changes

– Operations Superintendent approval for Standard Limit Changes (Hi/Low Alarms)

– MoC for alarms that cause trips (High High/Low Low Alarms)

• Implement an internal annual audit process

Approximately 10 Months Work

Page 8: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

BENEFITSQuantifying Success

Page 9: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

8

Benefits

• DynAMo generates reports to discover and troubleshoot alarm issues

– Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

• Saves time and effort

– Excel versus DynAMo’s Metrics & Reporting dashboards for KPI population

– Rationalization execution using DynAMo’s Documentation & Enforcement tool, versus manual modifications straight to the DCS

– Database Excel export for Audits, crosschecked with DynAMo’s Master Alarm Database

• Drives operator performance improvements

• Empowers leadership

• Everybody is part of the team

• Everybody collaborates to eliminate bad actors

Page 10: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

9

Old Spreadsheet with 2 KPI Macro

New DynAMo Metrics & Reporting KPI Dashboards with Alarm and Event history

Before and After

Page 11: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

10

Alarm Management

0

20

40

60

80

100

120

140

Mar-18 Jun-18 Dec-18 Mar-19 Category 4

Hourly Alarm RateStanding AlarmOverride

2018 – 2019 Reported KPI Evolution

Page 12: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

NEXT STEPSContinuing the Journey

Page 13: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

12

Lifecycle Implementation

Page 14: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

© 2019 by Honeywell International Inc. All rights reserved.

Questions

13

Page 15: DYNAMO: PROJECT ALARM ZERO - Honeywell · •DynAMo generates reports to discover and troubleshoot alarm issues –Alarm Rates, Bad Actors, Standing Alarms, Fleeting Alarms, etc.

THANK YOUwww.hwll.co/dynamo