DVRPC 2016 Competitive Congestion Mitigation and Air Quality (CMAQ) Program for Pennsylvania Guidance JANUARY 2016
44

DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

Jun 19, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

DVRPC 2016 Competitive Congestion Mitigation and Air Quality (CMAQ) Program for Pennsylvania Guidance

JANUARY 2016

Page 2: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

The Delaware Valley Regional Planning Commission

is dedicated to uniting the region’s elected officials,

planning professionals, and the public with a common

vision of making a great region even greater. Shaping

the way we live, work, and play, DVRPC builds consensus

on improving transportation, promoting smart growth, protecting the

environment, and enhancing the economy.

We serve a diverse region of nine counties: Bucks,

Chester, Delaware, Montgomery, and Philadelphia in Pennsylvania; and Burlington, Camden, Gloucester, and

Mercer in New Jersey. DVRPC is the federally designated Metropolitan Planning Organization for the Greater

Philadelphia Region — leading the way to a better future.

The symbol in our logo is adapted from the official DVRPC seal and

is designed as a stylized image of the Delaware Valley. The outer

ring symbolizes the region as a whole while the diagonal bar signifies the

Delaware River. The two adjoining crescents represent the Commonwealth

of Pennsylvania and the State of New Jersey.

DVRPC is funded by a variety of funding sources including federal grants from the U.S. Department of

Transportation’s Federal Highway Administration (FHWA) and Federal Transit Administration (FTA), the

Pennsylvania and New Jersey departments of transportation, as well as by DVRPC’s state and local member

governments. The authors, however, are solely responsible for the findings and conclusions herein, which

may not represent the official views or policies of the funding agencies.

The Delaware Valley Regional Planning Commission (DVRPC) fully complies with Title VI of the Civil Rights

Act of 1964, the Civil Rights Restoration Act of 1987, Executive Order 12898 on Environmental Justice, and

related nondiscrimination statutes and regulations in all programs and activities. DVRPC’s website,

www.dvrpc.org, may be translated into multiple languages. Publications and other public documents can be

made available in alternative languages and formats, if requested. DVRPC public meetings are always held in

ADA-accessible facilities and in transit-accessible locations when possible. Auxiliary services can be provided

to individuals who submit a request at least seven days prior to a meeting. Requests made within seven days

will be accommodated to the greatest extent possible.

Any person who believes they have been aggrieved by an unlawful discriminatory practice by DVRPC under

Title VI has a right to file a formal complaint. Any such complaint may be in writing and filed with DVRPC’s

Title VI Compliance Manager and/or the appropriate state or federal agency within 180 days of the alleged

discriminatory occurrence. For more information on DVRPC’s Title VI program, or to obtain a Title VI

Complaint Form, please call (215) 238-2871 or email [email protected].

Page 3: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

i

Table of Contents

CHAPTER 1: Introduction ................................................................................................................................ 1

What Is the Congestion Mitigation and Air Quality Improvement Program? ........................................ 1

CHAPTER 2: Applying for CMAQ Funds ........................................................................................................ 3

How Much Funding Is Available? .............................................................................................................. 3

Who Is Eligible to Apply for Funds? .......................................................................................................... 3

Can Public–Private Partnerships Apply? .................................................................................................. 3

What Are Eligible Costs and How Are Projects Funded? ....................................................................... 3

Funding Requirements ............................................................................................................................... 4

• Funding Authorization ................................................................................................................... 4

CHAPTER 3: Project Eligibility ....................................................................................................................... 5

What Types of Projects Are Eligible? ........................................................................................................ 5

• Eligible Projects .............................................................................................................................. 5

• Operating Assistance ..................................................................................................................... 6

What Types of Projects Are NOT Eligible? ............................................................................................... 6

CHAPTER 4: Project Selection ....................................................................................................................... 7

How Will Projects Be Selected? ................................................................................................................. 7

• Emissions Analysis ........................................................................................................................ 7

• Pre-screening Questions ............................................................................................................... 8

• Consistency with Long-Range Plan or Local Comprehensive Plan Goals .............................. 8

• Located within a DVRPC Congested Sub-corridor ..................................................................... 8

• Public Agency or Public Agency Sponsor ................................................................................... 8

Project Selection Criteria ............................................................................................................................ 8

• Project Readiness (Weight = 25/100) ............................................................................................ 8

• Sponsor Capacity (Weight = 25/100) ............................................................................................ 9

• Emissions/VMT Reduction (Weight = 20/100) .............................................................................. 9

• Long-Term Viability of Emissions Benefit (Weight = 20/100) .................................................... 9

• Local Contribution (Weight = 5/100) ........................................................................................... 10

• Projects Serving an Environmental Justice (EJ) Community (Weight = 5/100) ..................... 10

Is the Project Scalable? ............................................................................................................................ 10

CHAPTER 5: Submitting the Application ..................................................................................................... 11

Page 4: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

i i

What Information Must Be Supplied? ..................................................................................................... 11

• Application Checklist ................................................................................................................... 11

• Project Abstract ............................................................................................................................ 11

• Application Form .......................................................................................................................... 11

• Project Readiness Checklist ....................................................................................................... 11

• Emissions Analysis Forms .......................................................................................................... 12

• Letter of Commitment .................................................................................................................. 12

Will There Be Any Information Sessions? .............................................................................................. 12

When Is the Application Deadline and How Should the Application Be Submitted? ......................... 13

What Is the Tentative Schedule? ............................................................................................................. 13

CHAPTER 6: Managing the Project .............................................................................................................. 15

What Assistance Is Available from DVRPC and PennDOT? ................................................................. 15

What Procedural and Regulatory Requirements Apply? ...................................................................... 15

• Typical Procedural and Regulatory Requirements ................................................................... 15

Appendices

Appendix A: Project Selection Criteria

Project Selection Criteria and Weights ................................................................................................. A-1

Appendix B: Project Implementation Procedural and Regulatory Requirements

Initiation of Project .................................................................................................................................. B-1

Reimbursement Agreement .................................................................................................................... B-1

Environmental Clearance ....................................................................................................................... B-1

Project Engineering ................................................................................................................................. B-1

Standards and Guidelines ...................................................................................................................... B-1

Right-of-Way Acquisition ........................................................................................................................ B-2

Utility Clearance....................................................................................................................................... B-2

Permits ...................................................................................................................................................... B-2

Public Utility Commission Involvement ................................................................................................ B-2

Bidding ..................................................................................................................................................... B-2

Construction and Implementation ......................................................................................................... B-2

Control, Use, and Maintenance .............................................................................................................. B-2

Page 5: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

i i i

Cancellation of a Project ......................................................................................................................... B-3

Appendix C: Committee Members

Congestion Mitigation and Air Quality Improvement (CMAQ) Program Selection Committee Members .............................................................................................................................. C–1

Appendix D: Appendix D: Sample Project Progress Report

Sample Project Progress Report .......................................................................................................... C–1

Page 6: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 7: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 1

CHAPTER 1: Introduction

What Is the Congestion Mitigation and Air Quality Improvement Program? The Congestion Mitigation and Air Quality (CMAQ) Program was created under the Intermodal Surface

Transportation Efficiency Act of 1991, continued under the Transportation Equity Act for the 21st Century, and

the Safe, Accountable, Flexible, Efficient , Transportation Equity Act: A Legacy for Users, and was

reauthorized by the Fixing America’s Surface Transportation Act (FAST Act) in 2015. CMAQ funds have

been allocated to the Pennsylvania portion of the DVRPC metropolitan area for projects that contribute to the

attainment of the Clean Air Act standards by reducing emissions from mobile sources.

The Fiscal Year (FY) 2017 Transportation Improvement Program (TIP) for Pennsylvania (FY 2017–2020) will

set aside funding for a Competitive CMAQ Program in DVRPC’s Pennsylvania counties to identify eligible

projects to be advanced in the coming years. The TIP is a list of all projects for which federal, state, or local

funds are anticipated; it represents the transportation improvement priorities of the region and is required by

federal law.

Under the DVRPC 2016 Competitive CMAQ Program for Pennsylvania, candidate projects will be submitted

to the Delaware Valley Regional Planning Commission (DVRPC) and reviewed by an oversight committee for

initial eligibility and general merits. The CMAQ Subcommittee consists of representatives from DVRPC’s

member governments and agencies as well as representatives of interests such as business and freight,

transit, and the general public. Projects that withstand this screening process will then be subjected to an air

quality emissions analysis. To remain eligible according to federal guidelines, individual projects must result

in a reduction in emissions using standardized tests.

Based on their emissions reduction potential, as well as other criteria (described in this document), candidate

projects will be evaluated, selected, and approved for funding by the DVRPC Board, and advanced to the

Pennsylvania Department of Transportation (PennDOT) for inclusion in the state TIP.

The DVRPC Competitive CMAQ Program creates a cooperative arrangement between the Federal Highway

Administration (FHWA), PennDOT, DVRPC, and project sponsors. As such, there are a number of

procedures, stipulations, and limitations associated with the use of CMAQ funds. The following sections of

this document explain what a prospective applicant must know about the program, how to apply for funds,

and what regulations recipients must follow to generate a successful project.

Page 8: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 9: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 3

CHAPTER 2: Applying for CMAQ Funds

How Much Funding Is Available?

In Pennsylvania, a total $20 million has been set aside for projects beginning in FY 2017 (fiscal years begin

on October 1).

Who Is Eligible to Apply for Funds?

Any public agency or incorporated private firm or non-profit entity may apply to DVRPC for CMAQ funds for

their project. However, there are certain restrictions that must be addressed if a private firm or non-profit

entity is applying for funds. Private firms and non-profits must partner with a public agency sponsor and have

a formal agreement in place with the public agency at the time of funding award (see “Can Public–Private

Partnerships Apply?” section below). Individuals may not apply.

In all cases, the prospective applicant is required to contact the county and municipal government(s) in

which the project will be implemented to inform them of the intent to apply and to coordinate the project effort.

Signal timing and equipment projects, in particular, are required to coordinate their project with the

county and PennDOT District 6-0. Project sponsors seeking to implement public transportation

improvements, such as transit shuttle service, must contact the public transit agency that provides service in

the proposed project area. Applicants applying for equipment purchases (transit vehicles or diesel engine

retrofits or repowers) must work with PennDOT or other state agency prior to applying for CMAQ funds, to

secure an agency “champion” who is willing to shepherd the project through the federal obligation process

should the project be awarded CMAQ funds. (County, regional, and state contacts are listed in Appendix C.)

Can Public–Private Partnerships Apply?

CMAQ funds may be used for projects that are cooperatively implemented under agreements between public

agencies and incorporated private firms or non-profit entities. The public agency partner is responsible for

applying for the CMAQ funds through DVRPC and overseeing and protecting the investment of the federal

funds used in a public–private partnership project. Projects will not be eligible if they result in creating a

competitive advantage of one private entity over another.

Federal law requires that a legal, written agreement be in place between the public agency and private or

non-profit entity before implementing any CMAQ-funded project. These agreements should clearly specify

the purpose of CMAQ funding; the roles and responsibilities of the participating agencies; cost-sharing

arrangements for capital investments and/or operating expenses; and how the disposition of land, facilities,

and equipment will be affected should the original terms of the agreement be changed, such as by insolvency

or a change in the ownership of the private entity. Though these agreements need not be finalized at the time

the application is submitted, the application must include letters of intent between the parties indicating

willingness to enter into such agreement if the project is selected.

What Are Eligible Costs and How Are Projects Funded?

All applicants should understand that the CMAQ Program is a reimbursement program for only those costs

that are eligible under federal law. The sponsor does not receive grant funds up front to start the project;

rather, the sponsor is reimbursed for costs incurred after receiving federal authorization of the project and a

notice to proceed. Federal funding is generally based on an 80/20 percentage cost split; that is, federal funds

may cover up to 80 percent of project costs and a non-federal local match would cover at least 20 percent.

Page 10: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

4 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

Funding Requirements

CMAQ project funding requests that are 80 percent or less of the total project cost will be considered more

favorably in the evaluation process.

DVRPC expects that all applicants expend their own funds for all pre-construction (i.e., environmental

clearance, engineering, design, utilities, right-of-way) or pre-acquisition (i.e., vehicle specifications,

lease arrangements, etc.) activities. CMAQ funds can then be requested to fund the construction or

acquisition phase. Applicants are advised that completed pre-construction or pre-acquisition activities

may make the project more favorable in the evaluation process as a part of the “Project Readiness”

Selection Criterion.

If the applicant of a construction or vehicle acquisition project feels they are not capable of directly

funding all pre-construction or pre-acquisition activities, then a request may be made for partial

CMAQ funding for any of these phases. The pre-construction or pre-acquisition phase(s) will be

funded with no more than 80 percent federal CMAQ funds and no less than 20 percent local matching

funds, as must the construction phase. (Example special request: engineering, 100 percent local;

right-of-way, 80 percent CMAQ and 20 percent local; construction, 80 percent CMAQ and 20 percent

local). Applicants are advised that incomplete pre-construction or pre-acquisition activities may make

the project less favorable in the evaluation process as a part of the “Project Readiness” Selection

Criterion.

For non-construction projects, or “soft” projects such as marketing, incentive plans, etc., applicants

must request funding with no more than 80 percent federal CMAQ funds and no less than 20 percent

local matching funds for all phases of the project.

Funding Authorization

Prior to initiating any project activities, the project must be approved by the DVRPC Board for inclusion in

DVRPC’s TIP, a project reimbursement agreement must be executed between the sponsor and PennDOT,

and federal project authorization must be received. PennDOT and/or DVRPC will provide assistance in

securing these approvals. If the project sponsor decides to cancel the project or drop out of the program once

the project has entered the design phase, the project sponsor will be required to pay back all federal funds

received as of that date and to make full payment of all outstanding invoices to engineers or contractors.

It is essential that accurate cost estimates be submitted as part of the application. If, after a project is

underway, it is determined that costs exceed expectations, whether due to unforeseen circumstances or

simply poor estimates, applicants should not expect additional funding from the program. Instead they will

have to: (a) bear the additional costs themselves, (b) reduce the scope of the project (with prior approval from

DVRPC), or (c) break the project into sections and obtain other sources of funding for those unfunded

sections. Project sponsors will be required to submit biannual progress reports, even during periods when

progress includes state or local permit review or agreement processing. DVRPC reserves the right to

withdraw its authorization from any project for lack of progress. A copy of the progress report is included in

Appendix D to this guidance.

Page 11: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 5

CHAPTER 3: Project Eligibility

What Types of Projects Are Eligible?

Every project that receives CMAQ funding must produce a reduction of harmful emissions related to

transportation and must also be for the public good (i.e., not benefiting one private entity over another).

Furthermore, all federal eligibility requirements for transportation projects must be met. (See FHWA CMAQ

Eligibility Guidance at www.dvrpc.org/CMAQ).

In addition to these requirements, certain activities are explicitly identified as either eligible or ineligible for

CMAQ funding. Listed below are the sixteen types of projects and activities that are eligible for CMAQ

funding:

Eligible Projects Transportation Control Measures (identified in Section 108 of the Clean Air Act);

extreme low-temperature cold start programs;

alternative fuels and vehicles;

congestion reduction and traffic flow improvements;

transit improvements;

bicycle and pedestrian facilities and programs;

travel demand management;

public education and outreach activities;

transportation management associations;

carpooling and vanpooling;

freight/intermodal;

diesel engine retrofits and advanced technologies;

idle reduction;

training;

inspection and maintenance programs; and

experimental pilot projects.

A more complete explanation of each activity is given in the FHWA CMAQ Program Guidance. This guidance

and a sampling of previously funded projects through the CMAQ Program can be found at

www.dvrpc.org/CMAQ/.

Page 12: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

6 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

Operating Assistance

Operating assistance is limited to new transit service, intermodal facilities, travel demand strategies, and the

incremental cost of expanding existing transit services. For this competitive CMAQ funding round, operating

assistance is limited to three years of funding with the flexibility to spread year–three funding into a fourth

year. The fourth year of funding is an extension of year three funding so that applicants can access a larger

share of the funding to initiate the project and then step that amount down to suppor tthe project as it

progresses and becomes self–sustaining. Applicants must show that funding in year’s three and four is less

than in years one and two.

The programmatic intent of this funding limitation, is to start up viable new transportation services that can

demonstrate air quality benefits and eventually cover their costs. Other funding sources should supplement

and ultimately replace CMAQ funds for operating assistance.

There are exceptions to the operating assistance limitations for certain public education, and travel demand

strategy expansion projects. These exceptions are detailed in Section VII of the FHWA CMAQ Program

Guidance under the eligible project type descriptions.

What Types of Projects Are NOT Eligible?

As a general rule, highway or transit maintenance and reconstruction projects and the construction of Single

Occupancy Vehicle capacity are not eligible activities. Also, measures that are statutorily mandated (e.g.,

phase-in of alternatively fueled fleets) may not be funded with CMAQ funds. DVRPC, in consultation with

FHWA and the Federal Transit Administration (FTA), will determine if any other activities are not eligible

under the federal rules and guidelines on a case by case basis.

In addition, DVRPC retains the prerogative to declare a class of projects not eligible as a matter of policy, if it

is determined that such use would not be in the best interest of our region. DVRPC can also deny funding to

an otherwise eligible project if it is determined that such funding would give one private firm an undue

competitive advantage over another—a federal regulation that must be observed.

Page 13: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 7

CHAPTER 4: Project Selection

How Will Projects Be Selected?

DVRPC will screen every application for completeness and basic eligibility. After it is determined that a

proposed project meets the basic eligibility requirements outlined in the federal guidance, it will be further

scrutinized according to a variety of criteria established by DVRPC and the selection committee. Each

eligible project will be evaluated based on its emissions reduction potential, as well as other factors such as:

project readiness, sponsor capacity, extent of local contribution, serving an Environmental Justice (EJ)

community, and degree to which the project implements the regional long-range plan or local comprehensive

plan. (Selection Criteria and their relative weights are identified in this chapter as well as in Appendix A of this

guidance document). The distribution of projects with regard to geographic location will also be considered,

as will the desire to produce a balanced program of mixed project types. However, no matter how well a

project scores in these other criteria; it cannot be selected unless it reduces mobile source transportation

emissions.

Following careful review and analysis, projects will be recommended to the DVRPC Board for selection.

Board action will amend the project into the region’s TIP and provide eligibility for federal funding. See

Chapter 5 for the tentative schedule for when Board action could occur. The steps to be taken after the

project is selected for the TIP are outlined in Chapter 6. Applicants are encouraged to view the FHWA “CMAQ

101 Training Course” video on YouTube at:

https://www.youtube.com/watch?v=XKXcs0WtNHA&feature=youtu.be to learn more about what will be

expected from FHWA should the project be selected

Emissions Analysis

All projects that pass the initial screening for eligibility will be evaluated for their effect on air quality using a

standardized set of analysis tools developed for PennDOT. Evaluation results will enable the projects to be

rated based on the following air quality and congestion mitigation factors:

change in emissions (volatile organic compounds [VOC], nitrogen oxides [NOx], fine particles [PM2.5]); and

change in Vehicle Miles Traveled (VMT).

This analysis will be performed by DVRPC staff based on information provided in the Emissions Analysis

Forms that are required to be submitted with the project application. If an Emissions Analysis Form is not

provided for the project type, the applicant must work with DVRPC staff to provide adequate information about

the project in order to determine its emissions impact.

In addition to being a basic program requirement, the magnitude of emissions or VMT reductions from the

project are also considered as part of the Project Selection Criteria.

In order to assist the applicant with judging the relative emissions or congestion mitigation benefits of their

project, links to FHWA and U.S. Environmental Protection Agency (EPA) studies that provide estimates of the

relative emissions benefits of the different project types are available at www.dvrpc.org/CMAQ .

Page 14: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

8 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

Pre-screening Questions

In addition to demonstrating a reduction of emissions, all applicants are expected to meet the three screening

criteria in Question 4. of the Application Document.

Consistency with Long-Range Plan or Local Comprehensive Plan Goals

In order to promote good planning and to encourage implementation of the Connections Long-Range Plan for

the region as well as county and local comprehensive plans, submitted projects are required to be consistent

with the goals of the Connections plan, or the appropriate county or municipal comprehensive plan.

Applicants are required to identify which plan goal(s) their project implements

The Connections Long-Range Plan is available at www.dvrpc.org/Connections. Implementing Connections:

A Guide for Municipalities is available at www.dvrpc.org/connections/implementation.htm.

Located within a DVRPC Congested Sub-corridor

In order to promote congestion reduction in the region, projects are required to be located within a congested

sub-corridor, as identified by DVRPC’s Congestion Management Process (CMP).

Applicants are required to identify which congested sub-corridor or corridors the project is located in.

Applicants are encouraged to use the interactive CMP web-page at www.dvrpc.org/webmaps/CMP/ for

corridor maps and lists of appropriate strategies to implement in those corridors.

Projects that are solely air quality improvements, such as diesel retrofits and alternative fuel vehicles, and do

not have a congestion reduction component, will not be judged on this question.

Questions regarding the CMP congested sub-corridors or the mapping tool should be directed to DVRPC

CMP staff at 215-238-2948.

Public Agency or Public Agency Sponsor

According to FHWA guidance, an eligible applicant must be a public agency or have a public agency sponsor

the project. See Chapter 2 for more details regarding applicant eligibility and the requirements for public–

private partnerships.

Project Selection Criteria

In addition to the emissions analysis and pre-screening questions, projects will be evaluated using criteria that

will help the selection committee choose projects that reflect programmatic and regional priorities and exhibit

likelihood of timely and successful implementation.

The primary Selection Criteria are described below. A table detailing the weights, as well as the project

scoring definitions, of each criterion is included in Appendix A of this document. Additional considerations will

be that the program will represent a balanced mix of project types and geographic diversity of the region.

Projects will be scored using a basic formula that includes a “Weight” for each of the six Selection Criteria and

a “Score” indicating how well each project meets the Selection Criteria. The criteria weight will be multiplied

by the project’s score for that criterion to yield a weighted score. The six weighted scores are then summed

to produce a total project score.

Project Readiness (Weight = 25/100)

Project readiness refers to the likelihood that a project will be implemented in a timely fashion. Projects that

have preliminary work or preparation completed in advance of CMAQ funding, or that demonstrate that work

Page 15: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 9

can begin soon after the CMAQ award announcement, will be viewed favorably. Candidates with a high level

of project readiness will have completed categorical exclusion documents and acquired right–of-way for

construction projects, identified equipment specifications and prepared bid documents for equipment

replacements or technology projects, or are implementing a recommendation of an adopted plan or survey for

education, TDM, or outreach projects. Projects that have good readiness will have matching funding sources

secured and will have identified a clear process for implementation.

Please note that applicants planning diesel engine repower or retrofit projects must confirm that equipment

will meet FHWA equipment purchase requirements, including “Buy America” provisions. A helpful list of “Buy

America” eligible heavy-duty truck manufacturers is posted at www.dvrpc.org/cmaq.

Applicants will demonstrate project readiness and feasibility of implementation by providing a realistic project

timeline that includes specific implementation milestones. The project milestones are intended to identify the

key steps in advancing the project toward funding approval and, ultimately, implementation. They will be

unique to each project depending on the project type, complexity, and coordination required. Steps taken to

advance a project before funding is awarded should be detailed in the project narrative and the provided

“Project Readiness” checklist.

Sponsor Capacity (Weight = 25/100)

Sponsor capacity refers to the project sponsor’s ability and commitment to implement the project should

CMAQ funding be awarded. Candidate projects should demonstrate that the sponsors have a clear

commitment to implement, operate, and maintain the project, during and after the CMAQ funding period.

Successful candidates will show the institutional capacity to manage the project and obtain the necessary

permits, bids, and contracts. Candidates with a history of implementing federally funded projects will be

considered to have a high level of sponsor capacity.

Project sponsors should convey capacity by describing their experience successfully managing grants for

similar projects, clearly defining the roles and responsibilities of each of the project partners, and

demonstrating that matching funds and other sources of project funds are secured.

Emissions/VMT Reduction (Weight = 20/100)

DVRPC staff will analyze the emissions and VMT reductions of each submitted project using the Air Quality

Off-Network Estimator (AQONE) model developed for PennDOT.

Inputs for the model will be provided by the applicant on the Emissions Analysis Forms. Applicants with

projects that cannot be analyzed using AQONE, or do not have Emissions Analysis Forms provided with their

application, will be required to provide sufficient information about the project so that emissions or VMT

impacts can be determined.

Emissions and VMT reductions will be scored based on the the total reduction of VOC, NOx and PM2.5

emissions expressed in kilograms per day (kg/day) or the reduction in VMT per day. Projects will receive the

score for whichever measure (emissions or VMT) yields the highest score.

Long-Term Viability of Emissions Benefit (Weight = 20/100)

The value of a project for helping the region meet and maintain the air quality standards depends on whether

those benefits can be sustained over time. Some projects will continue to provide air quality or emissions

reduction benefits into the future; other projects will have a defined lifespan that will decrease as technologies

change or equipment needs to be replaced; and a third category of projects will provide air quality benefits

only as long as the project is receiving funding. Projects that can demonstrate air quality benefits for greater

Page 16: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

1 0 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

than 10 years will receive a “high” ranking for this criterion; greater than five years will receive a “medium”

ranking; and projects that cannot definitively demonstrate benefits beyond five years will receive a “low” score

for this criterion. Applicants should explain, as specifically as possible, the long-term outlook and lifespan of

the air quality benefits of the project.

Local Contribution (Weight = 5/100)

As federal sources of funding become more difficult to obtain, local contributions become more important to

enhance a program’s reach. A good candidate project will demonstrate local commitment to the project

through innovative funding and a larger percentage of non-federal matching funds.

The applicant should describe all preliminary work performed to prepare the project for implementation and

quantify cash contributions and in-kind services dedicated to the project.

The percentage of the total project cost represented by local contribution will be used to score the project for

this criterion. A larger local contribution will result in a higher score for this criterion.

Projects Serving an Environmental Justice (EJ) Community (Weight = 5/100)

Environmental Justice communities suffer disproportionately from the health effects of air pollution. Projects

that can demonstrate benefits to an EJ community or population susceptible to air pollution will receive

consideration under this criterion. An EJ community for this purpose will be defined as a census tract with

three or more Potential Indicators of Disadvantage identified through the DVRPC’s EJ mapping tool.

(Applicants should use the EJ screening tool at www.dvrpc.org/webmaps/EJ2014 to demonstrate that their

project serves an EJ community). Applicants are encouraged to use the mapping tool to determine which

disadvantaged populations are present in the project area. Questions about using the EJ mapping tool

should be directed to DVRPC’s Public Involvement Manager at 215-238-2871.

Is the Project Scalable?

Project sponsors should indicate on the application if the submission is scalable in the event of partial funding

availability for a project. If applicants want to be considered for partial or scaled-back funding, they should

indicate on the application form which phases of the project they will implement or what their strategies are to

scale back the project scope.

Page 17: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 1 1

CHAPTER 5: Submitting the Application

What Information Must Be Supplied?

The following forms and documents must be submitted by the application deadline in order for an application

to be considered complete:

application checklist;

project abstract;

application form;

Project Readiness checklist;

applicable project Emissions Analysis Form or support materials detailing project emissions or VMT benefits; and

relevant letters of commitment (applicants are given 30 days after the application deadline to submit these letters).

Application Checklist

The application checklist is a simple list of the components required for a complete DVRPC Competitive

CMAQ Program application. This checklist will assist the applicant to ensure that all of the required forms and

attachments are submitted with the application.

Project Abstract

The project abstract is a brief description of the applicant’s proposal. The abstract will provide reviewers with

a synopsis of the project proposal and will assist reviewers with screening for project and sponsor eligibility.

Application Form

The application form poses a series of questions to help ensure that candidate projects are CMAQ-funding

eligible, that project sponsors are eligible or have executed the necessary agreements for public–private

partnerships, and that projects are consistent with regional and or local plans and the DVRPC CMP. There

are also questions that address the program Selection Criteria.

The application form requests a detailed project narrative, project timeline for implementation, project budget

that includes the amount of local contribution that the applicant is bringing to the project, and identification of

the party responsible for owning and maintaining the project or program after the CMAQ funding period has

ended.

There are certain types of projects that are limited to four years of operating assistance. Projects that fall into

this category must include a plan for continuing the funding of the service beyond the fourth year of operation.

Project sponsors should also be able to demonstrate a reduced need for CMAQ operating funds as a project

progresses from the first year to the fourth year of operations, what the source of funds will be that will

supplant CMAQ funding, and how the service will become self-supporting.

Project Readiness Checklist

A Project Readiness checklist is provided to help the applicant inform the reviewer of the types of actions that

have been taken to advance the project in preparation for federal funding. Construction projects are the most

Page 18: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

1 2 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

complex type of project and therefore require the most preparatory work to make the project ready for

implementation upon receiveing CMAQ funds. Other project types, such as equipment purchases and

outreach programs, must also demonstrate a level of preparedness in order to score well under this criterion.

Emissions Analysis Forms

For most eligible project types, DVRPC has supplied Emissions Analysis Forms that indicate to the applicant

what information is required so that DVRPC can measure the emissions benefits of a given project. For

project types where DVRPC does not provide Emissions Analysis Forms, the applicant is required to provide

justification for why the applicant feels that this project will reduce transportation-related emissions and/or

VMT. DVRPC staff will work with the applicants to request the needed information in order to perform an

emissions analysis on projects that lack an “Emissions Analysis” project form.

Both EPA and FHWA have provided resources that can be used to compare different project types to each

other with regard to emissions reductions and cost effectiveness. These resources are very general and are

provided to give the applicant a general sense of how their project will compare with other project types.

Links to these documents are available at www.dvrpc.org/CMAQ.

Letter of Commitment

In addition to this technical data, the applicant will also be required to submit letters of commitment for all

matching funds, and to own, operate, and maintain the project. Letters not included with the application must

be received by DVRPC no later than 30 days after the application deadline. Failure to submit these letters will

cause the project to be dropped from further consideration in the process. Projects that involve multiple

municipalities or entities must submit a letter from each party involved. Letters must be signed by an official

who is authorized to represent the organization, such as the township manager or chief elected official.

Will There Be Any Information Sessions?

DVRPC will conduct one information session to answer questions about the application process. Attendance

at the session is mandatory for prospective applicants. Should an applicant not be able to attend the

scheduled meeting, the applicant should contact DVRPC as soon as possible. The session is scheduled for:

4:00 PM, February 23, 2016

at

DVRPC Offices

190 N. Independence Mall West

8th Floor

Philadelphia, PA 19106

Page 19: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 1 3

When Is the Application Deadline and How Should the Application Be Submitted?

Electronic applications are preferred. If applicants submit electronic applications, DVRPC requests that they

send a separate email announcing the submission to provide a record in the unlikely event that the application

is not delivered. Should the applicant not be able to submit the application electronically, two copies of the

completed application must be received at the DVRPC offices by 5:00 PM on April 21, 2016. Facsimiles will

not be accepted. Applications received after the due date will not be considered.

Please submit the completed application to:

[email protected]

Or

CMAQ Application Office

DVRPC

190 N. Independence Mall West, 8th Floor

Philadelphia, PA 19106

What Is the Tentative Schedule?

DVRPC allows approximately 90 days for applications to be completed and submitted. Following that

deadline (see above), all projects will be screened for eligibility and assessed for their emissions reduction

potential during the late spring of 2016. The surviving projects will then be evaluated by the DVRPC CMAQ

Subcommittee using a number of different factors (as described in Chapter 4). We anticipate the final

selection by the DVRPC Board to occur in July 2016. All applicants will be notified within two (2) weeks of the

Board’s action. Applicants will then have 60 days to initiate the project by scheduling a kick-off scoping

meeting prior to starting the project.

CMAQ Program Schedule (Subject to Change)

Date Activity

January 21, 2016 Call for Eligible Projects

February 23, 2016 Technical Information Meetings

April 21, 2016 Applications Due

May 21, 2016 Deadline for Letters of Commitment

May/June 2016 Project Evaluation

June 2016 Final Project Selection

July 2016 DVRPC Committee Approval

August 2016 Letters to Winners

Page 20: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 21: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e 1 5

CHAPTER 6: Managing the Project

What Assistance Is Available from DVRPC and PennDOT?

During the application and evaluation phase, DVRPC will answer all questions concerning the eligibility of a

project, in consultation with FHWA and FTA. DVRPC staff will also answer questions on how to submit an

application for the CMAQ Program. DVRPC will not provide direct assistance to applicants with completing

their applications. It is our intention to remain neutral and objective in our role as program coordinator.

Once a project is selected, the development and implementation of the CMAQ project will be the primary

responsibility of the project sponsor. Each project sponsor will establish the implementation schedule for their

project; PennDOT, and DVRPC staff will be available to answer questions or address concerns, but it will be

up to the project sponsor to manage the project schedule.

During the implementation phase, PennDOT, and DVRPC staff will provide technical assistance and guidance

in the development of the CMAQ projects. In particular, state DOT project management staff can provide

assistance to the project sponsor in following all appropriate federal and state regulations to ensure that

project funding is not jeopardized.

What Procedural and Regulatory Requirements Apply?

There are a number of procedural and regulatory requirements that apply to the projects implemented under

the CMAQ Program. Project sponsors may not be acquainted with PennDOT, FHWA, or FTA procedures. If

necessary, it is expected that project sponsors will secure professional services (consulting engineers,

architects, or equipment vendors) to assist them in satisfying these requirements and advancing their

projects. Applicants must comply with PennDOT “Publication 93” requirements when selecting

consultant services.

PennDOT and DVRPC staff are also available to assist with the interpretation and application of these

requirements. A brief discussion of these requirements covering the following topics is provided in Appendix B

(actual requirements may vary slightly).

Typical Procedural and Regulatory Requirements

Initiation of Project;

Reimbursement Agreement/Notice to Proceed;

Environmental Clearance;

Project Engineering;

Standards and Guidelines;

Right-of-Way Acquisition;

Utility Clearance;

Permits;

Public Utility Commission Involvement;

Page 22: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

1 6 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

Bidding;

Construction and Implementation;

Maintenance; and

Cancellation of a Project.

Page 23: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

Appendix A

Page 24: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 25: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 2 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e A - 1

Appendix A: Project Selection Criteria

Project Selection Criteria and Weights

Criteria Weight

(out of 100)

Score

(%)

Weighted Score

(weight × score)

Best PossibleScore**

1. Project Readiness 25

1. High 25 100% 25

2. Medium 25 50% 12.5

3. Low 25 25% 6.75

4. Not ready 25 0 0

2. Sponsor Capacity 25

1. High 25 100% 25

2. Medium 25 50% 12.5

3. Low 25 25% 6.75

3. Emissions/VMT Reduction 20

1. Modeled emissions reductions for fine particles (PM2.5) + nitrogen oxides (NOx) + volatile organic compounds (VOC) = >50 kilograms per day (kg/day) or VMT reduction > 10,000 VMT/day

20 100% 20

2. Modeled emissions reductions for PM2.5 + NOx + VOC = 10–49.9 kg/day or VMT reduction between 1,000 and 10,000 VMT/day

20 50% 10

3. Modeled emissions reductions for PM2.5 + NOx + VOC = <10 kg/day or VMT reduction <1,000 VMT/day

20 25% 5

Page 26: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

A - 2 D V R P C 2 0 1 2 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

4. Long-Term Viability of Emissions Benefit 20

1. Projects that provide benefits for reducing emissions, Vehicle Miles Traveled, improving operations, or reducing congestion for >10 years.

20 100% 20

2. Projects with identifiable, >5 years, emissions benefit (benefit may expire as technology is replaced or equipment ages) or outreach project or transit subsidy with identified funding >5 years.

20 50% 10

3. Emissions benefit dependent on future funding; funding beyond first 5 years is uncertain.

20 25% 5

5. Local Contribution 5

1. >75% 5 100% 5.0

2. 50–74.9% 5 75% 3.75

3. 35–49.9% 5 50% 2.50

4. 20–34.9% 5 25% 1.25

5. <20% 5 0 0.00

6. Projects Serving an Environmental Justice Community 5

1. Yes 5 100% 5

2. No 5 0 0

Best Possible Score** 100

Page 27: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

Appendix B

Page 28: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 29: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e B - 1

Appendix B: Project Implementation Procedural and Regulatory Requirements

Initiation of Project

The sponsor must initiate their project within 60 days of notification of project selection. A project is

considered to be initiated when the sponsor has contacted the Pennsylvania Department of Transportation

(PennDOT) to schedule a project scoping meeting.

Reimbursement Agreement

The federal highway program is a reimbursable program. It is very important that record keeping be in

accordance with the “Federal Guidance for Third-Party Agreements." Only those costs specifically associated

with the implementation of the project are to be charged to the project. When there is a third-party consultant

or contractor performing the work, the administrative costs of the sponsor are not eligible.

The public entity must execute a standard reimbursement agreement with PennDOT prior to proceeding with

any work on the project for which they seek to be reimbursed. If the project is selected, the project sponsor

will work with PennDOT staff to draft and execute the agreement. Any project costs incurred prior to the

execution of a project reimbursement agreement will not be eligible for reimbursement.

Environmental Clearance

All projects involving construction will require an environmental clearance document as part of the

engineering phase of work. This document may be a Categorical Exclusion, Environmental Assessment, or

Environmental Impact Statement. The level of detail required will be determined by PennDOT based on the

nature of the specific project. Normally, when the scope of the project is being determined, a decision will be

made on the type of documentation required. It is the responsibility of the project sponsor to have the

environmental document prepared.

Project Engineering

Projects must follow standard federal and state procedures for all phases of work. If project sponsors do not

have a qualified professional on staff, they should acquire the services of a consultant to oversee the

development and implementation of the project and ensure compliance with all state and federal

requirements. The acquisition of consultant services must be in accordance with federal procedures. In the

case of municipally sponsored projects, municipalities may choose to use their municipal engineers with

PennDOT approval, or follow an approved consultant selection process. It is important to recognize that the

design and/or construction engineers are employed by the project sponsor, not by the Delaware Valley

Regional Planning Commission or PennDOT. Project sponsors MUST comply with PennDOT

“Publication 93” requirements for the selection of a project consultant.

Standards and Guidelines

Standards are established to protect the health and safety of the public. All projects must be designed to

meet federal and state standards. However, in some instances, traditional federal and state highway

standards may not apply to a particular project. In such cases, sponsors should follow whatever guidance is

available that applies to their project with federal and state concurrence. Examples include guidelines

prepared by the Rails to Trails Conservancy, the American Association of State Highway and Transportation

Officials, the Secretary of Interior's Standards for the Treatment of Historic Properties, and the Manual of

Uniform Traffic Control Devices.

Page 30: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

B - 2 D V R P C 2 0 1 2 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

Right-of-Way Acquisition

All right-of-way acquisition must follow federal regulations and the Uniform Relocation Assistance Act. In

particular, property owners must be advised that federal funding is being used to implement the project and

they are entitled to fair market value for their property. In addition, if the sponsor does not have the authority

to acquire property by eminent domain, the property owner must be so advised prior to any offer being made.

This requirement does not preclude the voluntary donations of property to the project. Proof of ownership of

the right-of-way will be required for all projects prior to advertising for construction bids.

Utility Clearance

All projects involving construction must have utility clearance prior to the advertisement for bids. This

procedure requires that the sponsor certify that all necessary arrangements have been completed for the

relocation of any affected utility. PennDOT personnel will provide assistance with this process.

Permits

It will be the responsibility of the project sponsor to secure all necessary permits to design and implement the

project. These may involve Departments of Environmental Resources, the U.S. Army Corps of Engineers,

local municipal permits, DOT highway occupancy permits, etc.

Public Utility Commission Involvement

Certain projects, such as rails to trails projects or those involving railroad crossings may require the

involvement of the Public Utility Commission. It will be the responsibility of the project sponsor to contact the

Public Utility Commission to secure the necessary actions by that agency.

Bidding

For projects that require a contractor to perform physical construction, the sponsor's professional engineer will

assemble the contract proposal package. The Plans, Specifications, and Estimate (PS&E) package will be

reviewed by the PennDOT District 6-0 Office. Bidding will be managed by the project sponsor or the

PennDOT District 6-0 Office, as agreed upon at project inception, and must follow federal procurement

procedures.

Specification of proprietary or sole source items will not be permitted without the prior written approval of

PennDOT.

Construction and Implementation

Project sponsors may proceed with the construction or implementation phase of the project upon receipt of

written authorization to do so from PennDOT. This will ensure that all necessary approvals have been

secured. Construction or implementation must be performed by an approved contractor. All material used in

conjunction with the project must meet project specifications (including special provisions included in the

PS&E).

Control, Use, and Maintenance

The project sponsor will be responsible for the continuing control, use, and maintenance of the project after

completion of construction. No federal Congestion Mitigation and Air Quality Program funding will be provided

for maintenance activities.

Page 31: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e B - 3

Cancellation of a Project

A project sponsor may, at any time in the project development process, decide to cancel the project and drop

out of the program. The project sponsor will be responsible for the reimbursement of all federal funds received

as of that date and for the payment of all outstanding invoices to engineers or contractors.

Page 32: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 33: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e B - 1

Appendix C

Page 34: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 35: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e C – 1

Appendix C: Committee Members

Congestion Mitigation and Air Quality Improvement (CMAQ) Program Selection Committee Members

Delaware Valley Regional Planning Commission Competitive CMAQ Program  Committee Members 

*Indicates a Voting Member of the Committee  **Indicates a Shared Seat Name and Address  Phone/Fax/Email DVRPC 

Elizabeth Schoonmaker Manager, Office of Capital Programming Delaware Valley Regional Planning Commission The ACP Building – 8th Floor 190 N. Independence Mall West Philadelphia, PA  19106‐1520 

(215) 238‐2938 – P(215) 592‐9125 – F [email protected]  

Sean Greene Senior Transportation Planner Delaware Valley Regional Planning Commission The ACP Building – 8th Floor 190 N. Independence Mall West Philadelphia, PA  19106‐1520 

(215) 238‐2860 – P(215) 592‐9125 – F [email protected] 

Kwan Hui Transportation Planner Delaware Valley Regional Planning Commission The ACP Building – 8th Floor 190 N. Independence Mall West Philadelphia, PA  19106‐1520 

(215) 238‐2894 – P(215) 592‐9125 – F [email protected]  

Pennsylvania Department of Transportation 

PennDOT Linda Guarini* Manager, Planning & Programming Pennsylvania Department of Transportation District 6‐0 7000 Geerdes Blvd. King of Prussia, PA  19406 

(610) 205‐6950 – P(610) 205‐6914 – F [email protected]  

James Mosca* Metropolitan Manger, Center for Program Development and Management Pennsylvania Department of Transportation P.O. Box 3365 400 North Street –  6th Floor Harrisburg, PA  17105‐3365 

(717) 787‐1250 – P(717) 787‐5247 – F [email protected]  

Page 36: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

C – 2 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

Delaware Valley Regional Planning Commission Competitive CMAQ Program Committee Contacts (con’t) Bucks County Richard G. Brahler, Jr.* Senior Transportation Planner Bucks County Planning Commission The Almshouse Neshaminy Manor Center Doylestown, PA  18901 

(215) 345‐3427 – [email protected] 

Chester County Randy Waltermyer* Director of Transportation Services Chester County Planning Commission 601 Westtown Road – Suite 270 P.O. Box 2747 West Chester, PA  19380‐0990 

(610)344‐6285 – P (610) 344‐6515 – F [email protected]  

Bill Deguffroy Transportation Planner Chester County Planning Commission 601 Westtown Road – Suite 270 P.O. Box 2747 West Chester, PA  19380‐0990 

(610) 344‐6285 – P(610) 344‐6515 – F  [email protected]   

Delaware County Tom Shaffer* Manager, Transportation Planning Delaware County Planning DepartmentCourt House – Government Center 201 W. Front Street Media, PA 19063  

(610) 891‐5217 – P(610) 891‐5203 – F [email protected]  

Alex John Highway/Bicycle Planner Delaware County Planning Department201 W. Front Street Court House – Government Center Media, PA 19063 

(610) 891‐4396 – P(610) 891‐5203 – F [email protected]    

Montgomery County Matthew J. Edmond* Transportation Planner Montgomery County Planning Commission Court House P.O. Box 311 Norristown, PA  19404‐0311 

(610) 278‐3742 – P(610) 278‐3941 – F [email protected]  

Page 37: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e C – 3

Delaware Valley Regional Planning Commission Competitive CMAQ Program Committee Contacts (con’t) City of Philadelphia Angie Dixon** Director of Strategic Initiatives Mayor’s Office of Transportation and Utilities City of Philadelphia 1401 John F. Kennedy Blvd. –  Suite 1430 Philadelphia, PA  19102 

(215) 686‐8158 – [email protected]  

David Kanthor, AICP** Transportation Planner Philadelphia City Planning Commission 1515 Arch Street, 13th Floor  Philadelphia, PA 19102  

215.683.4643 ‐ [email protected]  

Nicholas Baker ** Transportation Planner Philadelphia Department of Streets 1401 John F. Kennedy Blvd. 830 Municipal Service Building Philadelphia, PA  19102 

(215) 686‐5579 – P(215) 686‐5059 – F [email protected]  

Michelle Webb ** Transportation Planner Philadelphia Department of Streets 1401 John F. Kennedy Blvd. 830 Municipal Service Building Philadelphia, PA  19102 

(215) 686‐5538 – P [email protected]  

Southeastern Pennsylvania Transportation Authority Zoe Robertson * Manager Grant Development, Finance & Planning Southeastern Pennsylvania Transportation Authority 1234 Market Street Philadelphia, PA  19107 

215) 580‐8217 – P(215) 580‐7321 – F [email protected] 

 

Federal Highway Administration—Pennsylvania Dan Walston Federal Highway Administration  228 Walnut Street – Room 508 Harrisburg, PA  17101‐1720 

(717) 221‐2219 – [email protected] 

Delaware River Port Authority/Port Authority Transit Corporation Barbara Holcomb* Grant Specialist, Government Relations Grants Admin./Security Delaware River Port Authority One Port Center 2 Riverside Drive P.O. Box 1949 Camden, NJ 08101‐1949 

(856) 968‐2107 – P(856) 968‐2256 – F [email protected]   

Page 38: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

C – 4 D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e

Delaware Valley Regional Planning Commission Competitive CMAQ Program Committee Contacts (con’t) Delaware Valley Goods Movement Task Force Gerard J. Coyle*  Vice President, Environmental & Sustainable Operations The Evans Network of Companies 2502 Wheatsheaf Lane Philadelphia, PA 19137 

215‐535‐1766 – P215‐533‐2265 – F [email protected] 

DVRPC Public Participation Task Force 

Ms. Lindsey Graham* 

c/o DVRPC215‐238‐2817 [email protected] 

Page 39: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

C — 1

Appendix D

Page 40: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 41: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e D – 1

Appendix D: Sample Project Progress Report

Date:

Project Title: MPMS Number:

Project Sponsor: Sponsor Contact: Phone Number: Email: Award Amount: PennDOT Project Manager: Approved project Description:

Project Milestones

Estimated Date of Completion

Actual Date of Completion

Date of PennDOT Approval Comments

Project Kick-Off Meeting

Project Scoping Field View Meeting

Scoping Approval

Reimbursement Agreement

Environmental Clearance

ADA Lighting Proprietary Approval

Safety Review Submission

Safety Review Approval

Traffic Approval Structures Approval

Construction Approval

ROW Clearance Utility Clearance DM3 Plan Review PS&E Submitted PS&E Approved Construction Inspector Hired

Construction Authorization

Page 42: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality
Page 43: DVRPC 2016 Competitive Congestion Mitigation and Air ......DVRPC 2016 Competitive CMAQ Program Guidance 1 CHAPTER 1: Introduction What Is the Congestion Mitigation and Air Quality

D V R P C 2 0 1 6 C o m p e t i t i v e C M A Q P r o g r a m G u i d a n c e D – 1