Durga Shanker Mishra, IAS Secretary, MOHUA, GoI & Chairman, BMRCL Pradeep Singh Kharola, IAS Managing Director Vijay Kumar Dhir Director (P&P) N.M. Dhoke Director (RSE & OM) U.A. Vasanth Rao General Manager (T&R) & Chief Public Relations Officer Editorial Team T. L. Ravi Prakash Senior Manager-Public Relations & Srivas Rajagopalan Registered Office Address Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road, Shantinagar, Bengaluru—560 027 Telephone / Fax Nos Ph: +91-080-22969300 / 301 Fax : 080-22969222 Co. Identification No. (CIN) U16286KA1994GOI016286 Your feedback helps us serve you better. For any suggestions about Namma Metro email us at [email protected] or [email protected]You can also call on BMRCL along with BEML celebrated Vigilance Awareness Week from 30.10.2017 to 04.11.2017
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
REACH-2Extension-Reach-2A:- Construction of Elevated Structures of Length 3.945 kms (approx)
from Mysuru Road Station dead end to Pattanagere Station including 4 Nos. of Elevated Metro
Stations viz Nayandahalli Station, Rajarajeshwarinagar Station, Jnanabharathi Station and
Pattanagere Station in the extension on west side of East-West Corridor of Bangalore Metro
Rail Project, Phase-2.
Name of the Contractor :- M/s IL&FS Engineering Construction Company Limited
Total Cost of the Project :- Rs. 327.00 Crores
Shifting of Water Supply Lines & Underground Drainage (UGD) Lines:- The affected water supply lines
and Underground Drainage Lines are identified along with concerned BWSSB Engineers for the entire stretch.
The drawings are prepared and submitted to BWSSB for shifting the identified utilities to the new location of utility
corridor. BWSSB has submitted the estimate. According to that BMRCL deposited the estimated amount to
BWSSB. The work has been taken up by BWSSB and completed at Jnanabharathi, Rajarajeshwari station and
Nayandahalli station in all respects.
Road Widening Works:- Road Widening works from Nayandahalli to Rajarajeshwarinagar both side
completed and Jnanabharathi Station 100% road works completed and also at Pattanagere station. In Station’s
both side drain work with Road widening/diversion work is in Progress. Retaining wall work is under construction.
The Estimate for road widening from Jnanabharathi to Pattanagere has been submitted by National Highway
PWD Karnataka to BMRCL. The required amount has been deposited by BMRCL for Road Widening purpose for
National Highway, PWD. Road Widening work from Jnanabharathi to R.V College is completed by National
Highway PWD, Karnataka.
Viaduct & Stations:-
The construction of 3.945 KM viaduct and four stations has been awarded to M/s IL&FS construction Pvt Ltd.
and the work is in progress. Uncharted utility checking, Piling, Pile Cap, Pier and Pier Cap works under
progress. Segment Erection for Thirty one spans completed.
In Stations – Pile, Pile Cap, Column – Up to Concourse Level and Portal beam at concourse level casting
work is in progress. Column from Concourse Level to Platform Level and Cross Beam at Platform and Rail
Level is under progress at Nayandahalli Station, BGUC, Jnanabharathi Station. Portal Cross Beam at BGUC
completed at concourse level and nine numbers at Pattanagere Station casting is completed, three numbers
Portal Beam at Concourse Level is casted at Nayandahalli and six numbers at Rajarajeshwarinagar Station.
Phase1 incomplete Portal Pier No 438 B Pier has casted.
220 KV High Tension Tower line has been shifted from P457 & P473 and piling work also completed for this
pier.
Precast concrete works of Segment Casting, I Girder Casting under Progress at Casting Yard. Parapet casting work is under progress at casting yard. Piling work 100% completed in all the four stations. Nayandahalli, Rajarajeshwari, Jnanabharathi and Pattanagere station. The site office for field work has been established at Deepanjalinagar Property Development area.
59 Nos of Span Segment Casting is completed for Viaduct
LG – 1 = Segment Erection work is under progress and Twenty seven numbers of Spans erected.
LG – 2 = Segment erection work is under progress and Twenty Five Span erected from P571.
Physical progress completed as on October 2017 is as below :
Sl
No
Description
Viaduct
Stations
Total
Nos Nayandahalli
(NYH)
Rajarajeshwarinagar
(RRN)
Jnanabharathi
(JNB)
Pattanagere
(PTN)
1 Test Pile 2 1 1 1 1 6
2 Initial Vertical Pile load test
2 1 1 1 1 6
3 Pile-1200 mm dia 596 108 108 90 108 1010
4 Pile-600 mm dia —- 95 88 81 91 355
5 Pile Cap-Viaduct 127 25 25 27 27 231
6 Pile Cap-Off Road — 20 2 16 04 42
7 Pier—Viaduct 110 31 31 33 36 241
8 Portal beam at concourse level
1
7
8
11
12
39
9 Column at Concourse Level
—
6
12
33
25
76
10 Portal beam at Platform Level
— 1 1
7 1
10
11 Crash Barrier 81 5 6 — — 92
12 Segment Erection 57 — — — — 57
13 Segment 711 — —- — — 711
14 Parapet 761 — — —- — 761
15 I-Girder Pre Tension (Concourse Level)
—
2
76
52
40
170
16 I-Girder-Pre Tension (Platform Level)
— 17 40 35 33 125
17 I-Girder Post Tension —- 1 33 14 —- 48
18 I-Girder Erection — — — 27 — 27
I Girder Erection work is in progress at
Jnanabharathi Station at Reach-2A of
Phase-2
Road relaying work is in progress at Nayandahalli
Station at Reach 2A of Phase-2
Portal Beam Concreting work is in progress at
Reach 2A of Phase-2
Road Work near P560 Left Hand Side (LHS) at Viaduct at Reach-2A of Phase-2
Segment sand blasting work is in progress at Casting Yard at Reach-2B of Phase-2
REACH-2Extension-Reach-2B:- Construction of Elevated Structures (Viaduct) of length of
4.869 Kms. (approx.) from Pattanagere Station (excluding) to beginning of Challagatta Depot including 2 Nos of Elevated Metro Stations viz. Mailasandra Station and Kengeri Station in the extension on west side of E-W Corridor on Bangalore Metro Rail Project, Phase – 2
Name of the Contractor :- M/s Soma Enterprise Limited,
Total Cost of the Project :- Rs. 332.00 Crores
Land Acquisition:- The land acquisition for Reach-2B from Pattanagere Station to Kengeri Arch Bridge is
complete and the land is in position with BMRCL. From Kengeri Arch Bridge to Challaghatta Depot the preliminary
notification for acquisition has been issued for Joint Measurement is in progress.
Building Condition Study & Structural Analysis:- The work has been awarded to M/s Civil Aid Techno
Clinic Pvt Ltd. and the work has been completed from Pattanagere Station to Kengeri Arch Bridge and from
Kengeri Arch Bridge to Challaghatta the work is in progress.
Demolition of Buildings / Structures Identified for Acquisition:- The work has been awarded to M/s Binyas
Contech Pvt Ltd and M/s Sai Retro Fabs. The work has been completed from Pattanagere station to Kengeri Arch
Bridge and from Kengeri Arch Bridge the work will commence after acquisition of properties.
Road Widening Works:- From Pattanagere Station to NICE Road the Road Widening work has been
started by National Highway PWD Karnataka. 97% of the work is completed.
Viaduct & Stations:- The construction of 4.869 KMs Viaduct and Stations has been awarded to M/s SOMA
Enterprises Limited and the work is in progress.
Test Pile :- Two numbers of Initial Vertical Pile Load test is completed for the Viaduct. Barricading work is
in progress. Working Pile:- The work is in progress.
Casting Yard at Kanminike near Bidadi:- Two numbers of Batching Plant, Segment Casting Bed is in
progress. The site office for field work has been established at Deepanjalinagar, Property Development area. All
other preliminary works is under progress.
REACH WISE PROGRESS OF WORKS OF PHASE-II
Span Segment lifting work is in progress at Reach-2B
of Phase-2
Physical progress for the month of October 2017 is as below:
REACH-3Extension-Reach-3C:- Extension line of Reach-3b of Phase-1 on Northern Corridor from
Hessaraghatta Cross to Bangalore International Exhibition Centre (BIEC) viz
Manjunathanagara Stn., Jindal Stn., & BIEC Stn. The section length is 3.77 Kms with
3 Stations and fully Elevated Section.
Name of the Contractor :- M/s Simplex Infrastructures Limited.
Total Cost of the Project :- ` 298.65 Crores, Letter of Acceptance is issued on 27.02.2017.
Land Acquisition:- Payment of compensation towards acquired land and taking over of land by KIADB is
under progress. Handing over of land to the Engineering section part by part is under progress. Out of 62 private
properties, 39 Nos. of properties are handed over to Engineering section for execution of work. 31 properties are
clear from any issues.
Demolition of Buildings / Structures Identified for Acquisition:- The work of demolition of buildings has
been awarded to M/s. SAI Retro Fabs for the entire stretch. Out of 54 properties to be demolished 18 properties
have been demolished.
Viaduct & Stations (including Road Widening works):- Issue of GFC drawings is in progress from the
Design wing of BMRCL. The process for obtaining permission for use of NHAI service road/ROW for construction
of viaduct and stations of Bangalore Metro Rail is under progress, with NHAI.
REACH WISE PROGRESS OF WORKS OF PHASE-II
Sl No
Particulars
Unit
Viaduct
Stations
Total Nos Mailasandra Kengeri
1 Barricade Erection Nos 2450 100 140 2790
2 Initial Vertical Pile Load Test Nos 2 — — 2
3 Initial Lateral Pile Load Test Nos 2 — — 2
4 Piles Nos 596 — 60 656
5 Pile Cap Nos 94 — 9 103
6 Segment Casting Nos 618 — — 618
7 Secant Piles Nos —- 101 — 101
8 Pier & Pier Cap Nos 57 —- 9 66
9 Raft foundation concrete Rmt — 135 — 135
10 Upper Basement Slab Rmt — 135 — 135
11 Ground Floor Slab Rmt — 135 — 135
12 Concourse Slab Rmt — 45 — 45
13 I-Girder Casting (Post Tension) Nos 8 19 — 27
14 I-Girder Casting (Pre Tension) Nos — — 21 21
15 Parapet Casting Nos 53 — — 53
16 Segment Erection Span 12 — — 12
Notice to proceed to start the work has been issued on 27.04.2017 to the contractor, M/s. Simplex Infrastructures
Limited.
Development of casting yard is under progress. Project office of Simplex is ready at casting yard. Quality lab
set up has been completed and calibration of equipment's completed. Erection of one no. of batching plant is
complete and its calibration completed. Bed preparation for gantry is complete and gantry (15MT) erection is
under progress. Preparation of segment casting beds is under progress.
Fabrication of 165 Numbers of barricading boards are completed of which 96 boards are erected at
Manjunathnagar work site.
Construction of drain, retaining wall, wherever necessary and cable duct works at Manjunathnagar Station is
in progress.
Construction of 100 Rmt drain at Manjunatha Nagar Station is completed except drain cover.
4 nos. of Test piles & 18 working piles at Manjunatha Nagar Station and 4 piles of viaduct are casted as on
October 2017.
Initial vertical pile load testing arrangements of 3 No’s of test pile is under progress.
17 nos. of Borehole for soil investigation is complete as on date. Fabrication of one set of segment moulds
and one set of pier and pier cap shutters are completed at fabrication work shop and ready for dispatch.
REACH WISE PROGRESS OF WORKS OF PHASE-II
15 Meter Gantry erected at the casting yard
Retaining wall works is in progress
Working Pile at Viaduct
Progress of Work for the month of October-2017
Sl.
No Description Unit
Total
Qty
Work completed
up to
Sept 2017
Target for the month of Oct
2017
Achieved during
Oct 2017
% age achieved
during the
month
Cum. Progress up to Oct
2017
Balance work to
be done
% age of
work
Done
% age work to be
Done
A) VIADUCT
1 Road Widening Works % 100 — — — — — 100 0 100
2 Piling Works Nos 370 — 4 4 100 4 366 1 99
3 Pile Cap Works Nos 94 — — — — — 94 0 100
4 Pier & Pier Cap Works Nos 94 — — — — — 94 0 100
5 Segment Casting Works Nos 828 — — — — — 828 0 100
REACH-4Extension-Reach-4B:- Construction of Elevated Structures of length 6.524 km (approx)
from Puttenahalli Cross Station to Anjanapura Township Station and further viaduct including 5 Nos. of Elevated Metro Stations Viz. Anjanapura Road Cross Station, Krishna Leela Park Station, Vajrahalli Station, Thalaghattapura Station and Anjanapura Township Station.
Name of the Contractor :- M/s Nagarjuna Constructions Company Limited.
Total Cost of the Project :- Rs. 508.86 Crores.
Viaduct & Stations:-
The work of Construction of this Project is awarded to M/s Nagarjuna Constructions Company Limited and the
work is in progress.
All Works like Barricading, Cross trenching, Piling, Pile caps, Piers and Pier caps, Road widening, Drain works
etc. are in progress along Viaduct.
Works like Drain works, Service Road and Foundation works are in progress at Anjanapura Cross Road
Station, Krishna Leela Park Station, Vajarahalli Station, Thalaghattapura Station & Anjanapura Township
Station.
698 nos of Piles out of 1028 piles are completed for Viaduct structures.
743 nos of Piles out of 830 piles are completed for Station locations.
153 nos of Pile caps out of 222 nos are completed for Viaduct structures.
129 nos of Pile caps are completed out of 320 nos for Off-road structures at Station locations.
45 nos of Pile caps are completed out of 50 nos for C-Grid at Station locations.
134 nos of Piers are completed out of 222 nos for Viaduct structures & 45 Nos of Piers upto Concourse Level
out of 50 nos are completed at Station locations.
38 nos of Pier Arm for Concourse level are completed out of 50 nos at Station locations.
36 nos of Piers above Concourse level are completed out of 50 nos at Station locations.
33 numbers of Pier Arm for Platform Level is completed out of 50 numbers at Station locations.
9 numbers of concourse slabs are completed at Station locations out of 45 numbers.