Courtyard 2 7500 Jefferson St. NE Albuquerque, NM 87109-4335 www.bhinc.com voice: 505.823.1000 facsimile: 505.798.7988 TO: Patrick Chavez, PE Storm Water Quality Engineer DATE: 9/28/2020 REPORT NUMBER: 189 PROJECT NUMBER: 20190447 PROJECT: AMAFCA Lower Bear Tributary Water Quality Improvements LOCATION: Wyoming Blvd. to Spain. North of Arroyo Del Oso Park OWNER: AMAFCA PRIME CONTRACTOR: SUB-CONTRACTORS: AUI Inc. None PROJECT MANAGER: OBSERVER: David Perko Robert Carr DATE: Monday 9/28/2020 WEATHER: High: 86°F, Low: 46°F, Clear. Wind Speed: 8mph, Gusts: 15 mph CONTRACTOR HOURS: 7:00am - 4:30pm FIELD OBSERVATIONS: 8:30am to 12:30pm VISITORS ON SITE: None Reported SUB-CONTRACTORS ON SITE: Mans construction EQUIPMENT ON SITE: AUI Inc. 1 Bobcat Mini Excavator 1 Concrete Pump Truck Hernadez 1 Golden G700 Blade 1 John Deere 644K Loader 1 Kenworth 2500 Gallon Water Truck 1 Kubota SVL 75-2 Skidster 1 Volvo 45D Compactor Smooth Drum Vibratory PERSONNEL ON SITE: Mans construction 1 Foreman 1 Operator 1 Laborer AUI Inc. 1 Superintendent 1 Foreman 2 Concrete Finisher 6 Laborer 2 Carpenter WORK DESCRIPTION: Car-1 AUI set forms for 6' wide valley gutter at Sta.26+73 LT, also set forms for 4' wide valley gutter at Sta.25+09 LT. Concrete will be placed tomorrow. Also continued with rubbing the wall on both sides of the channel. AUI's crew: 2 carpenters, 1 laborer, 3 finishers. Car-2 Man's Construction backfilled bottom of channel Sta.23+25 to Sta.23+45. Man's crew: 1 foreman, 1 operator, 4 laborers. AUI cut out spall area sections on grade wall structure at Sta.21+57. AUI crew: 3 laborers. Car-3 AUI cut out spall area sections on grade wall structures at Sta.18+96. AUI crew 3 laborers. Car-4 AUI cut out spall area sections on grade wall structures at Sta.16+36. AUI crew 3 laborers.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Courtyard 27500 Jefferson St. NEAlbuquerque, NM87109-4335www.bhinc.comvoice: 505.823.1000facsimile: 505.798.7988
TO: Patrick Chavez, PEStorm Water Quality Engineer
DATE: 9/28/2020
REPORT NUMBER: 189
PROJECT NUMBER: 20190447
PROJECT: AMAFCA Lower Bear Tributary Water QualityImprovements
LOCATION: Wyoming Blvd. to Spain. North of Arroyo DelOso Park
AUI set forms for 6' wide valley gutter at Sta.26+73 LT, also set forms for 4' wide valley gutter at Sta.25+09 LT. Concrete willbe placed tomorrow.Also continued with rubbing the wall on both sides of the channel.AUI's crew: 2 carpenters, 1 laborer, 3 finishers.
Car-2
Man's Construction backfilled bottom of channel Sta.23+25 to Sta.23+45.Man's crew: 1 foreman, 1 operator, 4 laborers.AUI cut out spall area sections on grade wall structure at Sta.21+57.AUI crew: 3 laborers.
Car-3
AUI cut out spall area sections on grade wall structures at Sta.18+96.AUI crew 3 laborers.
Car-4
AUI cut out spall area sections on grade wall structures at Sta.16+36.AUI crew 3 laborers.
IMAGES:
4' wide valley gutter Sta.25+09.
6' wide valley gutter Sta.26+73.
Car-2 spall repair for grade structure wall Sta.21+57.
Car-3 spall repair for grade structure wall Sta.18+96.
CONTRACTOR HOURS:7:00am - 4:30pmFIELD OBSERVATIONS:8:30am to 12:30pm
VISITORS ON SITE:
None Reported
SUB-CONTRACTORS ON SITE:
Mans construction
EQUIPMENT ON SITE:AUI Inc.
1 Bobcat Mini Excavator1 Golden G700 Blade1 John Deere 644K Loader1 Kenworth 2500 Gallon Water Truck1 Kubota SVL 75-2 Skidster1 Volvo 45D Compactor Smooth DrumVibratory
PERSONNEL ON SITE:Mans construction
1 Foreman1 Operator4 Laborer
AUI Inc.1 Superintendent1 Foreman2 Concrete Finisher6 Laborer2 Iron Worker
WORK DESCRIPTION:
Car-1
AUI placed concrete for 6' wide valley gutter at Sta.26+73 LT and 4' wide valley gutter at Sta.25+09 LT.BHI testing lab sampled concrete for valley gutters, concrete met job specifications.AUI crew: 2 concrete finishers, 1 laborer.AUI installing reinforcement for 6' curb to bottom of channel LT & RT.AUI crew: 1 foreman, 2 iron workers, 4 laborers.Man's Construction rubbing walls on north side of channel.Man's crew: 2 laborers.
CAR-3
Man's Construction remove previously placed erosion gravel on RT side of channel. Man's crew: 1 foreman, 2 operators.
CONTRACTOR HOURS:7:00am - 4:30pmFIELD OBSERVATIONS:8:30am to 12:30pm
VISITORS ON SITE:
None Reported
SUB-CONTRACTORS ON SITE:
Mans construction
EQUIPMENT ON SITE:AUI Inc.
1 Bobcat Mini Excavator1 Golden G700 Blade1 John Deere 644K Loader1 Kenworth 2500 Gallon Water Truck1 Kubota SVL 75-2 Skidster1 Volvo 45D Compactor Smooth DrumVibratory
PERSONNEL ON SITE:Mans construction
1 Foreman2 Operator3 Laborer
AUI Inc.1 Superintendent1 Foreman2 Concrete Finisher4 Laborer2 Iron Worker
WORK DESCRIPTION:
Car-1
AUI completed installing reinforcement and angle iron for 6" curb.AUI's crew: 1 foreman, 2 iron workers, 4 laborers, 3 carpenters.Man's construction completed rubbing the walls of the channel.Man's crew: 2 laborers.
Car-3
Man's Construction grading the bottom of channel and slopes, the mats should arrive on the job next week.Man's crew: 1 foreman, 2 operators, 1 laborer.
IMAGES:
Car-1 North side of 6" curb with reinforcement and angle iron.
Car-1 showing angle iron bolts tied to reinforcement.
AUI placed 15 cubic yards of concrete for 6" curb.Testing lab on site to test two trucks, which met job site requirements.AUI's crew: 1 foreman, 4 finishers, 4 laborer's.Man's Construction not on site.
IMAGES:
Car-1 reinforcement and angle iron installed, All debris was washed away from 6" curb area.