Due Date Planning for Complex Product Systems with Uncertain Processing Times By: Dongping Song Supervisor: Dr. C.Hicks and Dr. C.F.Earl Dept. of MMM Eng. Univ. of Newcastle upon Tyne April, 1999
28

Due Date Planning for Complex Product Systems with Uncertain Processing Times

Jan 01, 2016

Download

Documents

Due Date Planning for Complex Product Systems with Uncertain Processing Times. By : Dongping Song Supervisor : Dr. C.Hicks and Dr. C.F.Earl Dept. of MMM Eng. Univ. of Newcastle upon Tyne April, 1999. Overview. 1. Introduction 2. Literature review - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Due Date Planning for Complex Product Systems

with Uncertain Processing Times

By: Dongping Song

Supervisor: Dr. C.Hicks and Dr. C.F.Earl

Dept. of MMM Eng.

Univ. of Newcastle upon Tyne

April, 1999

Page 2: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Overview

1. Introduction

2. Literature review

3. Leadtime distribution estimation

4. Due date planning

5. Industrial case study

6. Discussion and conclusion

7. Further work

Page 3: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Introduction

Production planning

Upper level

MIddle level

Lower level

Product due date planning

Stage due date planning

Scheduling

Sequencing

Page 4: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Uncertainty in processing• disrupt the timing of material receipt

• result in deviation of completion time from due date

2

3

1

+ =

Page 5: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Introduction• Complex product system

– Assembly and product structure– Uncertain processing times– Cumulative and interacting

• Problem : setting due date in complex product systems with uncertain processing times

Page 6: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Uncertainty in complex products

1

3

4 5

6 7

2

Page 7: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Literature ReviewTwo principal research streams

[Cheng(1989), Lawrence(1995)]

• Empirical method: based on job characteristics and

shop status. Such as: TWK, SLK, NOP, JIQ, JIS

Due date(DD) = k1TWK + k2

• Analytic method: queuing networks, mathematical

programming etc. by minimising a cost function

Page 8: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Literature Review

Limitation of above research

• Both focus on job shop situations

• Empirical - rely on simulation, time consuming

in stochastic systems

• Analytic - limited to “small” problems

Page 9: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Appr. procedure for product DDAnalytical / numerical

method

Moments of two-stageleadtime

Approximate leadtimedistribution

Product due dateplanning

Page 10: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Appr. procedure for stage DD

Analytical / numericalmethod

Moments of two-stageleadtime

Approximate leadtimedistribution

Stage due dateplanning

Page 11: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

• Product structure

Simple Two Stage System

ComponentManufacturing

Assembly

11 12 1n

1

Page 12: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Planned start time S1, S1i

component 11

component 12

component 1n

assembly proc. time

assembly proc. time

component 1n

S 1S 11

S 12

S 1n

... ...

• Holding cost at subsequent stage• Resource capacity limitation• Reduce variability

Page 13: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Minimum processing time M1

Prob. density func.(PDF) Cumul. distr. func.(CDF) • Big variance may result in negative operation times

Page 14: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Analytical Result• CDF of leadtime W is:

FW(t) = 0, t<M1+S1;

FW(t) = F1(M1) FZ(t-M1) + F1FZ, t M1 + S1.where

F1 CDF of assembly processing time;

FZ CDF of actual assembly start time;

FZ(t)= 1n F1i(t-S1i)

convolution operator in [M1, t - S1];

F1FZ= F1(x) FZ(x-t)dx

Page 15: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Leadtime Distribution EstimationComplex product structure approximate method

Assumptions normally distributed processing times approximate leadtime by truncated normal distribution

(Soroush, 1999)

Page 16: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Leadtime Distribution Estimation

Normal distribution approximation Compute mean and variance of assembly start time Z and

assembly process time Q : Z, Z2 and Q, Q

2

Obtain mean and variance of leadtime W(=Z+Q):

W = Q+Z, W2 = Q

2+Z2

Approximate W by truncated normal distribution:

N(W, W2), t M1+ S1.

More moments are needed if using general

distribution to approximate

Page 17: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Due Date Planning• Achieve a specified probability

DD* by N(0, 1)

Page 18: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Due Date Planning

• Mean absolute lateness (MAL)

DD* = median

• Standard deviation lateness (SDL)

DD* = mean

• Asymmetric earliness and tardiness cost

DD* by root finding method

Page 19: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Industrial Case Study• Product structure

17 components 17 components

Stage 1

Stage 2

Stage 3

Stage 4

Stage 5

Stage 6 … … … …

Page 20: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

System parameters setting

• normal processing times• at stage 6: =7 days for 32 components,

=3.5 days for the other two.

• at other stages : =28 days

• standard deviation: = 0.1

• backward scheduling based on mean data• planned start time: 0 for 32 components and 3.5 for

other two.

Page 21: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Simulation histogram & Appr. PDF

Page 22: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Simulation histogram & Appr. PDF

Page 23: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Product Due Date

Prob. 0.50 0.60 0.70 0.80 0.90

due simu. 150.86 152.11 153.44 155.26 157.46

date appr. 151.66 152.85 154.12 155.61 157.72

• Simulation verification for product due date to achieve specified probability

Page 24: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Stage Due Dates

Stage 6 5 4 3 2 1

Due Date 8 40 72 104 135 167

Prob.achievedin simul.

90.6%

88.3%

90.8%

89.9%

91.8%

89.9%

• Simulation verification for stage due dates to achieve 90% probability

Page 25: Due Date Planning for  Complex Product Systems with Uncertain Processing Times
Page 26: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Discussion

• Minimum processing time

• Production plan

• Stage due date

Page 27: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Conclusion

• Complex product systems with uncertainty

• A procedure to estimate leadtime distribution

• Approximate method to set due dates

• Used to design planned start times

Page 28: Due Date Planning for  Complex Product Systems with Uncertain Processing Times

Further Work

• Skewed processing times

• Using more general distribution to

approximate, like -type distribution

• Resource constraint systems