Top Banner
Drainage Services Department 1 DSD New Engineering Contract Improvement of Fuk Man Road Nullah in Sai Kung CHAN Kin-kwong Assistant Director/Projects & Development 2 February 2012
21

DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Mar 31, 2018

Download

Documents

LêKhánh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Drainage Services Department

11

DSD New Engineering Contract Improvement of Fuk Man Road

Nullah in Sai Kung

CHAN Kin-kwong

Assistant Director/Projects & Development

2 February 2012

Page 2: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

2

Content

Background

NEC Administration Experience

Observations

2

Page 3: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

333

BackgroundCIRC Report 2001

Recommendations38 – wider adoption of partnering39 – integrate partnering approach into contractual relationship44 – wider adoption of alternative procurement approach (e.g., target cost)

In 2006, Government decided to try out NEC3

Page 4: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

44

Fuk Man Road Project

Improvement of Fuk Man Road Nullah in Sai KungDecking of 180m long 12m wide open nullah, road & landscaping worksContract sum $50MContract period 33 months, from Aug 2009 to May 2012

Page 5: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

DSD’s NEC ProcessOption evaluation, tender

document preparationDEVB, LAD(W), ICAC, Works

Departments

5

2007

Appoint NEC technical consultant

Briefing to contractors (PQ stage)

Briefing + Dummy Tender Ex. (Tender stage)

20082006 2009

Project selected as NEC

Documents consulted HKCA

Page 6: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

6

NEC OptionAdopt Option C– Target Cost with Activity Schedule

Pain/gain share – encourage joint problem solvingFair risk sharingOpen book accountingPopular in other countries

Gain share

Pain share (Cap at 11 0

%)

Targ

et C

ost

Targ

et C

ost

Actu

al C

ost

Actu

al C

ost

Page 7: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

7

NEC Administration Experience

7

“10.1 – The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation”

Page 8: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

8

June 2009, appointed NEC adviser for post-contract advisory service

Partnering workshops

Partnering

Joint NEC training

Page 9: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

9

Partnering

Partnering workshopsInitial Partnering Workshop – set up mutual objectives : time, budget, quality, etc

Page 10: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

1010

Partnering

Bi-monthly Champion Group MeetingProject Manager, Supervisor, ContractorReview team’s performance towards collaborative working

Pioneer GroupFrontline staff

Page 11: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

1111

Supervisor’s ARE

Contractor’s E

Partnering

Joint Site OfficePM, Supervisor, Contractor sitting close togetherFacilitate joint problem solving

Page 12: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Monitor Performance

12

Bi-monthly Champion Group Meeting

Partnering workshop held

Partnering workshop held

0 = Poor1 = Fair2 = Adequate3 = Good4 = Very Good5 = Excellent

Page 13: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Key Roles of PM

Time Clause 31.3 – Accept programmeClause 30.2 – Certify completion

CostClause 50.1 and 51.1 – Assess and certify payment

13

Project Manager

Page 14: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Management of Risks Early warningsRisk reduction meeting

CommunicationClause 13.4 – Reply to communication (within 2 weeks)Clause 13.5 – Extend period of reply if PM and Contractor agree

14

Key Roles of PM

Project Manager

Page 15: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Key Roles of PM

Management of Compensation Events(As at 15.12.2011)

15

No. of CE related correspondence (both PM and Contractor’s correspondence included)

336

Average time to reply 22 days

Average time to agree a CE (count from Contractor’s submission of quotation)

52 days

Extension of period of reply for complicated case

Project Manager

Page 16: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

16

Clause 16.1 – Early WarningThe C and PM give an early warning by notifying the other asap

PricesDelay CompletionAffect quality

Early resolution of problems

16

Contract Key Issues

Page 17: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Interim PaymentTransparent

Facilitates CEs assessment

Cost Auditing NEC AdviserDSD Staff

100% Check?

17

Contract Key Issues

Page 18: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Observations from Project Team:Collaborative working at managerial levelCulture at frontline level – Need time to changeTraining and team building – very important !!

18

Observations

Page 19: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

19

Page 20: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

20

Latest Actual Cost – $67.0MLatest Target Cost – $68.5M

Gain Share

Programme – 3 months ahead (or more!)Compensation Events

107 CEs issued81 CEs agreed, out of 93 quotations submitted (87% agreement)

Early warnings15 Early Warning Notices, all resolved

Finalization – Expected to be 2 / 3 months after completion

Observations

Page 21: DSD New Engineering Contract Improvement of Fuk …cv.hkie.org.hk/DocDown.aspx?imgDoc=20_20120202+NEC+workshop+2...DSD New Engineering Contract Improvement of Fuk Man Road ... road

Drainage Services Department

2121

~ Thanks! ~