Ministry of Transport, Maritime Affairs and Communications
of the Republic of Turkey
2nd Meeting of the Working Group on Dry Ports
-Dry Ports Structuring in Turkey-
Bülent SÜLOĞLU
Head
DG for Dangerous Goods and Combined Transport
Bangkok, 14-15 November 2017
THE CONCEPT OF DRY PORTS
Rising container flows, Crowded terminals at sea-port areas,
Prolonged dwell times for containers, Neccessity to expand,
Expansion is too costly due to prices for land
UNECE Definition: a Dry Port is simply « an inland terminal which is directly linked
to a maritime port.»
The objectives of dry ports are to enhance the maritime business…
Another definition that captures the essence of the concept of Dry ports;
« An inland intermodal terminal directly connected to seaport with high capacity
transport mean, where customers can leave/pick up their standardised units
as if directly to a seaport.»
It is a maritime-centric issue!!!
THE EVOLUTION OF DRY PORTS CONCEPT IN TURKEY
A platform further promote rail-based freight operations (rail-centric)
The idea is to increase the share of rail transport services dedicated
to seaports
In 2016, total cargo transported via rail amounted to 29 million tons of
which 10 million tons were hauled in containers.
2023 Targets: 76 million ton cargo to be transported by rail.
LOGISTICS CENTERS/INTERMODAL FREIGHT TERMINALS
21 logistics centers with rail connections enabling freight shift from road to rail.
8 out of 21 are functioning for the time being.
Additionally 34 million ton capacity and 10 million m2 stocking and handling
area for container transport
NATIONAL TRANSPORT MASTER PLANHOW TO APPROACH DRY PORT CONCEPT
• National Transport Master Plan (NTMP) process started in October 2015 and isexpected to complete by the end of the current year 2017.
• How Dry Ports are being handled within the process of NTMP?
• Dry ports must be connected by rail.
• Dry ports are designed to handle unitized Cargo.