7/28/2019 Drilling+Efficiency
1/40
Drilling Efficiency
7/28/2019 Drilling+Efficiency
2/40
About This Program This program was developed by the drilling
personnel of Global Marine UK Drilling Co.as a consequence of GM UK being awardeda five well turnkey job for Fina Oil and afour well incentive alliance drilling program,
both in the UK North Sea.
The program was developed with the ideathat working efficiently would reduce the
time and costs of drilling the wells withoutcompromising safety or causing damage tothe drilling equipment.
7/28/2019 Drilling+Efficiency
3/40
Drilling Efficiency Overview
The Concept Consists of the Following:
Morning Meetings
Meetings are not more that 20 minutes Should involve drilling contractor supervisors, all
Operator representatives and third party personnel that
will be involved in the drilling program for that day
Meetings should be a daily program
7/28/2019 Drilling+Efficiency
4/40
Drilling Efficiency Overview
Continued Tool Box Meetings
Crew level meetings, i.e. driller and drill crew,crane operator and roustabout crew,mechanic/chief engineer and maintenance crew.
Checklists
Needs to cover the activities of that day.
Needs to cover all aspects of the job.
Needs to assign a person responsible.
Allows the responsible person to sign off thatthe job has been done.
7/28/2019 Drilling+Efficiency
5/40
Drilling Efficiency Overview
Continued Written Instructions
Write instructions for all critical procedures.
Must be short and cover routine as well as non-routine jobs.
Involves the input of the operator, drilling
contractor supervisors and third party personnel
as appropriate.
7/28/2019 Drilling+Efficiency
6/40
SampleWritten InstructionsNow that the 26 hole has been drilled, it is time to run the 20 casing. All tools, etc. required for this operation havebeen prepared in accordance with the checklist for Running 20 Casing. The casing has been measured ahead of timeand a running list will be made out. The casing running list, usually made out by the operators drilling supervisor orengineer, is basically a list defining the correct order in which the casing is to be ran.
The first joint to be picked up is the shoe joint. The bottom 10 15 is painted white to aid visibility when entering the30 housing. A rotating ring is attached to this joint, about 10-12 feet from the bottom, for guide ropes.
When the shoe joint is picked up, water is pumped into it to test the integrity of the shoe. The shoe is basically a nonreturn valve. When the shoe joint is confirmed to be in good working order and is lowered through the rotary, the guideropes can be secured from the rotating ring to the guide lines. These guide ropes act as a guide for entering the 30housing. Now all of the remaining intermediate joints can be ran. After these joints have been ran, it is time to pick upthe 18 3/4 wellhead housing. Depending on the operator, the housing may already be made up and standing in thederrick, or the running tool will have been installed on deck.
Before picking up the wellhead housing it is good practice to count the joints of casing remaining on deck to confirm thetotal joints ran reflects the the running list. With the wellhead resting on the rotary table, a third party engineer willcheck operation of the running tool. With the running tool checked and reinstalled, the complete casing string is ran ondrill pipe (landing string). Prior to stabbing the 30 housing, the compensator should be unlocked and put in mid stroke.The ROV should be present on the seabed to aid in stabbing. The last stand of the landing string will have a crossoverfrom the pipe connection to a 2A weco union fitted on top. The landing string will have been spaced out so that the
wellhead when landed in the 30 will have approximately 10-20 feet of pipe sticking up above the rotary. Once thewellhead is landed, a 20,000 lbs. over pull will be taken to ensure engagement of the latch ring that connects thewellhead to the 30 housing.
Satisfied that the latch has connected, a circulating line from the mud pumps/cement line can be rigged up. All of theequipment required for the cement job will have been checked according to the checklist Cement 20 casing
Once the circulating line has been hooked up, it is customary to to pump at least the volume of the casing using either therig mud pump or the cement pump. When pumping is complete, the cement unit will be lined up to the circulating line,etc., etc., etc.
7/28/2019 Drilling+Efficiency
7/40
Drilling Efficiency Overview
Continued
Critical Path Planning
Needs to be done for all rig activities.
Best to use Gantt charts or pert charts. Best to use Microsoft Project Manager.
Identification of tools and equipment to facilitate the
drilling program, i.e. rotating mousehole, step on
slips, automatic driller, iron roughneck, E-Z torque,etc.
7/28/2019 Drilling+Efficiency
8/40
Overview Continued
Identifying Constraints in the drilling process
Identification of the limitations of the drilling
process, i.e. tools, equipment, personnel,training, shorebase management, third party
equipment and services, etc.
Problem identification and problem solving
7/28/2019 Drilling+Efficiency
9/40
Some Grade School Management
Concepts
Develop Clear Objectives.
Clearly Communicate the Importance of
Achieving the Objectives.
Make a plan to achieve the objectives.
Successfully implement the plan.
A goal without a plan is but a dream
7/28/2019 Drilling+Efficiency
10/40
Some Common Goals of the
Operator and Contractor
Safety
Downtime Control
Good Food
Clean Rig
7/28/2019 Drilling+Efficiency
11/40
Some not so Common Goals
Operator - Drill the well on or under budget. Contractor - Operate the rig under budget.
Operator - Drill the well as fast as possible.
Contractor - Keep the rig on contract as longas possible.
Operator - Find a suitable rig for the lowestdayrate possible.
Contractor - Find a job for the rig with thehighest dayrate possible.
7/28/2019 Drilling+Efficiency
12/40
Drilling Efficiency
Unfortunately, contract drilling is one of the fewindustries in which the service provider does not
consistently identify with the clients objectives.Contractors usually do not develop a plan to meetthe clients objectives.
Contractors need to:
Identify the clients objectives. Establish a goal to meet the clients objectives.
Formulate a plan to meet the clients objectives.
Execute the plan to achieve the clients objectives.
7/28/2019 Drilling+Efficiency
13/40
Good Plans / Bad Plans If the goal is to meet or beat the drilling time curve,
a bad plan to achieve this goal would be: Run the mud pumps to 130 SPM
Run the mud pumps to 4800 PSI
Run the maximum weight on the bit by running the drill
pipe in compression.
Run the blocks up and down as fast as possible while
tripping or making a connection.
Move the rig with a full load of liquid mud, casing, drill
pipe in the derrick, etc.
Compromise safety by getting in a hurry.
Cause damage to the rig equipment by exceeding the
equipment limitations.
7/28/2019 Drilling+Efficiency
14/40
Good Plans / Bad Plans
A Bad Plan Will:
Compromise safety for speed.
Will also eventually cause damage to the rig
equipment resulting in expensive
mechanical downtime.
This is not what we want to accomplish.
7/28/2019 Drilling+Efficiency
15/40
Do We Really Need a Learning Curve?
NOWe can do it: The First Time - On
Time - Every Time.
7/28/2019 Drilling+Efficiency
16/40
Critical Path Planning
Identify the critical path.
Do good task analysis.
The drilling program should be a planned project.
It is not a daily episode, waiting on a crisis.
Managing the past or planning the future.
What is a poorly planned round trip?
What is a well planned round trip?
7/28/2019 Drilling+Efficiency
17/40
Task Analysis
Start / Start
Task 1
Task 2 Task 3
Finish / Finish
Task 1
Task 2
Task 3
7/28/2019 Drilling+Efficiency
18/40
Task Analysis
Finish / Start
Task 1
Task 2
Task 3
Lead Time
Task 1 Task 2
Task 3
7/28/2019 Drilling+Efficiency
19/40
Task Analysis
Lag Time
Task 1
Task 2
Task 3
T k R l i U i Mi f
7/28/2019 Drilling+Efficiency
20/40
Task Relations Using Microsoft
Project Manager
7/28/2019 Drilling+Efficiency
21/40
Critical Path Planning
Drilling a Well is a Project
We Recommend Using Microsoft Project Manager.
And, Using a Gantt Chart for Following the Critical
Path.
What is a Critical Path?
A critical path is the linking of tasks that must be done on
a Finish/Start or a Lead Time Relation.
S l G tt Ch t P U i Mi ft P j t M
7/28/2019 Drilling+Efficiency
22/40
Sample Gantt Chart Page Using Microsoft Project Manager
S l G tt Ch t P f S i b ibl
7/28/2019 Drilling+Efficiency
23/40
Sample Gantt Chart Page for Semisubmersible
7/28/2019 Drilling+Efficiency
24/40
Critical Path Planning
If a task has a Finish/Finish or a Start/Start
Relation, then it should be on a checklist.
7/28/2019 Drilling+Efficiency
25/40
Planning Meeting A planning meeting should be held daily.
It should be only 15 - 20 minutes long.
Who Should Attend?
Contractor Supervisors
Operator Supervisors Third Party Personnel as Appropriate
What Should Be Discussed?
Critical path planning
Checklists
Narratives (Written Plans)
Review Potential Problems and Discuss Safety
7/28/2019 Drilling+Efficiency
26/40
Bad Trip - No Planning Drilling
Mix Slug
Pump Slug Pull Out of Hole
Call Drilling Supt for Bit Info Bring Bit to Floor
Bring Pliers & Jets to Floor
Install Jets Call Drilling Sup for BHA Info
Drilling Supt Calls Shorebase
Shorebase Calls Directional Co.
Shorebase Calls Rig
Bring Subs to Floor
Rig Down Old BHA Pick up New BHA
Double Handle BHA
RIH
Total = 22.75 Hours
7/28/2019 Drilling+Efficiency
27/40
Good Trip - Well Planned Drilling
Mix Slug
Pump Slug Pull Out of Hole
Call Drilling Supt for Bit Info Bring Bit to Floor
Bring Pliers & Jets to Floor
Install Jets Call Drilling Supt for BHA Info
Drilling Supt Calls Shorebase
Shorebase Calls Directional Co.
Shorebase Calls Rig
Bring Subs to Floor
Rig Down Old BHA Pick up New BHA
RIH
Total = 13 Hours
Bad Trip Using Microsoft Project Manager
7/28/2019 Drilling+Efficiency
28/40
Bad Trip Using Microsoft Project Manager
ID Task Name Durati
1 Dril l ing 1 h
2 Mix Slug 1 h3 Pump Slug 0.5 hr
4 Pull Out Of Hole 4 hrs
5 Call Dri l l ing Sup For Bit I 0.25 hr
6Bring Bit To Floor 0.5 hr
7 Bring P liers & Jets To Fl 0 .5 hr
8 Install Jets 0.5 hr
9 Call Drill ing Sup For BH 0.5 hr
10 Dril l ing Sup Calls Shore 1 h
11 Shorebase Cal ls Directio 1 h12 Shorebase Calls Rig 0.5 hr
13 Bring Subs To Dril l Floo 1 h
14 Rig Down Old BHA 2 hrs
15Pick Up New Bit 0.5 hr
16 Pick Up New BHA 2 hrs
1 2 3 4 5 6 7 8 9 10 11 12
Good Trip Planning Using Microsoft Project Manager
7/28/2019 Drilling+Efficiency
29/40
ID Task Name Duration
1 Drilling 6 hrs
2 Mix Slug 1 hr3 Pump Slug 0.5 hrs
4 Pill Out Of Hole 4 hrs
5 Call Drilling Sup For Bit Info 0.25 hrs
6 Bring Bit To Floor 0.5 hrs
7 Bring Pliers & Jets To Floor 0.5 hrs8 Ins tall Jets 0.5 hrs
9 Call Drilling Sup For BHA Info 0.5 hrs
10 Drilling Sup Calls Shorebase 1 hr
11 Shorebase Calls D irectional Co 1 hr
12
Shorebase Ca lls Rig0.5 hrs
13 Bring Subs To Drill Floor 1 hr
14 Rig Down Old BHA 2 hrs
15 Pick Up New Bit 0.5 hrs
16 Pick Up New BHA 2 hrs
17
RIH4 hrs
18 Total 13 Hrs 0 days
4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9
Mon May 1
Good Trip Planning Using Microsoft Project Manager
7/28/2019 Drilling+Efficiency
30/40
Good Trip / Bad Trip Costs No. of Hours - Good Planning Bad Planning
Mix Slug 00.0 1.00
Pump Slug 00.5 0.50
Pull Out of Hole 4.00 4.00
Call Drilling Supt for Bit Info 00.0 0.25 Bring Bit to Floor 0.00 0.50
Bring Pliers & Jets to Floor 0.00 0.50
Install Jets 0.00 0.50
Call Drilling Supt for BHA Info 0.00 0.50
Drilling Supt Calls Shorebase 0.00 1.00
Shorebase Calls Directional Co. 0.00 1.00
Shorebase Calls Rig 0.00 0.50
Bring Subs to Floor 0.00 1.00
Rig Down Old BHA 2.00 2.00
Pick up New BHA 0.50 0.50
Double Handle BHA 0.00 3.00
RIH 4.00 4.00
Total = 13.0 Hrs 22.75 Hrs
At 100,000/Day Spread Cost = $54,166 $94,791
The bad trip cost was $40,625
7/28/2019 Drilling+Efficiency
31/40
Good Task / Bad Task
Relationship
Just as we have a good trip/bad trip
situation, we also have a good cementing
operation/bad cementing operation, goodnipple up/bad nipple up, etc.
We can reduce the time for any project by
changing the task relationships or by notdoing the task at all.
7/28/2019 Drilling+Efficiency
32/40
Checklists
What is a checklist task and what is a
critical path task?
A critical path task is a task that must be done
in sequence. It must be done as a lead time
relation or a finish/start relation.
A checklist item is a task that must be done butcan be taken off the critical path and made into
a finish/finish or a start/start relation.
7/28/2019 Drilling+Efficiency
33/40
Checklists
Checklists
Should be job specific
Should be rig specific
Are basic outlines
Should address potential problems
Should be a live system, i.e. readily changeable
Jackup Drilling Rig Equipment and Procedures ChecklistChecklist
7/28/2019 Drilling+Efficiency
34/40
Jackup Drilling Rig Equipment and Procedures Checklist
Operation: Tripping
OPERATOR: WELL: RIG: DATE:
ITEM CHECKS ASSIGNED INITIALS
Pre - Trip
Equipment
Checks
The following are to be completed prior to
tripping drill pipe.
Person or
title
When
completed
Tongs Check and replace tong dies as necessary
Check for spare tong dies
Check jaws
Check and repair/replace retainer
bolts/pins as required.
Iron Roughneck Check & replace worn/slick dies
Inspect hydraulic/hoses/couplings forleaks and damage
Check operation
Spinning wrench Check operation
Check and replace worn dies
Check hydraulic hoses/couplings for leaks
& damage.
D.P. Elevators Check & repair worn retainer bolts on
ears.
D.C. Elevators Check & repair worn retainer bolts on
ears
Check & repair retainer bolts
Link arms and
link ears
Check for excessive wear and cracks
Traveling block
hook & bail
Check for cracks and excessive wear
Master bushing
and slips
Check fit and check for wear.
Checklist
Sample
Portion
7/28/2019 Drilling+Efficiency
35/40
Checklists
Pre-operations start-up
Prepare to spud
Drive Pipe
Drill conductor hole
Run conductor casing
Cement conductor casing Grout conductor casing (Top Job)
Grout conductor (With BOP Installed)
7/28/2019 Drilling+Efficiency
36/40
Checklists
Install Diverter System Drill surface hole (17 1/2)
Under-ream surface hole
Run surface casing Cement surface casing
Install wellhead
Nipple up BOPs
Test BOPs
Drill intermediate hole (12 1/4)
7/28/2019 Drilling+Efficiency
37/40
Checklists
Establish shut in procedure
Establish kill procedure
Logging operations
Run intermediate casing (9 5/8)
Cement intermediate casing Install casing spool
Install and nipple up BOPs
7/28/2019 Drilling+Efficiency
38/40
Checklists
Drill production hole (8 1/2)
Run production casing
Run production liner
Cement casing
Cement liner Set P&A plugs
Cut and retrieve casings
7/28/2019 Drilling+Efficiency
39/40
Review of Drilling Efficiency
Drilling Efficiency is:
Controlling costs by working efficiently (Reducing the time ittakes to drill a well).
Critical path planning.
Using Checklists.
Holding a daily planning meeting. Holding toolbox meetings.
Using narrative (written) instructions.
Identifying tools and equipment to facilitate the drilling program,i.e. rotating mousehole, auto driller etc.
Identify Constraints, i.e. solids control equipment, rig power,pumps, etc. rig crews, shorebase management, training, etc.
Utilizing constructive criticism, i.e. Report Card with feedback.
7/28/2019 Drilling+Efficiency
40/40