Top Banner

of 40

Drilling+Efficiency

Apr 03, 2018

Download

Documents

ipm1234
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/28/2019 Drilling+Efficiency

    1/40

    Drilling Efficiency

  • 7/28/2019 Drilling+Efficiency

    2/40

    About This Program This program was developed by the drilling

    personnel of Global Marine UK Drilling Co.as a consequence of GM UK being awardeda five well turnkey job for Fina Oil and afour well incentive alliance drilling program,

    both in the UK North Sea.

    The program was developed with the ideathat working efficiently would reduce the

    time and costs of drilling the wells withoutcompromising safety or causing damage tothe drilling equipment.

  • 7/28/2019 Drilling+Efficiency

    3/40

    Drilling Efficiency Overview

    The Concept Consists of the Following:

    Morning Meetings

    Meetings are not more that 20 minutes Should involve drilling contractor supervisors, all

    Operator representatives and third party personnel that

    will be involved in the drilling program for that day

    Meetings should be a daily program

  • 7/28/2019 Drilling+Efficiency

    4/40

    Drilling Efficiency Overview

    Continued Tool Box Meetings

    Crew level meetings, i.e. driller and drill crew,crane operator and roustabout crew,mechanic/chief engineer and maintenance crew.

    Checklists

    Needs to cover the activities of that day.

    Needs to cover all aspects of the job.

    Needs to assign a person responsible.

    Allows the responsible person to sign off thatthe job has been done.

  • 7/28/2019 Drilling+Efficiency

    5/40

    Drilling Efficiency Overview

    Continued Written Instructions

    Write instructions for all critical procedures.

    Must be short and cover routine as well as non-routine jobs.

    Involves the input of the operator, drilling

    contractor supervisors and third party personnel

    as appropriate.

  • 7/28/2019 Drilling+Efficiency

    6/40

    SampleWritten InstructionsNow that the 26 hole has been drilled, it is time to run the 20 casing. All tools, etc. required for this operation havebeen prepared in accordance with the checklist for Running 20 Casing. The casing has been measured ahead of timeand a running list will be made out. The casing running list, usually made out by the operators drilling supervisor orengineer, is basically a list defining the correct order in which the casing is to be ran.

    The first joint to be picked up is the shoe joint. The bottom 10 15 is painted white to aid visibility when entering the30 housing. A rotating ring is attached to this joint, about 10-12 feet from the bottom, for guide ropes.

    When the shoe joint is picked up, water is pumped into it to test the integrity of the shoe. The shoe is basically a nonreturn valve. When the shoe joint is confirmed to be in good working order and is lowered through the rotary, the guideropes can be secured from the rotating ring to the guide lines. These guide ropes act as a guide for entering the 30housing. Now all of the remaining intermediate joints can be ran. After these joints have been ran, it is time to pick upthe 18 3/4 wellhead housing. Depending on the operator, the housing may already be made up and standing in thederrick, or the running tool will have been installed on deck.

    Before picking up the wellhead housing it is good practice to count the joints of casing remaining on deck to confirm thetotal joints ran reflects the the running list. With the wellhead resting on the rotary table, a third party engineer willcheck operation of the running tool. With the running tool checked and reinstalled, the complete casing string is ran ondrill pipe (landing string). Prior to stabbing the 30 housing, the compensator should be unlocked and put in mid stroke.The ROV should be present on the seabed to aid in stabbing. The last stand of the landing string will have a crossoverfrom the pipe connection to a 2A weco union fitted on top. The landing string will have been spaced out so that the

    wellhead when landed in the 30 will have approximately 10-20 feet of pipe sticking up above the rotary. Once thewellhead is landed, a 20,000 lbs. over pull will be taken to ensure engagement of the latch ring that connects thewellhead to the 30 housing.

    Satisfied that the latch has connected, a circulating line from the mud pumps/cement line can be rigged up. All of theequipment required for the cement job will have been checked according to the checklist Cement 20 casing

    Once the circulating line has been hooked up, it is customary to to pump at least the volume of the casing using either therig mud pump or the cement pump. When pumping is complete, the cement unit will be lined up to the circulating line,etc., etc., etc.

  • 7/28/2019 Drilling+Efficiency

    7/40

    Drilling Efficiency Overview

    Continued

    Critical Path Planning

    Needs to be done for all rig activities.

    Best to use Gantt charts or pert charts. Best to use Microsoft Project Manager.

    Identification of tools and equipment to facilitate the

    drilling program, i.e. rotating mousehole, step on

    slips, automatic driller, iron roughneck, E-Z torque,etc.

  • 7/28/2019 Drilling+Efficiency

    8/40

    Overview Continued

    Identifying Constraints in the drilling process

    Identification of the limitations of the drilling

    process, i.e. tools, equipment, personnel,training, shorebase management, third party

    equipment and services, etc.

    Problem identification and problem solving

  • 7/28/2019 Drilling+Efficiency

    9/40

    Some Grade School Management

    Concepts

    Develop Clear Objectives.

    Clearly Communicate the Importance of

    Achieving the Objectives.

    Make a plan to achieve the objectives.

    Successfully implement the plan.

    A goal without a plan is but a dream

  • 7/28/2019 Drilling+Efficiency

    10/40

    Some Common Goals of the

    Operator and Contractor

    Safety

    Downtime Control

    Good Food

    Clean Rig

  • 7/28/2019 Drilling+Efficiency

    11/40

    Some not so Common Goals

    Operator - Drill the well on or under budget. Contractor - Operate the rig under budget.

    Operator - Drill the well as fast as possible.

    Contractor - Keep the rig on contract as longas possible.

    Operator - Find a suitable rig for the lowestdayrate possible.

    Contractor - Find a job for the rig with thehighest dayrate possible.

  • 7/28/2019 Drilling+Efficiency

    12/40

    Drilling Efficiency

    Unfortunately, contract drilling is one of the fewindustries in which the service provider does not

    consistently identify with the clients objectives.Contractors usually do not develop a plan to meetthe clients objectives.

    Contractors need to:

    Identify the clients objectives. Establish a goal to meet the clients objectives.

    Formulate a plan to meet the clients objectives.

    Execute the plan to achieve the clients objectives.

  • 7/28/2019 Drilling+Efficiency

    13/40

    Good Plans / Bad Plans If the goal is to meet or beat the drilling time curve,

    a bad plan to achieve this goal would be: Run the mud pumps to 130 SPM

    Run the mud pumps to 4800 PSI

    Run the maximum weight on the bit by running the drill

    pipe in compression.

    Run the blocks up and down as fast as possible while

    tripping or making a connection.

    Move the rig with a full load of liquid mud, casing, drill

    pipe in the derrick, etc.

    Compromise safety by getting in a hurry.

    Cause damage to the rig equipment by exceeding the

    equipment limitations.

  • 7/28/2019 Drilling+Efficiency

    14/40

    Good Plans / Bad Plans

    A Bad Plan Will:

    Compromise safety for speed.

    Will also eventually cause damage to the rig

    equipment resulting in expensive

    mechanical downtime.

    This is not what we want to accomplish.

  • 7/28/2019 Drilling+Efficiency

    15/40

    Do We Really Need a Learning Curve?

    NOWe can do it: The First Time - On

    Time - Every Time.

  • 7/28/2019 Drilling+Efficiency

    16/40

    Critical Path Planning

    Identify the critical path.

    Do good task analysis.

    The drilling program should be a planned project.

    It is not a daily episode, waiting on a crisis.

    Managing the past or planning the future.

    What is a poorly planned round trip?

    What is a well planned round trip?

  • 7/28/2019 Drilling+Efficiency

    17/40

    Task Analysis

    Start / Start

    Task 1

    Task 2 Task 3

    Finish / Finish

    Task 1

    Task 2

    Task 3

  • 7/28/2019 Drilling+Efficiency

    18/40

    Task Analysis

    Finish / Start

    Task 1

    Task 2

    Task 3

    Lead Time

    Task 1 Task 2

    Task 3

  • 7/28/2019 Drilling+Efficiency

    19/40

    Task Analysis

    Lag Time

    Task 1

    Task 2

    Task 3

    T k R l i U i Mi f

  • 7/28/2019 Drilling+Efficiency

    20/40

    Task Relations Using Microsoft

    Project Manager

  • 7/28/2019 Drilling+Efficiency

    21/40

    Critical Path Planning

    Drilling a Well is a Project

    We Recommend Using Microsoft Project Manager.

    And, Using a Gantt Chart for Following the Critical

    Path.

    What is a Critical Path?

    A critical path is the linking of tasks that must be done on

    a Finish/Start or a Lead Time Relation.

    S l G tt Ch t P U i Mi ft P j t M

  • 7/28/2019 Drilling+Efficiency

    22/40

    Sample Gantt Chart Page Using Microsoft Project Manager

    S l G tt Ch t P f S i b ibl

  • 7/28/2019 Drilling+Efficiency

    23/40

    Sample Gantt Chart Page for Semisubmersible

  • 7/28/2019 Drilling+Efficiency

    24/40

    Critical Path Planning

    If a task has a Finish/Finish or a Start/Start

    Relation, then it should be on a checklist.

  • 7/28/2019 Drilling+Efficiency

    25/40

    Planning Meeting A planning meeting should be held daily.

    It should be only 15 - 20 minutes long.

    Who Should Attend?

    Contractor Supervisors

    Operator Supervisors Third Party Personnel as Appropriate

    What Should Be Discussed?

    Critical path planning

    Checklists

    Narratives (Written Plans)

    Review Potential Problems and Discuss Safety

  • 7/28/2019 Drilling+Efficiency

    26/40

    Bad Trip - No Planning Drilling

    Mix Slug

    Pump Slug Pull Out of Hole

    Call Drilling Supt for Bit Info Bring Bit to Floor

    Bring Pliers & Jets to Floor

    Install Jets Call Drilling Sup for BHA Info

    Drilling Supt Calls Shorebase

    Shorebase Calls Directional Co.

    Shorebase Calls Rig

    Bring Subs to Floor

    Rig Down Old BHA Pick up New BHA

    Double Handle BHA

    RIH

    Total = 22.75 Hours

  • 7/28/2019 Drilling+Efficiency

    27/40

    Good Trip - Well Planned Drilling

    Mix Slug

    Pump Slug Pull Out of Hole

    Call Drilling Supt for Bit Info Bring Bit to Floor

    Bring Pliers & Jets to Floor

    Install Jets Call Drilling Supt for BHA Info

    Drilling Supt Calls Shorebase

    Shorebase Calls Directional Co.

    Shorebase Calls Rig

    Bring Subs to Floor

    Rig Down Old BHA Pick up New BHA

    RIH

    Total = 13 Hours

    Bad Trip Using Microsoft Project Manager

  • 7/28/2019 Drilling+Efficiency

    28/40

    Bad Trip Using Microsoft Project Manager

    ID Task Name Durati

    1 Dril l ing 1 h

    2 Mix Slug 1 h3 Pump Slug 0.5 hr

    4 Pull Out Of Hole 4 hrs

    5 Call Dri l l ing Sup For Bit I 0.25 hr

    6Bring Bit To Floor 0.5 hr

    7 Bring P liers & Jets To Fl 0 .5 hr

    8 Install Jets 0.5 hr

    9 Call Drill ing Sup For BH 0.5 hr

    10 Dril l ing Sup Calls Shore 1 h

    11 Shorebase Cal ls Directio 1 h12 Shorebase Calls Rig 0.5 hr

    13 Bring Subs To Dril l Floo 1 h

    14 Rig Down Old BHA 2 hrs

    15Pick Up New Bit 0.5 hr

    16 Pick Up New BHA 2 hrs

    1 2 3 4 5 6 7 8 9 10 11 12

    Good Trip Planning Using Microsoft Project Manager

  • 7/28/2019 Drilling+Efficiency

    29/40

    ID Task Name Duration

    1 Drilling 6 hrs

    2 Mix Slug 1 hr3 Pump Slug 0.5 hrs

    4 Pill Out Of Hole 4 hrs

    5 Call Drilling Sup For Bit Info 0.25 hrs

    6 Bring Bit To Floor 0.5 hrs

    7 Bring Pliers & Jets To Floor 0.5 hrs8 Ins tall Jets 0.5 hrs

    9 Call Drilling Sup For BHA Info 0.5 hrs

    10 Drilling Sup Calls Shorebase 1 hr

    11 Shorebase Calls D irectional Co 1 hr

    12

    Shorebase Ca lls Rig0.5 hrs

    13 Bring Subs To Drill Floor 1 hr

    14 Rig Down Old BHA 2 hrs

    15 Pick Up New Bit 0.5 hrs

    16 Pick Up New BHA 2 hrs

    17

    RIH4 hrs

    18 Total 13 Hrs 0 days

    4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9

    Mon May 1

    Good Trip Planning Using Microsoft Project Manager

  • 7/28/2019 Drilling+Efficiency

    30/40

    Good Trip / Bad Trip Costs No. of Hours - Good Planning Bad Planning

    Mix Slug 00.0 1.00

    Pump Slug 00.5 0.50

    Pull Out of Hole 4.00 4.00

    Call Drilling Supt for Bit Info 00.0 0.25 Bring Bit to Floor 0.00 0.50

    Bring Pliers & Jets to Floor 0.00 0.50

    Install Jets 0.00 0.50

    Call Drilling Supt for BHA Info 0.00 0.50

    Drilling Supt Calls Shorebase 0.00 1.00

    Shorebase Calls Directional Co. 0.00 1.00

    Shorebase Calls Rig 0.00 0.50

    Bring Subs to Floor 0.00 1.00

    Rig Down Old BHA 2.00 2.00

    Pick up New BHA 0.50 0.50

    Double Handle BHA 0.00 3.00

    RIH 4.00 4.00

    Total = 13.0 Hrs 22.75 Hrs

    At 100,000/Day Spread Cost = $54,166 $94,791

    The bad trip cost was $40,625

  • 7/28/2019 Drilling+Efficiency

    31/40

    Good Task / Bad Task

    Relationship

    Just as we have a good trip/bad trip

    situation, we also have a good cementing

    operation/bad cementing operation, goodnipple up/bad nipple up, etc.

    We can reduce the time for any project by

    changing the task relationships or by notdoing the task at all.

  • 7/28/2019 Drilling+Efficiency

    32/40

    Checklists

    What is a checklist task and what is a

    critical path task?

    A critical path task is a task that must be done

    in sequence. It must be done as a lead time

    relation or a finish/start relation.

    A checklist item is a task that must be done butcan be taken off the critical path and made into

    a finish/finish or a start/start relation.

  • 7/28/2019 Drilling+Efficiency

    33/40

    Checklists

    Checklists

    Should be job specific

    Should be rig specific

    Are basic outlines

    Should address potential problems

    Should be a live system, i.e. readily changeable

    Jackup Drilling Rig Equipment and Procedures ChecklistChecklist

  • 7/28/2019 Drilling+Efficiency

    34/40

    Jackup Drilling Rig Equipment and Procedures Checklist

    Operation: Tripping

    OPERATOR: WELL: RIG: DATE:

    ITEM CHECKS ASSIGNED INITIALS

    Pre - Trip

    Equipment

    Checks

    The following are to be completed prior to

    tripping drill pipe.

    Person or

    title

    When

    completed

    Tongs Check and replace tong dies as necessary

    Check for spare tong dies

    Check jaws

    Check and repair/replace retainer

    bolts/pins as required.

    Iron Roughneck Check & replace worn/slick dies

    Inspect hydraulic/hoses/couplings forleaks and damage

    Check operation

    Spinning wrench Check operation

    Check and replace worn dies

    Check hydraulic hoses/couplings for leaks

    & damage.

    D.P. Elevators Check & repair worn retainer bolts on

    ears.

    D.C. Elevators Check & repair worn retainer bolts on

    ears

    Check & repair retainer bolts

    Link arms and

    link ears

    Check for excessive wear and cracks

    Traveling block

    hook & bail

    Check for cracks and excessive wear

    Master bushing

    and slips

    Check fit and check for wear.

    Checklist

    Sample

    Portion

  • 7/28/2019 Drilling+Efficiency

    35/40

    Checklists

    Pre-operations start-up

    Prepare to spud

    Drive Pipe

    Drill conductor hole

    Run conductor casing

    Cement conductor casing Grout conductor casing (Top Job)

    Grout conductor (With BOP Installed)

  • 7/28/2019 Drilling+Efficiency

    36/40

    Checklists

    Install Diverter System Drill surface hole (17 1/2)

    Under-ream surface hole

    Run surface casing Cement surface casing

    Install wellhead

    Nipple up BOPs

    Test BOPs

    Drill intermediate hole (12 1/4)

  • 7/28/2019 Drilling+Efficiency

    37/40

    Checklists

    Establish shut in procedure

    Establish kill procedure

    Logging operations

    Run intermediate casing (9 5/8)

    Cement intermediate casing Install casing spool

    Install and nipple up BOPs

  • 7/28/2019 Drilling+Efficiency

    38/40

    Checklists

    Drill production hole (8 1/2)

    Run production casing

    Run production liner

    Cement casing

    Cement liner Set P&A plugs

    Cut and retrieve casings

  • 7/28/2019 Drilling+Efficiency

    39/40

    Review of Drilling Efficiency

    Drilling Efficiency is:

    Controlling costs by working efficiently (Reducing the time ittakes to drill a well).

    Critical path planning.

    Using Checklists.

    Holding a daily planning meeting. Holding toolbox meetings.

    Using narrative (written) instructions.

    Identifying tools and equipment to facilitate the drilling program,i.e. rotating mousehole, auto driller etc.

    Identify Constraints, i.e. solids control equipment, rig power,pumps, etc. rig crews, shorebase management, training, etc.

    Utilizing constructive criticism, i.e. Report Card with feedback.

  • 7/28/2019 Drilling+Efficiency

    40/40