Top Banner
Drawing AOA and AON networks Project Management (lecture)
26

Drawing AOA and AON networks

Dec 31, 2015

Download

Documents

isaac-curry

Drawing AOA and AON networks. Project Management (lecture). Activity on Arrow (AoA) diagrams. Elements of an AoA (Activity-on-Arrow) diagram. Activity (arrow) Work element or task Can be real or not real Name or identification of the tasks (label) must be added Event (node) - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Drawing AOA and  AON networks

Drawing AOA and AON networks

Project Management

(lecture)

Page 2: Drawing AOA and  AON networks

Activity on Arrow (AoA)diagrams

Page 3: Drawing AOA and  AON networks

Elements of an AoA (Activity-on-Arrow) diagram• Activity (arrow)

– Work element or task– Can be real or not real– Name or identification of the tasks (label)

must be added

• Event (node)– The start and/or finish of one or more

activities– Tail (preceding) and head (succeeding) nodes

Page 4: Drawing AOA and  AON networks

Conventions• Time flows from left to right

– Arrows’ direction

– Labels’ order

• Head nodes always have a number (or label) higher that of the tail node. This is the same with the arrow labels (alphabetic order).

• Activity labels are placed below the arrow (despite the pictures in the textbook), duration of activity is based above the arrow

• A network has only one starting and only one ending event.• These conventions are not universal. There are many other

to choose from.

Page 5: Drawing AOA and  AON networks

Graphical representation

• Arrows, nodes, bending

• Identification of activities

• Representation of time

• Representation of deadlines (external constraints)

Page 6: Drawing AOA and  AON networks

Dependency rule

b depends on a (b is a successor of a):

b and c are independent from each other:

1 2 3a b

3

4

21

b

c

a

12 13

13

12

8

Page 7: Drawing AOA and  AON networks

Consequences of the dependency rule

• An event cannot be realised until all activities leading to it are complete.

• No activity can start until its tail event is realised.

Page 8: Drawing AOA and  AON networks

Merge and burst nodes

• Merge nodes:– Events into which a number of activities enter

and one (or several) leave.

• Burst nodes:– Events that have one (or more) entering

activities generating a number of emerging activities.

Page 9: Drawing AOA and  AON networks

Two typical errors in logic

• Looping: underlying logic must be at fault

• Dangling: an activity is undertaken with no result

2 4 5enda c d

1star

t

3

b

5 6

7

e

fg

Page 10: Drawing AOA and  AON networks

Interfacing

• When an event is common to two or more subnetworks it is said to be an ‘interface’ event between those subnetworks and is represented by a pair of concentric circles.

11 13

13

aa

acab

21ba

24bc

24bb bd

1222

Page 11: Drawing AOA and  AON networks

Milestones

• Events which have been identified as being of particular importance in the progress of the project.

• Identified by an inverted triangle over the event node (occasionally with an imposed time for the event)

1 2 3a b

1/1/20141/1/2014

Page 12: Drawing AOA and  AON networks

Multiple starts and finishes

• Only used in computer programs

• All starting activities can occur at the start and all finish activities will occur at the end of the project.

Page 13: Drawing AOA and  AON networks

Hammock activities

• Artificial activities created for the representation of the overhead cost with the aim of cost control.

• Embrace activities belong to the same cost centre

• Zero duration time (not taking part in the time analysis)

• Overhead cost rate is assumed to be constant over the life of the hammock.

Page 14: Drawing AOA and  AON networks

Hammock activity

1 2 3 4ba c

h(hammock)

h(hammock)

12 1 2

0

Page 15: Drawing AOA and  AON networks

Dummy activities

• Activities that do not require resources but may in some cases take time.

• They are drawn as broken arrows.

• They are always subject to the basic dependency rule.

• Thre occassions to use dummies:– Identity dummies– Logic dummies– Transit time dummies

Page 16: Drawing AOA and  AON networks

Identity dummies

• When two or more parallel activities have the same tail and head nodes.

1 3

2

a

b

4

3

Page 17: Drawing AOA and  AON networks

Logic dummies

• When two chains of activities have a common node yet they are at least partly independent of each other. Hint: examine ANY crossroads.

• Example:– Activitiy c depends on activity a– Activity d depends on activities a and b

• Solution: – separate c from b with a dummy activity

Page 18: Drawing AOA and  AON networks

Logic dummy example:What is the difference?

2 5

4

a

b3 6

71

g

f

e

d

c

h

2 64

a

b3 7

81

g

f

e

d

c

h5

Page 19: Drawing AOA and  AON networks

Transit time dummies

• If a delay must occur after the competition of an activity before the successor activity can start.

22 4

a

b3

1

d

c

5

2

2 2

1

Page 20: Drawing AOA and  AON networks

Overlapping activities• If the activities are not fully discrete

• The second activity can start before the first is completed but not before it is at least partly completed.

1 2a 3b

10 15

b

1 2 3a1 a2

5

3 7

15

Page 21: Drawing AOA and  AON networks

Activity on Node (AoN)diagrams

Page 22: Drawing AOA and  AON networks

Graphical representation• Rectangles instead of circles

• Representation of dependency time: lags(no dummy activities are used)

• Artifical Start and Finish activities are used when needed, to have only one beginning and end of the diagram

a2

b2

c1

d2

START FINISH

2

2 4

a

b3

1

d

c

5

2

2 2

1

2

Convert the AoA network above to an AoN diagram

Page 23: Drawing AOA and  AON networks

Elements of an AoN diagram

• Activity (node)– Work element or task– Name or identification of the tasks must be

added– No need for dummy (unreal) activities

• Dependency or sequence arrow– Shows the interrelationship between activities

Page 24: Drawing AOA and  AON networks

CPA, CPM and PERT• Critical Path Analysis (CPA), Critical

Path Method (CPM)– deterministic with only one estimation

• Program Evaluation and Review Technique (PERT)– probabilistic with three estimated durations

Page 25: Drawing AOA and  AON networks

Readings

• Lockyer – Gordon (2005) Chapter 11-12

Page 26: Drawing AOA and  AON networks

Thanks for the attention!