Top Banner

of 17

Drainage System Project

Jul 07, 2018

Download

Documents

Kei Chan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/18/2019 Drainage System Project

    1/17

     

    Question 1

    A) 

    Determine the total Loading Unit (L.U.) of the system

    Given the design flow rate, demand time, frequency of use of each sanitary fitment, demandunit of each fitment can be found.

    Usage ratio =  

    Since the demand of one basin is 1 Loading Unit (L.U.), one basin is our base appliance.

    Proportion of base appliance ratio = ( .) 

    Proportion of base appliance flow rate = (.) 

    Demand figure = proportion of base appliance ratio x proportion of base appliance flow rate

    Demand unit = round up number of the demand figure = loading unit of each fitment

    Fitment QuantityDemand

    unit

    total Loading unit

    (L.U.) of each type of

    fitment(Quantity x Demand

    unit

    Basin 10 1 10

    Sink 2 5 10

    Shower 10 5 50

    Clothwasher

    2 5 10

    Hence, the total Loading Unit (L.U.) of the system = 10 +10 +50+ 10 = 80

    Given in the question Calculations

    Fitment

    Flow

    rate(L/s)

    Demand

    time (s)

    Frequency

    Of use(s)

    Usage

    ratio

     proportionof base

    appliance

    ratio

     proportionof base

    appliance

    flow rate

    Demand

    figure

    Demand

    unit

    Basin 0.12 30 1800 0.017 1.00 1.00 1 1

    Sink 0.3 60 1800 0.033 2.00 2.50 5 5

    Shower 0.18 300 6000 0.050 3.00 1.50 4.5 5

    Cloth

    washer 0.2 450 9000 0.050 3.00 1.67 5 5

  • 8/18/2019 Drainage System Project

    2/17

     

    Determine the simultaneous demand in L/s of the system

    Fitment n

    P= Usage

    ratio m

    Probability of

    occurrence Accumulating

    Basin 10 0.017 0 P0= 0.845

    1 P1= 0.143 0.9892 P2= 0.011 0.999

    Sink 2 0.033 0 P0= 0.934

    1 P1= 0.064 0.999

    Shower 10 0.05 0 P0= 0.599

    1 P1= 0.315 0.914

    2 P2= 0.075 0.988

    3 P3= 0.010 0.999

    clothwasher 2 0.05 0 P0= 0.903

    1 P1= 0.095 0.998

    Based on probability theory, probability of having a sanitary fitment in use at a certain time

    can be calculated.

    = ( !! ( )!) (1 )− Where n = total number of fittings having the same probability

    m= number of fitting in use at any one time

    Pm = probability of occurrence

    Consider the first case where a group of 10 basins, with a certain design demand time and

    frequency of use, the probability factor of a particular number of draw off points occurring at

    any one time, P indicated above the chart on the third column from the left, can be computed.

    P =  

    Since the design intent is to serve 99% of all conditions, in the “accumulating” column as

    long as shows nearly close to 0.99 meaning with this number of fitments or less in use at one

    single time can serve 99% of all times.

    For the basin case, 2 basins become the simultaneous demand.

    For the sink case, 1 sink becomes the simultaneous demand.

    For the shower case, 3 showers become the simultaneous demand.

    For the cloth washer case, 1 cloth washer becomes the simultaneous demand.

  • 8/18/2019 Drainage System Project

    3/17

     

    Hence, the simultaneous demand of the system, 0.24+0.3+0.54+0.2=1.28 L/s

    B)  Determine the pump rating and size of the pneumatic tank

    The booster system at 20/F serves the toilets three floors above (21/F, 22/F and 23/F) and

    three floors below (17/F, 18/F and 19/F). Assume vertical pipe loss=0.1mH/m run.

    Technically, the cut- in pressure of the pump only occurs from the booster system at 20/F to

    the water point at 23/F since that is the highest water point which has to be satisfied with the

    minimum pump pressure need for the entire booster system. In addition, the cut-out pressure

    of the pump only occurs at the 17/F since gravity will add up along the pipe going down.

    Hence, we only need to consider two conditions: pump cut-in pressure from 20/F to 23/F and

     pump cut-out pressure from 20/F to 17/F.

    Consider three floors below (17/F, 18/F, and 19/F) and ignore the top three floors for a

    moment.

    Given maximum residual pressure 4.5bar = 45mH

    Head gain from the booster system (20/F) to 17/F = 3.5mH x3=10.5mH

    Pump cut-out pressure = 45m-10.5 + 0.1x3.5x3 = 35.55mH

    Consider three floors above (21/F, 22/F and 23/F) and ignore the down three floors for a

    moment.

    Given minimum residual pressure 1.0 bar = 10mH

    Head loss from the booster system (20/F) to 23/F = 3.5mH x3=10.5mH

    Pump Cut-in pressure= 10mH+10.5+ 0.1x3.5mx3H= 21.55mH

    To sum up, pump cut-in pressure is 21.55mH and pump cut-out pressure is 35.55mH in the

     booster system which is acceptable since their pressure difference is within the range of 10 -

    20 mH.

    Fitment Flow rate (L/s) Simultaneous demand

    Flow rate x

    simultaneous demand(L/s)

    Basin 0.12 2 0.24

    Sink 0.3 1 0.3

    Shower 0.18 3 0.54Cloth

    washer0.2 1 0.2

  • 8/18/2019 Drainage System Project

    4/17

     

    Each floor has a male, female and disabled toilet: 4 basins for male, 5 basins for female and

    1 basin for disabled toilet. Therefore, each floor has 10 basins.

    Since the booster system serves the basins in toilets three floors above and three floors below,

    The simultaneous demand for 6 floors = 1 LU x 6 floors x 10 basins = 60 LU

    Flow rate based on 60LU (See Pipe sizing Chart on the next page, graph 3)

    For a 10 minute cut-out cycle, this ‘effective volume’ = 0.9 L/s x 10min x 60sec =540 L

    P1 V1 = pressure and volume at initial conditions

    (P1 =100kPa (abs) for normal atm. Condition)

    P2V2 = pressure volume at ‘Pump Cut-in’

    P3V3 = pressure volume at ‘Pump Cut-out’ 

    V2  – V3 = effective capacity of tank = 540L = 0.54m3

    P2 = 21.55mH (gauge) = 100 + 215.5 = 315.5kPa (abs) (lower limit)P3 = 35.55mH (gauge) = 100 +355.5 = 455.5kPa (abs) (upper limit)

    According to Ideal gas law =  315500 ( +0.54) =455500  = 1.22   =  100000 =455500∗1.22  =5.54 The actual size of the pneumatic tank = 5.54m

    3

    Pump rating: Pump Cut-in pressure= 21.55mH; Pump Cut-out pressure = 35.55mH

  • 8/18/2019 Drainage System Project

    5/17

     

     Pipe Sizing Chart

    Source: Plumbing Engineering Services Design Guide (2002)

    0.9 L/s

  • 8/18/2019 Drainage System Project

    6/17

     

    Question 2

    A)  Determine whether the existing hot water system is sufficient for the present demand

    and give recommendations if the analysis shows dissatisfaction of the system

    Hour

    Consumption

    (L )

    0:00 16801:00 1260

    2:00 590

    3:00 170

    4:00 160

    5:00 250

    6:00 170

    7:00 840

    8:00 1680

    9:00 2015

    10:00 67011:00 250

    Hour

    Consumption

    (L )

    12:00 8013:00 85

    14:00 505

    15:00 1090

    16:00 1085

    17:00 2100

    18:00 2770

    19:00 3360

    20:00 4200

    21:00 4620

    22:00 378023:00 2100

    Table A: Peak hourly loads (above)

    Table B: Peak hourly loads

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    5000

            0     :        0        0

            1     :        0        0

            2     :        0        0

            3     :        0        0

            4     :        0        0

           5     :        0        0

            6     :        0        0

           7     :        0        0

            8     :        0        0

            9     :        0        0

            1        0     :        0        0

            1        1     :        0        0

            1        2     :        0        0

            1        3     :        0        0

            1        4     :        0        0

            1       5     :        0        0

            1        6     :        0        0

            1       7     :        0        0

            1        8     :        0        0

            1        9     :        0        0

            2        0     :        0        0

            2        1     :        0        0

            2        2     :        0        0

            2        3     :        0        0

       C   o   n   s   u   m   p   t   i   o   n    (   L    )

    Hour (hr)

    Demand Profile of a Hot Water

  • 8/18/2019 Drainage System Project

    7/17

     

    Peak

    hours

    litres

    used

    litres per

    hour

    1 4620 4620

    2 8820 4410

    3 12600 4200

    4 15960 39905 18730 3746

    6 20830 3472

    7 22930 3276

    8 24015 3002

    9 25105 2789

    10 25610 2561

    11 25695 2336

    12 25775 2148

    13 26025 2002

    Peak

    hours

    litres

    used

    litres per

    hour

    14 26695 1907

    15 28710 1914

    16 30390 1899

    17 31230 183718 31400 1744

    19 31650 1666

    20 31810 1591

    21 31980 1523

    22 32570 1480

    23 33830 1471

    24 35510 1480

    24hr average:

    35510/24 = 1479.6 =1480 L/hrTable B: Peak hourly loads (above)

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    5000

    0 5000 10000 15000 20000 25000 30000 35000 40000

       R   e   c   o   v   e   r   y    (   L    /    h   r    )

    Storage-litres (L)

    Storage make-up ratio curve peak hour 1peak hour 2

    peak hour 3

    peak hour 4

    peak hour 5

    peak hour 6

    peak hour 7

    peak hour 8

    peak hour 9

    peak hour 10

    peak hour 11

    peak hour 12

    peak hour 13

    peak hour 14

    peak hour 15

    peak hour 16

    peak hour 17

    peak hour 18

    peak hour 19

    peak hour 20

    peak hour 21

    peak hour 22

    peak hour 23

    peak hour 24

    Min recovery rate =1480 L/hr

    Recovery/storage curve

  • 8/18/2019 Drainage System Project

    8/17

     

    Given that

    -Existing hot water tank = 8000 L

    -Existing hot water heater Q= 120kW

    -Design cold and hot water temperature = Tw=10°C & Th= 65°C

    -Heat capacity of water, cp= 4.2 kJ/kgK

    Assume water density as 1kg/L = ∆120= 4.2 (6 5 1 0)  = 0.52 / 

    = 0.52 1 / 3600 /ℎ 

    = 1872ℎ  In the existing system, the 8000L hot water tank is at a recovery rate of 1872L/hr. However, in

    the storage make-up ratio curve, under the condition of a 8000L hot water demand, the required

    recovery rate is at least roughly 2300L/hr. Hence, the existing system is not sufficient for the

     present hot water demand.

    Recommendations:

    If the hot water tank storage to 8000L is kept,

    = ∆ = 80001ℎ 1ℎ3600   11 4.2 (6 5 1 0) =147.6  The power output of the heater requires to be larger so as to satisfy the required hot water

    demand instead of the existing smaller power output of 120kW. Moreover, finding a heater with

    a recovery rate of exactly 2300 L/hr on the existing market is not very possible although

    2300L/hr recovery rate is the theoretical value based on the plot. Perhaps, we can pick a

    2500L/hr recovery rate heater that should be available on the market for our need.

    Or if the power output of the heater is kept to 120kW, with 1872L/hr recovery rate, based on the

    storage make-up ratio, the hot water tank should require around 12000L

  • 8/18/2019 Drainage System Project

    9/17

     

    B) Sizing the primary and secondary pipework  

    Consider a primary circuit of a hot water system,

    Design flow rate = 2.0 L/s

    Cold water = 20 °C (density 998 kg/ m3)

    Hot water = 65° C (density 980 kg/m3)

    The height difference between boiler and calorifier = 8m

    Pressure difference of two columns of water=∆ℎ= (998 –  980) x 9.81x 8 = 1413 PaAssume the overall hydraulic length of the pipe = 24m (measured pipe length + length of fittings)

    Allowable pressure drop = 1413Pa/ 24m = 59 Pa/m

    From the pipe sizing chart for copper pipe, at design flow =2.0L/s,

    Based on average 989kg/m3,

    Head loss per meter run = 59   = 0.006 /,(see Pipe Sizing Chart  on the next page) 76mm pipe suits the requirement.

     

    Consider secondary pipework of a hot water system

    The secondary return pipe has to be sized based on the minimum

    flow rate to determine the possible heat loss from hot water pipe.

    Given from the diagram that supply temperature of water=65°C

    Return temperature of water = 55°C

    Consider insulated supply pipe size =54mm OD (~21W/m run heat

    loss), with the assumption of head loss = 0.1 mH/m at 3.5L/s (see

     Pipe Sizing Chart  on the next page)

    Supply pipe length = 20m

    Heat loss= 21W/m x 20m = 320W

    Assume water density as 1kg/L

    Temperature drop ∆ = 5°C (from 65°C - 60°C at the end of supply) = ∆  21 20 = 4200   5°C =0.02/ This is the minimum flow rate in the secondary circuit to ensure the end of the supply still has

    60°C

    As for the secondary return, = ∆  ℎ 20 = 0.02 4200   (6055)°C ℎ = 21  

  • 8/18/2019 Drainage System Project

    10/17

     

    Since the secondary return has very similar conditions, including same temperature drop, same

    mass flow rate, same pipe length, the size of secondary return should be 54mm OD same as the

    secondary supply pipe.

     Pipe Sizing Chart

    Source: Plumbing Engineering Services Design Guide (2002)

    For primary

    circuit (orange)

    For secondary

    supply circuit

    (red)

  • 8/18/2019 Drainage System Project

    11/17

     

    Question 3

    A) Wobbe index is equal to higher heating value (calorific value) in MJ/m3 divided by square

    root of gas specific gravity. The Wobbe index is used to compare the combustion energy output

    of different fuel gases, such as natural gas, liquefied petroleum gas (LPG), and town gas, in an

    appliance, like a water heater. If two fuels have identical Wobbe indices, then for a given

     pressure and valve setting, the energy output will also be the same. For example, under the same

     pressure and valve setting condition, if gas A with a Wobbe index of 24 and gas B also with the

    same Wobbe index of 24, although they both have different calorific values and specific gravity

    values, both gases will give the same energy output. Hence, we can make use of any fuels that

    have the identical Wobbe index and give out same combustion energy output to substitute one

    another.

    Town

    gas LPG

    calorific value (MJ/m3) 17.27 104.9

    specific gravity 0.52 2.05

    wobbe index= √    24 73Consider 1 water heater and 1 table top cooker

    Water heater rating = 102.2 MJ/hr

    Table top cooker rating = 51.3 MJ/hr

    Total = 102.2 +51.3 =153.5 MJ/hr =././ =8.89/ℎ 

    The Pole formula is used for determining the flow of gas in pipes.

    =0.0071  ℎ  Where Q = flow (m

    3/hr),

    d= diameter of pipe (mm),

    h =pressure drop (mbar), assume 100 Pa = 1mbar,

    l= length of pipe (m), in this case, measured length of pipe: 5+8+1 =14m, length of fitting around

    4m

    s =specific gravity of gas (town gas =0.52)

    8.89=0.0071  1

    0.5218  = 2 7  Gas supply pipes from the gas meter to the individual appliances = 32mm (available on the

    market)

  • 8/18/2019 Drainage System Project

    12/17

     

    B) Determine pressure drop of steam pipe work and then size the steam pipe 

    Given:

    A boiler plant producing 180°C superheated steam at 600kPa (absolute) = 6 bar

    Minimum pressure at the heater at 150 °C = 475kPa =4.75 bar (absolute) from steam table

    Pressure drop of steam pipe work = 6bar -4.75 bar = 1.25bar (absolute)

    Steam loading of the heater =300kg/hr

    Overall equivalent length of the steam pipe = 40m

    Consider the heat loss from pipework = 3.5% of heater load per 100m

    Hence, revised steam load = 300kg/hr + 300 x(3.5% x 40/100)=304kg/hr

    Steam pressure drop factor table

    6bar =43.54 (blue circle)

    4.75bar= (29.27+30.27)/2=29.77

    =  where F= pressure factor, P1 = factor based on theinlet pressure, P2 = factor based on the pressure at a

    distance of L metres, L= equivalent length of pipe (m) = .−.   = 0 . 3 4 From pipeline capacity table (see the next page),

    F=0.3, capacity =487.3kg/hr> 304kg/hr

    Size =32mm

    Steam = 304kg/hr at 6 bar

    Specific volume = 0.316m3/kg at 6 bar

    Volume flow = 96.064 m3/hr = 96.064/3600= 0.027m

    3/s

    32mm pipe area = 0.0008m2

    Thus pipe velocity = 0.027m3/s / 0.0008 = 33.75m/s

    The pipe size is within the normal design velocity range ( 24-36m/s)

  • 8/18/2019 Drainage System Project

    13/17

     

  • 8/18/2019 Drainage System Project

    14/17

     

    Question 4

    A) Given:

    60% water depth for the drain pipe at peak hours

    A measured velocity, v0.6= 1.2 m/s

    450mm drain pipe is laid to fall at 1:225

    Proportional flow chart:

    . = ℎ = 0.6 . =1.05

     

    = 1.2 / 1.05 = 1.14/   , = 4  = 0.454   = 0.159    , =  

    = 1 . 1 4 0.159 

    =0.181/ 

    =181/ . =0.65 .181 =0.65  ,. = 118 / Lets assume full potential as ¾ bore flow.

  • 8/18/2019 Drainage System Project

    15/17

     

    . =0.9. = 0.181 0.9 . =0.1629/ . =162.9 /Amount of discharge to reach its full potential=162.9118=44.9L/s

    Since design daily discharge per occupant =225 L per day, ½ of the discharge is recorded in a 6

    hour period,

    Originally, with the existing drain12 ( 225)6ℎ =118/12 ( 225)6ℎ 1ℎ3600 =118/ =22656

     

    To reach its full potential (3/4 bore flow)12 ( 225)6ℎ =162.9/12 ( 225)6ℎ 1ℎ3600 =162.9/ =31277  Therefore, the drain can accommodate 31277 – 22656 = 8621 people on top of the original

     population.

    B)

    = Where Q is rain water flow (L/s)C is the impermeability factor or run-off coefficient

    A is drainage or catchment area (m2)

    I is rainfall intensity (m/hr)   = +0.5 Where Af  is the catchment floor area (m

    2),

    Aw is the area of vertical wall (m2)

    A is catchment area (m2)

      = 1010 

      = 100 Determine: the time of concentration of the storm water for the roof = 0.14465 ( . .) 

    Where tc is time of concentration (min)

    H is average fall (m per 100m) from the summit of catchment to the point of drainage

    outlet

  • 8/18/2019 Drainage System Project

    16/17

     

    L is the largest distance from catchment boundary to the point of drainage outlet (m)

    A is the catchment area (m2)

    = 0.14465 ( 1 0 + 5(1).(100).) 

    =1.37  

    Determine the extreme mean intensity of the rainfall, i , for a 10 year rainstorm return period

    = 603( +4.4). Where td duration of rainfall in min. In this case td is equal to tc at a peak discharge of the

    rainstorm system

    = 603(1.37+4.4

    ).  = 279 /ℎ Determine stormwater flow rate to be handled by the system, Q = 0.278/ 

    Where Q is rain water flow (L/s)

    C is the impermeability factor or run-off coefficient, in this case, assume 0.95 for roof

    A is drainage or catchment area (m2)

    I is rainfall intensity (m/hr)

    = 0.951002791000 0.278 

    = 7 . 3 6  

    Determine the expected bore flow of the storm water pipe

    Based on empirical formula of vertical stacks

    =  Where Q is rain water flow (L/s), k is a coefficient to determine which bore flow is expected, D

    is the diameter of pipe (mm)

    7.36=(100)  = 3.4 10− So 1 / 4 bore full is expected of the storm water pipe.

  • 8/18/2019 Drainage System Project

    17/17