Top Banner
Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux 10/28/2013 Copyright 2013, Analytic Project Management, Swampscott, MA 1 A P M Analytic Project Management 72 Blodgett Ave. Swampscott, MA 01907 (781) 598-1222 [email protected] TM
38

Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Dec 17, 2015

Download

Documents

Hope Morris
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Drag and Drag Cost:

The Missing Critical Path Metrics***** 

A One Hour Presentation

for

PMI Baltimore Lunch Meeting,

Columbia, MD

by

Stephen A. Devaux

10/28/2013

Copyright 2013, Analytic Project Management, Swampscott, MA 1

A

P

M

Analytic Project Management

72 Blodgett Ave.

Swampscott, MA 01907

(781) 598-1222

[email protected]

Page 2: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

2

What Is Critical Path Drag?Critical path drag is a critical (literally!) new

CPM metric that was introduced in my 1999 book Total Project Control (TPC).

It is NOT the only, or even the most important technique or metric of TPC.

But it IS the one whose value is most intuitively obvious.

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 3: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

What Critical Path Drag is NOT!It is NOT Steve Devaux’s invention!

3

It’s not an invention at all! EVERY project has a critical path and therefore EVERY

project has activities with drag!

I just identified the importance of critical path drag and how to compute it.

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 4: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

All Projects Are Investments.

“An investment in work to create a unique product, service or result.”

4

(http://dictionary.reference.com/browse/value)

“Value: n; relative worth, merit or importance.”

In any investment, “value” means value to the investor!

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 5: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

5

Externalities

(A)n externality is a cost or benefit… incurred by a party who did not agree to the action causing the cost or benefit… (P)rices do not reflect the full costs or benefits of producing or consuming a product or service.

http://en.wikipedia.org/wiki/Externalities

Copyright 2013, Analytic Project Management, Swampscott, MA

Items which are left as externalities are measured at zero!

Page 6: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

6

The Two Externalities in Projects

Externalities!

SCOPE

COST TIME

If two sides of the project investment

triangle are left unmonetized, and the third side is COST, is it any

wonder that justifying additional resources is almost

impossible?

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 7: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Integrating the Project Investment

$ Invested forResources

7

SCOPE

COST TIME

Copyright 2013, Analytic Project Management, Swampscott, MA

SCOPE generates the project’s value!

If invested resources are measured in dollars, the other sides of the triangle should be, too.

Otherwise, how can we justify spending even one dollar on resources?

Page 8: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Every Project……is an investment of the resources needed…

8

SCOPE

COST TIME

Copyright 2013, Analytic Project Management, Swampscott, MA

…to create SCOPE that is expected to generate greater value than the budget…

…and which is modified by TIME andprojectduration.

Page 9: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

SCOPE Generates the Project’s Value

EXP. PROJECT PROFIT = $EMV of SCOPE - $COST of resources

SCOPE

COST TIME

$Expected Monetary Value (EMV)

$BUDGET

If a project is an investment, then every project is performed for the difference between its expected value and its cost.

Copyright 2013, Analytic Project Management, Swampscott, MA

9

What about TIME?

TIME modifiesthe value ofthe SCOPE.

TIME also can impactresource usage and COST.

Page 10: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

The Impact of TIME on EMV

Typically, the sooner the delivery, the greater the $EMV.The later the delivery, the lower the $EMV.

SCOPE

COST TIME

$EMV

($+ or $- per time unit against...)

Delivering the product generates almost all the value.

(as of a given completion date.)

10

Copyright 2013, Analytic Project Management, Swampscott, MA

$BUDGET

Page 11: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Planning Value thru the DIPP

PROJECT PROFIT = ($EMV of SCOPE $Accel/Delay) – ($BUDGET COST Variance)

SCOPE

COST TIME

$Expected Monetary Value (EMV)

$BUDGET

Copyright 2013, Analytic Project Management, Swampscott, MA

11

($+ or $- per time unit against...)

* See “When the DIPP Dips”, Project Management Journal, Sep-Oct 1992.

Planned Simple DIPP * = $EMV of SCOPE

$Planned Cost ETC

Page 12: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Tracking Value thru the DIPP

SCOPE

COST TIME

$EMV

$BUDGET

Copyright 2013, Analytic Project Management, Swampscott, MA

12

($+ or $- per time unit against...)

Actual Simple DIPP = ($EMV of SCOPE $Accel/Delay)

($BUDGET COST Variance)

Planned Simple DIPP = $EMV of SCOPE

$Planned Cost ETC

DIPP Progress Index (DPI) = Actual DIPP

Planned DIPP

Page 13: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

The DIPP and the DPI The following 26 week project has an EMV of $240,000 and an initial budget of $90,560:

DIPP Progress Index (DPI) = Actual DIPP ÷ Planned DIPP

What is the DPI at Week 18 if the Actual DIPP is 5.43?

What events could cause an Actual DIPP that’s lower or higher than planned?

5.43 / 6.03 = .90

What is the DPI at Week 18 if the Actual DIPP is 6.33? 6.33 / 6.03 = 1.05

Copyright 2013, Analytic Project Management, Swampscott, MA

*

Page 14: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

14

Estimating the Cost/Value of Time is ESSENTIAL to Good

Project Management!Otherwise it will be an externality – worth zero!

Copyright 2013, Analytic Project Management, Swampscott, MA

In many project schedules, the cost of resources is often less than the cost of the time that they would save!

This is especially true on enabler projects within a program, i.e., projects that enable other valuable projects.

Page 15: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Introducing:Paradise Island!

A luxury Resort Island for YOUR Investment,

And for YOUR Exquisite Pleasure!

Grand Opening Jan 1, 2017!Copyright 2013, Analytic Project Management, Swampscott, MA

Page 16: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

With magnificent golf courses…

PROFITS:

$104M/year

…And a marina…PROFITS:

$156M/year

…And luxury hotels and restaurants!

PROFITS:

$258M/year!

All construction scheduled to begin Jan 1, 2014!Copyright 2013, Analytic Project Management, Swampscott, MA

Page 17: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Guest Privacy Guaranteed!

Access to island ONLY via Garden of Eden Bridge!(Under construction, scheduled completion Dec 31, 2013)

(EXPECTED PROFITS from TOLLS: $2M/year.) Copyright 2013, Analytic Project Management, Swampscott, MA

Page 18: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Five Key Milestones!Bridge scheduled completion Dec 31, 2013

PROFITS: $104M/year ($2,000,000/week)

Golf course construction scheduled to begin Jan 1, 2014

PROFITS: $156M/year ($3,000,000/weekMarina construction scheduled to begin Jan 1, 2014

PROFITS: $2M/year ($40,000/week)

PROFITS: $258M/year ($5,000,000/week)Hotel/Restaurant construction scheduled to begin Jan 1, 2014

PROFITS: $520M/year ($10,000,000/week)Grand Opening scheduled for Jan 1, 2017

WEEKLY COST OF DELAY: $10,000,000/week

WEEKLY COST OF DELAY: $5,000,000/week

WEEKLY COST OF DELAY: $3,000,000/week

WEEKLY COST OF DELAY: $2,000,000/week

WEEKLY COST OF DELAY: $10,000,000/week!

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 19: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

19

Enabler Projects

The value of an enabler project is multiplied by the value of the projects it enables.

Copyright 2013, Analytic Project Management, Swampscott, MA

Additionally, the value/cost of time on an enabler project is often multiplied by the value of the projects it enables.

Page 20: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

20Copyright 2013, Analytic Project Management, Swampscott, MA

The Drag Efficient

And So To Critical Path Drag Every project is as long as its

longest path of activities.

We can choose to plan and optimize that path, or we can ignore it.

But the project will STILL be as long as its actual longest path!

What impacts a project’s delivery date?

Failure to manage the critical path properly means failure to control the impact of duration on the investment.

The work, delays, constraints, and bottlenecks that comprise a project’s critical path (and have drag!).

Page 21: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

The Forward & Backward Passes

1. EARLY START

2. EARLY FINISH

3. LATE START

4. LATE FINISH

Copyright 2013, Analytic Project Management, Swampscott, MA

LFLS

ES EF

DUR.

ACT.ID

21

Page 22: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

What Does CPM Say?

Total float = amount of time an activity can slip without delaying the end of the project.

TF=6

But what about ON the critical path? What does CP analysis say about critical activities?

22Answer: ZERO (Float = 0)!Copyright 2013, Analytic Project Management, Swampscott, MA

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 71

Page 23: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

But about stuff that’s ON the critical path, traditional CPM (and CPM software) says “ZERO!

TF=3.5M

TF=3M

TF=2M

Traditional CPM Quantifies…

Off the critical path On the critical path ¨ Total Float ¨ Total Float = ¨ Free Float

23

0

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 24: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

24

Where to Shorten?

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 711 15

40

51

39 5116

22

52 71

Suppose each unit of duration cuts ROI by $5,000?Of the four activities on the CP (A, C, D, E),

which TWO should we look at first to shorten?

TF=0

TF=6

TF=0TF=0

TF=0

1. A & C? 2. A & D? 3. A & E? 4. C & D? 5. C & E?

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 25: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

25

Computing Drag in a Simple Network

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 711 15

40

51

39 5116

22

52 71TF=0

DRAG=15

TF=6

TF=0DRAG=6

TF=0DRAG=6

TF=0DRAG=20

Drag is ONLY on the critical path. It is the amount of time that an activity is ADDING to the project duration.

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 26: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 711 15

40

51

39 5116

22

52 71TF=0

DRAG=15

TF=6

TF=0DRAG=4

TF=0DRAG=4

TF=0DRAG=20

20

16 47

51

32

F

TF=4

Computing DRAG in a Simple Network (cont.)

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 27: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

27

Computing DRAG in a Simple Network (cont.)

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 711 15

40

51

39 5116

22

52 71TF=0

DRAG=15

TF=6

TF=0DRAG=4

TF=0DRAG=4

TF=0DRAG=20

20

16 47

51

32

F

TF=4

16

16 37

37

22

C38

38 39

39

2

G

TF=0DRAG=2

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 28: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

28

Formula for Computing DRAG

1. If it has no parallel path activities:DRAG of Activity X = its duration.

• Sumatra.com’s Project Optimizer software, an add-on to MS Project.

• Spider Project released a version in April 2009 that computes drag.

• InterPlan Systems is releasing a drag-computing version this year

2. If there are parallel paths:DRAG of Activity X = whichever is LESS:

Its duration OR

the TF of the parallel activity with the least TF.

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 29: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Drag Exercise 1

Copyright 2013, Analytic Project Management, Swampscott, MA

10 15 5 5

20

29

Page 30: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Computing DRAG Cost

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 711 15

40

51

39 5116

22

52 71DRAG=15

DRAG=4DRAG=4

DRAG=20

20

16 47

51

32

F

16

16 37

37

22

C38

38 39

39

2

C’

DRAG=2

30

If every unit of time reduces project profit by $10,000:

Copyright 2013, Analytic Project Management, Swampscott, MA

DC=$150K

DC=$40KDC=$40K DC=$20K

DC=$200K

The drag cost metric is what you use tojustify the additional resources you need!

Page 31: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

What is the True Cost of an Activity?

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 711 15

40

51

39 5116

22

52 71

20

16 47

51

32

F

16

16 37

37

22

C38

38 39

39

2

G

Imagine that this project has a budget of $300,000, allotted as follows:

BUDG=$30,000

31

BUDG=$65,000

BUDG=$50,000

BUDG=$75,000

BUDG=$40,000BUDG=$5,000

BUDG=$35,000

Which two work activities TRULY cost the most?

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 32: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Computing True Cost

A

15

C

24

D

20

E

B

30

12

1 15

16

16 40

45

39 51

52 711 15

40

51

39 5116

22

52 71DRAG=15

DRAG=4DRAG=4

DRAG=20

20

16 47

51

32

F

16

16 37

37

22

C38

38 39

39

2

C’

DRAG=2

BUDG=$30,000

32

BUDG=$65,000

BUDG=$50,000

BUDG=$75,000

BUDG=$40,000BUDG=$5,000

BUDG=$35,000

If every unit of time reduces project profit by $10,000:

Copyright 2013, Analytic Project Management, Swampscott, MA

DC=$150K

DC=$40KDC=$40K DC=$20K

DC=$200K

TC=$25,000 TC=$80,000TC=$90,000

TC=$180,000TC=$235,000

TC=$75,000

TC=$65,000

If E’s budget is doubled to $70,000

and its duration thusreduced to 10:

DC=$100K

TC=$170,000

Page 33: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Adding Resources to Reduce Drag

33

1. Drag shows which activities will benefit the project most by being shortened – both up front and when things slip!

2. Drag Cost justifies resources -- if an activity has a DRAG Cost of $10,000 per week, that justifies up to $30,000 to lessen its DRAG by three weeks.

4. Each good decision displays its worth by increasing the project ROI, DIPP and DPI, the whole reason for the project investment!

3. If a CP activity has significant drag and is resource elastic, why does it have part-time resources?

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 34: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

DRAG Puts the Focus…

34

DRAG=2MDRAG=2M

DRAG=2M D=1.5M

…where it belongs: ON the critical path!

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 35: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

It’s NOT Always That Simple……Larger projects and complex dependencies makecomputing DRAG more problematic.

35

Start-to-Start (SS)

Finish-to-Finish (FF)

Start-to-Finish (SF)

Start-to-Start (SS)with lag

Finish-to-Finish (FF)with lag

Start-to-Finish (SF)with lag

Copyright 2013, Analytic Project Management, Swampscott, MA

Page 36: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

1. SS with lag

2. FF with lag

3. SF with lag

Decomposition With Lags

36

Relationship Decomposition

TF=2D=4TF=0

D=2TF=0D=4+2=6

TF=3

D=3TF=0

D=3

TF=3

D=3TF=0

D=3

D=3

TF=1

D=1TF=0D=4

Copyright 2013, Analytic Project Management, Swampscott, MA

N

10

Page 37: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Eight Points in Conclusion

37

1. All projects are investments.

Copyright 2013, Analytic Project Management, Swampscott, MA

2. Almost all project investments are very time sensitive – shorter adds to ROI, longer subtracts.

3. We MUST start estimating the value/cost of time!

4. Project durations are driven by the critical path.

5. Traditional CPM metrics quantify non-CP work.

6. CP drag tells us what is costing how much time!

7. That time can be human lives. And pain. And MONEY!

8. That money can justify both resources and the value that a good scheduler can bring to a project.

Page 38: Drag and Drag Cost: The Missing Critical Path Metrics ***** A One Hour Presentation for PMI Baltimore Lunch Meeting, Columbia, MD by Stephen A. Devaux.

Stephen A. Devaux, MSPM, PMPPresident, Analytic Project Management72 Blodgett Ave., Swampscott, MA 01907

Office: 781-598-1222 Cell: 617-763-3067 Email: [email protected]

38

PUBLICATIONS• Total Project Control: A Manager’s Guide to Integrated Project Planning, Measuring, and Tracking ,

May 1999, John Wiley & Sons.

• “The Drag Efficient,” article in Jan/Feb 2012 issue of Defense AT&L Magazine . Reprinted in CRC Press’s book Project Management in the Oil and Gas Industry.

• “Time is a Murderer,” chapter in CRC Press’s 2013 book Handbook of Emergency Response.

•Six-part series on TPC methods, published in Projects@Work on-line magazine, Oct-Dec 2006:“The Value-abled Project” “Moneyproject” “Time is a Crook”“Delay Tactics” “Drag Racing on the Critical Path” “Paving the Critical Path”

“Scheduling is a Drag, “published in Projects@Work on-line magazine, Jan 2009, (co-author with William Duncan, author of the 1996 PMBOK Guide).

•“When the DIPP Dips,” Project Management Journal, September 1992. Reprinted in PMI’s book

Essentials of Project Control, 1999, Pinto & Trailer, ed.

•“Moneyproject: Metrics, Baseball, and PM”, webinar for PMI’s Metrics SIG, 2005. •“Total Project Control in IS Projects: Managing Projects and Portfolios for Maximum Value”,

webinar for PMI’s Information Systems SIG (IS-SIG), 2003.

Copyright 2013, Analytic Project Management, Swampscott, MA