Page 1 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)
29

Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Apr 03, 2018

Download

Documents

vuongcong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 1 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 2: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 2 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Environment Clearance Compliance Report

Name of Project

M/s UltraTech Cement Ltd; Unit – Jhajjar Cement Works (Formerly known as M/s Grasim Industries Ltd), Located at/near Village -Jharli, Tehsil - Matanhail, Distt – Jhajjar (Haryana).124106

Environment Clearance Letter No.

SEIAA/HR/2014/481 Dated 14.03.2014 Cement Grinding Unit (1.8 MTPA capacity) along with D.G Set (2x6 MW)

Period of Compliance Report October-2014 to March-2015

A ) SPECIFIC CONDITIONS : S.N. CONDITIONS COMPLIANCE

[1] Particulate emissions shall be controlled within 50 mg/Nm3 by

installing adequate air pollution control system viz. Bag house

filters and stacks of adequate height etc. Data on ambient air,

fugitive and stack emissions shall be submitted to the Ministry's

Regional Office at Chandigarh, SEIAA Haryana, HSPCB,

Panchkula and CPCB regularly.

o Plant is under project stage. o All major sources of air pollution

(Cement Mill and Packing Plant)

will be provided with bag house

and bag filters to maintain the

dust emission level within

prescribed norms beside stack of

adequate height will be provided.

Erection of Pollution Control

equipments under progress

(Image enclosed as Annexure-1)

o Quarterly Ambient Air Quality

Monitoring is carried out and

reports submitted to State

Pollution Control Board (Copy of AAQM Report is enclosed as Annexure-2)

[2] The National Ambient Air Quality Standards issued by the

Ministry vide G.S.R. No. 826(E) dated 16th November, 2009

should be followed.

o The National Ambient Air Quality

Standards issued by the Ministry

vide G.S.R. No. 826(E) dated

Page 3: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 3 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

16th November, 2009 is being

followed.

[3] Gaseous emission levels including secondary fugitive emissions

from all the sources shall be controlled within the latest

permissible limits issued by the Ministry and regularly monitored.

Guidelines/ Code of Practice issued by the CPCB should be

followed.

o Agreed

[4] This company shall install adequate dust collection and extraction

system to control fugitive dust emissions at various transfer

points, vehicular movement, bagging and packing areas etc.All

the raw material stock piles shall be covered. A closed clinker

stockpile system shall be provided. All conveyers shall be

covered with GI sheets. Covered sheds for storage of raw

material and fully covered conveyers for transportation of material

shall be provided besides cement, fly ash and clinker shall be

stored in silos. Pneumatic system shall be used for fly ash

handling.

o All material transfer points will be

provided with bag dust collectors,

& roads and movement area will

be concreted to control fugitive

dust emission

o Gypsum will be stored in covered

shed. Fly ash and Clinker will be

stored in silo.

o .All belt conveyor inside plant

premises will be covered with

conveyor belts.

o Fly ash will be pneumatically

transferred and stored in Silo.

(Clinker Silo & Fly Ash Silo erection image is attached as Annexure -3)

[5] Asphalting/concreting of roads and water spray all around the

stockyard and loading/unloading areas in the plant shall be

carried out to control fugitive emissions. Regular water sprinkling

shall be carried out in critical area prone to air pollution and

having high levels of PM and RSPM such as haul road, loading

and unloading points, transfer points and other vulnerable areas.

It shall be ensured that the ambient air quality parameters

conform to the norms prescribed by the Central Pollution Control

Board in this regard.

o Roads within the plant premises

will be concreted. Sprinkling of

water will be done along the

internal roads and around raw

material handling area in plant in

order to control the dust arising

due to vehicular movement.

o Ambient Air Quality Monitoring is

regularly carried out and

parameters conform to the norms

prescribed by the Central

Page 4: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Pollution Control Board. AAQM

reports are regularly submitted to

State Pollution Control Board

(AAQM Report attached as Annexure -2)

[6] Efforts shall be made to reduce impact of the transport of the raw

materials and end products on the surrounding environment

including agricultural land. All the raw materials including fly ash

shall be transport in the closed containers only and should not be

overloaded. Vehicular emissions should be regularly monitored.

The vehicles should have Pollution Under Control certificate.

o The plant is in project stage. The

same shall be complied during

operational phase.

o Vehicular emissions will be

regularly monitored. Company

operated vehicles will go through

regular maintenance and pollution

check up.

[7] Total ground water requirement for the cement plant shall not

exceed 250m3/day and necessary permission for the drawl shall

be obtained. All the treated wastewater shall be recycled and

reused in the process and/or for dust suppression and green belt

development and other plant related activities etc .No process

wastewater shall be discharged outside the factory premises and

'zero' discharge shall be adopted.

o Agreed. The permission for drawl

of ground water has been

obtained from CGWA vide their

letter no.21-

4(627)/NWR/CGWA/2014-

1879,dated 17Nov 2014

o Treated domestic waste water will

be used in plantation & dust

suppression. No waste water will

be generated from the cement

grinding process.

.

[8] Efforts shall be made to make use of rain water harvested. If

needed, capacity of the reservoir shall be enhanced to meet the

maximum water requirement. Only balance water requirement

shall be met from other sources.

o Rain water harvesting is being

planned

[9] All the bag filter dust, clinker dust and cement dust from pollution

control devices shall be recycled and reused in the process used

for cement manufacturing. Spent oil and batteries shall be sold to

o All bag filters are equipped with

dust extraction system. All dust

will be recycled & reused in the

Page 5: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 5 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

authorized recycled/ re- processors only.

process at relevant stage.

o Spent oil and batteries willl be

sold to authorized recycled/ re-

processors.

[10] The project proponent shall develop 3 meter wide green belt as

buffer zone around the plant boundary as sound barrier. Green

belt shall be developed in at least 33% area in and around the

cement plant as per the CPCB guideline to mitigate the effect of

the air emissions in consultation with local DFO

o Total green area / belt will be

developed on 34.47 acres (33%)

of the project / plot area and local

and native species will be

selected in consultation with local

DFO in phase wise manner.

o We have planted -2450 plants till

from April-14 to March-15.

[11] At least 5% of the total cost of the project shall be earmarked

towards the Enterprise Social Commitment based on locals need

and item-wise details along with time bound action plan should

be prepared and submitted to the SEIAA Haryana/ RO MoEF,

Gol, Chandigarh. Implementation of such program should be

ensured accordingly in a time bound manner.

o Agreed .CSR Action Plan has

been submitted. Copy of CSR

Action Plan enclosed as

Annexure 4

[12] The company shall provide housing for construction labour within

the site with all necessary infrastructure and facilities such as fuel

for cooking, safe drinking water, medical health care, crèche etc.

The housing may be in the form of temporary structures to be

removed after the completion of the project.

o We have provided housing for

construction labour along with

necessary infrastructure like Safe

drinking water, labour canteen

etc..

[13] The Sewage Treatment Plant (STP) of 20 KLD capacity shall be

installed for the treatment of the sewage to be prescribed

standards including odour and treated effluent will be recycled to

achieve zero exit discharge. The installation of STP should be

certified by an independent expert and a report in this regard

should be submitted to the SEIAA, Haryana before the project is

commissioned for operation. Tertiary treatment of waste water is

mandatory. Discharge of treated sewage shall conform to the

norms and standards of HSPCB, Panchkula. Project Proponent

shall implement such STP technology which does not require

filter backwash.

o Ours is a small plant and there is

no staff colony proposed.

Domestic wastewater generation

will be very less which will be

treated via soak pit & septic tank.

The treated water will be reused

for dust suppression & plantation

activity.

Page 6: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 6 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

[14] The sullage generated shall be treated and used as manure.

o Noted

[15] The project proponent shall take adequate preparation for fire

and other kinds of disaster including chemical disaster. On-site,

off-site emergency plan should be prepared and rehearsed in

regular mock drills.

o Approval has been taken for

firefighting scheme (Annexure-5) . Fire system shall cover portable

fire extinguisher and sprinkler

system.

Portable fire extinguishers and

water sprinklers are planned to

use during construction phase.

o Onsite and offsite emergency

plan have been prepared.

[16] The project Proponent shall initiate a long term study through a

reputed institution to assess the cumulative impact of the power

plants on the AAQ of the area. The study shall in particular

assess the impact of emission of the HSD based DG sets on the

chemistry of upper atmosphere and on concentration of PM10,

PM2.5. It shall be ensured that the worst seasonal atmosphere

conditions are taken into account in the above said study.

o Agreed

[17] Standards for discharge of environmental pollutants as enshrined

in various schedules of rule 3 of environment protection rule 1986

shall be complied with.

o Agreed

[18] The project proponent shall appoint well qualified fire supervisor. o Noted

[19] The project proponent shall ensure that transportation of raw

materials by railway mode; never falls below 90% of the traffic on

any single month of operation of plant.

o Noted

[20] All connecting roads from Plant to National highway shall be

maintained by project proponent so that it can withstand heavy

traffic caused by the plant.

o Our project is located on 33 feet

wide existing pucca road, along

with this approach road we have

left 27 feet strip for road widening.

This approach road is connecting

to MDR 130 having width of 60

Page 7: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 7 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

feet, which connects to national

highways.

[21] The project proponent shall ensure that no construction activity is

undertaken either on surface or below or above surface of

revenue rasta passing through the project area.

o Agreed

[22] The project proponent shall indicate the width and length of

revenue rasta passing through the project area on sign board and

shall display the same at both the ends of revenue rasta stretch,

for awareness of public. Sign board shall also display the

message that this is public rasta/road and any citizen can use it.

There shall not be any gate with or without guards on revenue

rasta further project proponent shall not encroach revenue rasta

and shall not cross internal roads over revenue rasta.

o Complied. Sign board has been

displayed (copy enclosed as

Annexure-6)

[23] The project proponent shall obtain electricity connection for

operation of plant and shall ensure that the plant is not operated

on DG sets only.

o Agreed

B. GENERAL CONDITIONS :

S.N.

CONDITIONS

COMPLIANCE

[i] The project authority must strictly adhered to stipulations made

by Haryana State Pollution Control Board & the State

Government

o All the stipulations made by

Haryana State Pollution Control

Board & the State Government

will be adhered to.

[ii] No further expansion or modification in the plant shall be carried

out without approval of SEIAA Haryana

o Agreed

[iii] The gaseous emissions from various process units shall

conform to the load/mass based standard notified by Ministry on

19th May, 1993 and standards prescribed from time to time. The

state Pollution Control Board may specify more stringent

standards for the relevant parameters keeping in view the nature

of the industry and its size and location.

o Plant in project stage. The same

shall be complied during

operation.

o Noted

Page 8: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 8 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

[iv] The project proponent shall set up continuous online AAQ

monitoring system (supervisor control & data acquisition) in the

project area to monitor the parameters viz PM2.5, PM10, NOx,

SOx and CO. The project proponent shall ensure that the values

of these parameters are within the prescribed limits of

CPCB/HSPCB.

o Our's is a grinding unit having

capacity of only 1.8 MTPA. As per

MoEF circular dated 06.04.2011,

Cement Plant having capacity >

3MTPA needs to install

Continuous Ambient Air Quality

Monitoring. Accordingly same

shall not be applicable to us.

[v] The overall noise levels in and around the plant area shall be

kept well within the standards (85dBA) by providing noise

control measures including acoustic hoods, silencers, enclosure

etc. on all sources of noise generation. The ambient noise levels

shall conform to the standards prescribed under EPA Rules, 189

viz. 75 dBA (day time) and 70 dBA (nighttime).

o All DG sets will be as per the E(P)

rule and noise level from the DG

sets will maintained as per the

prevailing standards. DG sets

shall be provided with acoustic

enclosures / room to modulate the

noise generation.

o During project stage Quarterly

Ambient Noise Monitoring is

being carried out and report

submitted to Pollution Control

Board (Copy attached as

Annexure 2)

[vi] Occupational health surveillance of the workers should be done

on a regular basis and records maintained as per the Factories

Act.

o Agreed

[vii] The project proponent shall also comply with all the

environmental protection measures and safeguards

recommended in the EIA/EMP report Further, the company must

undertake socio-economic development activities in the

surrounding villages like community development programmes,

educational programmes, drinking water supply and health care

etc.

o All the environmental protection

measures and safeguards

recommended in the EIA/EMP

report will be complied. Socio

economic development activity

will be taken as CSR Action plan

submitted. (Annexure 4)

[viii] A copy of clearance letter shall be sent by the proponent to

concerned Panchayat, Zila Parishad/Municipal Corporation,

Urban Local Body and the local NGO, if any, from whom

o Copy of clearance letter sent to

concerned.(Annexure 7)

o EC Letter uploaded on company

Page 9: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 9 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

suggestions/representations, if any, were received while

processing the proposal. The clearance letter shall also be put

on the web site of the company by the proponent.

website. (Screenshot attached as

Annexure 8)

[ix] The project proponent shall upload the status of compliance of

the stipulated environment clearance conditions, including,

results of monitored data on their website and shall update the

same periodically. It shall simultaneously be sent to the SEIAA

Haryana, Regional office of the MoEF at Chandigarh and

HSPCB Panchkula. The criteria pollutant levels namely; PM2.5,

PM10, SO2, NOx (ambient levels as well as stack emissions) or

critical sectoral parameters, indicated for the projects shall be

monitored and displayed at a convenient location near the main

gate of the company in the public domain.

o Agreed

[x] The project proponent shall also submit six monthly reports on

the status of the compliance of the stipulated environmental

conditions including results of monitored data (both in hard

copies as well as by e-mail) to the SEIAA Haryana, Regional

office of MoEF, Chandigarh and HSPCB Panchkula.

o Complied. The six monthly EC

Compliance report along with

monitoring data is regularly

submitted to SEIAA Haryana,

Regional office of MoEF,

Chandigarh and HSPCB

Panchkula.

o Last EC Compliance report was

submitted vide letter no-

UTCL/ENV/JHA/2014 dated

21/10/2014

[xi] The environmental statement for each financial year ending 31st

March in Form -V as is mandated to be submitted by the project

proponent to the concerned State Pollution Control Board as

prescribed under the Environment (Protection) Rules, 1986, as

amended subsequently, shall also be put on the website of the

company along with the status of compliance of environmental

conditions and shall also be sent to SEIAA Haryana and

Regional office of the MOEF at Chandigarh by e-mail.

o Plant is under construction. The

same shall be submitted during

operational phase.

[xii] The project proponent should inform the public that the project

has been accorded Environment Clearance by the SEIAA and

copies of the clearance letter are available with the Haryana

o Information of Environment

clearance is made to General

Public through Newspaper "The

Page 10: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 10 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

State Pollution Control Board & SEIAA. This should be

advertised within 7 days from the date circulated in the region

and the copy of the same should be forwarded to SEIAA

Haryana. A Copy of Environment Clearance conditions shall

also be put on project proponent's web site for public

awareness. Project authorities shall inform the Regional office

as well as the Ministry, the date of financial closure and final

approval of the project by the concerned authorities and the date

of commencing the land development work.

Times of India & Dainik Jagran"

on 26th March 2014.

Information is sent to SEIAA,

Haryana (Copy of newspaper

enclosed as Annexure-9)

o EC copy uploaded on Company's

website (Screenshot attached as

Annexure 8)

[xiii] The SEIAA Haryana may revoke or suspend the clearance if

implementation of any of the above condition is not satisfactory

o Noted

[xiv] The SEIAA Haryana reserve the right to stipulate additional

conditions if found necessary. The company in a time bound

manner shall implement these conditions.

o Noted

[xv] The above conditions shall be enforced, inter-alia under the

provisions of the Water(Prevention & Control of Pollution) Act

1974, The Air (Prevention & Control of Pollution) Act 1981, The

Environment (Protection) Act 1986, Hazardous Waste

(Management, Handling & Transboundary Movement) Rules,

2008 and The Public (Insurance) Liability Act 1991 along with

their amendments and Rules.

o Noted

[xvi] An Environment Cell shall be created at the project site itself

and shall be headed by qualified officer, who is well versed with

the environment aspects of the plant. It shall be ensured that the

Head of the Cell shall directly report to the Board of Directors.

o Agreed

Page 11: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 11 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure list of Six Monthly Compliance Report (From October,2014 to March,2015)

Page 12: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 12 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure:-1

Erection of Pollution Control Equipment

Page 13: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 13 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure:-2

Quarterly monitoring test report submitted letter to MoEF

Page 14: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 14 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 15: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 15 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 16: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 16 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 17: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 17 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 18: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 18 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 19: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 19 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 20: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 20 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Page 21: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 21 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure- 3

Erection of Clinker Silo & Fly Ash Silo

Page 22: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 22 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure-4

CSR Activities Carried out from Oct-14 to March-15

S.No Month Village Activities Total Expenses Beneficiaries

1 Nov-14

Jharli Ambulance provided to villagers(Arranged on hired basis) 3,084

Sasroli Medical Camp to school children at sasroli school 44,984

360 Students

Jharli Agriculture Training to Farmers including Fertilizers & Pesticides distribution

124,012 380 Person

Jhamri Veterinary Camp at Jhamri 104,521 460 Villagers

Sasroli Plantation & Chocolates distribution(Childrens Day) Sasroli School

22,979 280 Students/100 Plants

Jharli Plantation & Sweater distribution Jharli School 85,819

302 Students/100 Plants Jhamri Dari/Mat given to Jhamri School 5,208

2 Dec-14 Maliyawas Cement Given for construction/Repair of Mandir at vill-Maliyawas 60,000

3 Jan-15

Jharli Door & Windows Repairing/Replacement(Govt.School Jharli)

315,000

Jhamri Fan,Tubelites including electrical fitting at Govt.School Jhamri 60,500

15 Fan,31 Tubelites CSR Society

Jhajjar Youth for Rural Developement committee(For Developement of Youth) 50,000

Jharli Scholorship Award at Jharli School(Republic Day) 18,200

14 students

Jharli Republic Day Celebration at Jharli School 21,963 302 students

4 Feb-15

Jharli & other nearby Inter Village Sports Competition 103,647 30 Team of Nearby

Villages CSR Society

Jhajjar Youth for Rural Developement committee(For Developement of Youth) 50,000

Bajitpur Bajitpur SunderKand Path at Village 3,959

Jharli White Wash & Painting Work at Govt Sr.Secondary School Jharli (Work is in progress)

156,515

5 Mar-15 Jharli Govt.School

First Aid Training Training for School Studends at Govt.School Jharli 2,500

77 Students

1,232,891

Page 23: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 23 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure-5

Approval of firing fighting scheme from fire safety

Page 24: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 24 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure-6

Page 25: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 25 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure:-7

Submission of Copy of EC to Gram Panchayat

Page 26: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 26 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure:-8

Screenshot showing EC Uploaded on Company (UTCL Website)

Page 27: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 27 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure:-09

EC approved by SEIAA & Public through Newspaper "The Times of India & Dainik Jagran

Page 28: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 28 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)

Annexure:-10

Last EC Compliance submitted letter

Page 29: Draft-EC Compliance-Oct 14-March 15-Jhajjar Grinding …nromoef.gov.in/SMPR/12112015/55.pdf · Page 4 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set) Pollution Control

Page 29 EC Compliance report (1.8 MTPA Cement Grinding & 6x2 MW D.G.Set)