2/11/2016 1 TSUMEB SMELTER TOUR February 10, 2016 DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM 2 David Rae – EVP and COO Brent Johnson – Vice President, Environment Thinus Loftie-Eaton – Acting Vice President & General Manager, Tsumeb Smelter Barcelona Plaatjies – Director, Operations Buks Kruger – Director, Technical Services Sam Januarie – Director, Support Services Jeff Pennock – Senior Finance Advisor (Acting Finance Director) Isai Nekundi – Manager, Stakeholder & Administrative Affairs Hannes Zandberg – Project Manager, Acid Plant Project PARTICIPANTS
10

DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

Apr 23, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

1

TSUMEB SMELTER TOURFebruary 10, 2016

DPM TSUMEB

OVERVIEW SMELTERSITE TOUR

FEBRUARY, 2016

TSX:DPM 2

• David Rae – EVP and COO

• Brent Johnson – Vice President, Environment

• Thinus Loftie-Eaton – Acting Vice President & General Manager, Tsumeb Smelter

• Barcelona Plaatjies – Director, Operations

• Buks Kruger – Director, Technical Services

• Sam Januarie – Director, Support Services

• Jeff Pennock – Senior Finance Advisor (Acting Finance Director)

• Isai Nekundi – Manager, Stakeholder & Administrative Affairs

• Hannes Zandberg – Project Manager, Acid Plant Project

PARTICIPANTS

Page 2: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

2

TSX:DPM 3

SITE TOUR OVERVIEW

Effluent plant

Acid plant

Ausmelt

New converters

Acid storage tanks

Acid loading

Ausmelt baghouse

Hygiene baghouse

Arsenic plant

Old converters

Off‐gas

Acid plant laydown area

Fin‐fan coolers

1

2

3

4

5

6

7

8

Oxygen plant

TSX:DPM 4

1. New Oxygen Plant

2. Put PPE - see the effluent plant, the fin fan coolers

3. New bag houses and acid plant view

4. Layout of the site (ausmelt and converters), and fugitive bag houses, receiving bay (Ausmelt roof)

5. Converters, blister casting area and old reverbs

6. New converter area, acid loading, acid storage tanks

7. Acid plant

8. Arsenic plant

MAIN STOP POINTS

Page 3: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

3

TSX:DPM 5

• Second oxygen plant is constructed – with capacity 400 tpd

• The capacity of the old plant is 170 tpd

2ND OXYGEN PLANT

back

TSX:DPM 6

• New ausmelt baghouse was constructed – commissioned in 2013

AUSMELT BAGHOUSE

The new baghouse is built on the place of an old sinter plant

back

Page 4: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

4

TSX:DPM 7

AUSMELT / CONVERTERSSEQUENTIAL IMPROVEMENT ACTIVITIES

back

TSX:DPM 8

• Build on the place of the old gas producer

NEW HYGIENE BAGHOUSE

New hygiene baghouse

after

before

back

Page 5: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

5

TSX:DPM 9

During construction

Before the project

NEW CONVERTER SECTION

back

NOW

TSX:DPM 10

ACID PLANTFIN – FAN COOLERS

back

During constructionDuring construction

NOW

Page 6: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

6

TSX:DPM 11

EFFLUENT PLANT

back

NOW

During construction

TSX:DPM 12

• Earth works

NEW ACID PLANT

Before: Old baghouse (demolished)

During construction - 2014

During construction -2014

back

NOW

Page 7: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

7

TSX:DPM 13

Baghouse; Before, During and After backfilling

During construction – base of the converter

NEW ACID CONVERTER SECTION

Baghouse; Before, During and After backfilling

back

before

NOW

TSX:DPM 14

• New receiving bins for

ARSENIC PLANT – PNEUMATIC TRANSFER AND DUST CONTROL

Old arsenic bag house ‐ decommissionedNew baghouse

before

Pneumatic conveying and dust handling 

back

Page 8: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

8

TSX:DPM 15

ACID PLANT PROJECT – LAYDOWN AREA

June’14

January’14January’14

back

TSX:DPM 16

before

During construction 

ACID STORAGE TANKS

back

Page 9: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

9

TSX:DPM 17

ACID LOADING

back

TSX:DPM 18

• Old Converters

• Temporary hoods installed

• 3 units 10*20’ dimension

• Significant fugitive SO2 generator

• All material is charged when the converter is out of stack

CONVERTERS –PEARCE-SMITH

New Converters

• Set to be replaced with 2 new 13*30’ converters as part of the acid plant project

• Ability to charge material in-stack (flux and reverts)

• Significant reduction in fugitive emissions (SO2

capture)

• Improved energy efficiency

back

Page 10: DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016s21.q4cdn.com/589145389/files/doc_presentations/2016/DPM-Tsum… · DPM TSUMEB OVERVIEW SMELTER SITE TOUR FEBRUARY, 2016 TSX:DPM

2/11/2016

10

TSX:DPM 19

AUSMELT FURNACE

backOutotec® Ausmelt TSL Furnace Technology.MP4

TSX:DPM 20

• A hazardous waste storage was build ensuring compliance with international environmental standards

HAZARDOUS WASTE DISPOSAL SITE

back