-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 1 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
CONTENTSSection Page
SCOPE
............................................................................................................................................................4
REFERENCES
................................................................................................................................................4
INTRODUCTION
.............................................................................................................................................4
FACILITY
TYPES............................................................................................................................................5
DATA NEEDS
.................................................................................................................................................9
NAVIGATIONAL APPROACH
........................................................................................................................9
ORIENTATION OF PORT ENTRANCE & CHANNELS
........................................................................10
WIDTH OF PORT ENTRANCE &
CHANNELS.....................................................................................12Channel
Bends...................................................................................................................................13Channel
Side
Slopes..........................................................................................................................14Maneuvering
Area & Turning Basin
...................................................................................................14Area
Alongside the Berth
...................................................................................................................14Water
Depth
.......................................................................................................................................15
LOCATION AND ORIENTATION OF FIXED BERTH(S)
..............................................................................15
ENVIRONMENTAL
CONDITIONS........................................................................................................15
SPACING GUIDELINES
.......................................................................................................................15
SPECIAL CONSIDERATIONS FOR LNG BERTHS
.............................................................................16
LAYOUT OF BREASTING AND MOORING DOLPHINS
.............................................................................17
LOADING PLATFORMS
.......................................................................................................................17Elevation
............................................................................................................................................17Alignment
&
Setback..........................................................................................................................18Dimensions
........................................................................................................................................18
EQUIPMENT
SPACING........................................................................................................................19Loading
Arms
.....................................................................................................................................19Hose
/ Hose
Tower.............................................................................................................................21
BUNKERING.........................................................................................................................................22
GANGWAYS (POWERED / MANUAL)
.................................................................................................23
PIPELINE MANIFOLDS
........................................................................................................................24
METER RUNS /
PROVERS..................................................................................................................27
OPERATORS SHELTER
.....................................................................................................................27
CRANES (HOSE / GANGWAY HANDLING OR MAINTENANCE)
.......................................................28
CONTAINMENT AREA
.........................................................................................................................28
FIRE FIGHTING (PUMPS, DRUM, MONITORS,
ETC.)........................................................................29Fire
Pumps.........................................................................................................................................29Foam
Tanks
.......................................................................................................................................30Water
/ Foam
Monitors.......................................................................................................................30Fire
Hydrants / Hose Reels
................................................................................................................30Fire
Equipment
Cabinet......................................................................................................................30
EMERGENCY ISOLATION
EQUIPMENT.............................................................................................30
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 2 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
CONTENTS (Cont)Section Page
UTILITY RACKS, BACKFLOW PREVENTER & METER
.....................................................................
31
ELECTRICAL PANELS / JUNCTION BOXES
......................................................................................
32
OIL SPILL RESPONSE EQUIPMENT
..................................................................................................
32
MVR VAPOR HEADER &
ARRESTORS..............................................................................................
32
WALKWAY / OPEN AREAS
.................................................................................................................
32
SMALL CRAFT / LAUNCH
ACCESS....................................................................................................
32
ACCESS TRESTLE
......................................................................................................................................
33
OTHER FACILITIES AND EQUIPMENT
......................................................................................................
36
ANCHORAGE.......................................................................................................................................
36Breakwaters
.......................................................................................................................................
37Navigational Aids
...............................................................................................................................
38Small Boat
Harbor..............................................................................................................................
38Tier 1 Oil Spill Response Equipment
.................................................................................................
38
BUOY TERMINALS (MBM & SPM)
..............................................................................................................
38
LOCATION
...........................................................................................................................................
38
ORIENTATION
.....................................................................................................................................
40Water
Depth.......................................................................................................................................
40
CBB SHIP ANCHOR LAYOUT CONSIDERATIONS
............................................................................
40
CBB BUOY LAYOUT
CONSIDERATIONS...........................................................................................
41
CBB PLEM LOCATION CONSIDERATIONS
.......................................................................................
43
TABLESTable 1 Port Entrance Channel Segment
Length.......................................................................
10Table 2 Loading Arm Spacing Guidelines
..................................................................................
19Table 3 Loading Arm Setback Guidelines
..................................................................................
20Table 4 Space Guidelines for Meter Runs
.................................................................................
27Table 5 Space Guidelines for Meter Provers
.............................................................................
27Table 6 Space Guidelines for Isolation
Valves...........................................................................
30Table 7 Pipeline Loop
Dimensions.............................................................................................
36Table 8 Tanker Anchor Chain Length
........................................................................................
40
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 3 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
CONTENTS (Cont)Section Page
FIGURESFigure 1 Types of Conventional
Piers..........................................................................................6Figure
2 Types of Sea Islands
.....................................................................................................6Figure
3 Types of Multiple Buoy Berths
.......................................................................................7Figure
4 Types of Single Point Mooring
Berths............................................................................8Figure
5 Channel
Sections...........................................................................................................9Figure
6 Types of Harbors /
Ports..............................................................................................11Figure
7 Navigational Channel Lane Types
...............................................................................12Figure
8 Channel Segment Arrangement
..................................................................................13Figure
9 Layout of Widened Parallel
Bends...............................................................................14Figure
10 Finger Pier Spacing
.....................................................................................................16Figure
11 Loading Platform Alignment & Setback
.......................................................................18Figure
12 Loading Arm Layout and
Spacing................................................................................21Figure
13 Space Allocation for Hose
Towers...............................................................................22Figure
14 Space Allocation for Tower
Gangway..........................................................................24Figure
15 Pipeline Manifold Layout -- Single Corridor
Arrangement............................................25Figure 16
Pipeline Manifold Layout -- Dual Corridor Arrangement
..............................................26Figure 17 Meter Run
Typical Arrangement
...............................................................................27Figure
18 Meter Prover -- Typical
Arrangement...........................................................................28Figure
19 Typical Layout for Firewater Pump Station
..................................................................29Figure
20 Isolation Valve Vertical Installation
...........................................................................31Figure
21 Isolation Valve Horizontal Installation
.......................................................................31Figure
22A Access Trestle Arrangement #1
..................................................................................33Figure
22B Access Trestle Arrangement #1
..................................................................................34Figure
23A Access Trestle Arrangement #2
..................................................................................34Figure
23B Access Trestle Arrangement #2
..................................................................................35Figure
24A Diameter of Free-Swinging Anchorage
Areas..............................................................37Figure
24B Maneuvering at Conventional MBMs
..........................................................................39Figure
25 Layout of
SPMs...........................................................................................................39Figure
26 Layout of
MBMs...........................................................................................................41Figure
27 MBM with Forward Breast Buoy
..................................................................................42
Revision Memo
12/00 Initial issue of Design Practice XXXI-C.
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 4 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
SCOPE
This design practice covers the layout and spacing
considerations for conventional piers, sea islands, multi-buoy
moorings, andsingle point moorings. These considerations are
primarily intended to apply to the design of new terminals or new
berths atexisting terminals. This Design Practice may also be used
to determine if an existing berth is suitable to handle a
differentsize / type of vessel.
This Design Practice provides general guidelines and rules of
thumb for use in the early planning phases of projects (Gate
1review). These considerations should be supplemented and
reconfirmed by detailed studies e.g. shiphandling simulation,model
testing, mooring analysis, numerical modeling of coastal processes,
etc prior to project approval and final design.
Because the basic units for this technology are metric, the
usual convention of using customary first has been reversed for
theunits.
REFERENCES
DESIGN PRACTICES
Section XXXI-I Safety Considerations for the Design of Marine
Terminals
Section XXXI-L Evacuation, Egress, and Safe Haven
Considerations
Section XXXI-M Fender Systems
INTERNATIONAL PRACTICES
IP 3-2-3 Firewater Systems
IP 3-7-1 Piping Layout, Supports and Flexibility
OTHER REFERENCES
1. Approach Channels A Guide for Design, Permanent International
Association of Navigation Congresses (PIANC), June1997
2. Site Selection and Design for LNG Ports and Jetties, Society
of International Gas Tanker and Terminal Operators,Information
Paper 14, 1st Edition, January 1997
3. Design Manual 26.1 Harbors, Naval Facilities Engineering
Command, December 1984
4. Port Engineering Volume 1, 4th Edition, Per Brun, Gulf
Publishing, 1989
5. Underkeel Clearance in Ports, Exxon International Tanker
Department, EII.1TTM.82, Nov. 1982
6. Design Manual 25.1 Piers & Wharves, Naval Facilities
Engineering Command, October 1987
7. Marine Safety Criteria for Industry Vessels in ExxonMobil
Service, International Marine Transportation Ltd., 2000 Edition
8. Planning and Design of Pier Facilities, Mobil Technology
Company, MP 05-P-02, July 1999
9. Manual of Petroleum Measurements, API
10. Shore Protection Manual, US Army Corps of Engineers,
1984
11. Planning and Selection Guide for Oil Spill Response
Equipment, ER&E Report No. EE.39E.93
12. Rules for Classifying and Building Steel Vessels-Part 3,
American Bureau of Shipping (ABS), 1997
INTRODUCTION
The siting and layout of a berth and the navigational approach
are critically important to a project with respect to
riskprevention, berth operability, and investment costs. The
orientation, layout and dimensioning of navigational channels
andmaneuvering areas should be properly determined in order to
reduce the probability of port passage collisions and
groundingincidents. Conventional piers, Sea Islands, and multiple
buoy moorings (MBM) should be carefully positioned and oriented
tominimize exposure to waves so that berth downtime is minimized.
The investment cost will be significantly impacted if a pier orsea
island is positioned without suitable natural sheltering thus
requiring construction of a breakwater. The need for dredgingand/or
installation of a long access trestle or submarine pipeline length
from shore can also significantly affect the investmentcost. The
layout of the berth structures and loading platform can help to
prevent and mitigate berth-related incidents (berthing,mooring,
fires, etc.).
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 5 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
FACILITY TYPES
Many different types of marine facilities exist to satisfy
different geographical conditions, environmental conditions,
andoperating requirements. Marine berth facilities are broadly
classified into the following four categories:
Conventional Piers
Sea Islands
Multiple Buoy Moorings (MBM)
Single Point Moorings (SPM)Downstream terminals typically fall
in the first three categories with most being conventional piers.
Upstream terminalsfrequently are of the single point mooring
type.
Conventional Piers - Encompass all variations of wharf,
bulkhead, breasting platform and dolphin-type piers.
Conventionalpiers are generally sub-categorized into the following
two types of piers based on their orientation to the shoreline:
Marginal Pier Oriented parallel to the shoreline because of
current patterns or pier line or channel restrictions.
Finger Pier Oriented perpendicular to the shoreline usually due
to limited waterfront area and the need for multiple
berthsBreasting Dolphins A water based structure, independent of
the loading platform, that absorbs the impact of a berthing shipand
against which a moored ship breasts.
Breasting Platform A water based structure that serves the dual
purpose of breasting dolphins and a loading platform.
Bulkhead / Quay Wall A continuous faced, land based type of pier
typically oriented parallel to the shoreline and backed byfill.
Loading Platform A water based structure used to support cargo
transfer equipment, firefighting and safety equipment,sumps, etc.
when breasting dolphins are used.
Mooring Dolphin A water based structure, independent of the
loading platform, to which the vessels mooring lines
areattached.
Mooring Point A land based structure, to which the vessels
mooring lines are attached.
Trestle A water based structure used to connect a breasting or
loading platform to shore. Trestles usually consist of pipesupports
and a roadway.
Turning Dolphin A water based structure, located at the offshore
end of a finger pier that may be contacted by the vesselduring the
turning maneuver into the berth and to which the vessels mooring
lines are attached.
Wharf A continuous faced, water based type of construction used
for finger piers and supported on piles.
Generally, dolphin type piers usually require less investment
than wharf or bulkhead type terminals. Bulkhead type terminalsare
normally suitable for water depths of 7 meters or less. Breasting
platforms are generally not recommended due toconcerns of possible
damage to cargo transfer equipment (and spill) should a berthing
incident occur.
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 6 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
FACILITY TYPES (Cont)
FIGURE 1TYPES OF CONVENTIONAL PIERS
Bresting Dolphin
Roadway
DOLPHIN TYPE WHARF TYPE
MARGINAL PIERS FINGER PIERS
Mooring Dolphin
Loading PplatformPipe Trestle
Shoreline
Shoreline
Turning Dolphin
BREASTING PLATFORM TYPEBULKHEAD/QUAY WALL TYPEDP31Cf01
Sea Islands Offshore berths that are similar in construction to
dolphin or breasting platform types of conventional piersexcept
that their only connection to shore is by submarine pipelines. Sea
Islands can be designed to service ships on one orboth sides.
FIGURE 2TYPES OF SEA ISLANDS
SINGLE SIDE TYPE DUAL SIDE TYPE
Loading Platform
Submarine PipelinesMooringDolphins
Breasting Dolphin
DP31Cf02
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 7 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
FACILITY TYPES (Cont)
Multiple Buoy Moorings (MBM) There are two main categories of
Multiple Buoy Moorings (MBM):
Conventional Buoy Berth (CBB) Offshore berths in which the ships
bow is held in position by the ships ownanchors while 3 to 7
mooring buoys are used to secure the stern. CBB are themost common
type of MBM.
All Buoy Berth (ABB) Offshore berths in which both the ships bow
and stern are held in position by atotal of four to eight mooring
buoys. ABBs are generally located where bottomconditions prevent
the use of ships anchors or where additional mooring restraintis
needed for the expected environmental conditions.
At buoy berths, submarine pipelines run from shore tankage to
the area of the buoys. Loading or unloading operations
areaccomplished through a system of flexible hoses that are
connected between the submarine pipeline end manifold and theships
manifold.
FIGURE 3TYPES OF MULTIPLE BUOY BERTHS
CONVENTIONAL BUOY BERTH (CBB) ALL BUOY BERTH (ABB)
Buoy Chain
Anchor
Hose
Pipeline
Mooring lines
Ship's Anchorand Chain
Hoses
Pipelines
Anchors
Mooring lines
Mooring lines
End Manifold Pipelineto Shore
DP31Cf03(May have 3,5,or 7 Bouys, Shown Above)
Single Point Moorings (SPM) At SPMs, ships are moored with only
a bowline to a single buoy or tower. Consequently, theship is free
to weathervane around the point to which the bowline is attached.
The cargo is transferred by rubber hosesbetween the ships manifold
and a cargo swivel located on the SPM. The two most common types of
SPMs are:
CALMs Catenary Anchor Leg Moorings are comprised of a single
buoy restrained by afive to eight conventional chain-anchor legs.
The cargo is conveyed between thesubmarine pipeline and the buoy by
submarine hoses. The mooring line isconnected to the cargo swivel
on the buoy by a lever arm. This device is used torotate the swivel
with the mooring line. Floating hoses connect the cargo swivelon
the buoy to the vessel manifolds. CALMs are the most common type of
singlepoint mooring.
SALMs Single Anchor Leg Moorings are comprised of a buoy moored
by means of onevertical chain or pipe attached to a single base
anchored to the seabed. Thecargo is transferred from a submerged
cargo swivel to the ships manifold byrubber hoses. The swivel is
turned by the cargo hoses. The ships bow mooringline is attached to
the buoy.
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 8 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
FACILITY TYPES (Cont)
FIGURE 4TYPES OF SINGLE POINT MOORING BERTHS
TYPICAL CALM SYSTEM
Turntable
SubmarineHose Strings
Seabed
FloatingHose Strings
Manifold
Mooring Assemblies
Anchor Chain
MSL
Pipeline EndManifolds
SubmarinePipeline Anchors or
Anchor Piles
TYPICAL SALM SYSTEM
MSL
Manifold
Seabed
Hose Strings
Piles
Mooring Buoy
Mooring
Anchor Leg Swivel
Anchor Leg
Fluid Swivel Assembly
UniversalJoints
Jumper hose
Pipeline End Manifold
DP31Cf04
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 9 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
DATA NEEDS
The principal information needed for the siting and layout of
the berth and navigational channel include:
Hydrographic Charts & Bathymetry
Tidal Range & Water Level Variations
Environmental Conditions:(For different return periods)
+ Wave Intensity & Direction
+ Current patterns, velocity & direction
+ Wind Rose
+ Other (seismicity, ice, fog, etc.)
Geotechnical Information of Seabed Conditions &
Materials
Location of Environmentally Sensitive Areas and Navigational
Restrictions
Fleet of Vessels (parameters for expected range of products and
sizes)
NAVIGATIONAL APPROACH
The general location of the terminal site and the navigational
approach often will be often be dictated by the proximity to
theonshore process or producing facilities. Guidelines for port
siting is are not covered in the Design Practice. Siting
guidelinesare covered in References 1-4. Layout, orientation and
dimensioning of navigational approaches should be jointly developed
inconsultation with a nautical specialist from one of ExxonMobils
marine transportation companies (SeaRiver Maritime orInternational
Marine Transportation).
For a particular site location, the first step in developing a
preliminary layout of the navigational approach is to subdivide it
intosections based on the severity of the environmental conditions.
Typically, these sections include (Figure 5):
Outer Approach Channel & Port Entrance
Inner Approach Channel
Vessel Stopping Area and Turning Basin
Berth Maneuvering Area
FIGURE 5CHANNEL SECTIONS
BERTHS MANEUVERING AREA
InteriorChannel
Open Ocean wave
Environment
Transition to Protected
Wave Environment
EntranceChannel
Port Entrance
OuterChannelEntrance
Vessel StoppingArea and Turning
Basin
Berth area
DP31Cf05
~
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 10 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
NAVIGATIONAL APPROACH (Cont)
The terminal may be sited within different types of natural or
artificially protected harbors (Figure 6) that include
landextensions (man-made or natural) that border and protect the
inner port area. The port entrance provides vessel passage fromthe
outer channel in the open sea to a wave-sheltered inner channel and
berth area. Where there is no defined barrier, theentrance to the
dredged approach channel may be considered as the port entrance. In
the latter case, the design of theapproach channel from the sea
entrance to the maneuvering area at the berth should be adjusted
along its length to accountfor the differences in natural
sheltering and environmental conditions.
ORIENTATION OF PORT ENTRANCE & CHANNELS
The principle considerations governing the layout of channels
are:
Shortest channel length
Conditions / basins at either end of the channel
The need to avoid obstacles that are difficult / costly to
remove / dredge and areas subject to high siltation rates that
wouldrequire excessive maintenance dredging
Prevailing winds, currents and waves
Avoiding bends near port entrances
The edge of channels should be positioned such that passing
ships do not damage neighboring berths, facilities and do notcause
excessive movements / forces on moored vessels.
Channels should be oriented parallel to the berth lines and
directed to a safe position off the berth (to avoid possibility
ofdirect collision with the berth if vessel engine fails).
The outer channel and port entrance should be designed so that
the action of waves, currents and winds are directed as closeas
possible toward the bow or stern of the ship. Both outer and inner
channels should follow as straight a line as possible.Bends in
close proximity to the entrance should be avoided with straight
channel segments extending to and from the entrance.Length of
straight segments on either side of the port entrance should be set
based on length of the largest vessel and speedper Table 1.
TABLE 1PORT ENTRANCE CHANNEL SEGMENT LENGTH
PORT ENTRANCE CHANNELS
VESSEL SPEED, (KNOTS) STRAIGHT SEGMENT LENGTH*
5 - 8 2.5-3 L
8 - 12 3-4 L
> 12 4-5 L
* - Multiplier of largest vessel LOA
The effect of cross currents, winds or waves together with
limited maneuverability or speed results in vessels
proceedingforward at a small angle (drift) to their correct course.
The orientation of the channel / entrance should consider
theenvironmental conditions and vessel maneuverability and should
be adjusted as needed to ensure that the drift angle does notexceed
10 - 15 degrees.
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 11 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
NAVIGATIONAL APPROACH (Cont)
FIGURE 6TYPES OF HARBORS / PORTS
ARTIFICIAL HARBORS
Inland Basin Offshore Basin
PROTECTED HARBORS
Natural Harbor
River Harbor
Bay Indentation Offshore Island
DP31Cf06
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 12 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
NAVIGATIONAL APPROACH (Cont)
WIDTH OF PORT ENTRANCE & CHANNELS
Channels can be classified for either one way or two way ship
traffic. The width of a channel for one way traffic is determinedby
subdividing into lanes, a basic maneuvering lane with additions for
environmental and operational conditions and a bankclearance on
each side of the channel. For channels with two-way traffic, an
additional lane or width for the passing clearancebetween ship
lanes is provided. The lanes are illustrated on Figure 7.
FIGURE 7NAVIGATIONAL CHANNEL LANE TYPES
Channel Axis
PassingDistance
Manuvering
Lane
Manuvering
Lane
Bank ClearanceBank Clearance
DP31Cf07
The basic maneuvering lane is the vessels beam plus the distance
required for the pilot to identify and execute a requiredchange in
course. This lane is expanded to account for the additional channel
width necessary to contain the ships track dueto wind, wave, and
current effects and account for other operational factors. A bank
clearance is included on each side of thechannel if there is a
natural bank or bank created by dredging.
The width of the channels and port entrance should be determined
in accordance with Reference 1 with the following inputdata:
Maximum Vessel Size (Length & Beam)
Channel Use (one-way or two-way)
Vessel Maneuverability
Vessel speed
Prevailing cross wind & current, longitudinal current,
&wave conditions
Navigation aids
Depth to draft ratio
Seabed conditions
Cargo Hazard Level
Bank Condition
Port Traffic DensityReference 1 (Section 5.3) defines the
channel width as a multiple of the ship beam based on the above
factors. Differentvalues are provided for outer channels exposed to
open sea and for inner channels in protected waters. Values for
outerchannels should be selected if the section of channel is
exposed to waves of significant wave height of 1 meter or
more.Channel use i.e. one-way or two-way, should consider the
number of vessels calling at the terminal and any other traffic
callingat other terminals within the port. The operational delay
cost of incoming vessels awaiting departure and clearance of
outgoingvessels needs to be weighed against the additional
investment cost of dredging a wider channel.
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 13 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
NAVIGATIONAL APPROACH (Cont)
Moderate vessel maneuverability may be assumed for most tankers
and gas carriers in selecting the width of the basicmaneuvering
lane width (1.5 times beam) from Reference 1. Assumptions regarding
vessel speed should be checked with anautical specialist from one
of ExxonMobils marine companies (SeaRiver Maritime or International
Marine Transportation).The selection of environmental parameters
should reflect site-specific metaocean conditions and be set high
enough to avoidexcessive port downtime. The value of the
navigational aid factor should be assumed as moderate for most port
locationsunless site-specific visibility conditions warrant an
adjustment. Cargo hazard should be assumed as moderate for tankers
andhigh for gas carriers. Reference 2 states that the total channel
width should be about five times the beam for LNG ships.
The width of the port entrance should be determined from
Reference 1 using the above approach or set equal to the
vessellength, whichever is greater.
Channel Bends
A channel bend should be included in a design only where
absolutely necessary. Channel bends increase the risk of
vesselgrounding due to failure of the steering gear or human error.
The change in water flow in a bend will also affect the handling
ofthe vessel and requires more width than a straight section. Other
factors that increase the difficulty of maneuvering in a
bendinclude the reduction of clear sight distance and navigational
aid effectiveness.
Where possible, channels should also be oriented to meet the
following idealized objectives:
A single curve is preferred over a sequence of smaller turns at
close intervals, provided the channel is clearly marked.
Straight segments with lengths not less than five times the
vessel LOA should separate successive bends (Figure 8).
FIGURE 8CHANNEL SEGMENT ARRANGEMENT
Preferred Arrangement of NavigationalBuoys
(Gated Buoys)
R
R
R
RR = Bend Radiusa = Bend Angle
DW= Additional Width
W+DW
a
a
W1
W2
W+DW
5L
DP31Cf08
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 14 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
NAVIGATIONAL APPROACH (Cont)
For single screw tankers and other vessels with limited
maneuverability, a widened parallel curve is required (Figure
9).Widening of the curve should begin as a transition from the
preceding channel and reach its full width at the start of the
bend.Such a transition causes a change in the hydrodynamic forces
acting on the vessel as it enters the turn. Reference 3 statesthat
a transition length of 10 times the additional width is required.
Reference 1 defines the required radius of the bend andwidth as a
function of vessel rudder angle and water depth to draft ratio. For
the bend radius, values are given in terms as aratio of the vessel
length between perpendiculars. The additional width is the
difference between the value obtained fromReference 1 for the bend
and straight segments. In order to provide a maneuvering safety
margin, the bend dimensions shouldbe based on a vessel rudder angle
not exceeding 20 degrees.
FIGURE 9LAYOUT OF WIDENED PARALLEL BENDS
d Angle of Deflection
20
1
20 1
Transition
Ly
w+dw
w
R
20
20
1
1
Ly
Transit
ion
w
d Central Angled = Constant
DP31Cf09
2
dw
2
wRR1 = 2
dw
2
wRR2 ++=
Channel Side Slopes
For dredged channels, the effect of the side seabed slopes on
the channel layout and dredging quantities should also
beconsidered. Underwater slopes are usually much flatter than
abovewater slopes in order to avoid excessive sloughing
andredeposition in the channel due to exposure to waves, currents,
propeller wash, etc. For soft, muddy bottoms, side slopes of1:10
(vertical to horizontal) are common. For denser, sandy bottoms,
side slopes of 1:5 are common. Final selection of theseabed slope
should be based on the results of a geotechnical investigation.
Maneuvering Area & Turning Basin
The actions of stopping and turning of vessels governs the
layout and dimensioning of the maneuvering area. The distance
inwhich a vessel is stopped is a function of several parameters
including initial vessel speed, water depth,
environmentalconditions and tug assistance. The length of the
channel and maneuvering area should be sufficient to ensure that
the vesselcan safely stop without overshooting the berth area. For
planning studies, stopping distances should be checked on the
basisof one vessel length for each knot of initial vessel
speed.
Section XXXI-I states the required minimum diameter for turning
basins. Reference 2 states that the diameter of turningbasins for
LNG ships be two to three times the vessel length.
Area Alongside the Berth
The length of the area alongside the berth should be sufficient
to satisfy the spacing criteria provided in Section XXXI-I for
thelargest vessel. There should be a gradual transition between
this area alongside the berth out to the full dimensions of
theturning basin / maneuvering area.
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 15 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
NAVIGATIONAL APPROACH (Cont)
Water Depth
Section XXXI-I provides minimum requirements for water depth and
minimum underkeel clearance for the berth area for aconventional
pier or Sea Island, and maneuvering area / turning basin. The
immediate berth area is defined with a length asstated above and a
width of 1.5 times the beam from the berth fender line. To allow
for flexibility so that the vessel can eitherbe turned on arrival
or at departure from the berth, the turning basin depth should be
also based on the maximum vessel draft.
Reference 5 provides a rational approach for determining the
underkeel clearance for the inner channel, and outer channel
/entrance. The primary difference in calculating underkeel
clearance between the berth area and the channel / entrance areasis
the effect of vessel response to waves and squat. Squat is the
combined effect of sinkage and trim due to the forwardvelocity of a
ship. In the absence of a detailed analysis using Reference 5, a
minimum underkeel clearance can be set at 15%of maximum draft for
inner channels and at 30% for outer channels and port
entrances.
Whereas, the water depth in the berth area should consider the
maximum draft at low tide, a higher tidal level may beconsidered
for the design of the approach channel and entrance. However, it is
imperative that the selected tidal level allowssufficient time for
the vessel to transit the channel with additional safety / time
margin (to account for possible vessel delays andbreakdowns). The
impact of tidal restrictions on vessel delay costs and berth
occupancy should also be evaluated. Theselection of a tidal level
above low tide for the basis of the channel depth should be jointly
developed with a nautical specialistand based on a comprehensive
risk assessment. For example, the risk assessment should evaluate
provisions (channeldepth, anchorage area, tug assistance, etc.)
necessary to keep the vessel afloat through the full tidal cycle
should failure of themain engine occur during the port passage.
LOCATION AND ORIENTATION OF FIXED BERTH(S)
Where possible, berths should not be located along bends of an
existing navigational channel. Berths situated off the outsidelimit
of a channel bend are subjected to increased risks of collision
from passing ships experiencing engine or steering gearfailure.
Berths situated off the inside limit may experience higher
siltation rates and higher costs of maintenance dredging.
ENVIRONMENTAL CONDITIONS
In general, conventional piers and sea islands should be aligned
parallel to the direction of the predominant environment inorder to
minimize loads on the moored ship and reduce the probability of
mooring incidents. Where there is no predominantenvironment, the
pier should be oriented to minimize initial construction costs and
any periodic maintenance dredging costs.The location and
orientation of the berth should consider the following:
Conventional piers and sea islands should normally be sited with
sufficient sheltering such that significant wave heights areless
than 1.2 meters more than 90% of the time. Somewhat higher waves
(up to 1.5-2 meters) may be accommodated ifthe wave sector is well
defined and narrow, and the vessel aligned such than waves strike
the bow. More restrictiveconditions should be considered for piers
and Sea Islands handling vessels less than 5 KDWT.
Piers and Sea Islands, where wave heights do not exceed 1.2
meters, should be aligned parallel with the direction of
thestrongest current, if the velocity exceeds 1 knot.
Piers and Sea Islands with mild wave and current conditions
(i.e. below the above limits) but subject to strong prevailingwinds
should be oriented such that wind forces tend to push the vessel
onto the berth fenders.
The above factors are critical to determining whether a marginal
or finger pier type of conventional pier is appropriate.
SPACING GUIDELINES
For marginal type piers, there should be a spacing of at least
125 + B (meters) between the limit / edge of the
navigationalchannel and the berth fender line, where B equals the
beam of the largest moored vessel.
Minimum spacing guidelines covering vessel to grounding contour
(or wall or other fixed obstruction) and vessel to vesselspacing
(for marginal berths) are stated in Section XXXI-I. Figure 10
illustrates the required spacing between finger piers(from
Reference 6).
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 16 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LOCATION AND ORIENTATION OF FIXED BERTH(S) (Cont)
FIGURE 10FINGER PIER SPACING
MULTIPLE BERTH PIERS
C PierL C PierL
7 x Ship
Beam
DP31Cf10SINGLE BERTH PIERS
6 x Ship
Beam
L LC PierC Pier
SPECIAL CONSIDERATIONS FOR LNG BERTHS
Per Reference 2, the following items should be also be
considered for LNG jetties:
Jetty location should be remote from populated area and should
also be well removed from other marine traffic and anyport activity
that may cause a hazard.
The maximum credible spill and its estimated gas cloud range
should be carefully established.
River bends and narrow channels should not be considered as
appropriate for LNG jetties.
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 17 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS
The layout of breasting and mooring dolphins at conventional
piers and Sea Islands should meet the requirements as stated
inSection XXXI-I and Section XXXI-M and those stated herein:
Breasting dolphins / fenders should be spaced (centerline to
centerline) at a distance greater than 0.25 LOA of the
largestvessel and less than 0.5 LOA of the smallest vessel calling
at the berth. If these limits can not be fully satisfied by
twobreasting dolphins, intermediate dolphins / fenders should be
provided as required to satisfy these limits. Breastingdolphins
should be located as symmetrically as possible about the centerline
of the hose connection manifold or loadingarm group.
For berths handling barges, a continuous independent fender
system or breasting beam supported from the breastingdolphins
should be provided in front of the loading platform to protect it
against accidental contact.
For berths handling barge tows, sufficient breasting points
should be provided along the fender line to ensure that
eachindividual barge in the tow is supported by at least two
breasting points.
All fenders should lie on the same breasting line.
Spacing of outer mooring points should be slightly greater than
the LOA of the largest vessel.
For providing effective breast, head and stern line leads, there
should a sufficient number and positioning of mooring pointssuch
that the orientation of mooring lines relative to the vessel
longitudinal axis is between 60-120 degrees (+/- 30 degreesfrom
perpendicular).
The setback of the mooring points from the breasting line should
be sufficient to limit the vertical inclination of mooringlines to
30 degrees or less for tankers and 45 degrees or less for barges
for their expected range of freeboard and tideconditions. The
setback of the mooring points from the fender line should normally
not exceed a distance equal to thebeam of the largest tanker. For
barge berths, the setback should be limited to the beam of the
largest single barge.
Mooring points should be arranged such that lines from adjacent
vessels do not cross.
The total number of mooring bollards and hooks should exceed the
maximum number of mooring lines stated in Reference7 for the
maximum size vessel. Additional bollards and hooks typically will
be required to accommodate different sizevessels and to provide
allowance to run extra lines during inclement weather.
Dolphins should be interconnected by walkways for access by line
handling crews and terminal personnel and foremergency egress from
the loading platform. At least one dolphin should be designated as
the primary evacuation pointfor Sea Islands and as a secondary
evacuation point for conventional piers with a main access trestle.
Evacuation pointsshould be located at least 60 meters from the fire
risk area on the loading platform. For conventional marginal piers,
awalkway from the evacuation point back to shore should be
considered. Additional emergency evacuation, egress, andsafe haven
considerations will be provided in a future Section XXXI-L.
LOADING PLATFORMS
All equipment and systems provided on the loading platform
should be located considering the proximity and orientation
relativeto the vessel, and must be able to function while not
interfering with the operation of other systems that either may
operatesimultaneously or may be at rest. Each system also requires
sufficient spacing from other equipment for access by operatingand
maintenance personnel. The equipment spacing requirements and
loading platform dimensions are covered herein.
Elevation
The deck elevation of the loading platform should be
sufficiently high so it is not submerged during high waters or is
overtoppedby waves. The minimum deck elevation should be calculated
as follows:
ELDECK = ELDATUM + HHHWL + HMSS + H60MW
where: ELDECK = Deck elevationELDATUM = Chart datumHHHWL =
Height of maximum tide above datumHMSS = Height of maximum storm
surgeH60MW = 60% of the height of the maximum wave
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 18 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
Other factors affecting the deck elevation include:
Elevation range of the vessel deck and the impact on mooring
line vertical angles,
Elevations of adjacent existing berth structures and shoreline
and the impact on the slope of the access road / trestleslope,
Depth allowance for the platform deck and support beams so they
are positioned above waves in order to eliminatesplashing and wave
loading.
Alignment & Setback
The centerline of the loading platform should normally coincide
with the centerline of the cargo transfer system as shown inFigure
11. This is desirable so that the vessel manifold can be aligned
with both the cargo transfer system as well as thecenter of the
platform and berth.
The offshore face of the loading platform should be set at least
1.8 m (6 ft) to the shore side of the breasting line (Reference
9)as shown in Figure 11.
FIGURE 11LOADING PLATFORM ALIGNMENT & SETBACK
Loading Platform andCargo Transfer System
Mooring Dolphin(typ.)
20m to 26m(min.)
LC
LCShip's Manifold
1.8m (typ.)
DP31Cf11
13m
to 1
8m
(min
.)
Dimensions
Loading platform dimensions are directly related to the type of
facility and the total area required to accommodate the
varioussystems and equipment. Finger piers, whether wharf or
breasting platform type, usually serve two vessels and have
largerdeck areas than a dolphin type marginal pier serving only one
similar size vessel. Finger pier sizes may be controlled
primarilyby structural / mooring / berthing considerations, whereas
the loading platform size in a dolphin type marginal pier is
usuallycontrolled by the facilities it carries. Each systems space
requirement is separately discussed in the following paragraphs.The
length may be affected by the positioning of mooring hooks for
spring lines and the width by hooks for the breast lines(keeping
vertical angle of lines below 30 degrees).
Typical width of loading platforms is in the range of 13 18 m
(40 60 ft). Typical minimum width of a two-sided two-berth pieris
15 m (50 ft), due primarily to fire fighting and safety
considerations. Typical length is in the range of 20 30 meters (65
100 ft).
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 19 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
The loading platforms overall dimensions, layout and space
allocation is determined considering the following
systems,structures, and operations:
Cargo transfer systems (loading arms, hoses, etc.)
Material handling systems (cranes, winches, etc.)
Cargo dock piping (manifolds, stripping, sampling, blending,
metering, and pigging)
Cargo drainage, sumps, and oily water containment facilities
Vessel access systems (or space for the vessels gangway
landing)
Fire fighting systems (foam / water, hydrants / monitors,
etc.)
Utility service connections and utility dock piping (potable
water, storm drainage, compressed air, steam, nitrogen, etc.)
Mooring equipment
Dock operator shelter
Vehicular access and maneuvering
O&M personnel access
EQUIPMENT SPACING
Loading Arms
Deck space allocation for all-metal loading arms depend on
factors such as:
Operating envelopes to be accommodated
Size (pipe diameter, riser / inboard / outboard arms
lengths)
Type and manufacturer
Optional equipment (piggy-back vapor lines, ERS and
quick-connect couplings, etc.)
Manifold location, spacing and number of lines in / out
Simultaneous service requirements
Fender system geometry
Maintenance requirements (of the arms)Typical positioning and
deck space allocation for loading arms on a loading platform is
illustrated on Figure 12 and coveredherein. Spacing of loading arms
should normally equal or exceed the spacing between the lines on
the vessel manifold andshould be sufficient to avoid clashing. For
planning purposes, the spacing (distance between adjacent loading
arm centerlines)guidelines in Table 2 may be used.
TABLE 2LOADING ARM SPACING GUIDELINES
ARM SIZE DIAMETER (in.) ARM CENTERLINE SPACING (m)
6 - 8 2.0 - 2.5
10 - 12 2.5 - 3.0
16 3.0 - 3.5
> 16 3.5 - 4.0
If a bank of loading arms includes arms of different sizes,
uniform arm spacing based on the largest arm, should be used.
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 20 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
For planning purposes, the setback (distance between adjacent
loading arm centerlines) guidelines in Table 3 may be usedwith the
following considerations:
Positioned sufficiently away from the edge of the platform to
enable personnel access along the face of the berth for
armmaintenance, and to prevent any contact between a berthing
vessel and the stored arms.
Positioned at a close proximity to the front of the platform /
fender line in order to minimize the reach and thereby reducethe
arm size (length).
Positioned such that the outboard end flange of the loading arm
in the stored position is situated at least 0.3 0.6 m (1 2ft)
inboard of the inside face of the containment curb.
If a bank of loading arms includes arms of different sizes, the
setback of largest arm governs.
TABLE 3LOADING ARM SETBACK GUIDELINES
ARM SIZE DIAMETER (in.) ARM RISER CENTERLINE SETBACKFROM
PLATFORM FACE (m)
6 - 8 2.0 - 2.5
10 - 12 2.5 - 3.0
16 3.0 - 3.5
> 16 3.5 - 4.0
Access must be provided in the design of loading arms for
periodic and other maintenance of moving parts. Typically,
thisspace includes:
Sufficient area in front of the arm so that the triple joint can
be placed on the pier deck.
Room for access ladders and work platforms, whether part of the
arm or not, to maintain the trunnion and the apex swiveljoints.
Sufficient deck area behind the arms to permit the arm to be
placed in a laid-back maintenance position (sometimesnecessary for
maintenance on apex swivels for manual arms).
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 21 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
FIGURE 12LOADING ARM LAYOUT AND SPACING
Operator'sShelter
Rest Po
sition
Access Trestle
Cargo Transfer/Loading PlatformLCLC
Piping CrossoverManifold
Area
Outboard Faceof Triple-SwivelFlange in StoredPosition
Column Gangwaywith Foam Monitor
2.0 to 4.0m (typ.)
Foam Monitor(typ.)
IsolationValve (typ.)
Loading arm(typ.)
Cabinet1.5 x 2.4m (typ.)
1.8 to 2.4mDiameter Footprint(typ.)
Fire Hydrant(typ.)
H
Stripping/SlopTank(UnderDeck)
4.0m
H
Metering &Proving Skid
Oily WaterSump forCurbed Area(Under Deck)
Curb 20cmHigh (min.) Pier
Monitor(typ.)
MooringBollard(typ.)
(typ.)
Fire Equipment
0.3
to
0.6
m\P
(min
.)
30 to 35m (min.)
2m
(typ
.)
2m(typ.)
5.5
m
5m
3m
DP31Cf12
2.0 TO
4m
Hose / Hose Tower
Hose based cargo transfer systems may vary in complexity from a
single hose string handled and maneuvered by the vesselsderrick to
a multi-hose string system, handled and maneuvered by an elaborate
hose tower equipped with hoists, yokes,cradles and a crane.
Deck space allocation for hoses and hose towers (where needed)
depend on factors such as:
Location
Operating envelopes to be accommodated
Manifold location, spacing and number of lines in / out
Number of hose strings in a bank
Hose size variations (diameter and length)
Types of hose handling equipment (winches, terminal crane or
vessel crane)
Auxiliary equipment (saddle, swivels, stripping spool piece and
valve, etc.)
Simultaneous service requirements
Fender system geometry
Maintenance requirements (of the hoses and auxiliary
equipment)
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 22 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
Single hose or sometimes two simultaneously operated hose
strings are widely used for small barge loading / unloading. Inthis
arrangement the hose, which is not permanently installed, is
directly connected to the piping manifold closely located to
theface of the pier. In this arrangement, however, the hose is not
suspended / supported. Therefore, this type of system requiresa lot
of manual handling of the hose/s before and after each transfer and
it also requires deck space for hose/s storage. Deckspace
requirements for such a system also includes the piping manifold,
associated valves, and spill containment pans. For athree-line
manifold this typically amounts to a 2.4-m x 1.8-m (8-ft x 6-ft)
rectangular area stretching along the face of the pier.
Hose towers serving a wide range of vessels with multi-hose
strings and multi-product handling capabilities are fed from
apipeline manifold (product crossover) located behind the hose
tower through pipes entering the hose tower. Each entering pipeends
with a valve and a flange. The hoses are connected to these flanges
and run toward the front of the tower, supportedeither by a
structural member or by a saddle and with its outboard end either
loose facing the deck or hung and facing up.
A typical 10-hose-string tower with hoses in the size range of 6
10 in. and hose length of 14 m (46 ft), requires a footprint of8.5
m x 4.8 m (28-ft x 16-ft) rectangular area. A typical
10-hose-string tower with hoses in the size range of 8 12 in. and
hoselength of 17 m (56 ft), requires a footprint of 11 m x 4.8 m
(35-ft x 16-ft) rectangular area. In both cases the longer
dimension isalong the face of the pier, the front row of the tower
columns is setback approximately 2.4 3 m (8 10 ft) from the face of
thepier, and the area includes space for stairways.
Typical hose / hose tower arrangement and deck space allocation
on a typical loading platform is shown in Figure 13.
FIGURE 13SPACE ALLOCATION FOR HOSE TOWERS
Operator'sShelter
Curb 20cm
LC
PipingCrossoverManifold
Area
Hose Towerwith Crane
ConventationalGangway
2.4 to 3m
Access Trestle
High (min.)
Cargo Transfer/Loading Platform
Foam Monitor(typ.)
12 to 1
8m
(m
in.)
4.8
m
0.65m to 1.0m(typ.)
8.5 to 11m
1.2m
15m
20 to 26m (min.)
DP31Cf13
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 23 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (CONT)
BUNKERING
Vessel bunkering may be carried out using a dedicated loading
arm or a hose. Bunkering loading arms are added to the bankof cargo
loading arms, maintaining the appropriate spacing and setback as
previously discussed for loading arms. The locationof a bunkering
arm is determined by operational considerations, usually at one end
of the loading arm bank. When a hose isused for bunkering, a
bunkering manifold is provided on deck of the loading platform.
Typical footprint of such a manifold is 1m x 1 m (3-ft x 3-ft)
square.
GANGWAYS (POWERED / MANUAL)
Personnel access must be provided to a vessel at berth at all
times. Shore-based gangway systems range in sophisticationfrom a
conventional gangway (simple ramp equipped with rollers at the pier
end and gunwale clips or rollers at the vessel end)to a fully
powered, self-leveling, telescoping and free wheeling column or
tower gangway. The complexity of a gangwaysystem depends primarily
on the operating envelope the gangway has to cover. The following
factors may affect the deckspace requirements for a gangway:
The inclination angle of a gangway walkway should not exceed 45
degrees (above or below the horizon).
A gangway walkway should have a minimum clear width of 1-m (3
ft)Conventional gangways are widely used for barges and light
vessels when the elevation difference between the vessel deckand
the loading platform is up to about 10 m (30 ft). Typical
conventional gangways long enough to accommodate theindicated
elevation differences and still within the 45 degrees inclination
limit, are up to 15 m (50 ft) long. The deck spacerequirement for
this ramp will be a 15-m x 1.2-m (50-ft x 4-ft) rectangular area as
shown on Figure 13. Also, the area will haveto be within the reach
of a crane capable of deploying the ramp.
A column gangway consists of a column-mounted elevated platform
(gangway control and landing), turntable (walkway slewingmotion)
and attached telescopic walkway. The column base plate is bolted to
the pier platform. An integrated stairway runsfrom the pier
platform to the elevated platform. Typical projection of the
gangway system on the pier platform is a 3.6-m x 3.6-m (12-ft x
12-ft) square as shown on Figure 12. The integrated stairway
projection extends this square by 1.2 m (4-ft) wide anda varying
length rectangular extension, which depends on the column height.
If the telescopic walkway rests on the pierplatform when not in
use, then an additional deck area is required for the gangway
system.
A tower gangway consists of a tower-mounted carriage system,
running vertically on tracks installed on the face of the tower.The
moving carriage carries the turntable (walkway slewing motion) and
attached telescopic walkway. The tower is bolted tothe pier
platform. An integrated stairway runs inside the tower frame from
the pier platform to the top of the tower. Typicalprojection of the
gangway system on the pier platform is a 6.7-m x 4.8-m (22-ft x
16-ft) rectangle as shown on Figure 14. If thetelescopic walkway
rests on the pier platform when not in use, then an additional deck
area is required for the gangway system.
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 24 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
FIGURE 14SPACE ALLOCATION FOR TOWER GANGWAY
Operator'sShelter
Curb 20cm
Cargo Transfer/Loading PlatformLCLC
Metering &Proving Skid
PipingCrossoverManifold
Area
GangwayTower withCrane
Ship's ManifoldFoam Monitor(typ.)
Access Trestle
Rest Position
High (min.)
40 to 50m (min.)
4.8
m
6.7m
20 to 3
0m
(m
in.)
DP31Cf14
PIPELINE MANIFOLDS
Pipeline manifolds are usually provided in a marine terminal to
enable flexibility in cargo product line crossovers. The manifoldis
characterized by the number of cargo pipelines running from the
tank farm to the manifold and by the number of lines runningfrom
the manifold to the cargo transfer system. In terminals handling
both light and dark products the manifolds are
usuallyseparated.
Depending on the number of loading arms / hose strings being
served, a typical manifold consists of one or more headersfeeding
the cargo transfer system. Each header is dedicated to one loading
arm / hose string. The pipelines from the tankfarm are branched
into each such header (i.e., loading arm / hose) intended to serve
that particular product. The connectionbetween the cargo pipeline
and the header is through a vertical riser, which includes a double
block and bleed segregationvalve. Each header runs at the top of
all the risers feeding it. The headers and the respective risers
are arranged in a parallelconfiguration so that all segregation
valve stems are oriented between two adjacent rows of risers.
Sufficient room is providedbetween these rows of risers to
accommodate the valve stems, valve actuators (if applicable), valve
hand wheels and O&Mpersonnel movement.
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 25 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
Typically, the cargo pipelines running from the tank farm to the
manifold, when entering the manifold area, are spaced at 0.6 m(2
ft) on centers or 8 10 in. clearance between adjacent pipes,
whichever provides larger spacing. Header / riser row spacingwith
valve stem and O&M allowance is 2.4 3 m (8 10 ft) on centers.
Figures 15-16 illustrate a single corridor and a doublecorridor
layout arrangement for pipeline cross-over manifolds. Either
configuration may be used with consideration given to
thefollowing:
The number of pipelines and product types from the tank farm to
the cross-over manifold and the number of lines from themanifold to
the cargo transfer system.
The range of pipe sizes entering the manifold. The double
corridor layout is more advantageous for a broader range ofpipe
sizes.
The available space on the platform (size and shape). Given the
same number, sizes, and types of pipelines, the doublecorridor
layout is more compact than the single corridor layout.
FIGURE 15PIPELINE MANIFOLD LAYOUT -- SINGLE CORRIDOR
ARRANGEMENT
0.5m(min.)(typ.)
2.4
to 3
m(m
in.)
ValveHandWheel(typ.)
0.5
m(m
in.)
(typ
.)
PlatformCurb 20cm
Cargo Piping from Shore/Trestleto Product Line Crossover
Manifold
Cargo Piping from Headersto Loading Arms/Hose Tower
High (min.)
4.0
m (
min
.)
8.0m (min.)
DP31Cf15
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 26 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
FIGURE 16PIPELINE MANIFOLD LAYOUT -- DUAL CORRIDOR
ARRANGEMENT
2.4
to
3m
(min
.)
0.5
m(m
in.)
(typ
.)
Platform
Cargo Piping from Shore/Trestle to Product LineCrossover
Manifold
Curb 20cm
Cargo Piping from Headersto Loading Arms/Hose Tower
0.5m(min.)(typ.)
ValveHandWheel(typ.)
1 t
o 1
.5m
(min
.)2
.4 t
o 3
m(m
in.)
High (min.)
0.65 to 1.0m (typ.)
5.25m (min.)
7.2
5m
min
.)
DP31Cf16
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 27 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
METER RUNS / PROVERS
Metering and proving systems are installed on loading platform
based on custody transfer requirements and in accordance withAPI
Manual of Petroleum Measurement Standards (Reference 9). Typical
meter run arrangement is shown on Figure 17.Typical meter run
footprint areas are shown in Table 4 for three different meter
sizes.
TABLE 4SPACE GUIDELINES FOR METER RUNS
METER SIZE(in.)
NUMBER OF PARALLELMETER RUNS
TYPICAL METER RUNLENGTH [m] (ft)
TYPICAL WIDTH OFPROJECTED AREA [m] (ft)
4 2 11.6 (38) 1.8 (6)
8 2 12.8 (42) 3 (10)
12 3 14 (46) 5.4 (18)
A typical conventional, bi-directional, prover assembly /
arrangement is shown on Figure 18. Footprint areas are provided
inTable 5.
TABLE 5SPACE GUIDELINES FOR METER PROVERS
PROVERDIAMETER (in.)
MINIMUM LENGTHBETWEEN DETECTORS [m]
(ft)
TYPICAL PROVERASSEMBLY LENGTH [m] (ft)
TYPICAL WIDTH OFPROJECTED AREA [m] (ft)
6 15 (50) 12.8 (42) 1.8 (6)
20 18 (60) 18 (60) 4.6 (15)
OPERATORS SHELTER
A small shelter is usually provided on the loading platform for
the dock operator. This shelter serves the dock operators as
anoffice; protected location for centralized operating controls and
provides limited storage. Shelters may also include a washroomand
toilet. The design footprint of a typical operators shelter, for 1
operator is 3 m x 4 m (10 ft x 13 ft). The shelter should
beinstalled at a safe area of the loading platform adjacent to an
emergency evacuation route to shore.
FIGURE 17METER RUN TYPICAL ARRANGEMENT
DPIPI
TI
DiametersDiameters
StrainerMeterFilter
Block Valve(typ.)
TemperatureIndicator
PressureIndicator
CheckValve
ControlValve
Connectionto Prover
See Table 4
Meter Run
10 5
Se
e T
ab
le 4
DP31Cf17
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 28 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
FIGURE 18METER PROVER -- TYPICAL ARRANGEMENT
TYPICAL U-TYPE PROVER
Sphere Inlet/Outlet
Connectionto Meter Run
Flow reversingValve
See Table 5
Se
e T
ab
le 5
DP31Cf18
CRANES (HOSE / GANGWAY HANDLING OR MAINTENANCE)
Marine cranes, either mobile or permanently fixed to the loading
platform, are used for cargo hose handling, gangwaydeployment and
maintenance removal and installation of dock equipment. These
cranes, whether hydraulic or electric driven,are sized to safely
maneuver the maximum anticipated load within the crane design
envelope. The cranes may be equippedwith straight or extendible
booms (fixed length or telescopic). Cranes may be mounted on
columns, dedicated elevated towers,gangway tower / column, or on
top of a hose tower.
Typical footprint of a crane pedestal on the loading platform
deck is a circular area with a diameter in the range 1.2 3 m (4 10
ft). The crane needs to be also positioned so as to avoid clashing
(considering the range / elevation of the boom) with othertall
equipment e.g. loading arms, light poles, etc
CONTAINMENT AREA
Loading platform design must provide means to contain cargo
product releases due to stripping, draining or purging of
loadingsystems and piping. It also should provide containment for
all hydrocarbon releases mixed with rainwater. Spill containment
isused to prevent any of the released cargo from flowing into the
water. The following considerations should be applied for thedesign
and sizing of spill containment:
The primary potential spill areas include the footprint and
on-deck projection of the cargo transfer systems and the
cargoproduct manifolds (including all piping, fittings and
valves).
Sources of spills and leaks include cargo piping flanged joints,
valves and other components with non-welded joints, etc.
All potential spill sources should be curbed with a 20-cm
(8-in.) high / thick curb surrounding the area. A commoncontainment
curb may be used for adjacent primary spill areas. The outside
surface of any cargo liquid conveyingcomponent in these systems
should be, as a minimum, 0.5 m (18 in.) inboard from the inside
face of the curb.
All the liquid collected by the curbed area should be drained to
oily water collection sumps for discharge to shore
treatmentfacilities.
Also, a curb around the perimeter of the loading platform should
be provided to contain infrequent accidental productreleases
The containment area shall be provided with an impervious
concrete deck.
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 29 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
Figures 12-13 and 15-16 show typical layouts and dimensions of
the containment system.
Hydrocarbon sump tanks may be in the range of 250 gal. for
8-hose string tower, 8 in. each hose, to 3,200 gal. for a two
sidedtwo berth terminal equipped with 10 loading arms (4-16, 4-10,
2-8). The footprint associated with the 250 gal. sump is 0.6 mx 6 m
(2 ft x 20 ft). The footprint associated with the 3,200 gal.
hydrocarbon sump is 1.5 m x 7.3 m (5 ft x 24 ft).
The oily water sump capacity is a function of the total curbed
area and the rate of rainfall. For a berth with a total curbed
areais 1300 sq.-m. and the oily water sump is a 5,800 gal. The
footprint associated with a 5,800 gal. oily water sump is 1.8 m x
6.7m (6 ft x 22 ft).
A typical sampling station may occupy a footprint of 1 m x 1.5 m
(3.2 ft x 5 ft).
FIRE FIGHTING (PUMPS, DRUM, MONITORS, ETC.)
Fire fighting means on a loading platform may consist of a
combination of water, foam, fire hydrants and fire monitors as
shownin Figure 12.
Fire Pumps
Fire pumps may be either diesel driven or electric motor driven
vertical turbine pump submerged in the water through a deckopening.
The pump capacity depends on the size of the facility, the cargo
type and other pertinent factors. As a minimum, twopumps should be
provided where each is capable of delivering the full-required
capacity. For redundancy, one pump should bediesel driven and the
other should be electric motor driven.
Typical footprint of a diesel driven 275 300 bhp, 14 in.
discharge line pump, including all accessories up to a common
header,is 8 m x 1.5 m (26 ft x 5 ft). Typical footprint of an
electric motor driven 275 300 bhp, 14 in. discharge line pump,
including allaccessories up to a common header, is 4.8 m x 1.5 m
(16 ft x 5 ft). Figure 19 shows a typical piping layout of a fire
waterpump station.
FIGURE 19TYPICAL LAYOUT FOR FIREWATER PUMP STATION
ReliefValve(typ.)
CheckValve(typ.)
GateValve(typ.)
ElectricMotorDrive
Pumps
Suction PipeThrough DeckOpening intoWater (typ.)
DieselDrives
LC
FIRE WATER PUMP STATION
4.5m (typ.)
1.8m (typ.) 1.8m (typ.)8m
(ty
p.)
DP31Cf19
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 30 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
Foam Tanks
Foam requirements are addressed in Section XXXI-I. Typical foam
tank sizes may run in the range between 1,500 and 5,000gallon
depending on the size of vessels and the concentration of foam
(depends on type of foam selected). Typical footprint ofa
5,000-gallon foam tank is 9 m x 6 m (30 ft x 20 ft), whereas a 500
gallon foam tank takes 2.4 m x 1.8 m (8 ft x 6 ft) of
deckspace.
Water / Foam Monitors
Water / foam monitors for loading arm / hose, berth manifold,
and vessel manifold coverage are usually mounted on anelevated
mast, are remotely operated, and are installed along the berthing
face on the two opposite corners of the loadingplatform. Additional
pedestal-mounted, manually operated monitors may be installed in
the rear of the loading platform. Atypical fire monitor mast
occupies a 1.8-m (6-ft) diameter circular deck area. A pedestal
mounted manual monitor may occupya 2.4-m (8-ft) diameter circular
deck area.
Fire Hydrants / Hose Reels
As many fire hydrants as required to supply the firewater (not
less than two) should be placed on the loading platform within 75-m
(250-ft) from objects requiring firewater. Fire hydrants and fire
hose reels also should be located at 90 m (300 ft) spacingalong the
access trestle. A 1.8-m (6-ft) diameter circular area, where the
hydrant is located in the center, should be allocatedfor each
hydrant or hose reel station.
Fire Equipment Cabinet
Fire equipment cabinet contains fire hoses, nozzle fittings,
couplings, wrenches, and other accessories. The cabinet is kept
onthe loading platform in a visible and accessible area. Typical
cabinet would occupy a deck area of 1.5 m x 2.4 m (5 ft x 8
ft).
EMERGENCY ISOLATION EQUIPMENT
Isolation valves are installed in each product line to
facilitate an emergency shutdown of the cargo pipeline. An
isolation valvemay be installed either vertically in the line (for
sizes up to 10 in.), or horizontally over a concrete pad (for sizes
over 10 in.).The footprint of an isolation valve when installed
vertically amounts to the valve flange projection extended by the
valve stemand actuator projections, as shown in Figure 20. The
footprint when the valve is installed horizontally, amounts to the
valveprojection extended by piping, as shown in Figure 21. Table 6
presents some typical projected dimensions for commonly usedvalve
sizes.
TABLE 6SPACE GUIDELINES FOR ISOLATION VALVES
ISOLATIONVALVE SIZE (in.)
ORIENTATION(V = VERTICAL,
H = HORIZONTAL)
TYPICAL LENGTH OFPROJECTED AREA [m] (ft)
TYPICAL WIDTH OFPROJECTED AREA [m] (ft)
6 V 1 (3.3) 0.4 (1-4)
8 V 1.2 (4) 0.5 (1-8)
8 H 1.4 (4.6) 0.5 (1-8)
10 V 1.4 (4.6) 0.6 (2)
10 H 1.4 (4.6) 0.6 (2)
12 H 1.5 (5) 0.6 (2)
16 H 1.5 (5) 0.7 (2-4)
24 H 2.4 (8) 1.1 (3-8)
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 31 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
FIGURE 20ISOLATION VALVE VERTICAL INSTALLATION
CargoTransferSystem
See Table 6
See T
able
6
DP31Cf20
FIGURE 21ISOLATION VALVE HORIZONTAL INSTALLATION
1 to1.5m(typ.)
CargoTransferSystem
DripPan
ConcretePad
Manual/Remote OperatedShore Isolation Valve (typ.)
Se
e T
ab
le 6
Se
e T
ab
le 6
DP31Cf21
UTILITY RACKS, BACKFLOW PREVENTER & METER
The utilities usually provided in a marine terminal include
potable water, firewater and compressed air. Other potential
utilitiesmay include:
Sanitary sewer, if a bathroom is built on the loading
platform
Steam, if any handled product requires steam tracing
Nitrogen, if purging is provided.
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 32 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
LAYOUT OF BREASTING AND MOORING DOLPHINS (Cont)
Potable water, if used for water bunkering, will include a meter
and a backflow preventer. Since the potable water line may bein the
range of 2 4 in., the footprint of a corresponding meter and
backflow preventer is 0.6 m x 1.2 m (2 ft x 4 ft) and 0.6 m x1.8 m
(2 ft x 6 ft), respectively. Firewater was addressed
separately.
Other utilities are routed with the cargo piping over the piping
racks into the marine terminal. These utilities may be clusteredand
installed at several locations (at least two) on the platform. A
typical size of a utility cluster is 0.6 m x 1.2 m (2 ft x 4
ft).
ELECTRICAL PANELS / JUNCTION BOXES
Electrical panels and junction boxes are provided consistent
with the functionality of the terminal, and the overall layout of
theloading platform and the trestle. The complexity of the terminal
layout may dictate the spread of various parts of the
electricalgear. Space requirements for Transformer, Switchboard,
and Motor Control Center (MCC) may vary as follows:
Typical Complex Terminal Two sided, two berth terminal,
10-loading arms, multi valve manifolds, trestle fire pumpstation,
and on-shore electrical service point.
Loading Platform - Includes Operations Building, Control Center
and Switchboards / MCCs, with the building size of 7.6 mx 12.2 m
(25 ft x 40 ft). Two Switchboards / MCCs sizes 0.6 m x 9 m (2 ft x
30 ft) and 0.6 m x 2.4 m (2 ft x 8 ft).
Service Platform - Includes Transformer, Switchboard and MCC.
Two Switchboards / MCCs sizes 0.6 m x 2.7 m (2 ft x 9ft) and 0.6 m
x 1.8 m (2 ft x 6 ft). Transformer with HV and LV Switchgear sized
1.8 m x 6.4 m (6 ft x 21 ft).
Electrical Service Point - Includes Transformer, Switchboard and
MCC. One Switchboard / MCC sized 0.6 m x 1.5 m (2 ftx 5 ft).
Transformer with HV and LC Switchgear sized 1.8 m x 5.5 m (6 ft x
18 ft).
Typical Hose Tower Terminal A single berth, 8-8 hoses with
simple manifold.Loading Platform - Includes Control Shed and
Switchboard. A single control shed sized 1.8 m x 2.4 m (6 ft x 8
ft).Switchboard Outdoor sized 0.6 m x 3.6 m (2 ft x 12 ft).
On-Shore - Includes Transformer and Switchboard. One switchboard
sized 0.6 m x 2.4 m (2 ft x 8 ft). One transformersized 1.8 m x 2.4
m (6 ft x 8 ft).
Typical Small Hose Terminal A single berth, 4-deck mounted
hoses, simple Manifold.Loading Platform - Includes a single main
distribution panel sized 0.6 m x 0.45 m (2 ft x 1-6).
OIL SPILL RESPONSE EQUIPMENT
Oil spill response equipment that is kept on the loading
platform, usually is stored in the vicinity of the operators
shelter.Typical footprint of the spill response equipment cabinet
is 1 m x 2 m (3.2 ft x 6.4 ft) for a single berth facility with a
hose tower.
MVR VAPOR HEADER & ARRESTORS
MVR vapor header is used to return the vapors emitted during
vessel loading of volatile products to a shore recovery system.The
footprint of a MVR skid handling a 12 vapor line is 10 m x 4.4 m
(33 ft x 14 ft).
WALKWAY / OPEN AREAS
Open areas (2 meter clear width) should be provided to allow
personnel access around major systems and equipment:
Loading arms
Hose tower
Crossover manifold
Meter / Prover
Gangway
SMALL CRAFT / LAUNCH ACCESS
Small craft access is usually provided alongside the trestle to
the loading platform and it accommodates the small boats used
towork around the terminal and sometimes the tugboat. This access
usually includes a platform extension at the trestle /
loadingplatform level with stairways leading down to one or more
landings at lower deck elevations. Typical sizes of the small craft
/launch access are 1 m x 2 m through 2 m x 4 m.
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 33 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
ACCESS TRESTLE
The access trestle in a marine terminal provides vehicular and
personnel access from shore to the loading platform.Cantilevered or
pile-supported beams / racks along the trestle serve as the
structural supports for the cargo piping and utilitiesbetween the
shore and the loading platform. Fire hydrants are placed at equal
spacing along the trestle. In many installations,the trestle is
widened to include vehicular parking spaces and to include the fire
water pump station, foam tank, and the firefighting control
station. Figures 22a/b and 23a/b show an access trestle, various
functions it serves and typical space requiredfor each
function.
If vehicular access to the loading platform is not required, the
access trestle may consist of a personnel walkway. A
typicalpersonnel walkway is 1 m (3 ft) wide. A typical single-lane
roadway includes both a personnel walkway and a traffic lane and
is4.5 m (13 ft) wide.
Vehicle parking and turning spaces may be provided along long
trestles. Usually, parking and turning areas are on the sameside of
the trestle as the firewater pumping station and opposite to the
pipelines racks. Where the loading platform providessufficient
space, turning area along the trestle is not required. Typical
parking space for 1 vehicle is a 6.4 m x 3 m (21 ft x 10
ft)rectangular footprint.
FIGURE 22AACCESS TRESTLE ARRANGEMENT #1
C= 10 ft (min.) for Single Lane Roadway Plus a 3 ft Wide (min.)
Pedestrian Walkway
C= 24 ft (min.) for a Double Lane Roadway, Includes Pedestrian
Walkway
Typical TwoTier Pipe Rack
AccessRoadway
Piles(typ.)
Parking/VehicleTurn-Around
TRESTLE CROSS-SECTION VIEW
C
DP31Cf22A
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 34 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
ACCESS TRESTLE (Cont)
FIGURE 22BACCESS TRESTLE ARRANGEMENT #1
PLAN VIEW
AccessRoadway
Parking/VehicleTurn-Around
Varies(Dependenton numberof parkingspaces)
H
H
90m(typ.)
Fire Hydrant(typ.)
ExpansionLoop
6.5m(min.)
DP31Cf22B
FIGURE 23AACCESS TRESTLE ARRANGEMENT #2
TRESTLE CROSS-SECTION VIEW
AccessRoadway
Piles(typ.)
Typical SingleTier Pipe Rack
Fire Pump Houseand Pump Platform8 -10cm Gap (min.) typ.
DP31Cf23A
-
ExxonMobil Proprietary
MARINE TERMINAL Section Page
FACILITY LAYOUT CONSIDERATIONS XXXI-C 35 of 43
DESIGN PRACTICES December, 2000
ExxonMobil Research and Engineering Company Fairfax, VA
ACCESS TRESTLE (Cont)
FIGURE 23BACCESS TRESTLE ARRANGEMENT #2
PLAN VIEW
AccessRoadway
Fire Pump PlatformIncluding: Foam
Tanks, Fire FightingPanel and Auxiliary
Equipment
ElectricalSubstationSwitchgear
H
H
90m
(ty
p.)
Fire Hydrant(typ.)
ExpansionLoop
B
(see
Tab
le 7
)
(SeeTable 7)
A
6.5m (min.)
DP31Cf23B
The trestle serves as the structural support for the cargo
piping and utilities between the shore and the loading platform.
Pipingmay be routed on either side or on both sides of the trestle.
Often, hydrocarbon lines are routed on one side of the
trestlewhereas utilities run on the other side. The determination
of how to route the piping primarily depends on the number and
sizesof pipelines, and the economics associated with each potential
scheme.
A one-sided single-tier of racks may suffice for a small number
of pipelines as shown in Figure 23. For a larger number /
largersize pipelines, a trade-off analysis among two-sided
single-tier, one-sided two-tier, and any other combination of pipe
rackarrangements has to be conducted. Figure 22 shows a typical
one-sided two-tier pipe rack. The pipe racks are usually
eithercantilevered (short racks) or pile-supported beams (long
racks) along the trestle. Where expansion loops are needed
toaccommodate pipeline thermal expansion, the same racks are
extended horizontally to support horizontal expansion loops.
Where the pipelines from shore to the loading platform are
supported by overhead pipe racks (one or more tiers), there is
noneed for pipe racks on either side of the trestle. In this case
expansion loops are accommodated either horizontally orvertically.
Table 7 presents some typical loop dimensions for commonly used
pipe sizes.
-
ExxonMobil Proprietary
Section Page MARINE TERMINAL
XXXI-C 36 of 43 FACILITY LAYOUT CONSIDERATIONSDecember, 2000
DESIGN PRACTICES
ExxonMobil Research and Engineering Company Fairfax, VA
AC