Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014
25

Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Mar 31, 2015

Download

Documents

Lana Mille
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Doug Thiessen, P.E.Managing Director of Engineering

Update on the Port of Long Beach

ACEC LAJanuary 15, 2014

Page 2: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Port of Long BeachPremier gateway for U.S-Asia

trade, major Southern California economic engine

Page 3: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Who We Are

• 3,500 acres of land

• 4,600 acres of water

• 6 container terminals

• 66 Ship-to-Shore cranes

• 76-foot-deep main channel

• 2nd busiest U.S. container cargo seaport

• Part of the world’s 9th busiest port complex

Page 4: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Diverse Cargo3,500-acre Port moves

cars, crude oil, petroleum coke,

lumber and container cargoes.

Page 5: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Big Ship Ready

7,100 TEU1996

1997 8,100 TEU

15,500 TEU2006

18,000 TEU2013

Page 6: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Largest to Call North America

14,000-TEU MSC Corte Real came in October 2013 – too wide to pass

through the expanded Panama Canal.

Page 7: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Investing in the FuturePort has begun a $4 billion upgrade of facilities to stay competitive

Page 8: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Current Major Programs• Pier G Redevelopment• Middle Harbor

Redevelopment• Gerald Desmond Bridge

Replacement• On-and Near-Dock Rail• Shore-to-Ship Power• Fire Protection Program

Page 9: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Middle Harbor$1.2 billion facility will be one of the most technologically advanced terminals in the world.

Page 10: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Middle HarborPhase 1 Currently Underway

Page 11: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Phase 2

Phase 2 Phase 1

Phase 1

Middle Harbor Redevelopment

305-acre facility under construction in two

phases.

Page 12: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Middle Harbor RedevelopmentPhase 1- $779.3 Million• 10 construction projects• Third-party utility

improvements/relocationsPhase 2- $449.7 Million• 9 construction projects• Third-party utility

improvements/relocations

Page 13: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Gerald Desmond Bridge Replacement$1.3 billion cable-stay bridge; $650 million design-build contract awarded to Shimmick, FCC & Impregilo on July 2012.

Page 14: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Pre-ConstructionPreliminary engineering

complete, two-thirds through Right-of-Way

work.

Page 15: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Future Opportunity Demolition of Existing Bridge

Page 16: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

On & Near Dock Rail Improvements

Ocean Blvd. Track Realignment

Middle Harbor On-Dock Rail

*Future project

Pier G SouthRail Yard*

Pier B On-Dock Rail

Support Facility*

Page 17: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Shore Power ProjectsPort is reducing air quality impacts through the Clean Air Action Plan. The state has enacted a regulation requiring shore power in 2014.

Page 18: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Major EffortSimultaneous construction at

all container terminals and 12 berths

Page 19: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Project Budget

Actual Cost to Date

Estimated Final Cost

Pier A

$19.4 million $16.3 million $18.3 million

Pier G

$17.9 million $13.9 million $16.5 million

Pier J $56.1 million $43.2 million $49.9 million

Pier T

$33.6 million $24.1 million $31.1 million

Total $127 million $97.5 million$115.8 million

Project Budgets

Page 20: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Fire-Protection Program• New Fireboats for Station 15 & 20• Fireboat Station 15 Replacement

Project• Fireboat Station 20 Replacement

Project (Site Selection Underway)

Page 21: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

New FireboatTwo fireboats under construction in Seattle

Page 22: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Upcoming Consultant OpportunitiesConstruction Management Division:• CM Services – Pier G Redevelopment

(under evaluation)• On-Call, Inspection & Material Testing

(under evaluation)• As-Needed Hydrographic Services • (under evaluation)• CM Services – New Fire Stations, 2014• On-Call Construction Mgmt. Services,

2014Other Engineering Divisions:• On-Call Cost Estimating Services,

2014

Page 23: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

Upcoming Contractor Opportunities(Next 12 months)• Pier C, Upgrade of Water Facilities, 2013• Berths F209 Chemoil Facility Improvements,

2013• NRG Facilities Relocation/Demolition, 2013• Harbor Scenic Water Valve Replacement,

2013• Pier F, Cut-off Wall & Pavement Rehab., 2013• Edison Avenue Street Improvement, 2014• Pier J, Bike & Pedestrian Path, 2014

Page 24: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.

The Future is BigWe face big challenges, but we see

big opportunities that will bring a promising future to the Port of Long

Beach

Page 25: Doug Thiessen, P.E. Managing Director of Engineering Update on the Port of Long Beach ACEC LA January 15, 2014.