EPCI MILA- A ASTI D Date October 11 th, 2015 Number 11/DOR-CNO/RPE/X/ASTI Period from 6.00 October 11 th, 2015 to 6.00 October 12 th, 2015 Location ASTI-A, CNOOC area 1. WORKING PROGRESS 1.1.MAIN No Job Description 1 Anchor Job and Barge Setup 1.1 Anchor Job and Barge Setup at Asti A P/F 1.2 TRA-2 and Simop 2 Preparation 2.1 Transfer equipment to Asti - A P/F 2.2 Line Mapping (Mechanical and E & I) 2.3 Install Scaffolding 3 Mechanical Work 3.1 Install Support and Mechanical Equipment 3.2 Structure reinstatement 3.3 Install sum caisson 3.4 Install pump caisson 3.5 Install riser cable I-tube 4 Piping 4.1 Piping valve and fitting reinstatement 4.2 Piping Field weld 4.3 Riser and subsea spool installation 4.4 Painting and Touch-up 5 Installation Electrical 5.1 Continuity and insulation test cable 5.2 Install cable ladder, tray and support 5.3 Pulling cable 5.4 Glanding 5.5 Install electric Equipment 5.6 Termination 6 Installation Instrument 6.1 Continuity and insulation test cable 6.2 Install cable ladder, tray and support 6.3 Pulling cable 6.4 Glanding 6.5 Running tubing 6.6 Install Instrument equipment 6.7 Termination 7 Precomissioning 7.1 Piping 7.2 Hydrotest piping 7.3 Mechanical 7.4 Riser Pipeline 7.5 Electrical
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
EPCI MILA- A ASTI PLATFORM AND PIPELINE 2nd CAMPAIGN
DAILY OPERATION REPORT
Date October 11 th, 2015Number 11/DOR-CNO/RPE/X/ASTIPeriod from 6.00 October 11 th, 2015 to 6.00 October 12 th, 2015Location ASTI-A, CNOOC area
1. WORKING PROGRESS1.1.MAIN
No Job Description
1 Anchor Job and Barge Setup1.1 Anchor Job and Barge Setup at Asti A P/F1.2 TRA-2 and Simop2 Preparation
2.1 Transfer equipment to Asti - A P/F2.2 Line Mapping (Mechanical and E & I)2.3 Install Scaffolding3 Mechanical Work
3.1 Install Support and Mechanical Equipment3.2 Structure reinstatement3.3 Install sum caisson3.4 Install pump caisson3.5 Install riser cable I-tube4 Piping
4.1 Piping valve and fitting reinstatement4.2 Piping Field weld4.3 Riser and subsea spool installation4.4 Painting and Touch-up5 Installation Electrical
5.1 Continuity and insulation test cable5.2 Install cable ladder, tray and support5.3 Pulling cable5.4 Glanding5.5 Install electric Equipment5.6 Termination6 Installation Instrument
6.1 Continuity and insulation test cable6.2 Install cable ladder, tray and support6.3 Pulling cable
1 Riser 35% 12 Subsea Spool A (fixed) 25% 13 Subsea Spool A (metrology) 40% 1
Total
1.3 ADDITIONAL WORK 2
No Item Qty Unit
1 38 Ea
2 38 Ea
Total
1.4 ADDITIONAL WORK 3 (FABRICATION AND INSTALL SAFETY EQUIPMENT)
No Description
1 Support for Carbon Dioxide Portable Extinguisher2 Support for Dry Chemical Portable Extinguisher 3 Support for Wheelded Dry Chemical Extinguisher4 Support for Self Contained Eye Wash Unit5 Support for Safety Equipment Cabinet6 Support for Emergency rescue kit7 Support for Life Buoy8 Support for Life Raft
TotalWeather Down Time Client Activities Insertion
Prev. Today Cum. Prev.(hours) 2 0 2 0
5. GENERAL ACTIVITY
Time Location Job Description
6:00 - 6:30 BC Toolbox meeting on main deck Bayu Construction
Piping, Structure and Mechanical6:30 - 17:00 ASTI ѻ Complete joining Water sea line (GRE) at subcellar deck, 2 joint
ASTI ѻ Continue touch-up painting at all area ASTI ѻ Continue SAT ICS by vendor at mezzanine deckASTI ѻ Continue setting Multi Phase Flow Meter by vendor at cellar deck
ASTI ѻ Install cable ladder clamps, 28 setsASTI ѻ Install and modify cable cover elbow, 2 eaASTI ѻ Install tagging marker cable electical JB and equipment field at all area
InstrumentASTI ѻ Modify additional support on pump injection MEG inside MEG skid at mezzanineASTI ѻ Re-location MEG pump position at mezanine deckASTI ѻ Install tagging marker cable instrument at all area
17:30 - 18:00 BC Break and crew change18:00 - 18:30 BC Toolbox meeting on main deck Bayu Construction
Piping, Structure and Mechanical18:30 - 5.30 ASTI ѻ Assist diver bolt tighting riser guard
BC ѻ Prepare and arrange filling pumps in preperation for pipline hydrotestASTI ѻ Continue cleaning all areaASTI ѻ Modifiy chemical sampling support
ѻ Modification washdown pump connection ѻ Modification Air compressor piping to get space for maintenanceѻ Need to maintenance jib crane after 2 year storage (change oil, grease, ect)ѻ Modification Corrosion inhibitor tubing line ѻ Modification Chemical injection tubing line
B. HIGHLIGHT
ѻ Outstanding duplex spool 6" to Carbon steel flange that fabrication at Jakarta(o/s 1 joint and Hydrotest)
ѻ Outstanding material for thermocouple that machining at Jakartaѻ Outstanding horn, swing limiter switch for Jib Craneѻ Outstanding enclosure seal for pig launcher
RPE GROUP - B.CON (CONSORTIUM)Prepared by : Checked by :
Didik Sudaryono Reza AjiputraConstruction Manager PT. RPE Engineer
EPCI MILA- A ASTI PLATFORM AND PIPELINE 2nd CAMPAIGN
DAILY OPERATION REPORT
Period Weather Wind Sea Picth06.00 to 08.00 Clear 15 - 16 moderate 0.5 - 1
12.00 to 13.00 Clear 15 - 16 rought 1 - 2
18.00 to 19.00 Clear 14 - 16 rought 1 - 2
24.00 to 01.00 Clear 14 - 16 rought 1 - 2
Weight factor (%) previous today to date
2.00% 2.0% 0.00% 2.00%
1.00% 100.0% 0.0% 100.0%
1.00% 100.0% 0.0% 100.0%
4.00% 3.97% 0.00% 3.97%
1.00% 97.0% 0.0% 97.0%
1.00% 100.0% 0.0% 100.0%
2.00% 100.0% 0.0% 100.0%
25.00% 24.2% 0.75% 24.98%
5.00% 84.6% 15.0% 99.6%
8.00% 100.0% 0.0% 100.0%
4.00% 100.0% 0.0% 100.0%
4.00% 100.0% 0.0% 100.0%
4.00% 100.0% 0.0% 100.0%
20.00% 17.75% 0.00% 17.75%
4.00% 98.8% 0.0% 98.8%
8.00% 98.1% 0.0% 98.1%
6.00% 92.6% 0.0% 92.6%
2.00% 19.8% 0.0% 19.8%
17.00% 16.44% 0.00% 16.44%
1.00% 100.0% 0.0% 100.0%
3.00% 99.1% 0.0% 99.1%
5.00% 98.4% 0.0% 98.4%
2.00% 91.6% 0.0% 91.6%
4.00% 100.0% 0.0% 100.0%
2.00% 85.9% 0.0% 85.9%
19.00% 17.66% 0.06% 17.72%
1.00% 84.0% 0.0% 84.0%
3.00% 98.8% 0.0% 98.8%
4.00% 97.6% 0.0% 97.6%
2.00% 91.5% 0.0% 91.5%
4.00% 90.1% 0.0% 90.1%
4.00% 91.6% 1.5% 93.1%
1.00% 85.4% 0.0% 85.4%
11.00% 5.8% 1.22% 7.05%
2.00% 74.1% 0.0% 74.1%
1.00% 92.1% 0.0% 92.1%
1.00% 20.0% 0.0% 20.0%
2.00% 100.0% 0.0% 100.0%
2.00% 52.0% 34.0% 86.0%
2.00% 9.8% 2.7% 12.5%
1.00% 0.0% 48.1% 48.1%
2.00% 0.0% 0.00% 0.00%
2.00% 0.0% 0.0% 0.0%
100% 87.89% 2.03% 89.92%
UnitNDT Precomm Progress
20% 70% 5% 5%
EA 100% 100% none 100% 95.5%
EA 100% 100% none 0% 90.0%
EA 100% 95% 100% 0% 91.5%
92.6%
Cut bevelFit Up Welding NDT Lift - Install Progress
20% 50% 5% 15%
100% 100% 100% 100% 100% 100.0%
100% 100% 100% 100% 0% 85.0%
93%
Total QtyCut & Fit-up Welding Painting Installation
25% 55% 10% 10%
4 EA 0.0% 0.0% 0.0% 0.0%7 EA 0.0% 0.0% 0.0% 0.0%2 EA 0.0% 0.0% 0.0% 0.0%1 EA none none none 100.0%1 EA 100.0% 100.0% 100.0% 100.0%1 EA 100.0% 100.0% 100.0% 100.0%12 EA 100.0% 100.0% 100.0% 100.0%2 EA 100.0% 100.0% 100.0% 100.0%30
11/DOR-CNO/RPE/X/ASTI
Lifting & positioning
Fit-up & welding or Bolting
Description of Work Location Permit authority Open Close
Bayu Construction Yudi 6:00
Bayu Construction Parlindungan 6:00
ASTI-A Baharudin 8:05
Fabriction, fit-up, welding, pipe riser 10" and support ASTI-A Yusran 8:05
Complete joining Water sea line (GRE) at subcellar deck, 2 jointContinue touch-up painting at all area Continue SAT ICS by vendor at mezzanine deckContinue setting Multi Phase Flow Meter by vendor at cellar deck
Install cable ladder cover, 16 lines at mezzanine deck
Install cable ladder clamps, 28 setsInstall and modify cable cover elbow, 2 eaInstall tagging marker cable electical JB and equipment field at all area
Modify additional support on pump injection MEG inside MEG skid at mezzanineRe-location MEG pump position at mezanine deckInstall tagging marker cable instrument at all area
Toolbox meeting on main deck Bayu Construction
Assist diver bolt tighting riser guardPrepare and arrange filling pumps in preperation for pipline hydrotestContinue cleaning all areaModifiy chemical sampling support
36 181 100.0% 97.6%Hydrotest complete 33 of 36Progress Precomm at B-con 30%
PRECOMISSIONING ELECTRIC ASTI-A PLATFORM (INTERNAL)
QTY LINE PER TEST
PAGKAGE
MATR' TRACE AND NDE
CLEARENCE
NO TEST SHEET
1 Low Voltage Switchgear and Motor Control Center2 Power Transformer3 Navigation Aid and Radar Beacon4 Battery charger5 Power, Control and Earthing Cable6 Low Voltage Induction Motor7 Lighting and Small Power Transformer8 High Resistance Grounding (HRG) Panel and Resistor9 Medium Voltage Fused Load Break Switch (FLBS)
10 Distribution Board (DB)11 Continuity and Megger Test12 Earhting Cable Resistance Test
1 Chemical Injection Skid (U-715)2 Chemical Injection Tank (T-175)3 Chemical Injection (P-175)4 Chemical Injection Skid (U-725)5 Chemical Injection Tank (T-725)6 Chemical Injection Tank (T-725)7 Submersible Pump/Wash down pump8 Closed Drain Pump9 Closed Drain Vessel10 Open Drain Pump11 Air instrument Vessel12 Jib Crane Equipment Y-905 (Cable)