ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 1. ZEMLJANI RADOVI 1. ZEMLJANI RADOVI 1.1. ČIŠĆENJE TERENA NA MJESTU OBJEKTA, TE 15 m OKO OBJEKATA SA SJEĆENJEM ŠIBLJA, PORAVNAVANJEM TERENA ITD. 66,45 x 50,65 = 3365,69 m 2 3365,69 1.2. SKIDANJE HUMUSA BULDOZEROM U SLOJU 20 cm S GURANJEM NA 20 m UDALJENU DEPONIJU 66,45 x 50,65 = 3365,69 m 2 3365,69 1.3. ŠIROKI ISKOP ZEMLJE U TLU III. KATEGORIJE BAGEROM m 3 4118,74 74 , 4118 82 , 3 2 65 , 20 45 , 36 39 , 30 19 , 46 = VLAD 1
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 1. ZEMLJANI RADOVI
1. ZEMLJANI RADOVI
1.1. ČIŠĆENJE TERENA NA MJESTU
OBJEKTA, TE 15 m OKO OBJEKATA
SA SJEĆENJEM ŠIBLJA,
PORAVNAVANJEM TERENA ITD.
66,45 x 50,65 = 3365,69m
23365,69
1.2. SKIDANJE HUMUSA BULDOZEROM
U SLOJU 20 cm S GURANJEM NA 20
m UDALJENU DEPONIJU
66,45 x 50,65 = 3365,69
m2 3365,69
1.3. ŠIROKI ISKOP ZEMLJE U TLU III.
KATEGORIJE BAGEROM
m3 4118,74
74,411882,32
65,2045,3639,3019,46=⋅
⋅+⋅
VLAD 1
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 1. ZEMLJANI RADOVI
1.4. PLANIRANJE ISKOPA
36,45 x 20,65= 752,69
m2
752,69
1.5. NASIPAVANJE OKO TRAKASTIH
TEMELJA I TEMELJA STUPA
→ koeficjent rastresitosti za zemlju = 1,30
(34,35 x 18,55) x 0,65 - 15 x (0,55 x
0,55) x 0,65 = 414,18 - 2,9 5= 411,23
m3
411,23
1.6. NASIPAVANJE OKO TRAKASTIH
TEMELJA I TEMELJA STUPA
→ koeficjent rastresitosti za zemlju = 1,30
(35,10 x 19,30) x 0,42 - 15 x (0,30 x
0,30) x 0,42= 284,52 - 0,52 = 283,95
m3
283,95
VLAD 2
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 1. ZEMLJANI RADOVI
1.7. NASIPAVANJE ŠLJUNKA ZA
TAMPONSKI SLOJ DEBLJINE d=15
cm
→ koeficjent rastresitosti za šljunak = 1,25
(35,10 x 19,30) x 0,15 - 15 x (0,30 x
0,30) x 0,15= 101,61 - 0,20 = 101,41
m3 101,41
1.8. RAZASTIRANJE I NABIJANJE
ŠLJUNKA
(35,10 x 19,30) - 15 x (0,30 x 0,30)=
677,43 - 1,35 = 675,88
m2
675,88
1.9. ZATRPAVANJE OKO GRAĐEVINE
→ volumen pruzet iz stavke 1.3. V=4118,74
4118,74 - {(35,10 x 19,30 x 3,17) +
(36,45 x 20,65 x 0,65)}= 4118,74 -
(2147,45 + 489,25)= 1482,04
m3
1482,04
1.10. NASIPAVANJE ŠLJUNKA KAO
POKROVA RAVNOG KROVA
DEBLJINE d=5 cm
35,10 x 19,30 x 0,05 =33,87
m3 33,87
VLAD 3
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 2. BETONSKI RADOVI
2. BETONSKI RADOVI
2.1. BETONIRANJE TRAKASTIH
TEMELJA BETONOM MB 20, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(36,45 x 1,05 x 0,65) x 2 + (18,55 x
1,05 x 0,65) x 2 = 49,75 + 25,32=
75,07
m3 75,07
2.2. BETONIRANJE TEMELJA SAMACA
BETONOM MB 20, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(0,55 X 0,55 X 0,65) X 15 = 2,95
m3 2,95
2.3. BETONIRANJE NADTEMELJNOG
ZIDA TRAKASTIH TEMELJA
BETONOM MB 20, BETON
SPRAVLJEN U CENTRALNOM
(35,86 x 0,38 x 0,65) x 2 + (19,30 x
0,38 x 0,65) x 2 = 17,71+ 9,53 = 27,24
m3 27,24
2.4. BETONIRANJE NADTEMELJNOG
ZIDA TEMELJA SAMCA BETONOM
MB 20, BETON SPRAVLJEN U
CENTRALNOM POGONU
(0,30 x 0,30 x 0,65) x 15 = 0,92
m3 0,92
VLAD 4
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 2. BETONSKI RADOVI
2.5. BETONIRANJE DONJE BETONSKE
PODLOGE DEBLJINE d=8 cm,
BETONOM MB 10, BETON
SPRAVLJEN U CENTRALNOM
POGONU
[(35,10 x 19,30) - 15 x (0,30 x 0,30)] x
0,08 = [677,43-1,35] x 0,08 = 54,09
m3 54,09
2.6. BETONIRANJE GORNJE BETONSKE
PODLOGE DEBLJINE d=7 cm,
BETONOM MB 10, BETON
SPRAVLJEN U CENTRALNOM
POGONU
[(35,10 x 19,30) - 15 x (0,30 x 0,30)] x
0,07 = [677,43-1,35] x 0,07 = 47,33
m3 47,33
2.7. BETONIRANJE BETONSKOG ZIDA U
PODRUMU ZGRADE DEBLJINE d=30
cm, BETONOM MB 20, BETON
SPRAVLJEN U CENTRALNOM
POGONU
35,10 x 0,30 x 2,72 =28,64
m3
28,64
VLAD 5
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 2. BETONSKI RADOVI
2.8. BETONIRANJE BETONSKE PLOČE U
PADU BETONOM MB 20, BETON
SPRAVLJEN U CENTRALNOM
POGONU
33,87+16,94=50,81
m3
50,81
=⋅⋅
+⋅⋅2
05,010,3530,19)05,010,3530,19(
VLAD 6
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 3. AB RADOVI
3. ARMIRANO BETONSKI RADOVI
PODRUM:
3.1. BETONIRANJE AB ZIDOVA
PODRUMA BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(35,7 x 2,92 x 0,30) + (19,60 x 2,92 x m3 65,61
3.2. BETONIRANJE AB STUPOVA
DIMENZIJE 30 x 30 BETONOM MB 30,
BETON SPRAVLJEN U
CENTRALNOM POGONU
(0,30 x 0,30 x 3,05) x 20 = 5,49
m3
5,49
VLAD 7
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 3. AB RADOVI
3.3. BETONIRANJE AB GREDA
BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(35,7 x 0,30 x 0,25) x 5 + (4,60 x 0,30 x
0,25) x 28 = 13,39 + 9,66 = 23,05
m3
23,05
3.4. BETONIRANJE AB PLOČE I
KONZOLE BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(35,70 x 19,90 x 0,25) + (23,9 x 1,5 x
0,25) + (6,0 x 1,5 x 0,25) x 2 - (5,60 x
4,60 x 0,25) = 184,63
m3
184,63
VLAD 8
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 3. AB RADOVI
PRIZEMLJE:
3.5. BETONIRANJE AB ZIDOVA
PRIZEMLJA BETONOM MB 30,
BETON SPRAVLJEN U
CENTRALNOM POGONU
(19,90 x 0,30 x 3,05) x 2 = 36,42
m3
36,42
3.6. BETONIRANJE AB STUPOVA
DIMENZIJE 30 x 30 BETONOM MB 30,
BETON SPRAVLJEN U
CENTRALNOM POGONU
(0,30 x 0,30 x 3,05) x 25 = 6,86
m3
6,86
3.7. BETONIRANJE AB GREDA ŠIRINE
30 cm BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(35,70 x 0,30 x 0,25) x 2 + (19,30 x
0,30 x 0,25) x 7 = 5,35 + 10,13 = 15,48
m3
15,48
3.8. BETONIRANJE AB GREDA ŠIRINE
15 cm BETONOM MB 30, BETON
(5,60 x 0,15 x 0,25) x 39 = 8,19
m3
8,19
3.9. BETONIRANJE AB HORIZONTALNIH
SERKLAŽA U OTVORU LIFTA
BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(5,60 x 0,0,30 x 0,25) x 2 = 0,84
m3 0,84
VLAD 9
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 3. AB RADOVI
3.10. BETONIRANJE AB PLOČE BETONOM
MB 30, BETON SPRAVLJEN U
CENTRALNOM POGONU
(35,70 x 19,90 x 0,25) - (5,60 x 4,60 x
0,25) = 177,61 - 6,44 = 171,17
m3
171,17
PRVI KAT:
3.11. BETONIRANJE AB ZIDOVA
PODRUMA BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(19,90 x 3,05 x 0,30) x 2 = 36,42
m3
36,42
3.12. BETONIRANJE AB STUPOVA
DIMENZIJE 30 x 30 BETONOM MB 30,
BETON SPRAVLJEN U
CENTRALNOM POGONU
(0,30 x 0,30 x 3,05) x 25 = 6,86
m3
6,86
VLAD 10
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 3. AB RADOVI
3.13. BETONIRANJE AB GREDA ŠIRINE
30 cm BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(35,70 x 0,30 x 0,25) x 2 + (19,30 x
0,30 x 0,25) x 7 = 5,35 + 10,13 = 15,48
m3 15,48
3.14. BETONIRANJE AB HORIZONTALNIH
SERKLAŽA U OTVORU LIFTA
BETONOM MB 30, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(5,60 x 0,0,30 x 0,25) x 2 = 0,84
m3
0,84
3.15. BETONIRANJE AB
SITNOREBRIČASTE PLOČE
DEBLJINE d=25 cm, SA AB REBRIMA
ŠIRINE 15 cm, BETONOM MB 30,
BETON SPRAVLJEN U
CENTRALNOM POGONU
(35,70 x 19,90 x 0,25) + (5,60 x 0,15 x
0,25) x 39 x 6 - {(5,60 x 0,15 x 0,25) x
2} = 177,61 + 49,14 - 0,42 = 226,33
m3
226,33
3.16. BETONIRANJE AB VIJENCA NA
KROVU, BETONOM MB 20, BETON
SPRAVLJEN U CENTRALNOM
POGONU
(35,70 x 0,30 x 0,40) x 2 + (19,30 x
0,30 x 0,40) x 2 = 8,57 + 4,63 = 13,20
m3
13,20
VLAD 11
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 4. ARMIRAČKI RADOVI
4. ARMIRAČKI RADOVI
PODRUM:
4.1. ARMIRANJE AB ZIDOVA PODRUMA
St. 3.1. x 10065,61 x 100 = 6561
60 % D SS = 0,6 x 6561 = 3936,6 kg 3936,340 % T SS = 0,4 x 6561 = 2624,4 kg 2624,4
4.2. ARMIRANJE AB STUPOVA
St. 3.2. x 1005,49 x 100 = 549
60 % D SS = 0,6 x 549 = 329,4 kg 329,440 % T SS = 0,4 x 549 = 219,6 kg 219,6
4.3. ARMIRANJE AB GREDA PODRUMA
St. 3.3. x 10023,05 x 100 = 2305
70 % D SS = 0,7 x 2305 = 1613,5 kg 1613,530 % T SS = 0,3 x2305 = 691,5 kg 691,5
4.4. ARMIRANJE AB PLOČE PODRUMA
St. 3.4. x 100184,63 x 100 = 18463
50 % D SL = 0,5 x 18463 = 9231,5 kg 9231,550 % T SL = 0,5 x 18463 = 9231,5 kg 9231,5
VLAD 12
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 4. ARMIRAČKI RADOVI
PRIZEMLJE:
4.5. ARMIRANJE AB ZIDOVA PRIZEMLJA
St. 3.5. x 10036,42 x 100 = 3642
60 % D SS = 0,6 x 3642 = 2185,2 kg 2185,240 % T SS = 0,4 x 3642 = 1456,8 kg 1456,8
4.6. ARMIRANJE AB STUPOVA
PRIZEMLJA
St. 3.6. x 1006,86 x 100 = 686
60 % D SS = 0,6 x 686 = 411,60 kg 411,640 % T SS = 0,4 x 686 = 274,40 kg 274,4
4.7. ARMIRANJE AB GREDA PRIZEMLJA
ŠIRINE 30 cm
St. 3.7. x 10015,48 x 100 = 1548
70 % D SS = 0,7 x 1548 = 1083,6 kg 1083,630 % T SS = 0,3 x 1548 = 464,4 kg 464,4
4.8. ARMIRANJE AB GREDA PRIZEMLJA
ŠIRINE 15 cm
St. 3.8. x 1008,19 x 100 = 819
50 % D SL = 0,5 x 819 = 409,5 kg 409,550 % T SL = 0,5 x 819 = 409,5 kg 409,5
4.9. ARMIRANJE AB HORIZONTALNIH
SERKLAŽA U OTVORU LIFTA
St. 3.9. x 1000,84 x 100 = 84
70 % D SS = 0,7 x 84 = 58,8 kg 58,830 % T SS = 0,3 x 84 = 25,2 kg 25,2
VLAD 13
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 4. ARMIRAČKI RADOVI
4.10. ARMIRANJE AB PLOČE PRIZEMLJA
St. 3.10. x 100171,17 x 100 = 17117
50 % D SL = 0,5 x 17117 = 8558,5 kg 8558,550 % T SL = 0,5 x 17117 = 8558,5 kg 8558,5
PRVI KAT:
4.11. ARMIRANJE AB ZIDOVA PRVOG
KATA
St. 3.11. x 10036,42 x 100 = 3642
60 % D SS = 0,6 x 3642 = 2185,2 kg 2185,240 % T SS = 0,4 x 3642 = 1456,8 kg 1456,8
4.12. ARMIRANJE AB STUPOVA PRVOG
KATA
St. 3.12. x 1006,86 x 100 = 686
60 % D SS = 0,6 x 686 = 411,60 kg 411,640 % T SS = 0,4 x 686 = 274,40 kg 274,4
4.13. ARMIRANJE AB GREDA PRVOG
KATA ŠIRINE 30 cm
St. 3.13. x 10015,48 x 100 = 1548
70 % D SS = 0,7 x 1548 = 1083,6 kg 1083,630 % T SS = 0,3 x 1548 = 464,4 kg 464,4
4.14. ARMIRANJE AB HORIZONTALNIH
SERKLAŽA U OTVORU LIFTA
St. 3.14. x 1000,84 x 100 = 84
70 % D SS = 0,7 x 84 = 58,8 kg 58,830 % T SS = 0,3 x 84 = 25,2 kg 25,2
VLAD 14
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 4. ARMIRAČKI RADOVI
4.15. ARMIRANJE AB PLOČE PRVOG
KATA
St. 3.15. x 100226,33 x 100 = 22633
50 % D SL = 0,5 x 22633 = 11316,5 kg 11316,550 % T SL = 0,5 x 22633 = 11316,5 kg 11316,5
4.16. ARMIRANJE AB VIJENCA NA KROVU
St. 3.16. x 10013,2 x 100 = 1320
60 % D SS = 0,6 x 1320 = 792 kg 792,040 % T SS = 0,4 x 1320 = 528 kg 528,0
VLAD 15
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 5. TESARSKI RADOVI
5. TESARSKI RADOVIPODRUM:
5.1. OPLATA TRAKASTOG TEMELJA
(36,45 x 0,65) x 2 + (34,35 x 0,65) x 2+
(20,65 x 0,65) x 2 +(18,55 x 0,65) x 2 =
47,39 + 44,66 + 26,85 + 24,12 =
143,02
m2 143,02
5.2. OPLATA TEMELJA SAMCA
(4 x 0,55 x 0,65) x 15 = 21,45
m2 21,45
5.3. OPLATA NADTEMELJNOG ZIDA
(35,86 x 0,65) x 2 + (35,10 x 0,65) x 2
+ (20,06 x 0,65) x 2 + (19,30 x 0,65) x
2 = 46,62 + 45,63 + 26,08 + 25,09 =
143,42
m2 143,42
5.4. OPLATA NADTEMELJNOG ZIDA
TEMELJA SAMCA
(4 x 0,30 x 0,65) x 15 = 11,70
m2 11,7
5.5. OPLATA AB ZIDOVA PODRUMA
(35,70 x 3,12) + (35,10 x 3,12) + (19,90
x 3,12) x 2 + (19,30 x 3,12) x 2 =
465,50
m2
465,5
VLAD 16
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 5. TESARSKI RADOVI
5.6. OPLATA BETONSKOG ZIDA
PODRUMA
(35,70 x 2,72) + (35,10 x 2,72) =
192,58
m2 192,58
5.7. OPLATA AB STUPA PODRUMA
(0,30 x 4 x 3,05) x 20 = 73,20
m2
73,2
5.8. OPLATA AB GREDA PODRUMA
(35,70 x 0,25) x 2 + (19,90 x 0,25) x 2
+ (5,60 x 0,25) x 48 + (4,60 x 0,25) x
48 + (5,60 x 0,30) x 22 + (4,60 x 0,30)
x 19 = 17,85 + 9,95 + 67,2 + 55,20 +
36,96 + 26,22 =213,38
m2 213,38
5.9. OPLATA AB PLOČE PODRUMA
(5,60 x 4,60) x 23 + (23,9 x 1,5) + (6,0x
1,5) x 2 = 592,48 + 35,85 + 18 =
646,33
m2 646,33
PRIZEMLJE
5.10. OPLATA AB ZIDOVA PRIZEMLJA
(19,90 x 3,05) x 4 + (0,30 x 3,05) x 4 =
242,78 + 3,66 = 246,44
m2 246,44
5.11. OPLATA AB STUPA PRIZEMLJA
(0,30 x 4 x 3,05) x 25 = 91,5
m2 91,5
VLAD 17
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 5. TESARSKI RADOVI
5.12. OPLATA AB GREDA PRIZEMLJA
ŠIRINE 30 cm
(35,70 x 0,25) x 2 + (19,90 x 0,25) x 2
+ (5,60 x 0,25) x 16 + (4,60 x 0,25) +
(2,3 x 0,25) x 64 + (2,23 x 0,25) x 24 +
(2,30 x 0,30) x 28 + (2,23 x 0,30) x 10
= 17,85 + 9,95 + 22,4 + 1,15 + 36,8 +
13,38 +19,32 + 6,69 = 127,54
m2 127,54
5.13. OPLATA AB GREDA PRIZEMLJA
ŠIRINE 15 cm
(5,60 x 0,25) x 2 x 39 + (5,60 x 0,15) x
39 = 109,2 + 32,76 = 141,96
m2
141,96
5.14. OPLATA AB HORIZONTALNIH
SERKLAŽA U OTVORU LIFTA
(5,60 x 0,25) x 4 = 5,60
m2
5,6
5.15. OPLATA AB PLOČE PRIZEMLJA
(2,23 x 5,60) x 12 + (2,3 x 5,60) x 34 =
149,86 + 437,92 = 587,78
m2
587,78
PRVI KAT:
5.16. OPLATA AB ZIDA PRVOG KATA
(19,90 x 3,05) x 2 + (19,30 X 3,05) x 2
= 121,39 + 117,73 = 239,12
m2 239,12
VLAD 18
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 5. TESARSKI RADOVI
5.17. OPLATA AB STUPA PRVOG KATA
(0,30 x 4 x 3,05) x 25 = 91,5
m2 91,5
5.18. OPLATA AB GREDA PRVOG KATA
ŠIRINE 30 cm
(35,70 x 0,25) x 2 + (19,90 x 0,25) x 2
+ (5,60 x 0,25) x 12 + (19,30 x 0,25) x
10 + (4,60 x 0,25) x 4 + (0,30 x 0,25) +
(4,60 x 0,30) x 19 = 17,85 +9,95 + 16,8
+ 48,25 + 4,6 + 0,08 + 26,22 = 123,75
m2
123,75
5.19. OPLATA AB HORIZONTALNIH
SERKLAŽA U OTVORU LIFTA
(5,60 x 0,25) x 4 = 5,60
m2
5,6
5.20. OPLATA AB SITNOREBRIČASTE
PLOČE
{(9 x 5,60 x 0,15) + (20 x 5,60 x 0,25) +
(5,60 x 0,2875 x 4) + (5,60 x 0,35 x 6)}
x 23 = (7,56 + 28 + 6,44 + 11,76) x 23=
1236,48
m2 1236,48
5.21. OPLATA AB VIJENCA NA KROVU
(35,70 x 0,40) x 2 + (35,10 x 0,40) x 2
+ (19,90 x 0,40) x 2 + (19,30 x 0,40) x
2 = 30 + 28,08 + 15,92 + 15,44= 89,44
m2 89,44
VLAD 19
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 6. ZIDARSKI RADOVI
6. ZIDARSKI RADOVI
6.1. ZIDANJE KANT ZIDA ZA ZAŠTITU H.I.
NF OPEKOM DEBLJIN d = 6,5 cm
PRODUŽNIM CEMENTNIM MORTOM
1:3:9
(35,86 x 2,52) x 2 + (19,90 x 2,52) x 2
= 180,73+100,30=281,03
m2
281,03
6.2. ZIDANJE ZIDA OKNA LIFTA NF
OPEKOM DEBLJINE ZIDA d = 12 cm
PRODUŽNIM CEMENTNIM MORTOM
1:3:9
(5,60 x 3,05 x 6) + (4,60 x 3,05 x 3)=
102,48 + 42,09 = 144,57
m2 144,57
6.3. ZIDANJE PARAPETNOG ZIDA NF
OPEKOM DEBLJINE ZIDA d = 30 cm
PRODUŽNIM CEMENTNIM MORTOM
1:3:9
(5,60 x 1,10 x 6) x 3 x 0,30= 110,88
m³ 33,26
VLAD 20
ORGANIZACIJA GRAĐENJA DOKAZNICA MJERA 6. ZIDARSKI RADOVI
6.4. POSTAVLJANJE HIDROIZOLACIJE
6.4.1. POSTAVLJANJE HORIZONTALNE
HIDROIZOLACIJE PODRUMA, SA
PRETHODNIM NANOŠENJEM
BITUMENSKE EMULZIJE.1
LJEPENKA + 2 BITUMENSKA
PREMAZA
(36,45 x 20,65) -15 x (0,30 x 0,30) =
752,69 - 1,35 = 751,34
m2 751,34
6.4.2. POSTAVLJANJE VERTIKALNE
HIDROIZOLACIJE PODRUMA. 1
LJEPENKA + 2 BITUMENSKA
PREMAZA
→ površina preuzeta iz stavke 6.1.P=281,03
m2
281,03
6.4.3. POSTAVLJANJE KROVNE
HORIZONTALNE HIDROIZOLACIJE,
SA PRETHODNIM NANOŠENJEM
BITUMENSKE EMULZIJE.2
LJEPENKA + 3 BITUMENSKA
35,10 x 19,30 = 677,43
m2
677,43
6.5. IZRADA PRODUŽNOG CEMENTNOG
MORTA 1:3:9m³ 24,86
VLAD 21
REDNI
BROJ
BROJ
STAVKEOPIS KOLIČINA
JEDINIČNA
MJERA
BROJ GRAĐ.
NORME
Jedinično Ukupno
1. 1.7.NASIPAVANJE ŠLJUNKA ZA
TAMPONSKI SLOJ DEBLJINE
d=15 cm
101,41 m3 - 1,25 126,7625
2. 1.8.RAZASTIRANJE I NABIJANJE
ŠLJUNKA675,88 m
3 - 1,25 844,85
3. 1.10.NASIPAVANJE ŠLJUNKA KAO
POKROVA RAVNOG KROVA
DEBLJINE d=5 cm
33,87 m3 - 1,25 42,3375
1013,95 UKUPNO
ŠLJUNAK
I. ZEMLJANI RADOVI
VLAD 1
BETON MB 20
REDNI
BROJ
BR.
STAVKOPIS KOLIČINA
JEDINIČNA
MJERA
BROJ GRAĐ.
NORME
Jedinično Ukupno
1. 2.1.BETONIRANJE TRAKASTIH
TEMELJA BETONOM MB 2075,07 m
3 - 1 75,07
2. 2.2.BETONIRANJE TEMELJA SAMACA
BETONOM MB 202,95 m3 - 1 2,95
3. 2.3.BETONIRANJE NADTEMELJNOG
ZIDA TRAKASTIH TEMELJA
BETONOM MB 20
27,24 m3 - 1 27,24
4. 2.4.BETONIRANJE NADTEMELJNOG
ZIDA TEMELJA SAMCA BETONOM
MB 20
0,92 m3 - 1 0,92
5. 2.7.
BETONIRANJE BETONSKOG ZIDA
U PODRUMU ZGRADE DEBLJINE
d=30 cm, BETONOM MB 2028,64 m
3 - 1 28,64
134,82
PODRUM
II. BETONSKI RADOVI
BETON MB 20 UKUPNO PODRUM
BETON
VLAD 2
BETON MB 10
REDNI
BROJ
BR.
STAVOPIS KOLIČINA
JEDINIČNA
MJERA
BROJ GRAĐ.
NORMEJedinično Ukupno
2.5.
BETONIRANJE DONJE BETONSKE
PODLOGE DEBLJINE d=8 cm,
BETONOM MB 1054,09 m
3 - 1 54,09
2.6.
BETONIRANJE GORNJE
BETONSKE PODLOGE DEBLJINE
d=7 cm, BETONOM MB 1047,33 m3 - 1 47,33
101,42
BETON MB 10
REDNI BR. OPIS KOLIČINA JEDINIČNA BROJ GRAĐ. Jedinično Ukupno
2.8.BETONIRANJE BETONSKE PLOČE
U PADU BETONOM MB 20 50,81 m3 - 1 50,81
50,81
PODRUM
PRVI KAT
BETON
BETON MB 10 UKUPNO PRVI KAT
BETON MB 10 UKUPNO PODRUM
BETON
II. BETONSKI RADOVI
VLAD 3
REDNI
BROJ
BROJ
STAVKEOPIS KOLIČINA
JEDINIČNA
MJERA
BROJ GRAĐ.
NORME
Jedinično Ukupno
1. 3.1.BETONIRANJE AB ZIDOVA
PODRUMA BETONOM MB 3065,61 m
3 - 1 65,61
2. 3.2.BETONIRANJE AB STUPOVA
DIMENZIJE 30 x 30 5,49 m
3 - 1 5,49
3. 3.3.BETONIRANJE AB GREDA
BETONOM MB 3023,05 m
3 - 1 23,05
4. 3.4.BETONIRANJE AB PLOČE I
KONZOLE BETONOM MB 30184,63 m3 - 1 184,63
278,78
III. ARMIRANO BETONSKI RADOVI
BETON
PODRUM
BETON MB 30 UKUPNO PODRUM
VLAD 4
5. 3.5.BETONIRANJE AB ZIDOVA
PRIZEMLJA BETONOM MB 3036,42 m3 - 1 36,42
6. 3.6.BETONIRANJE AB STUPOVA
BETONOM MB 306,86 m3 - 1 6,86
7. 3.7.BETONIRANJE AB GREDA
ŠIR. 30 cm BETONOM MB 3015,48 m3 - 1 15,48
8. 3.8.BETONIRANJE AB GREDA
ŠIR. 15 cm BETONOM MB 308,19 m3 - 1 8,19
9. 3.9.BETONIRANJE AB HOR.
SERKLAŽA BETONOM MB 300,84 m3 - 1 0,84
10. 3.10.BETONIRANJE AB PLOČE
BETONOM MB 30171,17 m3 - 1 171,17
238,96
PRIZEMLJE
III. ARMIRANO BETONSKI RADOVI
BETON MB 30 UKUPNO PRIZEMLJE
VLAD 5
REDNI
BROJ
BROJ
STAVKEOPIS KOLIČINA
JEDINIČNA
MJERA
BROJ GRAĐ.
NORME
Jedinično Ukupno
11. 3.11.BETONIRANJE AB ZIDOVA
PODRUMA BETONOM MB 3036,42 m3 - 1 36,42
12. 3.12.BETONIRANJE AB STUPOVA
BETONOM MB 306,86 m
3 - 1 6,86
13. 3.13.BETONIRANJE AB GREDA
ŠIR. 30 cm BETONOM MB 3015,48 m3 - 1 15,48
14. 3.14.BETONIRANJE AB HOR.
SERKLAŽA BETONOM MB 300,84 m3 - 1 0,84
15. 3.15.BETONIRANJE AB SITNORE.
PLOČE BETONOM MB 30, 226,33 m
3 - 1 226,33
285,93
16. 3.16.BETONIRANJE AB VIJENCA
KROVA, BETONOM MB 2013,2 m
3 - 1 13,2
13,2
PRVI KAT
BETON
BETON MB 30 UKUPNO PRVO KAT
BETON MB 20 UKUPNO PRVO KAT
III. ARMIRANO BETONSKI RADOVI
VLAD 6
ORGANIZACIJA GRAĐENJA IV. ARMIRAČKI RADOVI
RED.
BR
BROJ
STAVKOPIS KOLIČINA
JED.
MJ.
BR. GRAĐ.
NORME
Jedinično Ukupno Jedinično Ukupno
1. 4.1.ARMIRANJE AB ZIDOVA
PODRUMA
DEBELA 3936,3 kg 400,201-5 1,080 4251,20 0,0035 13,78TANKA 2624,4 kg 400,201-2 1,080 2834,35 0,0035 9,19
2. 4.2.ARMIRANJE AB STUPOVA
PODRUMA
DEBELA 329,4 kg 400,201-5 1,080 355,75 0,0035 1,15TANKA 219,6 kg 400,201-2 1,080 237,17 0,0035 0,77
3. 4.3.ARMIRANJE AB GREDA
PODRUMA
DEBELA 1613,5 kg 400,201-5 1,080 1742,58 0,0035 5,65TANKA 691,5 kg 400,201-2 1,080 746,82 0,0035 2,42
4. 4.4.ARMIRANJE AB PLOČE
PODRUMA
DEBELA 9231,5 kg 400,201-6 1,100 10154,65 0,004 36,93TANKA 9231,5 kg 400,201-3 1,100 10154,65 0,004 36,93