Activity Name OriginalDuration
Start Finish
PAINTING WORKS 14 15-Oct-14 27-Oct-14
Ceiling Painting 4 15-Oct-14 18-Oct-14
Wall Painting 4 24-Oct-14 27-Oct-14
WOODWORKS 9 24-Oct-14 01-Nov-14
Installation of NewDoor to WC Room 2 24-Oct-14 25-Oct-14Installation of Wooden Frames for Doors 3 28-Oct-14 30-Oct-14
Installation of Sliding Door Frame 3 28-Oct-14 30-Oct-14
Installation of Sliding Door 2 31-Oct-14 01-Nov-14
Installation of Wooden Doors 2 31-Oct-14 01-Nov-14
METAL WORKS 8 26-Oct-14 31-Oct-14
Installation of Metal Doors with Panic Bar Handle. 6 26-Oct-14 31-Oct-14
FURNITURES 18 19-Oct-14 03-Nov-14
SUPPLY AND INSTALLATIONOF LABORATORY FURNITURES 10 19-Oct-14 28-Oct-14
Supply of Laboratory Chairs 2 02-Nov-14 03-Nov-14
OTHERS 9 28-Oct-14 04-Nov-14
Installation of Signages 8 28-Oct-14 04-Nov-14
MEP WORKS-FINAL FIX 23 19-Oct-14 06-Nov-14
HVAC-Final 10 19-Oct-14 28-Oct-14
Electrical Works-Final 10 28-Oct-14 06-Nov-14
Fire Fighting-Final 8 28-Oct-14 04-Nov-14
CCTV-Final 10 28-Oct-14 06-Nov-14
Plumbing-Final 6 28-Oct-14 02-Nov-14
SNAGGING, CLEARING and HAND OVER 136 12-Jul-14 06-Nov-14
TESTING ANDCOMMISSIONING 93 12-Jul-14 12-Oct-14
CLEARING, REMOVAL OF TEMPORARY CLOSURE 2 05-Nov-14 06-Nov-14
FINAL HANDING OVER 0 06-Nov-14
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2014 2015
27-Oct-14, PAINTING WORKS
Ceiling Painting
Wall Painting
01-Nov-14, WOODWORKS
Installation of NewDoor to WC RoomInstallation of Wooden Frames for Doors
Installation of Sliding Door Frame
Installation of Sliding Door
Installation of Wooden Doors
31-Oct-14, METAL WORKS
Installat ion of Metal Doors with Panic Bar Handle.
03-Nov-14, FURNITURES
SUPPLY AND INSTALLATIONOF LABORATORY FURNITURES
Supply of Laboratory Chairs
04-Nov-14, OTHERS
Installation of Signages
06-Nov-14, MEP WORKS-FINAL FIX
HVAC-Final
Electrical Works-Final
Fire Fighting-Final
CCTV-Final
Plumbing-Final
06-Nov-14, SNAGGING, CLEARING and HAND OVER
TESTING AND COMMISSIONING
CLEARING, REMOVAL OF TEMPORARY CLOSURE
FINAL HANDING OVER
DOHA CLINIC HOSPITAL-PROGRAM Classic WBS Layout 24-Mar-14 09:46
Actual WorkRemaining W ork
Critical Remaining WorkMilestone
SummaryPage 4 of 4