DEPARTMENT OF ENERGY A Look Into the Mindanao Energy Plan 2012-2030 Dir. Jesus T. Tamang Cagayan de Oro February 22, 2013
Nov 02, 2014
DEPARTMENTOF ENERGY
A Look Into the Mindanao Energy Plan
2012-2030
Dir. Jesus T. TamangCagayan de OroFebruary 22, 2013
Energy Reform Agenda (ERA)
Good Governance thru stakeholder participation, transparency,
multi-sectoral partnership and use of ICT
Ensure Energy Security
Achieve OptimalEnergy Pricing
Develop aSustainable
Energy System
“Energy Access for More” A key priority of government to
mainstream access of the greater majority to reliable energy services and fuel, most importantly, local productivity
and countryside development
TransparencyInitiatives, Implementation and Information
Ensure Energy Security
Expand Energy Access
Promote Low-Carbon
Future
Climate Proof the Energy
Sector
Policy ThrustsPEP 2012-2030
Source: NREP 2011-2030
Ensure Energy SecurityTriple the RE Capacity by 2030
Sector Short Term(2011-2015)
Medium Term(2016-2020)
Long Term(2021-2030)
Total(in MW)
Geothermal 220.0 1,100.0 175.0 1,495.0
Hydropower 341.3 3,161.0 1,891.8 5,394.1
Biomass 276.7 276.7
Biofuels DC on E10 in 2011 Mandatory E10 to
all Gasoline by 2012
PNS for B5 by 2014
DC on B5 by 2015 Mandatory B5 to
all Diesel by 2015
PNS for B20 and E85 by 2020
DC on B10 and E20 by 2020
DC on B20 and E85 by 2025
Wind 200.0 700.0 1,445.0 2,345.0
Solar 50.0 100.0 200.0 350.0
Ocean Power
0 35.5 35.0 70.5
TOTAL (in MW)
1,088.0 5,096.5 3,746.8 9,931.3
Ensure Energy SecurityPromote Indigenous Fossil Fuels
*@10,000 BTU/lb
Fossil Fuel 2011 2012-2030
Oil (MMB) 2.3 78.0
Gas (BCF) 140.4 2,837.8
Condensate (MMB)
5.1 70.8
Coal (MMMT*) 6.9 229.9
PECR for Coal was launched on 01 December 2011 offering 38 prospective coal areas
Offered areas are located in:
Agusan del Norte, Misamis Oriental, Agusan del Sur, Surigao del Sur, Compostela Valley, Davao Oriental, Lanao del Sur, Lanao del Norte, South Cotabato, Sultan Kudarat, Saranggani, Zamboanga del Norte and Zamboanga Sibugay.
Ensure Energy SecurityPromote Indigenous Fossil Fuels
A. Increase installed capacityB. Upgrade and expand transmission and
distribution networkC. Interconnect the island gridsD. Expand energy market from Luzon-
Visayas to Mindanao and include RE.
Ensure Energy SecurityReliable and Efficient Power Sector, in MW
GridRequired by 2030
Installed (end 2011)
Committed Indicative Net
Luzon 20,707.7 11,811.1 868.7 6,819.3 1,280.7
Visayas 4,412.0 2,393.8 310.0 433.0 1,267.0
Mindanao 4,210.0 2,022.0 588.0 527.0 1,073.0
TOTAL 29,329.7
16,226.9
1,766.7 7,779.3 3,620.7
NGCP’s Grid Development Map
Ensure Energy SecurityReliable and Efficient Power Sector
Upgrade and expand the transmission lines
Interconnect Mindanao with the Visayas
Batangas-Mindoro Interconnection
Expand Energy Access Transmission Development Projects
Type of Project
Transmission Lines Substations
No. of Projects
Kilovolts (kV)
Kilometers (Km.)
No. of Project
s
No. of Substatio
ns Luzon
New 7 1,673 368.5 1 15 Upgrading/Expansion 4 1,035 133.55 11 50
Sub-total 11 2,708 502.05 12 65 Visayas
New 10 1,817 688.91 2 28 Upgrading/Expansion - - - 2 8
Sub-total 10 1,817 688.91 4 36 Mindanao
New 6 1,150 513.00 2 11 Upgrading/Expansion - - - 3 24
Sub-total 6 1,150 513.00 5 35 Philippines
New 23 4640 1570.41 5 54 Upgrading/Expansion 4 1035 133.55 16 82 TOTAL 27 5,675 1,703.96 21 136
Expand Energy AccessAchieve 90% Household Electrification by 2017
Achieve 100% Sitio Electrification by 2015
• Area / Regional Depots• Service / Refilling Stations• LPG Refilling Stations• Distribution Pipelines
Expand Energy AccessDownstream Oil Sector
The Bright Now! Campaign aims to educate and empower Filipinos to be smart energy users
Expand coverage of energy labeling program and move towards standardization
Government to lead 10.0 percent savings on fuel and electricity
Consistent with the ASEAN and APEC Targets
Promote Low-Carbon FutureAchieve 10.0 Percent Energy Savings by 2030
Energy Standards and Labeling Program will be expanded to cover:
Television sets
Washing machines
Refrigerators (up to 12 cubic feet)
New models of passenger cars and light duty vehicles
Promote Low-Carbon FutureAchieve 10.0 Percent Energy Savings by 2030
Promote Low-Carbon Future30% of Public Utility Vehicles on Alternative Fuels by 2030
Promote use of clean and alternative fuels 20% biofuels blending by 2030 Expand number of compressed natural gas (CNG) and
auto-LPG vehicles Massively deploy electric vehicles (EV)
Support expansion of mass transport system
Type 2011 2015 2016 2020 2025 2030
Number of Vehicles
CNG
Bus 61 1,000 5,000 6,900 9,200 15,000
Taxi 100 1,000 6,000 16,000
Auto-LPG
19,052 20,200 20,500 21,700 23,200 23,000
E-trikes 630 50,170 80,730 106,000 150,000 230,000
Biofuel Blending
Ethanol 10% 10% 10% 20% 20% 20%
CME 2% 5% 5% 10% 20% 20%
Promote Low-Carbon Future30% of Public Utility Vehicles on Alternative Fuels by 2030
(Biodiesel)
Note: Total Supply requirement of Biodiesel is equal to the total diesel to be displaced
Year
Diesel DemandBiodiesel Blend (Target)
Supply Requirement/Fuel
Displacement
(In Million Liters)
(In KTOE)
(In Million Liters)
(In KTOE)
2011 6,724 5,697 2% 134 114
2015 7,645 6,477 5% 382 324
2020 9,056 7,672 10% 906 767
2025 10,348 8,768 20% 2,070 1,754
2030 11,428 9,683 20% 2,286 1,937
Promote Low-Carbon Future30% of Public Utility Vehicles on Alternative Fuels by 2030
(Bioethanol)
Note: Total supply requirement of bioethanol is equal to total gasoline to be displaced
Year
Gasoline DemandBioetha
nol Blend
(Target)
Supply Requirement/Fuel
Displacement
(In Million Liters)
(In KTOE)
(In Million Liters)
(In KTOE)
2011 4,181 3,274 10% 418 327
2015 5,350 4,189 10% 535 419
2020 7,955 6,229 20% 1,591 1,246
2025 10,322 8,083 20% 2,064 1,617
2030 12,589 9,858 20% 2,518 1,972
Promote Low-Carbon Future30% of Public Utility Vehicles on Alternative Fuels by 2030
Promote Low-Carbon FutureUse of Natural Gas in All Sector
19
Mindanao Critical Infrastructure Projects
Pipeline Projects Target Year27.4 k.m. Pipeline System for Cagayan de Oro and PHIVIDEC Area 2014-2016
2x2 k.m. Distribution Pipeline in Iligan City 2014-2016
Note: Said Targets are still subject for review based on current socio-economic conditions.
Floating Storage & Regasification Unit (FSRU) Target Year
FSRU Facility in Macajalar Bay, Misamis Oriental 2014-2016
Storage Facility Target YearSatellite Supply Terminal (2 Storage Tanks each with 120 cu.m.) in South Iligan 2014-2016
Satellite Supply Terminal (1 Storage Tanks with 120 cu.m.) in North Iligan 2014-2016
Refilling Station Target Year
Liquefied Compressed Natural Gas (LCNG) Refueling Stations in Iligan City, CDO and PHIVIDEC Areas
2016-2017
Promote Low-Carbon FutureUse of Natural Gas in All Sector
20
Refilling Stations Target YearLiquefied Compressed Natural Gas (LCNG) Refueling Stations in General Santos and Davao
2016-2018
Note: Said Targets are still subject for review based on current socio-economic conditions.
Liquefied Natural Gas (LNG) Terminals Target Year
3 Satellite LNG Terminals in Davao via General Santos TBD
Pipeline Projects Target Year
53 k.m. Pipeline in General Santos 2016-2018
Mindanao Critical Infrastructure Projects
Promote Low-Carbon FutureUse of Natural Gas in All Sector
Climate Proof the Energy SectorPromote a climate change resilient energy sector
Implement the National Climate Change Action Plan (NCCAP) in the energy sector Mitigation action mainly through energy efficiency,
renewable energy and alternative fuels and technology programs
Conduct vulnerability assessment of the energy sector Identify and pursue adaptation programs
Upgrade standards for energy systems and facilities
Critical Drivers and Factors to Consider
• Sustained high economic
growth target • Re-entry of the
manufacturing sector• Infrastructure programs i.e.
roads, bridges, ports, etc.• Expanded RE and fuel mix• Climate change impacts• Mindanao-Visayas
interconnection• Full household electrification
by 2017
Mindanao Power Supply-Demand Outlook 2012-2030with Indicative Projects for 2013-2014
23
Critical Periods
2014 – initial relief period due to committed and indicative capacities
2018 – next critical period with committed capacity only
2020 - if with committed and indicative capacities
Additional capacity requirement will be more than calculated due to presence of suppressed demand
1000
1500
2000
2500
3000
3500
4000
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
Existing Capacity Existing +Committed Capacity
Plus Indicative Peak Demand @ 4.76 GR + RM
Peak Demand @ 5.28 GR+ RM
Notesa. Demand curve represents total of peak demand and required Regulating Reserve (RM)
i.e. 4% regulating reserve and contingency and dispatchable reserve requirement (RM).b. 4.76% peak demand growth rate resulted from aggregated demand as submitted by the
utilities to DOE.c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand
for electric power with national economic growth applied to 6.6 percent GDP growth rate (GR) for 2012.
d. Power demand in the island remains restrained. Grew by 1.84 % in 2012.
Interim Mindanao Electricity Market(iMEM)
Interim Mindanao Electricity Market DesignGoal:
Provide an immediate venue for transparent and efficient utilization of additional capacities to address current Mindanao energy supply shortfall
Participants•Generators
(Grid, Embedded, Firm, Non-Firm)
•Customers With Self Gen Capability (DUs)
•Demand-Side (VLC)
Pricing• Bid-based with Bid Cap
Scheduling• Day-Ahead Nomination• Real-time imbalance
correction
Financial Settlement•Uniform
Pricing (Market Clearing Price)
Interim Mindanao Electricity Market
- Price Determination Methodology and Cost Recovery Filing
- Engagement of Consultants
- Market Rules Drafting- Public Consultation- DC Issuance
-DC Issuance-MF Filing for utilization of savings
Policy and Budget Approval• Consultation• Promulgation
Market Rules Development• Consultation• Market Rules Promulgation
Regulatory Approvals• Rates• Cost Recovery
Market Development• Training and System Trial• Infra & System Development
Stakeholder Engagement
IMEM
*As presented during the public consultations
6 MonthsDC ISSUANCE:
9 JAN 2013LAUNCH DATE:
26 APR 20145 Months
J F M A M J J A S O N D J F M A 2013 2014
ERC
Filin
g fo
r PD
M a
nd C
RM
DATE FILED:21 JAN 2013
15 months starting from the Issuance of DC
Establishment Timeline
DEPARTMENTOF ENERGY
A Look Into the Mindanao Energy Plan
2012-2030
Dir. Jesus T. TamangCagayan de OroFebruary 22, 2013