Document of The World Bank Report No: ICR00003050 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2250) ON A GRANT IN THE AMOUNT OF SDR 12.24 MILLION (US$ 17.83 MILLION EQUIVALENT) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN FOR A AFGHANISTAN URBAN WATER SECTOR PROJECT December 23, 2014 Water Global Practice Afghanistan Country Management Unit South Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
54
Embed
Document of The World Bankdocuments.worldbank.org/curated/en/428701468193480… · · 2016-07-15Sector Manager: William Kingdom Project Team Leader: ... G. Ratings of Project Performance
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Document of
The World Bank
Report No: ICR00003050
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-H2250)
ON A
GRANT
IN THE AMOUNT OF SDR 12.24 MILLION
(US$ 17.83 MILLION EQUIVALENT)
TO THE
ISLAMIC REPUBLIC OF AFGHANISTAN
FOR A
AFGHANISTAN URBAN WATER SECTOR PROJECT
December 23, 2014
Water Global Practice
Afghanistan Country Management Unit
South Asia Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
(Exchange Rate Effective 12/07/2014)
Currency Unit = Afghani (Afs)
1.00 = US$ 0.017
US$ 1.00 = 57.55
FISCAL YEAR 2015
ABBREVIATIONS AND ACRONYMS
Afs Afghani
ARDS Afghanistan Reconstruction and Development Services
ARTF Afghanistan Reconstruction Trust Fund
AUWSSC Afghanistan Urban Water Supply and Sewerage Corporation
AUWSSC-HQ AUWSSC Headquarters
CAWSS Central Authority for Water Supply and Sewerage
1. Project Context, Development Objectives and Design ............................................... 1
2. Key Factors Affecting Implementation and Outcomes .............................................. 6 3. Assessment of Outcomes .......................................................................................... 11 4. Assessment of Risk to Development Outcome ......................................................... 16
5. Assessment of Bank and Borrower Performance ..................................................... 17 6. Lessons Learned..................................................................................................... 20
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 21
Annex 1. Project Costs and Financing .......................................................................... 22
Annex 2. Outputs by Component ................................................................................. 23 Annex 3. Economic and Financial Analysis ................................................................. 29
Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 30 Annex 5. Beneficiary Survey Results ........................................................................... 32 Annex 6. Stakeholder Workshop Report and Results ................................................... 33
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 34 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 42 Annex 9. List of Supporting Documents ...................................................................... 43 MAP .............................................................................................................................. 44
A. Basic Information
Country: Afghanistan Project Name: AF: Urban Water
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Unsatisfactory Government: Moderately
Unsatisfactory
Quality of Supervision: Moderately Satisfactory Implementing
Agency/Agencies: Moderately Satisfactory
Overall Bank
Performance:
Moderately
Unsatisfactory Overall Borrower
Performance: Moderately Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments
(if any) Rating
Potential Problem Project
at any time (Yes/No): Yes
Quality at Entry
(QEA): None
Problem Project at any
time (Yes/No): Yes
Quality of
Supervision (QSA): None
DO rating before
Closing/Inactive status:
Moderately
Satisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
Central government administration 27 27
Water supply 73 73
Theme Code (as % of total Bank financing)
City-wide Infrastructure and Service Delivery 29
Conflict prevention and post-conflict reconstruction 29
Infrastructure services for private sector development 14 2
State-owned enterprise restructuring and privatization 28 98
E. Bank Staff
Positions At ICR At Approval
Vice President: Annette Dixon Praful C. Patel
Country Director: Robert J. Saum Alastair J. McKechnie
Practice
Manager/Manager: William D. Kingdom Sonia Hammam
Project Team Leader: Deepali Tewari Christophe E. Bosch
ICR Team Leader: Deepali Tewari
ICR Primary Author: Pratibha Mistry
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document) At appraisal, the project development objective was: 'to assist the Recipient to develop
the capacity of the Afghanistan Urban Water Supply and Sewerage Corporation for
operational management and investment planning and implementation. The project
objectives will be to initiate actions to: (i) transform CAWSS into a technically viable
operation; (ii) establish the financial sustainability of the Afghanistan Urban Water
Supply and Sanitation Company UWSSC - CAWSS successor); (iii) increase access to
and reliability of the water supply service in Kabul; and (iv) prepare a follow-up project
under which more substantial institutional and financial objectives could be achieved and
coverage further expanded in Kabul and provincial towns'.
Revised Project Development Objectives (as approved by original approving authority)
The revised project development objective was to assist the Recipient to develop the
capacity of the Afghanistan Urban Water Supply and Sewerage Corporation for
operational management and investment planning and implementation.
The indicators reported below are for the restructured project. Only 2.5% of the original
grant amount had been disbursed towards the end of the original grant period, prior to
restructuring, to support the capacity building objective of the project. The project was
implemented as the restructured project and the indicators below are as approved for the
restructured project.
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved at
Completion or Target
Years
Indicator 1 : Number of water utilities that the project is supporting
Value
quantitative or
Qualitative)
0 1 1
Date achieved 06/01/2010 06/01/2010 06/30/2014
Comments
(incl. %
achievement)
The core indicator was incorporated at restructuring.
Indicator 2 : AUWSSC is fully corporatized and took over operation in urban areas
Value
quantitative or
Qualitative)
Not achieved
AUWSSC took
over operation in
all urban areas
where CAWSS
was operating
AUWSSC fully
corporatized. Urban
operations expanded to 43
towns (direct operations in
38 towns and joint
operations with local
municipalities in 5 towns)
Date achieved 06/01/2010 06/01/2010 06/30/2014
Comments
(incl. %
achievement)
Corporatization Features: AUWSSC accountable to its Board of Directors (BoD);
Ministry of Urban Development Affairs appoints BoD Members; BoD accountable to
Ministry; BoD appoints senior executives in AUWSSC; BoD responsible for AUWSSC's
financial results
Indicator 3 : Number of household connections in Kabul provided by small scale local providers
Value
quantitative or
Qualitative)
0 500 1,200
Date achieved 06/01/2010 06/01/2010 06/30/2014
Comments
(incl. %
achievement)
The pilot scheme by small scale providers currently benefits 1,200 households and is
expected to be extended to a further 800 households by the private operator.
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value Achieved
at Completion or
Target Years
Indicator 1 : Financial statements of AUWSSC is produced and audited
Value
(quantitative
or Qualitative)
AUWSSC is a new entity 2 4
Date achieved 06/01/2010 06/01/2010 06/30/2014
Comments
(incl. %
achievement)
Financial statements were produced and audited for four financial years: FY 1388
(2009/10), 1389 (2010/11), 1390 (2011/12), and 1391 (2012/13).
Indicator 2 : Accounts receivable (months)
Value
(quantitative
or Qualitative)
3.5* 2.0 3.0
Date achieved 06/01/2010 06/01/2010 06/30/2014
Comments
(incl. %
achievement)
The accounts receivable was defined as: Accounts receivable = (Year-end accounts
receivable/total annual operating revenues) x 12.
*from restructuring paper
Indicator 3 : Working Ratio
Value
(quantitative
or Qualitative)
1.17 1.0 0.68
Date achieved 06/01/2010 06/01/2010 06/30/2014
Comments
(incl. %
achievement)
Calculated as Total Annual Expenses excluding Depreciation/Total Annual Revenue
Indicator 4 : Average per connection collections (Afs)
15 06/30/2014 Moderately Satisfactory Moderately Satisfactory 15.08 *On June 14, 2014 the project was rated Moderately Unsatisfactory to emphasize the need for client action on disbursement
delays and audit completions. This was upgraded back to Moderately Satisfactory in the final supervision mission at the end of
June 2014.
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring & Key
Changes Made DO IP
06/01/2010 N MU MU 1.00
Extension of the grant closing date for 3
months, from June 30, 2010 to
September 30, 2010 to allow time for
Level 1 restructuring.
10/01/2010 Y MU MU 1.03
Cancellation of Component 3:
Extension of Kabul Water Supply
System. Extension of closing date from
September 30, 2010 to June 30. 2012
06/27/2012 S MS 3.48
Extension of closing date from June 30,
2012 to June 30, 2014. Reallocation
between disbursement categories.
03/25/2014 MS MS 8.61
Creation of one combined Disbursement
Category, elimination of monetary
thresholds
If PDO and/or Key Outcome Targets were formally revised (approved by the original approving body)
enter ratings below:
Outcome Ratings
Against Original PDO/Targets Unsatisfactory
Against Formally Revised PDO/Targets Moderately Satisfactory
Overall (weighted) rating Moderately Satisfactory
I. Disbursement Profile
1
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
1. Country and Sector Background. In the aftermath of September 11, 2001,
major changes took place in the political and military situation in Afghanistan: the first
post-war President was elected and a new Cabinet was inaugurated in 2004, and a new
Parliament was sworn in on December 19, 2005. The challenges of establishing national
unity, developing institutions, and implementing the Government’s long term vision for
development remained significant. The country’s economic infrastructure had been
devastated after decades of conflict, and most Afghans had little or no access to basic
services. In 2005, piped water coverage was estimated at 18%, among the lowest in the
world. The majority of urban households abstracted water from contaminated boreholes,
open wells, springs or streams. Sewerage coverage was limited to a few Soviet-era
apartment complexes in Kabul that served less than 2% of the population.
2. The Central Authority for Water Supply and Sewerage (CAWSS) was a
department within the Ministry of Urban Development Affairs (MUDA1) responsible for
urban service delivery across the country. There were functional gaps and overlapping
responsibilities between CAWSS and municipalities. CAWSS was responsible for urban
service delivery, and municipalities were responsible for on-site sanitation through their
local departments of sanitation. CAWSS’s operational, commercial and financial
performance was poor. During the period of conflict, communication with the provincial
towns was difficult, and regional operations were managed autonomously.
3. The Government’s Interim Afghanistan National Development Strategy (ANDS)
(March 2006) identified water supply and sanitation as a priority area for public
infrastructure investment. As part of its efforts to meet the Millennium Development
Goals, the Government aimed to supply piped water by 2010 to 50% of households in
Kabul, and 30% of households in other major urban centers. To achieve this target, the
Government developed the Urban Water Supply and Sewerage Sector Policy, Urban
Water Supply and Sewerage Sector Institutional Development Plan, and the Presidential
Decree to corporatize CAWSS to the Afghanistan Urban Water Supply and Sewerage
Corporation (AUWSSC). These policies underscored the government’s commitment to
extend access, improve sustainability of service provision, and emphasize full cost
recovery and financial sustainability of service providers.
4. Rationale for Bank Assistance. The Bank re-engaged in Afghanistan in 2002
with the US$ 37.6 million IDA financed Emergency Infrastructure Reconstruction
Project (EIRP) (2002-2006). This multi-sector project formed the basis for the Bank’s
subsequent sector specific projects in urban reconstruction, water supply and sanitation,
1 Formerly Ministry for Urban Development (MoUD).
2
and power. The Government developed the Short Term Program (STP) (2005-2007) and
the Medium Term Program (MTP) (2007-2011) as urban water supply and sanitation
sector investment plans to channel donor efforts more effectively.
5. The Bank’s Transitional Support Strategy of March 2003 identified water supply
and sanitation as a key priority for investment and a series of follow on projects from
EIRP were planned to support the sector. STP investments were packaged for support
under the Afghanistan Short Term Urban Water Supply and Sanitation Project (P092162)
financed by the Afghanistan Reconstruction Trust Fund (ARTF) and approved in 2005.
MTP investments were packaged under this project, the Afghanistan Urban Water Sector
Project (AUWSP), an Emergency Response Loan approved in May 2006. Both projects
were concurrently prepared by the same task team.
6. The Bank’s strong in-country presence and development leadership supported the
Government’s efforts to coordinate donor activities in the sector. The Bank’s knowledge
of operating effectively in fragile and post conflict states was evolving. Afghanistan
remained highly unstable and insecure. There was continuing insurgency, municipal
governments were weak, and internal revenue generation was tenuous. It was clear that in
addition to the planned development programs, even the maintenance of existing services
would have to rely on external funding for the foreseeable future. Donors were very
active in Afghanistan during this time and the largest donors in the sector at that time
were the German development agencies and IDA.
1.2 Original Project Development Objectives (PDO) and Key Indicators
7. The PDO was phrased differently in the project’s Technical Annex 2 and
Financing Agreement. In the Technical Annex the project’s objectives were:
“…to initiate actions to: (i) transform CAWSS into a technically viable operation; (ii)
establish the financial sustainability of the Afghan Urban Water Supply and Sanitation
Company (AUWSSC - CAWSS successor); (iii) increase access to and reliability of the
water supply service in Kabul; and (iv) prepare a follow-up project under which more
substantial institutional and financial objectives could be achieved and coverage further
expanded in Kabul and provincial towns.”
8. In the Financing Agreement the PDO was stated as:
“… to assist the Recipient in increasing access to, and reliability of, the water supply and
sewerage service in its urban centers by: (i) establishing adequate institutional
arrangements for the management of water supply and sewerage; and (ii) extending the
water supply system in Kabul.”
2 Report Number P7670-AF
3
9. The Technical Annex included the following key indicators::
Commercial performance per Strategic Business Unit (SBU) (and other AUWSSC
operations): Number of total and billed connections per category of customer; Population
served and service ratio; Production and sales (m3/year); Metering, billing and collection
(m3/year and Afs); and Non-Revenue Water (%).
Financial Performance per SBU (and other AUWSSC operations and AUWSSC/HQ):
Operating cost, including electricity, fuel, chemicals, parts, maintenance (Afs); Staff
costs, including salaries and bonuses (Afs); Management costs, including salaries and
bonuses (Afs); Revenues per SBU per category of customer (Afs); Accounts receivable
per category of customer (days of billing); and Working Ratio (%).
Service Performance per SBU/other operations: Per connection and per capita production
and sales (liters per capita per day); and Percentage of samples tested meeting residual
chlorine standards (%).
1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and
reasons/justification
10. By the end of the grant period in 2010, the project could not be implemented due
to: (i) an unrealistic project design that did not integrate the post-conflict context and
lessons emerging from other projects under implementation; (ii) the use of disbursement
conditions that could not be realistically met; (iii) increasing politicization of the
transition from CAWSS to AUWSSC; and (iv) delays in the preparation of detailed
designs for the infrastructure component that was financed by external donors.
11. Due to implementation delays and significant cost escalations, US$23 million of
the grant committed to Component 3: Extension of Kabul Water Supply System Works
was cancelled. Two additional activities were included in the project: (i) the preparation
of a new water supply project for Kabul, and (ii) implementation of a pilot scheme for
water supply expansion by private operators.
12. To reflect these changes the project development objective was revised to: to
assist the Recipient to develop the capacity of the Afghanistan Urban Water Supply and
Sewerage Corporation for operational management and investment planning and
implementation. PDO level indicators were revised to: i) Number of water utilities that
the project is supporting; ii) AUWSSC is fully corporatized and took over operation in
urban areas; iii) Number of household connections in Kabul provided by small scale local
providers.
1.4 Main Beneficiaries,
13. As originally designed, the following benefits were intended for the primary
beneficiaries: i) AUWSSC would increase its capacity for operational management,
4
investment planning and implementation, benefitting approximately 1.5 million people
being served in the urban areas (of which 0.74 million female); and ii) an estimated
600,000 (of which 294,000 female) residents of Kabul city would gain access to piped
water through the Logar II scheme.
14. After restructuring in 2010 the primary beneficiaries were: i) AUWSSC, to
improve operational management, investment planning and implementation for
approximately 1.5 million people being served in the urban areas (of which 0.74 million
female); and ii) 500 households in Kabul being connected using small scale local
providers.
1.5 Original Components
15. To achieve the project development objective, the project was designed around
the following three components:
Component 1: Institutional Development of AUWSSC (US$ 8.2 million)
16. Reorganization of CAWSS into a public corporation to be responsible for the
management and development of urban water supply and sewerage assets and for the
provision of quality water supply and sewerage services in urban areas, through the
provision of legal and technical advisory services.
17. Development and enhancement of capacity in the newly formed AUWSSC,
through the provision of technical assistance and training for, among other things: (i) the
preparation of operations, procurement, accounting and financial management
procedures; (ii) the monitoring and management of environment and social issues; (iii)
human resource development; (iv) the carrying out of feasibility studies and surveys; (v)
the carrying out of audits; and (vi) the carrying out of financial management, planning
and design, and management and implementation of water supply and sewerage activities.
18. Strengthening and improving the institutional capacities of SBUs through, among
other things, the preparation and execution of memoranda of understandings between
AUWSSC's headquarters and each SBU.
19. Designing of a public private partnership arrangement for the management of
water supply and sewerage services in selected cities.
Component 2: Financial Support to AUWSSC (US$ 5.5 million)
20. Strengthening of the newly created AUWSSC, through the provision of financial
support, including payment of: (i) operations and maintenance costs including salaries of
non-managerial was capped at 45% of expenses incurred in FY07 within the limit of
US$1 .9 million, 30% of expenses incurred in FY08 within the limit of US$1 .5 million
and 15% of expenses incurred in FY09 within the limit of US$1 million; (ii) salaries of
managerial staff at 100% of expenses incurred within the limit of US$300,000 per year in
5
FY07, 08 and 09; and (iii) bonuses of managerial staff at 100% of expenses incurred
within the limit of US$100,000 per year in FY07, 08 and 09.
Component 3: Extension of the Kabul Water Supply System (US$ 18.3 million)
21. Increasing access to and reliability of the water supply service in Kabul by
developing the Logar II Water Supply Scheme through, among other things, the
development and equipping of a well field, the construction of a pumping station, the
supply and laying of pipes and equipment for the construction of a transmission line and
the extension of the distribution network, and the construction of a reservoir.
22. The US$40.0 million from IDA was supplemented with US$24.5 million of
parallel financing from German development agencies, which were to provide
institutional development to transform CAWSS into the independent corporate utility
AUWSSC, invest in the first phase of the medium term investment plan for urban water
supply infrastructure, prepare the detailed engineering designs and costing, and conduct
construction supervision.
1.6 Revised Components
23. When the project was restructured (Level 1) in 2010, the following changes were
made: Component 1: Institutional development of AUWSSC was modified to include i)
preparation of an investment program to increase water supply for Kabul; and ii) the
development and implementation of a pilot scheme to expand water supply services by
small private operators. There were no changes to Component 2: Financial support to
AUWSSC operations. Component 3: Extension of the Kabul water supply system was
cancelled.
1.7 Other significant changes
24. On December 1 2006 IDA granted a month’s extension to the effectiveness
deadline to allow more time for the signing of a co-financing agreement between the
German Development Cooperation and the Government of Afghanistan. On June 23,
2010 the closing date was extended by three months from June 30, 2010 to September 30,
2010 to allow for the Bank’s internal processing of the Level 1 restructuring. The Level 1
restructuring was completed on October 1, 2010 which established June 30, 2012 as the
revised closing date.
25. On June 27 2012, the closing date of the project was extended to June 30, 2014 to
allow for: (i) completion of technical assistance tasks; (ii) compilation of AUWSSC’s
financial statements and their audit to enable the Government to comply with the legal
covenant regarding AUWSSC’s audits and claim reimbursement of operating costs; (iii)
continuation of contracts for AUWSSC management that would otherwise end on June
30, 2012; and (iv) preparation of bidding documents for the next phase of investments.
The requirement for audited financial statements in the project design called for the
6
granting of an exception to the Bank’s financial management policy BP10.02 first, before
the closing date could be extended.
26. On March 25 2014, the project was restructured and the following changes
approved: (i) creation of one combined Disbursement Category to enable AUWSSC to
claim the allowed percentage of O&M expenditures permitted by the Financing
Agreement; and (ii) elimination of monetary thresholds, without changing the
percentages allocated for disbursements against operating costs. The allocation for
bonuses to managerial staff and the ‘Unallocated’ category were removed to allow further
reimbursement of operating costs. On October 29, 2014 the disbursement deadline of the
grace period was extended by two months from October 30, 2014 to December 31, 2014.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
27. Soundness of background analysis. In spite of project teams sharing technical
expertise, knowledge of emerging lessons from the implementation of other projects was
not sufficiently incorporated into the project design. For example, the risk of delays from
donor financed activities was emerging from the IDA financed Kabul Urban
Reconstruction Project (P083919), where water production investments to be financed
and implemented by KfW had not been completed when this project was appraised in
2006. A rapid analysis of AUWSSC’s performance and projections of future performance
were conducted with limited data collected over a six month period under the ARTF
project. This analysis was used to determine improvement targets for revenues, cost
recovery, and the levels of the declining operating subsidy that were unrealistic and based
on data that was not fully representative.
28. Assessment of project design. Conceptually, project design was consistent with
international practice in utility reform. However, it failed to sufficiently factor in the
capacity of implementing staff, the political and legal context of the post conflict state,
and the lack of data and information on public institutions. The project was designed on
the premise of AUWSSC being established before disbursements could be made against
the project, even though AUWSSC had not yet been established as a legal entity at
appraisal. AUWSSC was only the second State Owned Enterprise to be corporatized
under the Commercial Law of Afghanistan, and the legal framework was still being
established. During preparation, the Institutional Development Plan was approved and the
Presidential Decree for corporatization was secured. However, the statutes were still to be
approved by Cabinet and AUWSSC was still to be registered as a public corporation with
the Afghanistan Investment Support Agency.
29. Project preparation did not adequately take account of the fact that during the
period of conflict there were no functioning processes for the legal registration of land
and other facilities, in both the central government cadaster and in the municipalities. The
Procedures for Corporatization of State-Owned Enterprises required the creation of a list
7
of CAWSS assets and liabilities. This resulted in a lengthy process for asset re-
registration, assessment and title transfer from CAWSS to AUWSSC that delayed the
corporatization process.
30. Project preparation did not consider the scope of the undertaking to prepare
financial statements, including the challenges of asset transfer. Project design required
the preparation and audit of financial statements from the start of the project, and did not
allow for the establishment of data collection and reporting processes before requiring
audited financial statements. CAWSS did not maintain proper books of accounts and
underlying accounting records, and did not even have a simple asset register in place.
31. The infrastructure component was not ready for implementation at the time of
approval. Even though during preparation it was confirmed that “detailed designs are
ready and bidding documents can be prepared before end 2006 by consultants” it was
almost 18 months later, in June 2008, that the ISR notes that the Consultant was “now
finalizing the cost estimates based on the detailed design.”
32. Further complexity was introduced by the declining operating subsidy to be
implemented over three years. In the post-conflict context, it was unlikely that revenue
collection could be improved substantially over just three years, and it was known that a
major tariff increase was required to reach cost recovery. The declining operating subsidy
allowance led to unrealistic caps which became an impediment to AUWSSC’s ability to
claim the full percentage of O&M costs permitted under the Financing Agreement.
33. Assessment of risks. The risk assessment was not comprehensive, especially
when implementing reforms in the political and legal context of the post conflict state.
The project recognized major delays with CAWSS corporatization as an institutional risk
to the project. The grant covenants in the legal agreement were intended to mitigate the
risks by allowing the Bank to exercise legal remedies if required. The covenants were not
designed appropriately, and eventually prevented the government from accessing grant
funds for any productive use. Risks related to the lack of data and information, and
procurement delays, were not recognized. The project did not consider donor
coordination and joint implementation with the German development agencies as a risk,
even though donor financed activities in other projects were facing delays. The project’s
dependence on KfW for delivery of consulting services, the interconnected nature of the
works to be financed by the two partners, which were to be procured under different
agencies and rules, presented a major risk to implementation that was not recognized
during preparation.
2.2 Implementation
34. The corporatization of AUWSSC was a disbursement condition that could not be
realistically achieved in the timeframe developed during preparation, and led to the
situation where the allocated financing could not be productively used at all over the
original grant period. Eventually, the Articles of Incorporation of the new AUWSSC
8
were approved by the Cabinet on July 9, 2007 and gazetted by the Ministry of Justice on
July 11, 2007. CAWSS was effectively dissolved in 2009. It was only when AUWSSC
was established in May 2009 could the project implementation begin in earnest.
35. Implementation delays. The following contributed to delays in project
implementation (i) delays in the recruitment of the Management Team; (ii) delays in the
recruitment of the technical assistance consulting firm to provide technical assistance for
a three year period, which subsequently required an extension to the grant closing date;
and (iii) insufficient procurement capacity within AUWSSC.
36. Performance of consultancies. There were two major consultancies in the
project to (i) provide technical assistance to help operationalize AUWSSC by providing
management and operational assistance for improved efficiency, commercialization and
expansion; (ii) prepare a priority investment program in unserved areas in the eastern part
of Kabul City that was ready for bidding. Delays in consultant procurement, mobilization
and replacement of key staff during implementation resulted in consulting firms not
providing adequate technical expertise and having insufficient time to complete the
assignments to the required quality. At the same time AUWSSC did not have sufficient
experience or expertise to manage consultant contracts and review outputs.
37. Security. Project activities were delayed due to deterioration in the security
situation, particularly in 2013, when the political and security transition was compounded
by the protracted impasse around the Presidential elections, restricting travel and
resulting in consultants leaving unexpectedly.
38. Disbursement delays. The Ministry of Finance’s Special Disbursement Unit
(SDU) insisted on approving withdrawal applications against audited operating costs,
even though this was not a grant condition. Delays in the preparation of the financial
statements resulted from a first set of financial statements prepared by the donor partner
being found to be unreliable, requiring them to be prepared for the second time. Further
delays were caused by AUWSSC, which did not have a systematic process in place to
submit withdrawal applications and follow-up on them rigorously.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
39. M&E design. Indicators developed during project design are generally accepted
indicators to monitor commercial, financial and service performance of utilities. The
indicators were data intensive and impractical for AUWSSC to collect, especially in the
earlier years of project implementation. AUWSSC did not have any systems and
processes in place to collect operational and financial data from SBUs and collate it at
HQ level. The restructured PDO level indicators did not sufficiently represent the PDO
and monitor progress towards its achievement. Intermediate results indicators in the
restructured project were simplified to measure key performance areas that were more
realistic to measure.
9
40. M&E implementation. The development of a management information system
was built into the project design as part of the technical support consultancy. However,
delays in procurement of the technical support consultant led to insufficient time being
left in the contract to develop a comprehensive management information system.
AUWSSC Operations Department developed a manual system to collect operational data
from SBUs and consolidates it at AUWSSC HQ. The AUWSSC Finance Department
collects financial data from SBUs for the preparation of financial statements. Since data
is collected separately, there are sometimes discrepancies in reported data. Since the
recruitment of an internal auditor in December 2013, the Finance Department is
developing templates and procedures to improve data collection and data quality.
41. M&E utilization. Annual financial reports were produced by the Finance
Department that were audited by an external auditor. Operations data was collected, and
consolidated quarterly by the Operations Department. There is recognition within
AUWSSC for the need for a more systemized approach to data collection, storage and
use to drive decision making and resource allocation.
2.4 Safeguard and Fiduciary Compliance
Safeguards
42. The project was rated Category B, and the following safeguard policies were
triggered during appraisal in 2006, in context of the construction of the Logar II water