Dizdar Park City of Camarillo Community Preliminary Design Meeting March 22, 2022 City of Camarillo Department of Public Works
Dizdar ParkCity of Camarillo
Community PreliminaryDesign Meeting
March 22, 2022
City of CamarilloDepartment of Public Works
AGENDA
Introductions Purpose of meeting Design Progress Preliminary Design EIR Update Next Steps Public Input / Q & A
City of CamarilloDepartment of Public Works
INTRODUCTIONS
City Staff: Jonathan Pichardo, Associate Engineer/Project Manager James Campero, Deputy Director Public Works/Capital Projects
Consultants: Architect: David Goodale, Goodale Architecture Planning Landscape Architect: Bill Rabben, Rabben Herman Design Landscape Architect: Amy Kim, Rabben Herman Design EIR Consultant: Melissa Whittemore, Rincon Consultants Cultural Lead: Rachel Perzel, Rincon Consultants
City of CamarilloDepartment of Public Works
PURPOSE OF MEETING
Present Preliminary Project Design
Public Input / Q & A
City of CamarilloDepartment of Public Works
COMMUNITY WORKSHOP 1 : COURTHOUSE PROPERTY PROGRAM
January 29,2019
COMMUNITY WORKSHOP 1: DIZDAR PROGRAM
May 20, 2019
CITY COUNCIL REVIEW: COMBINED PROGRAMS
June 26, 2019
COMMUNITY WORKSHOP 2: 3 CONCEPTS PER SITE
September 24, 2019
CITY COUNCIL REVIEW: 3 CONCEPTS
November 20, 2019
CITY COUNCIL WORKSHOP: CONCEPT REFINEMENT
February 26, 2020
PROJECT STATUS MEETING
COMMUNITYENGAGEMENTSUMMARY
PARK COMPONENTS
City of CamarilloDepartment of Public Works
Entry Plaza / Signage Ventura Boulevard Frontage Trellis Design Sitting Garden / Signage Tot Lot Parking Band shell Restroom
LANDSCAPE DESIGN INTENT
Dizdar Park�s landscape design will complement new park features and activities. The design will respect its history while introducing a refreshing range of land-scape experiences celebrating the idea that everything old will be new again.
Planting DesignPlant selections feature drought tolerant natives, succu-lents and grasses arranged In natural grouping along with textures and colors requiring minimal maintenance.
Irrigation SystemsThe new park will include fully automatic irrigation systems supporting healthful plant growth and current water conserving consumption guidelines.
1
2
34
56
7
8
9
10
11
12
26
14
1516
17
18
19
20
21
23
24
10 11
24
23
25
13
13
13
KEYNOTE LEGEND
1 Plaza Shade Trees
New Central Plaza Feature Planters
Native Under-story Edge Definition
Plaza Entry Brick Paving Mat w/ Trellis Framing Centerpiece Planters
Meandering Walkway (Natural Gray P.I.P Concrete with Topcast Finish)
Multiple Seating & Viewing Options
Thematic Fire Truck Playground Structures
D.G Paving with Benches or Sculptural Seating Pods
Bio-swale Feature with Mix Juncus and Carex Evergreen Grasses
Central Trellis Feature w/ Benches
Shaded BBQ Pods with Table/Bench Seating
Holiday Celebration Tree
Bike Racks
Restrooms
2
3
4
5
6
7
8
9
10
11
12
13
14
15 Garden Entry Gateway with Brick Paving
City Sign Location
Band Shell
Flexible Sitting Garden w/ Public Art Display Plaques
Additional Parking Area with Shade Trees and Buffer Shrubs
Flowering Accent Tree w/ Landscape Berm
Dense Background Tree Bosque
Trash Enclosure
16
17
18
19
20
21
22
Enhanced Concrete Paving (Integral Color P.I.P Concrete with Topcast Finish)
Accent Banding (Integral Color P.I.P Concrete with Topcast Finish)
23
24
Relocated Statue25
Niche Seating under Mature Frontage Shade Trees26
Parking Lot Planter Islands27
Flowering Vine Fence Screen28
5
20
28
27
22
Plan
VENTURA BOULEVARD
KEYMAP (N.T.S)
Gateway Trellis to Sitting Garden
Ventura Blvd. Sidewalk
Public Right-Of-Way
Art Display Walls
Hedge to Screen Ex. Fence Beyond
Bio-swale Feature w/ Informal Sycamore Grouping
Gateway Trellis to Sitting Garden
Evergreen Trees Framing Sitting Garden Edge
Accent Flowering Tree Framing Gateway Feature
Flowering Accent Tree (Crape Myrtle) Shade Tree (Sycamore) Upright Screening Trees (Brisbane Box)
KEYMAP
Vine Planting to Screen Existing FenceExisting Tree
Ornamental Grass Mix Foreground Planting
Hedge Planting to Screen Existing Fence Evergreen Upright TreesExisting TreeParking Lot Shade Trees
Accent Tree Framing Entry Driveway to South Parking Lot
Existing Sidewalk along Glenn Drive
Public Right-Of-WayParking Lot Shade Trees
Upright Screening Trees(Brisbane Box)
Shade Trees(London Plane Tree)
Evergreen Canopy Trees(Southern Live Oak)
Evergreen Canopy Trees (Australian Willow)
Gateway Trellis to Sitting Garden
Ventura Blvd.
Accent Shrub Planting
Grass Planting Access to the Park
Circular Bench on D.G Paving
Existing Jacaranda TreesExisting Ficus Trees
Art Display Plaques
City Sign Wall
KEYMAP (N.T.S)
Bollard Lights
Existing Ventura Blvd Pole Lt. & Bollards
Accent Canopy & Tree Uplights
Pedestrian Pole Lights
10x10 Tent - Typ.Total (20) Shown
VENTURA BOULEVARD
G O O D A L EARCHITECTURE
PLANNING
DIZDAR PARK
Elevation View of Sitting Garden from Ventura Boulevard
CEQA PROCESSThe EIR Process
(45 days)
City of CamarilloDepartment of Public Works
Design Status Meeting for the Dizdar Park Renovation and Expansion Project | March 22, 2022
Lead Agency = City of Camarillo
Opportunities for Public Input =
Current Status =
Lead agency
considers certification of Final EIR and makes decision on the project
Lead agency gives public
Notice of Availability of Draft EIR
Public review period
(45 days)
Lead agency
prepares Final EIR, including responses
to comments
on Draft EIR
NEXT STEPSTask Approximate Timing
Public Design Workshop Early 2022
Design Review to City Council Summer 2022
Draft EIR circulated for public review and comment (for 45 calendar days)
Summer 2022
Complete Final EIR, including responses to public comments Fall 2022
City Council Meeting to consider certification of Final EIR and approval of project
Winter 2022
Finalize construction plans and documents Summer 2023
Construct project Fall 2023
City of CamarilloDepartment of Public Works
G O O D A L EARCHITECTURE
PLANNING
Public Restroom Options
Option B Option C
Option A
DIZDAR PARK RESTROOMS
G O O D A L EARCHITECTURE
PLANNING
Band Shell Options
Option B Option C
Option A
DIZDAR PARK BANDSHELL