Top Banner

of 116

Dissertation Kwaichunghousing[1]

Feb 04, 2018

Download

Documents

Gary Lo
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/21/2019 Dissertation Kwaichunghousing[1]

    1/116

    A Study of Virtual Prototyping in Construction

    Industry : A case study of Kwan Chung Public

    Housing Estate Project

    By

    Li Ka Ming

    DISSERTATION

    SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS

    FOR

    THE DEGREE OF BSC (HONS) IN BUILDING SURVEYING

    THE HONG KONG POLYTECHNIC UNIVERSITY

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    2/116

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    3/116

    Table of Contents

    Declaration i

    Table of Contents ii

    List of Tables vi

    List of Figures vii

    Acknowledgements x

    Abstract xi

    CHAPTER I: INTRODUCTION P.1

    1.1 Problem Statement P.2

    1.2 Purpose of Research P.4

    1.3 Research Objectives P.5

    1.4 Structure of the Dissertation P.5

    CHAPTER II: LITERATIVE REVIEW P.7

    2.1 Traditional Techniques for Construction Project Planning P.8

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    4/116

    2.2.1 3D P.13

    2.2.2 4D P.13

    2.2.3 Virtual Prototyping (VP) P.14

    2.2.4 CATIA P.15

    2.2.5 DELMIA P.16

    2.2.6 Advantage of Simulation P.17

    CHAPTER III: RESEARCH METHODOLOGY P.19

    3.1 Literature Search P.20

    3.2 Reasons for using Case Study and Interviews P.20

    3.3 Case Study P.21

    3.4 Interview P.22

    CHAPTER IV: VIRTUAL PROTOTYPING IN BUILDINGS P.23

    4.1 Design P.25

    4.2 Manufacture and Assembly P.26

    4.3 Sale & Promotion P.30

    4.4 Facilities Management P.32

    4.5 Demolition P.32

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    5/116

    5.6 Part Design and Modeling P.42

    5.7 Assembly Tools P.44

    5.8 Surfacing P.46

    5.9 Knowledge Ware P.47

    5.10 Simulation Process P.49

    CHAPTER VI: CASE STDUY AND ANALYSIS P.53

    6.1 Background Information P.53

    6.2 Project Features P.56

    6.3 Simulation Process P.56

    6.3.1 3D Model Construction P.56

    6.3.2 Construction Process Simulation P.61

    6.3.3 Day 1 P.64

    6.3.4 Day 2 P.67

    6.3.5 Day 3 P.70

    6.3.6 Day 4 P.73

    6.3.7 Day 5 P.75

    6.3.8 Day 6 P.77

    6.4 Summary of the Project P.79

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    6/116

    6.5.1.5 Information Management P.83

    6.5.1.6 Safety P.83

    6.5.2 Limitations P.84

    6.5.2.1 Design for Manufacture P.84

    6.5.2.2 License Fee P.84

    6.5.2.3 Lacking in Skilful Labour P.86

    6.5.2.4 Hardware Requirement P.86

    6.5.2.5 Human-Initiated Characteristic P.87

    CHAPTER VII: CONCLUSIONS AND RECOMMENDATIONS P.88

    7.1 Conclusions P.89

    7.2 Recommendations P.90

    REFERENCES AND BIBLIOGRAPHIES P.91

    LIST OF APPENDIX P.98

    APPENDIX I: Sample of Accompanying Letter P.99

    APPENDIX II: Sample of Questionnaire P.100

    APPENDIX III Method & Sequence of Construction P.101

    APPENDIX IV 6-day Cycle Programme for Typical Floors P.102

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    7/116

    List of Tables

    Table 4.1 Virtual Prototype Concept P.24

    Table 6.1 Project Particulars P.55

    Table 6.2 Cost Comparison of CATIA V5 & DELMIA and AutoCad

    2006

    P.85

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    8/116

    List of Figures

    Figure 4.1 Example of lighting analysis P.26

    Figure 4.2 Example of CFD Source P.26

    Figure 4.3 2/F B5 Column of HKCC P.28

    Figure 4.4 Clash of Reinforcement Bar P.28

    Figure 4.5 Five tower cranes operates simultaneously in Venetian

    Macau Hotel

    P.29

    Figure 4.6 Construction Method of Westland Road Office Project P.30

    Figure 4.7 Construction Process of Westland Road Office Project P.31

    Figure 5.1 CATIA V5 & DELMIA P2 Platform P.35

    Figure 5.2 Traditional Tool Bars, Keyboard Shortcuts & Drop Down

    Menu

    P.36

    Figure 5.3 CATIA V5 and DELMIA document types P.36

    Figure 5.4 CATIA V5 GUI P.38

    Figure 5.5 Rotation P.39

    Figure 5.6 Sketcher environment P.40

    Figure 5.7 Constraint Examples P.41

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    9/116

    Figure 5.14 A tangent cover P.46

    Figure 5.15 Simulation Process Work Bench P.50

    Figure 5.16 Insert Activity P.50

    Figure 5.17 Grab Activity P.51

    Figure 5.18 PERT Chart P.51

    Figure 5.19 Gantt Chart P.52

    Figure 6.1 Proposed Kwai Chung Public Housing Estate P.54

    Figure 6.2 Kwai Chung Public Housing Estate P.54

    Figure 6.3 Location of the Site P.55

    Figure 6.4 Concrete Slab P.57

    Figure 6.5 Wall Reinforcement P.58

    Figure 6.6 Fascade P.58

    Figure 6.7 Toilet P.59

    Figure 6.8 Temporary Wallform P.59

    Figure 6.9 Working Platform P.60

    Figure 6.10 Strut P.60

    Figure 6.11 Tower Crane P.61

    Figure 6.12 PERT CHART P.61

    Figure 6.13 PERT CHART P.62

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    10/116

    Figure 6.20 Movement of Wall Form P.67

    Figure 6.21 Day 2 a.m. P.68

    Figure 6.22 Day 2 noon P.68

    Figure 6.23 Day 2 p.m. P.69

    Figure 6.24 Construction Process P.69

    Figure 6.25 Day 3 a.m. P.70

    Figure 6.26 Day 3 noon P.71

    Figure 6.27 Day 3 p.m. P.71

    Figure 6.28 Movement of Concrete Boom P.72

    Figure 6.29 Concreting by Boom P.72

    Figure 6.30 Day 4 a.m. P.73

    Figure 6.31 Day 4 noon. P.74

    Figure 6.32 Day4 p.m. P.74

    Figure 6.33 Day 5 a.m. P.75

    Figure 6.34 Day 5 noon P.76

    Figure 6.35 Day 5 p.m P.76

    Figure 6.36 Fix Conduit & Reinforcement P.77

    Figure 6.37 Day 6 a.m P.78

    Figure 6.38 Day 6 noon P.78

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    11/116

    Acknowledgements

    I would like to express my respect, gratitude and foremost to my supervisor,

    Dr. Heng Li, Professor of Department of Building and Real Estate at the Hong

    Kong Polytechnic University, for his kindly patience and advice on my

    dissertation. He always makes me in critically thinking and lets me recognize

    the enjoyment and happiness of undergoing a dissertation.

    I would like to express my appreciation to Mr. Stephen C. W. Kong, Mr. Yuk

    Huen Chan and Mr. Ting Huang, the Project Associate, the Research

    Assistant and Ph. D. Candidate respectively of the Construction Virtual

    Prototyping Laboratory, in the Department of Building and Real Estate of the

    Hong Kong Polytechnic University, who shared their valuable time to give me

    suggestions and provide me with useful data which strengthened the content

    of this dissertation.

    Besides, i would like to thank Ms. Louie Law for spending her invaluable time

    to proof-read my dissertation and giving me useful advice on the use of

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    12/116

    Abstract

    This research presents an alternative tool, i.e. CATIA and DELMIA, for

    construction programme planning apart from traditional tools, e.g. AutoCAD,

    MicrosoftProject. Regarding the problems of traditional tools in terms of space

    and facilities management, scheduling and communication, the concept of

    Virtual Prototyping (VP) and functions of CATIA and DELMIA are introduced.

    An analysis concerning strengths and limitations of the new tool accompanied

    by an in-depth case study of Kwan Chung Public Housing Estate Project is

    administered. After investigation, it is found that CATIA and DELMIA can

    improve the planning process; however, they have not been extensively

    adopted in construction industry in Hong Kong because of its design purpose,

    license fee, requirement on hardware, also a lack of man power who

    familiarize with the software and its human-initiated characteristic.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    13/116

    CHAPTER I

    Introduction

    1.1 Problem Statement

    1.2 Purpose of Research

    1.3 Research Objective

    1.4 Research Structure

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    14/116

    Chapter 1 Introduction

    Chapter 1 INTRODUCTION

    1.1 Problem Statement

    In construction project management, planning process is critical to the

    successful development and execution of a construction project (Waly and

    Thabet 2003). However, the planners rely on their experience and intuition,

    imagination and judgment to extract data from paper-based design documents

    and to decide the appropriate method of construction, its timing and site usage

    layout (Zhang, 2004). This drives faults or inefficiency in site space and

    facilities management, communication and information storage and

    scheduling.

    Site space and facili ties management

    Present planning method has weakness in managing site space and facilities

    which is critical in a construction project as a result of the resources-driven

    nature of construction management a construction manager must develop a

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    15/116

    Chapter 1 Introduction

    of site space and facilities (Ma, Shen & Zhang, 2004).

    Communication

    2D drawings are not able to visualize the end product to the parties involved in

    a construction project, e.g. the clients, the contractors, etc. The increasing

    complexity of construction projects multiplies difficulties of handling huge

    amount of information. Much project information stored on paper as drawings

    and written documents is frequently unstructured and thus hinders its usage,

    also, it is very easy to lose or damage (Construct IT, 2000). This causes poor

    information transfer and communication among parties.

    Scheduling

    Critical Path Method (CPM) fails to seamlessly synchronize activity planning

    and resource planning, the two integral functions in project planning (Waugh

    and Froese 1990) Although it is used in time control and scheduling it is

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    16/116

    Chapter 1 Introduction

    Innovative Technology

    As a result, researches start investigating information technology to solve the

    above problems of paper-based documents, site space and facilities

    management and communication. Virtual Prototyping (VP) is one of the latest

    innovative technologies which integrates planning, visualization and simulation

    in construction programme, thus improves the efficiency of construction

    projects in planning stage.

    1.2 Purpose of Research

    The purpose of this research is to provide an alternative choice for

    construction project planning by studying the concept of VP and the application

    of the software of CATIA and DELMIA in construction industry in Hong Kong.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    17/116

    Chapter 1 Introduction

    1.3 Research Object ives

    The following objectives are examined in this study:

    1. To outline the general problems arisen from traditional construction project

    planning in Hong Kong

    2. To discuss the utilization of VP in construction industry

    3. To introduce the functions of CATIA and DELMIA

    4. To describe the construction simulation process of 6-day Cycle of Kwan

    Chung Public Housing Estate Project by CATIA and DELMIA (Case Study)

    5. To analyse the strengths and limitations of CATIA and DELMIA

    1.4 Structure of the Dissertation

    This dissertation is mainly divided into 7 parts.

    Part I Introduction

    This part states clearly problem statements purposes of research

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    18/116

    Chapter 1 Introduction

    problems, basic principles of VP and introduction to CATIA and

    DELMIA.

    Part III Research Methodology

    The research methods employed in this research are presented in

    this part.

    Part IV Funct ions of CATIA and DELMIA

    This part presents the main functions of CATIA and DELMIA.

    Part V Virtual Prototyping in Buildings

    This part presents the utilization of VP in areas relevant to buildings

    Part VI Case Study and Analysis

    This part describes the case of Kwan Chung Public Housing Estate

    Project and gives analysis from the case and interviews.

    Part VII Conclusions and Recommendations

    This part summarizes findings in this research, and makes a final

    conclusion

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    19/116

    CHAPTER II

    Literature Review

    2.1 Traditional Techniques for

    Construction Project

    Planning

    2.2 Latest Techniques for

    Construction Project

    Planning

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    20/116

    Chapter 2 Literature Review

    Chapter 2 LITERATUREREVIEW

    Planning is crucially important in construction projects. The planning of

    construction operations is a complicated activity involving abstraction of

    constriction activities from the drawings, choosing on suitable plans and

    falsework, allocation of construction schedule and site space management are

    essential to project management, as they directly influence security, machine

    running, material deployment, power distribution as well as construction

    progress and cost (Ma, Shen and Zhang, 2004), so planners use different tools

    to develop the programme. In this chapter, firstly, some drawing and

    scheduling tools will be discussed and secondly, VP, CATIA and DELMIA will

    be introduced.

    2.1 The Traditional Techniques for Construct ion Project Planning

    2 1 1 Drawing Tools: 2D Computer Aid Design (CAD)

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    21/116

    Chapter 2 Literature Review

    of the most commonly used software and largest share of the CAD market

    (Howard 1998).

    2.1.1.1 Strengths

    1. As Sun & Howard (2004) points out, 2D CAD tools increase productivity,

    especially at the information production stage. This benefit is more evident

    when design changes. Instead of reproducing all the drawings, CAD allows

    designers to make changes to the existing ones.

    2. Sun & Howard (2004) believes that 2D CAD tools help to improve the

    quality of design information. Using traditional paper drawings, keeping data

    accurate and consistent is a big challenge. In CAD drawings, all

    measurements are precise.

    3 2D CAD tools help to increase the speed of information exchange between

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    22/116

    Chapter 2 Literature Review

    4. 2D CAD tools allow designers to reuse previous drawings or part of the

    drawings (Sun & Howard 2004).

    5. 2D CAD tools make the drawing storage and archive task a lot easier. Paper

    drawings present storage problems as they deteriorate, are usually very large

    and cause documentation problems. A CAD file stored in a structured directory

    on a PC prevents these problems from occurring, which will also ease quality

    assurance issues (Sun & Howard 2004).

    2.1.1.2 Limitations

    1. In 2D CAD drawings, a building is represented by points, lines and surfaces,

    not by walls, windows and rooms. It cannot visualize the three-dimensional

    end product.

    2 2D CAD system cannot present the process of construction and thus is not

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    23/116

    Chapter 2 Literature Review

    software packages (Sun & Howard 2004).

    4. Most CAD packages are only suitable for drawing at the information

    production stage when all major design decisions have been made, not during

    the early design stages (Sun & Howard 2004).

    5. The user interface of many CAD programmes is complex. Designers often

    find it difficult to operate it effectively. As a result, they can sometimes be

    distracted form the design task that they should really be concentrating on.

    While not undervaluing the benefits of computer aided drafting systems

    especially for information production purposes, their weakness are also

    apparent (Sun & Howard 2004).

    2.1.2 Schedul ing Tools: Bar (Gantt ) Chart

    A bar chart is a graphic representation of project activities shown in a

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    24/116

    Chapter 2 Literature Review

    as a calendar which shows the timescale horizontally and flow of activities

    vertically. The vertical column also shows the timescale, duration and

    sequence of activity. It is commonly used in construction industry due to

    simplicity and ease of preparation and understanding. However, it lacks logical

    representation (relationships), too simple and insufficient to show the details of

    multitude of inter-related activities. It commonly used in small-sized project.

    2.1.3 Scheduling Tools : Crit ical Path Method (CPM)

    A critical path method (CPM) is a scheduling technique using networks for

    graphic display of the work plan (Mubarak S. A. 2005). The method is used to

    determine the length of a project and to identify the activities critical to project

    completion. It was developed during the 1950s by DuPont and US Navy. It is

    one of the common techniques used in practice for construction planning and

    scheduling. Microsoft Project (2003) is one of the common software product

    used for project scheduling The typical CPM is used to provide an overall view

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    25/116

    Chapter 2 Literature Review

    2.2 The Innovative Technique of Construction Planning

    The traditional construction planning tools restricted by their limitations are

    insufficient to meet with the planners requirements nowadays. The

    construction projects are currently becoming more and more complicated and

    the traditional tools are insufficient to manage the information in these projects,

    so a new planning concept, VP, has came to the industry. The concept of VP

    will be introduced gradually.

    2.2.1 3D

    3D modeling is the basic components for producing virtual environment. The

    planners, engineers can view the realistic images of construction projects in a

    3D environment. However, 3D models can only provide static images and

    cannot display the exact status of a project at a specific moment, which means,

    no integration and interaction between models and time presents.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    26/116

    Chapter 2 Literature Review

    and finish of activities in different colour. It provides the project participants with

    a better communication in utilizing the space.

    2.2.3 Virtual Prototyping (VP)

    VP provides a capacity to construct in the computer. It provides a modeling

    and simulation environment so powerful that the production, fabrication and

    assembly of construction components, including the associated operational

    processes, can be simulated in the computer (Karam 2004). VP takes into

    account all of variables in the project procurement process from feasibility

    analysis to maintenance management (Karam 2004). The primary objective is

    to evaluate the feasibility of construction processes with a view to minimize the

    time and resource use. VP can be described as simulation of construction

    activities in 3D Environment. All the construction activities are represented by

    dynamic behaviours of 3D CAD models and are linked by a simulation engine.

    The 3D CAD models resources information and construction schedule are

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    27/116

    Chapter 2 Literature Review

    2.2.4 Computer-aided Three-dimensional Interactive Appl ication

    (CATIA)

    Computer-aided Three-dimensional Interactive Application (CATIA) was first

    developed by Dassault System in the early 1980s for the aerospace industry.

    CATIA is one kind of VP software developed by IBM. It integrates a suite of

    collaborative product design software applications covering Computer Aided

    Design (CAD), Computer Aided Engineering (CAE) and Computer Aided

    Manufacturing (CAM).The latest vision is now CATIA V5. It allows users to

    design the products by 2D layouts as well as 3D models concurrently. The

    software has being applied by many manufacturing industries, e.g. aerospace,

    automotive, industrial machinery, electrical, electronics, shipbuilding, plant

    design, and consumer goods, including design for such diverse products as

    jewelry and clothing. It is now bringing into construction industry.

    According to Karam (2004) CATIA is the leading product development solution

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    28/116

    Chapter 2 Literature Review

    consumer goods, including design for such diverse products as jewelry and

    clothing.

    CATIA is the only solution capable of addressing the complete product

    development process, from product concept specifications through

    product-in-service, in a fully integrated and associative manner (Karam 2004).

    It facilitates true collaborative engineering across the multi-disciplinary

    extended enterprise, including style and form design, mechanical design and

    equipment and systems engineering, managing digital mock-up, machining,

    analysis, and simulation (Karam 2004).

    By enabling enterprises to reuse product design knowledge and accelerate

    development cycles, CATIA helps companies speed their responses to market

    needs and helps free users to focus on creativity and innovation (Kleismit

    2004)

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    29/116

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    30/116

    Chapter 2 Literature Review

    adopted as an effective presentation tools for various types of usage, eg.

    teaching. This is particularly true of simulation that make intelligent use of

    computer graphics and animation. Such simulators dynamically show the

    behaviour and relationship of all the simulated system's components, thereby

    providing the user with a meaningful understanding of the system's nature.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    31/116

    CHAPTER III

    Research Methodology

    3.1 Literature Search

    3.2 Reason for using Case Study

    & Interviews

    3.3 Case Study

    3.4 Interviews

    Ch t 3 R h M th d l

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    32/116

    Chapter 3 Research Methodology

    Chapter 3 RESEARCH METHODOLOGY

    This section describes the methodology used in achieving the research

    objectives. The dissertation is based on data collected from three main

    sources, namely literature, interview and case study.

    3.1 L iterature Search

    The data collection stage would rely on the reference books, journals, reports

    and websites which were mainly collected and obtained from the library and

    on-line electronic database systems, such as Sciencedirect and ProQuest.

    3.2 Reasons for using Case Study and Interviews

    After investigation, there are few projects which have used CATIA & DELMIA

    as a planning tool. People who familiarize with the application of CATIA &

    DELMIA in construction industry are also limited

    Chapter 3 Research Methodology

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    33/116

    Chapter 3 Research Methodology

    the utilization of CATIA & DELMIA in Hong Kong Construction Industry.

    3.3 Case Study

    The case of Kwan Chung Public Housing Estate Project (KC Project) was

    brought into analysis. In case study, the VP software CATIA and DELMIA was

    used to simulate the 6-day construction cycle in New Harmony Block (Option 2)

    in Kwan Chung. I have participated in the Project on development of 3D

    models and simulation on the Construction Virtual Prototyping Laboratory, the

    Department of Building and Real Estate of the Hong Kong Polytechnic

    University. The drawings, schedules and other relevant information of the

    cases are provided by Yau Lee Construction Co., Limited.

    Chapter 3 Research Methodology

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    34/116

    Chapter 3 Research Methodology

    3.4 Interviews

    Interviews with construction professionals were carried out to have a further

    understanding on the practice of VP in KC Project.

    In this research, three professionals involved in from the project were

    interviewed.

    They are:

    1. Mr. Richard Lee, a Design Manager of the KC Project from Yau Lee

    Construction Co-operation Limited on 25 February 2006.

    2. Mr. Patrick Ho, Site Agent of the KC Project from Yau Lee Construction

    Co-opertaion Limited on 4 March 2006.

    3. Mr Zeon Yu, Project Manage of the KC Project from Yau Lee Construction

    Co-opertaion Limited on 11 March 2006.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    35/116

    CHAPTER IV

    VIRTUARL

    PROTOTYPING IN

    BUILDINGS

    4.1 Design

    4.2 Manufacture & Assembly

    4.3 Sale & Promotion

    4.4 Facilities Management

    4.5 Demolition

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    36/116

    Chapter 4 Virtual Prototyping in Buildings

    Chapter 4 VIRTUAL PROTOTYPING IN BUILDINGS

    Virtual Prototyping involves in different stages of a building life cycle, including

    design, manufacture, assembly, sales/promotion, facility management and

    even demolition. Extent utilization of Virtual Prototyping in construction

    industry is subject to the practicability of legacy, procurement and training

    (Brandon, 2003). The application of VP is discussed in the following sections.

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    37/116

    p yp g g

    4.1 Design

    In design inception stage, architects/engineers usually make scale models to

    illustrate their design concept with clients in order to make discussions and

    compromises. While alteration of design often happens, amending scale

    models frequently may be a problem. VP provides an easy changing visual

    model to designers.

    Secondly, a scale model is difficult to involve building services design. Steady

    state heat loss and heat gain calculation is utilizated currently, some factors,

    e.g. thermal mass, are neglected in building services design. VP allows the

    negligence to be involved and visualized, dynamic thermal modeling can be

    workable. (Stribling, 2003)

    Thirdly, integration of various kinds of design, e.g. building aesthetics, building

    services is feasible through the technology of VP which can include different

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    38/116

    Mechanics (CFD) (Figure 4.2). CFD can predict the internal climate which is

    widely used on assessment of HVAC system and ventilation strategies. These

    technologies can identify energy saving opportunities and thus reduces

    expenditure on energy.

    Fig 4.1 Example of lighting analysis Source:http://homepage.ntlworld.com

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    39/116

    4.2 Manufacture and Assembly

    Manufacture and assembly stages are merged together in construction. The

    successful of these stages depend on planning before works. Frequent faulty

    of sequences and crash of activities can seriously affect the construction

    progress causing uneconomical. VP gives various means to overcome these

    problems.

    Firstly, try before you use (Li, 2005) is a slogan of promoting the idea of VP in

    construction industry. That means project planner can preview the processes

    of the project visually in advance and test alternative courses of action. By

    preview, identification of idle time and resources, and rapidly experiment new

    alternatives to achieve optimization can be achieved. In the case of Ho Tung

    Lau Railway Extension Project, three alternative construction methods,

    including gantry, mobile crane and rolling trolley were tested.

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    40/116

    especially on suspended ceiling and raised floor. The function of identifying

    clash can detect whether there is any clashes of building services elements

    including air duct, fire sprinkler pipe, pipe, electricity trucking etc. To illustrate,

    in the project of Hong Kong Community College, the clashes of reinforcement

    bars between the precast elements was sorted out to shorten the construction

    period (Fig 4.3&4.4). In the project of Venetian Macau Hotel, VP can eliminate

    hurtles of five towel cranes which operate simultaneously (Fig 4.5).

    Fig. 4.3 2/F

    B5 Column of

    HKCC

    Fig.4.4 Clash of

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    41/116

    Fig.4.5 Five tower cranes operates simultaneously in Venetian Macau Hotel

    Thirdly, VP acts as a presentation tool to disseminate the complicated

    construction processes to project staff from top management to worker level,

    so they can understand planning information easily (Kong, 2006). In Westlands

    Road Office Building Project, contractors utilized the technology of VP to

    introduce the construction method(Figure 4.6) and the construction process to

    developers.

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    42/116

    Fig. 4.6 Construction Method of Westland Road Office Project

    4.3 Sales/Promotion

    In Property Sales, firstly, buyers may expect to preview the product before they

    buy. Sellers/developers in Hong Kong usually build show-room to fulfill buyers

    expectation Show-rooms can also be a promotion tool to attract potential

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    43/116

    Chapter 4 Virtual Prototyping in Buildings

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    44/116

    4.4 Facili ty Management

    According to Sarshar (2004), people responsible for collecting and archiving

    project data may not always understand the specific needs of those who will

    utilize it, such as those involved in building maintenance. VP has a function of

    storing information. The storage and transfer of construction information

    thoroughly by VP can contribute to a better management of facilities in future,

    e.g. providing a detail plan of building services to help the facility manager to

    sort out the problems.

    4.5 Demolition

    VP allows demolition professional to identify building technologies, process

    and methods, eg. Post-tension members, so the professionals can choose the

    most appropriate demolishing method for particular building. Time & Cost of

    investigating the buildings may be reduced.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    45/116

    CHAPTER V

    FUNCTONS OF

    CATIA V5 AND

    DELMIA

    5.1 Introduction

    5.2 Document Types

    5.3 CATIA V5 GUI

    5.4 View & Manipulating Object

    5.5 Sketching

    5.6 Part Design and Modeling

    5.7 Assembly Tools

    5.8 Surfacing

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    46/116

    Chapter 5 FUNCTIONS OF CATIA V5 AND DELMIA

    This chapter describes the main functions of CATIA and DELMIA. The

    software screen captures are used to illustrate how the functions work.

    5.1 Introduct ion

    CATIA is designed for collaborative product development. It is mostly used in

    virtual product design. DELMIA is designed for digital development of factory

    and production processes. It is mainly used in manufacturing process planning,

    detailing and simulation.

    CATIA V5 provides various configurations including Platform configuration,

    Application portfolios and Workbenches. The P2 Platform (Figure 5.1) is

    commonly used and provides the extended design tools and additional

    process oriented tools. The process tools are fully interchangeable and

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    47/116

    Part Design to Sheet Metal to Surfacing by CATIA, DPM Assembly Process

    Simulation by DELMIA.

    Fig.5.1 CATIA V5 & DELMIA P2 Platform

    CATIA V5 and DELMIA interface is more like a typical Windows-type

    environment It provides Window-like features (Figure 5 2) including object

    Workbench

    CATIA V5 Platform P2

    Application portfolios

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    48/116

    The change of object-orientated tools on the right side relies on which module

    is currently adopted. The first icon (Figure 5.2) shows which module (e.g. Part

    Design) is used. A set of selection tool is always available on the screen no

    matter which module is adopted.

    Fig. 5.2 Traditional Tool Bars, Keyboard Shortcuts & Drop Down Menu

    5.2 Document Types

    There are three types of document in CATIA V5 including Part Product and

    Dro Down Menu

    Traditional Tool Bars

    First Icon

    E . Part Desi n

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    49/116

    5.3 CATIA V5 GUI

    Generally, CATIA V5 and DELMIA share the same GUI. This helps users to

    famaliarise with the operation of both of them.

    5.3.1 Configuration Tree

    Configuration tree (Figure 5.4) is fundamental tool for manipulating, controlling,

    and organizing model elements and features. The branches along the tree

    comprise the history and processes used to create parts. For example, in

    Figure 5.4, when the Chamber icon is currently selected, the corresponding

    identification in the tree turns orange.

    5.3.2 Compass Tool

    Compass tool (Figure 5.4) is used to modify the location or orientation of part

    correspondent to the X-Y-Z co-ordinate system.

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    50/116

    Fig. 5.4 CATIA V5 GUI

    5.4 Viewing and Manipulating Objects

    CATIA allow objects viewed and manipulated easily. There are various

    functions including pan, rotation and zoom for object viewing and manipulating.

    Configuration Tree

    Compass Tool

    Chamber Element

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    51/116

    Rotation: To hold down the roll of mouse and either button of mouse and then

    move the mouse simultaneously to rotate (Fig. 5.5).

    Fig. 5.5 Rotation

    5.5 Sketching

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    52/116

    Figure 3.5 Rotation

    Fig.5.6 Sketcher environment

    The function of Constraints is commonly used in Sketcher Workbenches.

    Supplementary geometrical or dimensional constraints are added when

    creating or adjusting 2D elements. For example, the dimension of rectangle is

    easily edited by dimensional constraint and properties of line are edited by

    Position Display

    Sketcher Grid

    Sketcher Geometry

    Operation Toolbar

    X-Y Plane

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    53/116

    Fig. 5.7 Constraint Examples

    Constraint Toolbar

    Element Colour Description

    Under Constrained White

    Over Constrained Violet

    Inconsistent Red

    Selected Orange

    Constraint Defined

    in Dialog Box

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    54/116

    5.6 Part Design and Modeling

    A set of modeling tools (Figure 5.9) can be used after a 2D sketch is finished.

    The sketch-based toolbar (Figure 5.9) helps users to handle the functions of

    filleting, chamfering, shelling, hole creation etc. e.g. as shown in Figure 5.9, a

    2D element is constructed to 3D object by Pad and the dimensions of 3D

    object can be adjusted by dimensional constraint.

    Sketch-Based Toolbar

    2D Sketch

    Dimension Constraint

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    55/116

    number of formulas (Figure 5.10) can be established to modify the elements or

    objects from the original part file to a newly formed part file, so elements or

    objects in the original part files can be used in other projects in the future.

    In addition, as shown in Figure 5.10, there are different types of parameter in

    the design table. Options in the design table are entered, CATIA V5 can then

    automatically select the most appropriate option to be used in the elements or

    objects. If there is a change in parameters, it will also have an effect on

    construction cost and schedule generated by CATIA V5 and DELMIA.

    Formula

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    56/116

    The Compass tool located in the upper right corner makes the movement and

    rotation of 3D objects easier. The Compass tool can also be attached to an

    object for the purpose of moving and rotating it (Figure 3.10).

    Fig. 5.11 Compass Tool to move and rotate the element

    Compass Tool

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    57/116

    should be created before any changes of an object.

    Fig 5.12 CATProduct Sample

    CATParts

    Constraints

    ApplicationProduct Structure

    Toolbar

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    58/116

    5.8 Surfacing

    CATIA V5 provides basic surfacing tools including extrude, sweep, revolve and

    loft 2D profiles. The tools can also help to join, extend, split and trim surfaces

    and extract surfaces from a solid. There is also a healing tool and a Fill

    command which can be used to create a tangent cover for the shape shown in

    Figures 5.13 and 5.14. It solves most CAD programs problems.

    Fig. 5.13 Sample Creating top surface Fig. 5.14 A tangent cover

    (Source: http://www.3ds.com/products-solutions/plm-solutions/image-gallery/?no_cache=1)

    CATIA Generative Shape Design (GSD), a basic tool for constructing surfaces,

    Functions of CATIA V5 and DELMIA

    9 K l d W

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    59/116

    5.9 Knowledge Ware

    According to Beckert (2000), Dassault offers three KnowledgeWare products

    on CATIA V5 targeted at users performing advanced design and engineering.

    CATIA Knowledge Expert helps designers establish rule bases that capture

    and automate knowledge process such as best practices, profession

    processes, or design validation and corrections. CATIA Knowledge Advisor

    ensures design compliance with corporate standards early in the design

    cycle. CATIA Generative Knowledge, based on a scripting language, lets

    users declare and reuse specification in a script format to automatically

    generate intelligent designs. Those designs have to respect the softwares

    programmed constraints. For example, titanium cladding torques at this

    thickness but not at that or glass windows reflecting light at that angle will

    create heat traps. Therefore, the software allows for considerable freedom of

    design choices yet ensures that design decisions conform to corporate rules

    during the design process (Schrage 2000)

    Functions of CATIA V5 and DELMIA

    biliti A i th t dd it k h b d fi i l

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    60/116

    capabilities. A company using the system adds its know-how by defining rules

    in the knowledge base. These rules are then invoked by various means when

    the system is being used to support a specific process or scenario. For

    example, a company may determine that the treatment or material for screws,

    which are the basic connections between the framing members of building

    facades, will have a particular specification for a corrosive commodity. On

    placing the screws, the system can check the suitability against the rules and

    automatically assign the appropriate attribute.

    5.10 Simulation Process

    When the workbench changes to Assembly Simulation Process (Figure 5.15),

    it provides different sets of icon to carry out a simulation process by DELMIA. A

    clear overview of the sequences and links among processes, timing, cost, and

    resources shows in this workbench. All the components involved in the

    simulation process can be inserted in the lists which include Process Product

    Functions of CATIA V5 and DELMIA

    to operate a simulation process by means of simulation creation tool and the

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    61/116

    to operate a simulation process by means of simulation creation tool and the

    data can be adjusted if required. These data can be adjusted through Microsoft

    Excel.

    The sequence of activities can be adjusted by PERT Chart (Figure 5.18). Each

    activities and links are represented by pictures and symbols which are easily

    understood and modified if necessary. The function of Gantt Chart (Figure 5.19)

    is similar to Microsoft Project which shows the duration, start and end time of

    an activity and resource used in each activity (Figure 5.19). The changes in

    Gantt Chart or PERT Chart can directly reflect in the simulation process.

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    62/116

    Fig. 5.15 Simulation Process Work Bench

    Simulation Tools

    Simulation Creation Tools

    P.P.R List

    PERT Chart /Gantt Chart

    Movement Set up

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    63/116

    Fig. 5.17 Grab Activity

    Set Activities Icon

    Sequence of Activities

    Motion Set up

    Functions of CATIA V5 and DELMIA

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    64/116

    Fig. 5.19 Gantt Chart

    Duration of Activities

    CHAPTER VI

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    65/116

    CHAPTER VI

    CASE STUDY and

    Analysis

    6.1 Background Information

    6.2 Project Features

    6.3 Simulation Process

    6.4 Summary of the Project

    6.5 Analysis

    Chapter 6 Case Study and Analysis

    Chapter 6 CASE STUDY AND ANALYSIS

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    66/116

    Chapter 6 CASE STUDY AND ANALYSIS

    6.1 Background Information

    Fig. 6.1 Proposed Kwai Chung Public Housing Estate

    Chapter 6 Case Study and Analysis

    Project Name Redevelopment of Kwai Chung

    (C

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    67/116

    Flatted Factory, (Contract No.

    20040031),Kwai Chung Public Housing Estate

    Domestic 1983 Rental Flats

    Location Wo Tong Tsui Street, Kwan Chung,

    Hong Kong

    Architect, Engineer and QualitySurveyor

    Housing Department Developmentand construction division, The Hong

    Kong Housing Authority

    Main Contractor Yau Lee Constriction Co-operation

    Limited

    Cooking Bench, Sink Unit and Panel

    Wall

    Yau Lee Wah Concrete Precast

    Product Co., Limited

    Project Duration 18 Jan 2005 17Aug 2007

    Construction Time 31 Months

    Contract Sum HK$366M

    Project Situation Under Construction

    Table 6.1 Project Particulars

    Proposed Kwan Chung

    Public Housing Estate

    Chapter 6 Case Study and Analysis

    6.2 Project Features

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    68/116

    The works comprise the construction of two nos. 41 storey modified New

    Harmony 1 (Option 2) Blocks (Blocks 1 and 2), each block approximately 51.4

    x 46.4m overall on plan and approximately 127m high from ground floor to

    main roof level.

    The external fascade, walls (structural and non-structural), bathrooms,

    stair-core, lift shafts and bathroom-cum-kitchens of the domestic units to Block

    1 and 2 are proposed to construct in precast concrete panels/components. In

    this project, over 70% of the concrete elements are constructed by precast

    concrete.

    6.3 Simulation Process

    The construction process simulation of 6 Day Cycle of Harmony One was

    constructed by CATIA V5 and DELMIA for the purpose of developing a detailed

    Chapter 6 Case Study and Analysis

    cranes are draw. The concrete structure is divided into slab, beam and wall

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    69/116

    elements, as shown in the following figures. The division is made according to

    the sequence of concrete pouring and the layout of 6-day construction cycle.

    These elements can be easily regrouped when there is a change in

    construction sequence or redesign in layout of construction bays

    Parametric models are built for generating reinforcement elements. By

    adjusting parameters like dimensions of concrete elements, concrete cover,

    steel bar diameter, steel bar spacing, length of steel bar projection from

    concrete element, etc, the 3D slab, beam and wall reinforcement elements are

    generated automatically.

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    70/116

    Fig. 6.5 Wall Reinforcement

    After creating the basic elements, they can be grouped into external walls,

    internal wall panels, etc.

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    71/116

    Fig. 6.7 Toilet

    Temporary works elements including wall form, slab form, beam form and

    working platform are also generated from parametric models. Parameters in

    these models are defined according to their specific design criteria. All of the

    parametric models are stored in library and can be reused easily in the future

    projects

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    72/116

    Fig. 6.9 Working Platform

    Fig. 6.10 Strut

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    73/116

    Fig. 6.11 Tower Crane

    6.3.2 Construction Process Simulation

    The 6-day cycle for construction of typical floor in Kwan Chung Public Housing

    Estate is inputted through Gantt chart and PERT chart interface. Activity start

    time, duration and precedent activity are handled in Gantt chart interface, while

    logical sequence of activities is handled in PERT chart interface

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    74/116

    Figure 6.13 PERT CHART

    Chapter 6 Case Study and Analysis

    Microsoft EXCEL for update and modification. The duration of activities is

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    75/116

    linked to these parameters and are updated automatically when there is

    change in these parameters

    The duration of concreting is linked to concreting rate parameter and the

    measurement value of volume of concrete elements. The measurement value

    is taken directly from 3D models and is updated dynamically.

    The construction process simulation can run in real time or in accelerated and

    decelerated speed. In reality every construction material or temporary support

    is moved from one place to another by human or plant. In this Kwan Chung

    Public Housing Estate 6-day cycle simulation, only those movements involving

    use of tower crane are simulated, as other movements are considered not

    necessary for supporting the 6-day cycle planning. Construction activities

    without movement simulation are simulated by change in color Please refer to

    Chapter 6 Case Study and Analysis

    6.3.3 Day 1

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    76/116

    Wing B Install Precast component (Figure 6.15)

    Wind D Fix Reinforcement and Conduit (Blue while in progress) (Figure 6.15)

    Wing D Fix Precast Component Reinforcement & Conduit (Figure 6.16)

    Wing B Weld Type A Precast Wall (Figure 6.16)

    Wing B Install Wall From for Fascade and Type C Wall (Figure 6.17)

    Wing B Concrete to Wall (Red while in Progress) (Figure 6.17)

    Wing B

    Wing A

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    77/116

    Fig. 6.16 Day 1 noon.

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    78/116

    Fig. 6.18 Construction Process.

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    79/116

    Fig 6.20 Movement of Wall Form

    6.3.4 Day 2

    Wing A Fix Slab Reinforcement & Conduit (Blue while in Progress)(Fig. 6.21)

    Wing B Strike Wall Form (Green While in Progress) (Fig. 6.21)

    Wing C Install Precast Components (Blue while in Progress)(Fig. 6.22)

    Wing C Fix Precast Component Reinforcement & Conduit (Figure 6.22)

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    80/116

    Fig. 6.21 Day 2 a.m.

    Wing B

    Wing C

    Wing A

    Wing D

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    81/116

    Fig. 6.23 Day 2 p.m.

    Chapter 6 Case Study and Analysis

    6.3.5 DAY 3

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    82/116

    Wing C Strike Wall Form (Figure 6.25)

    Wing C Erect Scaffolding for Semi-precast Slab(Red while in progress)

    (Figure 6.25)

    Wing B Install Semi-Precast Slab (Red while in progress) (Figure 6.26)

    Wing B Grouting to Type A Precast Wall (Figure 6.26)

    Wing C Install Semi-precast Slab (Figure 6.26)

    Wing D Concrete to Floor Slab & Half Central Core (Figure 6.27)

    Wing A Concrete to Floor Slab (Figure 6.27)

    Wing B

    Wing A

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    83/116

    Fig. 6.26 Day 3 noon

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    84/116

    Fig. 6.28 Movement of Concrete Boom

    Chapter 6 Case Study and Analysis

    6.3.6 DAY 4

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    85/116

    Wing D Install Precast Components (Figure 6.30)

    Wing B Fix Slab Reinforcement & Conduits (Figure 6.30)

    Wing C Grout Fascade Joint (Blue while in progress) (Figure 6.30)

    Wing D Fix Precast Component Reinforcement & Conduit (Blue while in

    progress) (Figure 6.31)

    Wing D Weld Type A Precast Wall (Figure 6.31)

    Wing D Install Wall Form for Fascade and Type C Wall (Figure 6.32)

    Wing D Concrete to Wall (Red while in progress) (Figure 6.32)

    Wing B

    Wing A

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    86/116

    Fig. 6.31 Day 4 noon.

    Chapter 6 Case Study and Analysis

    6.3.7 DAY 5

    Wi D St ik W ll F (G hil i ) (Fi 6 33)

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    87/116

    Wing D Strike Wall Form (Green while in progress) (Figure 6.33)

    Wing C Fix Slab Reinforcement & Conduits (Blue while in progress) (Figure

    6.33)

    Wing A Install Precast Components (Figure 6.34)

    Wing A Fix Precast Component Reinforcement & Conduit (Figure 6.34)

    Wing D Erect Scaffolding for Semi-precast Slab (Figure 6.35)

    Wing A Grout Fascade Joint (Purple while in progress) (Figure 6.35)

    Wing A Concrete to Wall (Red while in progress) (Figure 6.35)

    Wing B

    Wing A

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    88/116

    Fig. 6.34 Day 5 noon

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    89/116

    Fig. 6.36 Fix Conduit and Reinforcement

    6.3.8 DAY 6

    Wing A Strike Wall Form (Green while in progress) (Figure 6.37)

    Wing A Erect Scaffolding for Semi-precast Slab (Figure 6.37)

    Wing D Install Semi-precase Slab (Figure 6.38)

    Wing D Grout Fascade Joint (Purple while in progress) (Figure 6 38)

    Chapter 6 Case Study and Analysis

    Wing A

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    90/116

    Fig. 6.37 Day 6 a.m

    Wing B

    Wing C

    Wing A

    Wing D

    Chapter 6 Case Study and Analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    91/116

    Fig. 6.39 Day 6 p.m

    6.4 Summary of the Project

    This project study the feasibility of a 6-days floor cycle in the construction of

    two 40th stories residential buildings. This pioneering project is the first to

    adopt the new precast public housing design from the Hong Kong Government.

    More than 70% of the building structure is made of pre-cast elements

    Chapter 6 Case Study and Analysis

    to fully utilize the tower crane and shorten the construction cycle. This project

    successfully shortens the 6 full days works to 5 days The simulation also

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    92/116

    successfully shortens the 6 full day s works to 5 days. The simulation also

    helps the contractor to produce an improved sequence of installing precast

    elements.

    Chapter 6 Case Study and Analysis

    6.5 Analysis

    Integrating the findings from the case and the interviews, an analysis

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    93/116

    Integrating the findings from the case and the interviews, an analysis

    concerning the strengths and limitations of utilizing CATIA and DELMIA is

    conducted.

    6.5.1 Strengths

    CATIA and DELMIA has the strengths of the present 2D CAD technology as

    mentioned in Chapter 2.1.1 2D Computer Aid Design and overcome some of

    its limitations which are discussed in the following sections.

    6.5.1.1 Drawings

    Referring Yip (2005), by using CATIA, it can offer the building industry a

    breakthrough 3D digital environment enabling the shift away from 2D drawing,

    layering-oriented systems originally used to produce paper documents. The

    object-orientated tools allow users to create model three dimensionally, but not

    Chapter 6 Case Study and Analysis

    utilizing CATIA and DELMIA which allows managing the site space visually.

    The simulation environment provides an intuitive way to plan storage (Kong,

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    94/116

    p y p g ( g,

    2006).

    6.5.1.3 Communication

    CATIA and DELMIA stimulates communication in various aspects. Holtzman

    (2002) explained that using CATIA can decrease the amount of discrepancy

    between different contractors work as everyone is directly referencing a single,

    complete, 3D model. The 3D model and the simulation process which provide

    an easy understanding platform allow planners to communicate within their

    team, with their clients and the contractors, e.g. the function of process

    simulation in DEMIA allows users to view various stages of a cycle, so the

    dynamic and interrelationship between activities can be understood by

    different parties (Kong, 2006). Subsequently, communication became more

    efficient and effective according to Lee (2006)

    Chapter 6 Case Study and Analysis

    types of resources usage report can be generated automatically from the

    simulation. The first type is report showing usage of a particular resource for

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    95/116

    yp p g g p

    which activities and at which time. The second type is report showing what

    resources are used for a particular activity and at what time. These reports can

    be in bar chart or table format to improve the flow and optimize the use of

    resources (Kong, 2006).

    6.5.1.5 Information Management

    One of the functions of CATIA is parameter editing. The case of 6-day cycle

    simulation is based on productivity rate parameters which can be checked

    against the real productivity rates measured during construction, and then, be

    adjusted to refine the simulation. The adjusted productivity rate can be used as

    a benchmark for projects in the future, so information management for future

    use is improved.

    Chapter 6 Case Study and Analysis

    6.5.2 Limi tations

    Although CATIA and DELMIA has plenty of advantages, planners do not adopt

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    96/116

    the technology in a large extent because there are still many limitations to be

    overcame.

    6.5.2.1 Design for Manufacture

    Martyn Day (2003) stated that although Dassault System (CATIA V5 and

    DELMIA) has perfectly viable systems for structural and mechanical, CATIA

    does not have any as it is not tailored to the building industry which involves

    huge amount of complex information. Buildings may contain 10 to 50,000

    structural plates and I-beams with corresponding numbers on the curtain

    wall and ductwork, so CATIA and DELMIA may not have the capability to

    integrate all that information so it still has modeling limitation.

    6 5 2 2 License Fee

    Chapter 6 Case Study and Analysis

    As a license that can be shared by moving between configurations

    A set of products bundled together to solve a particular design or engineering

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    97/116

    problem is called a configuration. Most of these configurations include four to

    twelve products and their price is quite high. After the first configuration is

    purchased, it is possible to expand the toolset by purchasing a single product.

    Moreover, the company has to pay for the license subscription fee annually.

    The license fee of CATIA and DELMIA is comparatively superior to the

    traditional CAD software, e.g. AutoCAD 2006, Microsoft Project 2003, etc, as

    shown in the following table.

    Software AutoCAD

    2006

    Microsoft

    Project 2003

    CATIA V5 & DELMIA

    License Fee HK$32,999a HK$6,999a >HK$1,000,000

    Remarks : (Asscess though www hkishop com on 20 February 2006)

    Chapter 6 Case Study and Analysis

    6.5.2.3 Lacking in skil lfu l labour

    CATIA and DELMIA is fresh to construction industry. According to Ho (2006),

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    98/116

    there is a lack of skillful labour who familiarize with the operation of CATIA and

    DELMIA in construction field (Lee, 2006). Although there are publications

    teaching CATIA and DELMIA, training programme is far lacking comparing with

    AutoCAD, Micro Station and Microsoft Project, etc.

    6.5.2.4 Hardware Requirement

    Apart from license fee and labour problem, CATIA and DELMIA requires high

    quality computer hardware to support processing of massive amount of data,

    e.g. according to website of IBM, an internal or external disk drive (minimum

    recommended size is 4 GB) is required to store program executables

    (installation of all CATIA Version 5 Products requires 2.0 GB on Windows, 2.4

    GB on AIX, 2.7 GB on HP-UX, 2.5 GB on IRIX, and 2.3 GB on Solaris),

    program data usage environment and paging space These are also a

    Chapter 6 Case Study and Analysis

    6.5.2.5 Human-Initiated Characteristic

    CATIA and DELMIA are obviously very powerful software to help planner

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    99/116

    design the construction programme, however, they cannot generate the best

    programme to achieve optimization by itself. Software cannot create the best

    programme without planner who design, prepare and input the basic data, and

    then, the software help to generate and simulate the possible programme in

    order to identify any possible planning errors. CATIA and DELMIA can improve

    the programme designed by planners, but not create a new one. They must be

    initiated by professionals.

    CHAPTER VII

    Conclusions and

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    100/116

    Conclusions andRecommendations

    7.1 Conclusions

    7.2 Recommendations

    Chapter 7 Conclusions & Recommendations

    Chapter 7 CONCLUSIONS & RECOMMENDATIONS

    7.1 Conclusions

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    101/116

    Inefficient site space and facilities management, crashes of activities and poor

    communication are common problems in construction projects. These

    problems often lead to inefficient utilization of cost and time. A comprehensive

    planning is the solution to solve the problems. CATIA and DELMIA provides a

    platform to create a comprehensive planning.

    Derived from the functions of CATIA V5 and DELMIA and interviews with

    professionals, advantages in terms of drawings, site space and facilities

    management, communication, scheduling and information management are

    found. However, there are some limitations to restrict the popularity of CATIA

    and DELMIA in construction industry in Hong Kong because, firstly, it was

    designed for manufacture, but not tailor made for construction, secondly, its

    Chapter 7 Conclusions & Recommendations

    design construction programme, however, they have not widely used in

    construction industry subject to the limitations mentioned in previous

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    102/116

    paragraph.

    7.2 Recommendations

    This research investigates the utilization of CATIA and DELMIA by qualitative

    method because of the limitation in collecting data from companies. However,

    it is worth to have further study on the issue by using quantitative method, e.g.

    comparing the cost and time invested in a project with and without using CATIA

    and DELMIA. It can provide investors with more convincing reasons to adopt

    this new tool in their developments.

    Reference and Bibliographies

    References and Bibliographies

    1 A till J W d R W W dh d (1990) C iti l th th d i

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    103/116

    1. Antill, J.W., and R.W. Woodhead. (1990).Critical path methods in

    construction practice. 4thed. New York: Wiley,

    2. Brandon, P. S., (1999) Product Process Development in 2000 Beyond,

    Berkeley-Stanford CE&M Workshop, Standford 1999.

    3. Beckert, Beverly A. (2000) CAD software gets "smarter", Computer -

    Aided Engineering Vol 19, Iss 1, Jan 2000

    4. Bocking C E, Rennie A E W and Jacobson D M (2003).Rapid and Virtual

    Prototyping and Applications, Professional Engineering Publishing

    Limited.

    Reference and Bibliographies

    York, New York, 1991.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    104/116

    7. Chau K, W,,Anson M, Zhang J.P. (2005). 4D dynamic construction

    management and visualization software : 1.Development. Automation in

    Construction 14(2005) 512-524.

    8. Chau C. K., S.H. and R.K. L. Gay (1999). Rapid Prototyping Verus Virtual

    Prototyping in Product Design and Manufacturing. Int J Adv Manuf

    Technol (1999) 15:597-603. Springer-Verlag London Limited.

    9. Chau K. W., M. Anson, J.P. Zhang (2004) 4D dynamic construction

    management and visualization software : 1. Development. Automation in

    Construction 14 (2005) 512-524.

    10 Construct IT (2000) Construction Modelling Methodologies for Intelligent

    Reference and Bibliographies

    Simulation with an Adaptable Graphical User Interface. St. John's

    Newfoundland

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    105/116

    12. Halpin, D., and Woodhead, T. (1998). Construction management, 2ndEd.,

    Wiley, New York

    13. Howard R., 1998, Computing in construction pioneers and the future.

    Butterworth Heinemann.

    14. Issa, R.,(1999) Virtual Reality: A solution to Seamless Technology

    Integration in the AEC Industry, Berkeley-Stanford CE&M Workshop,

    Stanford 1999.

    15. Karam Fred and Kleismit (2004), Using CATIA V5, Thomson Learning.

    Reference and Bibliographies

    17. Ma Z., Shen Q. & Zhang J. (2004) Application of 4D for dynamic site

    layout and management of construction projects. Automation in

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    106/116

    Construction 14 (2005) 369-381

    18. Malkawi Ali M. and Godfried Augenbroe (2003). Advanced Building

    Simulation, Spon Press .

    19. Mubarak, Saleh A. 2005. Construction project scheduling and control.

    Pearson Education limited.

    20. Popescu, C.M., and C. Charoenngam. 1995. Project Planning, scheduling

    and control in construction : An encyclopedia of terms and application.

    New York: Wiley.

    21. Pratt M. J.(1994), Virtual prototypes and product models in mechanical

    engineering Proceedings IFIP WE 5 10 on Virtual Environment and their

    Reference and Bibliographies

    Management Institute.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    107/116

    23. Ripley, Brian D., Stochastic Simulation, John Wiley & Sons, New York,

    New York, 1987

    24. Sarshar,M., Betts, M., Abbott, C., Aouad, G., (2000) A Vison for

    Construction IT 2005-2010, RICS (Royal Institute of Chartered Surveyors)

    Research Series, Dec 2000.

    25. Sarshar,M., Tanyer, A., Underwood, J.,(2002) A Vision for Construction IT

    2005-2010, RICS (Royal Institute of Chartered Surveyors) Research

    Series, Dec 2000.

    26. Sawhney, A., (1999) Research and Development Plan for the AEC

    Industry Berkeley Stanford CE&M Workshop Stanford 1999

    Reference and Bibliographies

    28. Shi, J. J. (1999) Computer Simulation in AEC and its Future

    Development, Berkeley-Stanford CE&M Workshop, Stanford 1999.

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    108/116

    29. Stribling, David (2003), Building Simulation Virtual prototyping for

    construction projects, Ingenia Issue 17 October/November (2003) 32-35.

    30. Sun Ming and Rob Howard (2004), Understanding I.T. in Construction.

    Spon Press

    31. Tang S.L., S.W. Poon, Syed M. Ahmed and Francis K.W. Wong. 2003.

    Modern Construction Project Management, second edition, 227- 230.

    Hong Kong University Press.

    32. Thabet, W., (1999). Design-Construction Integration Through Virtual

    Construction for Improved Constructability Berkeley Stanford CE&M

    Reference and Bibliographies

    139-154.

    34 W h L M d F T M (1990) C t i t k l d f

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    109/116

    34. Waugh, L. M., and Froese, T. M. (1990). Constraint knowledge for

    construction scheduling. IEE Conf. Publ., Institute of Electrical Engineers,

    London, 114-118.

    35. WISE consortium (2002) State of the Art Survey: Managing Engineer

    knowledge. The WISE consortium.

    36. Zeigler, Bernard P., Multifacetted Modelling and Discrete Event Simulation

    London, Academic Press, 1984.

    Appendix

    LIST OF APPENDICES

    Appendix I - Sample of Accompanying Letter

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    110/116

    Appendix II - Sample of Interview Question

    Appendix III - Method and Sequence of Construction at Typical Floor

    Appendix IV - 6-day Cycle Programme for Typical Floors

    Appendix

    Appendix I: Sample of Accompanying Letter

    February 2006

    Dear Sir,

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    111/116

    Invitation of Participating in a Research Interview

    I am hereby writing to invite you being the interviewee of a research. I am Li Ka

    Ming, a student of BSc (Hons) of the Building Surveying of the Department of

    Building and Real Estate in The Hong Kong Polytechnic University. I am currently

    carrying out a research project on The application of Virtual Prototyping in the

    Construction Industry : a case study of Kwan Chung Redevelopment Project .

    The main objectives of this project are to evaluate the effectiveness of construction

    simulation process, improve the traditional construction planning and make

    recommendations on the further development of virtual prototyping.

    I strongly believe that your experience and opinion is highly valuable to the

    academics and practitioners. The information you provide will be kept in strict

    confidentiality and used for academic purposes. Only generalized summaries and

    conclusion will be presented even in research reports.

    Time and place of interview can be arranged at your convenience. If you have further

    enquires, please contact me via mobile (no. 98511622) at your convenience. I am

    looking forward to hearing from you.

    Thank you for your assistance.

    Yours sincerely,

    Appendix

    Appendix II: Sample of Interview Questions

    Interview Questions Aims

    1. What are your expectations on the To collect the practitioners view on the

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    112/116

    technology of virtual prototyping in

    projects? Were the results complied

    with your expectations?

    expectations of virtual prototyping

    2. Why do you/your company invest

    in the technology of virtual

    prototyping?

    To collect the practitioners view on the

    investment of innovation technology

    3. Do you think that virtual

    prototyping is effective in

    improving the planning and

    construction of a project in term of

    time, cost and quality ?

    To evaluate the effectiveness of virtual

    prototyping to improve the planning and

    construction of a project

    4. What are the considerations/criteria

    of using virtual prototyping?

    To identify the relative importance of

    various factors using virtual prototyping.

    5. What do you think about the ease of

    use, practicability and cost of usingvirtual prototyping in construction

    industry ?

    To evaluate the attractiveness of using

    virtual prototyping in project planning

    6. Do you think virtual prototyping

    acts as a Design tool successfully ?

    To evaluate whether virtual prototyping

    helps designers to choose the best

    alternative designs

    7. What do you think about usingvirtual prototyping in project

    planning ?

    To collect the practitioners view on

    using virtual prototyping in the

    construction industry.

    Appendix

    Appendix III: Method and Sequence of Construction at Typical Floor

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    113/116

    Appendix

    Appendix IV: 6-day Cycle Programme for Typical Floors

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    114/116

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    115/116

  • 7/21/2019 Dissertation Kwaichunghousing[1]

    116/116