Top Banner
DISPUTES & ARBITRATION How to AVOID and MANAGE ? by Rajesh Prasad Executive Director Rail Vikas Nigam Limited, Kolkata 09.12.2016
69

Disputes and Arbitration- How to Avoid and Manage

Jan 17, 2017

Download

Education

Rajesh Prasad
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Disputes and Arbitration- How to Avoid and Manage

DISPUTES&

ARBITRATION

How to AVOID and MANAGE ?by

Rajesh PrasadExecutive Director

Rail Vikas Nigam Limited, Kolkata09.12.2016

Page 2: Disputes and Arbitration- How to Avoid and Manage

Thought

Some men worship rank, some worship heroes, some worship power, some worship God, some worship Amma, and over these ideals they DISPUTE and most of them worship MONEY.

Page 3: Disputes and Arbitration- How to Avoid and Manage

I have to get the work completed and

commissioned…..

I have to maximise profit and get some

claims from Arbitration

MeARBITRATOR

So it is all about Money,Dispute,Arbitration….

Page 4: Disputes and Arbitration- How to Avoid and Manage

Boundary line cases in Contract Management can lead to either way…… SIX or OUT……….

What a dispute……

Page 5: Disputes and Arbitration- How to Avoid and Manage

World cup 2007

https://youtu.be/saKJdNhDB_4

Page 6: Disputes and Arbitration- How to Avoid and Manage

The biggest unresolved dispute in the world is :

‘which one has come first CHICKEN or EGG?

Page 7: Disputes and Arbitration- How to Avoid and Manage

The dispute of Chicken or Egg is resolved in a restaurant….

what ever you order first we will give you

that first…….

Page 8: Disputes and Arbitration- How to Avoid and Manage

Dispute can be b/w Brothers in a family for property……

Page 9: Disputes and Arbitration- How to Avoid and Manage

Dispute on Land issue

August 24, 2008: Mamata Banerjee starts indefinite dharna at Singur outside the car plant.September 2, 2008: Tata Motors suspends work on Nano Plant at Singur.September 3, 2008: Governor Gopal Krishna Gandhi plays mediator; CPI(M)-led Left Front government and Trinamool agree to hold discussions.September 5, 2008: West Bengal government and Trinamool start negotiations.September 7, 2008: Talks break down.October 3, 2008: Tata Motors decides to move out of Singur. Read: We cannot run a plant with police protection, says TataOctober 7, 2008: Tata Motors announces new Nano Plant at Sanand in Gujarat.May 20, 2011: Mamata Banerjee sworn in as Chief Minister of West Bengal, announces first Cabinet decision to return 400 acres of land to unwilling Singur farmers.June 14, 2011: Singur Land Rehabilitation and Development Bill, 2011 passed in West Bengal Assembly.June 22, 2011: Tata Motors moves Calcutta High Court challenging the Bill.September 28, 2011: Calcutta High Court single bench upholds the Singur Land Rehabilitation and Development Act, 2011.June 22, 2012: A division bench of Calcutta High Court strikes down the Bill on an appeal by Tata Motors.August 31, 2016: Supreme Court sets aside January 18, 2008 order of Calcutta High Court, allows appeals filed by some farmers and NGOs

July 2006: Mamata Banerjee opposes the plant on fertile land.December 2006: Protests against the acquisition begins.December 2006: Mamata Banerjee holds 26-day hunger strike against the land acquisition | Also read: Singur and political posturingJanuary 21, 2007: Tata Motors starts construction of Nano car plant in West Bengal.January 18, 2008: Calcutta High Court upholds Singur land acquisition, following which farmers and NGO moved the Supreme Court challenging the HC order.

Page 10: Disputes and Arbitration- How to Avoid and Manage

Samudra Manthan was also a DISPUTE……

Page 11: Disputes and Arbitration- How to Avoid and Manage

Nature of Disputesi) Delay in completion of work.

ii) Delay in releasing payments.

iii) Delay in giving decisions on matters referred to.

iv) For extra items of work, quantity and rate their of.

v) Variations in scheduled quantities..

vi) Disputes regarding extension under penalty

clause or termination of contract under risk and

cost.

vii) Disputes in connection to measurements.

Page 12: Disputes and Arbitration- How to Avoid and Manage

viii) Claims for hiring plants and equipment.

ix) Various compensations and undue interest.

x) Some times claims are even raised for excepted

matters.

xi) Work getting deleted from Pink Book (Sanctioned

list) & payments are affected due to non-

availability of fund.

xii) Disputes in connection to specifications.

xiii) Disputes in connection to drawings.

xiv) Disputes in connection to poor workmanship.

Page 13: Disputes and Arbitration- How to Avoid and Manage

Dispute & Negotiation Can Take place any time, any where ……

I do not agree to your proposal tonight. You take these many actions and then I’ll think over ….

Page 14: Disputes and Arbitration- How to Avoid and Manage

Arbitration: Managing Disputes• Disputes unmanaged lead to arbitration

• Parties to a Contract– Client– Contractor– Consultant (in some cases)

• Objectives are different except one common thread;– “Successful contract completion”

Page 15: Disputes and Arbitration- How to Avoid and Manage

TimelyOrderlyDispute FreeCustomer Satisfaction

Aim of Executive :Execution of Work which is

Page 16: Disputes and Arbitration- How to Avoid and Manage

Hon’ble PM’s Address during recent commissioning of one of the RVNL projects

https://youtu.be/rlf-DgN9KdY

Page 17: Disputes and Arbitration- How to Avoid and Manage

Message

• Execution within Time frame.

• Execution within Estimated Cost.

• Execution with Proper Quality.• Above all Execution should be

dispute free.

Page 18: Disputes and Arbitration- How to Avoid and Manage

Project Management Triangle

ScopeQ

ualit

y

Page 19: Disputes and Arbitration- How to Avoid and Manage
Page 20: Disputes and Arbitration- How to Avoid and Manage
Page 21: Disputes and Arbitration- How to Avoid and Manage

Various ways of sorting DISPUTES

Page 22: Disputes and Arbitration- How to Avoid and Manage

ARBITRATION

Page 23: Disputes and Arbitration- How to Avoid and Manage

More than 300 Crores cases pending…It may take 300 years to settle….

Page 24: Disputes and Arbitration- How to Avoid and Manage

Reasons for arbitrations Incomplete and defective tender

schedule, conditions, poor rate. Delay in site, drawings, and decision

taking.

Contractors inclination towards arbitration.

Unforeseen circumstances.

Combination of the above.

Page 25: Disputes and Arbitration- How to Avoid and Manage

• There is a limit of changes in Drawing....

• Not sure & clear

Page 26: Disputes and Arbitration- How to Avoid and Manage

Reasons for ArbitrationEvery executive’s Aim : ORDERLY, TIMELY and DISPUTE FREE.

i) The contractor has also motive to earn money and arbitration may be an easy mode to extract the same.

ii) Unexpected changes in underground situations and unforeseen items.

iii) Awarding the contract to L1 irrespective of poor rate.

iv) Changes or revisions in technical decisions.v) Incorporation of new concepts/ideas.

Page 27: Disputes and Arbitration- How to Avoid and Manage

vi) Unexpected outside developments affecting the work.

vii) Non-maintaining proper and day today progress.

viii) Granting extensions without penalty to ensure completion and that also without a joint program signed by the contractor. A compromise is made to achieve the progress and sometimes this becomes the basis for arbitration.

ix) Time constraint in preparation of drawing, schedule, conditions etc. resulting variations in quantities and or in specifications.

x) Delay in finalization of drawing and construction details.

Page 28: Disputes and Arbitration- How to Avoid and Manage

xi) Erosion of the power of the executive to take bold decision based on the merit of the case due to various checks by Accounts, Vigilance, Audit etc.

xii) Delay in deciding rates for extra items.xiii) Delay in making the railway materials

available.xiv) Due to termination of contract on account

of contractor’s failures and improper follow up action

xv) Incomplete or contradicting schedule and/or specification.

Page 29: Disputes and Arbitration- How to Avoid and Manage

xvi) Claims for execution during over run period for which contractor is not responsible.

xvii) Deductions from bills due to Audit/Vigilance/Account’s examination or faulty measurements.

Executive should therefore, be very careful and particular in planning, framing tender documents, proper record keeping, taking timely decisions etc. In the present scenario increasing no. of disputes can not be avoided.

Page 30: Disputes and Arbitration- How to Avoid and Manage
Page 31: Disputes and Arbitration- How to Avoid and Manage

Prevention against Arbitrationi) Proper planning of tender schedule, drawing and

incorporating clear conditions.

ii) Granting of extensions with a joint program (may be a revised program) signed by the contractor.

iii) Finalization of the contract at the right time with realistic date of completion.

iv) Ensuring signing of all MB’s and bills with prescribed certificates.

v) Ensuring recoding of all level books in ink duly signed by the contractors and keeping in the safe custody of PD.

vi) Keeping record of actual daily progress. This includes engagement of labour, consumption of cement & steel.

Page 32: Disputes and Arbitration- How to Avoid and Manage

vii) All vague and fabricated allegations should be properly and

timely refuted.

viii) Proper procedures should be followed in finalization and

termination of the contract.

ix) Delay on the part of the contractor must be kept in writing.

x) Senior supervisors and junior officers should be advised not

to communicate to the contractor, only PD and CPM should

do that.

xi) Non-execution of work in anticipation of sanction.

Page 33: Disputes and Arbitration- How to Avoid and Manage

xii) A constant watch should be kept on contractor’s tendency to

create records for unjustified claims and prompt and proper

reply should be sent.

xiii) Last but not the least – as soon as the dispute arises and the

contractor’s intention is noticed, all basic records like level

books, cross-sections, MB’s, site records and various

correspondences should be sealed and kept under personal

custody of a responsible officer.

Page 34: Disputes and Arbitration- How to Avoid and Manage

Counterclaims and defending the proceedingsi) Continuation of speed restrictions (affected directly or

indirectly) due to prolonging of execution. The total loss can be calculated.

ii) Extra traffic/power block required due to fewer engagements of skilled/semi-skilled/un-skilled labors. The amount of loss can be calculated.

iii) For safety related works, cost of speed restriction and cost of any accident occurred due to non-completion or delay in completion can be claimed by railway.

iv) Cost of railway supervisors/officers for their idling or under utilization can be claimed.

Page 35: Disputes and Arbitration- How to Avoid and Manage

v) Various compensations and interests as claimed by the contractors can also be raised as part of counterclaims.

vi) Demurrage and wharfage dues, if any.

vii) In case the contractor does not return the railway material over a long period, the cost as per the rules along with interest should also be claimed.

The counterclaims should also be got vetted by local finance and law before submission to the arbitrator.

Page 36: Disputes and Arbitration- How to Avoid and Manage

Site not clear- Site not clear- Encroachments, Encroachments, Infringements,Infringements,DOT, Tree, DOT, Tree, ServicesServices

Page 37: Disputes and Arbitration- How to Avoid and Manage

Important letter/ instruction :1Letter date:12.05.2011The claim of Ms AFCONS Infrastructure Ltd. quashed by Arbitrators

i) Mr. M. Ravindraii) Mr. P . Sridhananiii) Mr S.M. Singla

Citing a lot of judgments Classical Case

Page 38: Disputes and Arbitration- How to Avoid and Manage
Page 39: Disputes and Arbitration- How to Avoid and Manage

Important letter/instructions:2

Risk Management with regard to contractors claims date 23.04.13

Page 40: Disputes and Arbitration- How to Avoid and Manage

POINTS REQUIRED TO BE MONITORED TO MINIMISE CLAIMS OF THE CONTRACTOR

1.Award of contracts to be done only after (i) availability of at least 50% land and availability of first stage forestry clearance in case of forest land is involved (ii) Preparation of detailed estimate as per procedure order No.C/Policy/Estimate dated 27.6.2012.

2.Tender for important bridges should be invited only after considering Geotechnical Investigation Report and finalization of GAD's3.Schedule of quantities should be prepared as per procedure order No.C/Policy/Estimate dated 27.6.2012. 4.The time frame for completion of work in the tender documents should be realistic duly stipulating mile stones for section wise completion. 5.The time frame for completion of work in the tender documents should be realistic duly stipulating mile stones for section wise completion. 6.Request for extension of time should be processed expeditiously within 7 working days of receipt of application.

Page 41: Disputes and Arbitration- How to Avoid and Manage

POINTS REQUIRED TO BE MONITORED TO MINIMISE CLAIMS OF THE CONTRACTOR

7.Process for sanction in variation in quantities and rates for deviated/substituted/ extra items expeditiously i.e. within 15 working days of receipt of information about the same. 8.Maintain all necessary records such as site order book, labour register, equipment register and cement consumption register properly. 9.All references received from the contractor must be invariably replied expeditiously covering all points raised with reference to the conditions of contract. 10.Periodic Review meetings should be held with the contractor and minutes should be invariably issued.11.Payment to Contractors should be made as quickly as possible, but in any case not later than the time limits specified in the contract. 12.Timely action should be taken to make available critical items such as rails, sleepers and any other items to be made available by the Employer, keeping in mind the milestones given in the contract document.

Page 42: Disputes and Arbitration- How to Avoid and Manage

Important letter/instructions: 3Appointment of Arbitrator date: 01.08.2013 Judgment (2013/4 Supreme Court cases 35) of the Supreme Court sent by Anit Seth, Advocate dated 25.07.13 wherein the Supreme Court has held that appointment / nomination of Arbitrator by Corporation after the Contractor has filed the application for appointment of Arbitrator is not valid and the Appointing Authority under agreement right is forfeited to appoint / nominate the Arbitrator for your information and necessary action please.

Page 43: Disputes and Arbitration- How to Avoid and Manage
Page 44: Disputes and Arbitration- How to Avoid and Manage

Important letter/instructions: 4

Monitoring of appointment of Arbitrators and progress of Arbitration cases Date:14.08.13

Page 45: Disputes and Arbitration- How to Avoid and Manage
Page 46: Disputes and Arbitration- How to Avoid and Manage

Handle contractors honestly & diplomatically. Otherwise………

Contract Management and defending arbitration is not an easy task…

Page 47: Disputes and Arbitration- How to Avoid and Manage
Page 48: Disputes and Arbitration- How to Avoid and Manage

Pre-amendment scenario making Arbitration costly and long-drawn

Ad-hoc arbitrations were left to the whims and fancies of the arbitrators;

Large number of sittings were there and arbitrations went on for years altogether;

Charging of higher fees per sitting, with several add-ons, without any ceiling, many a time resulted in the cost of arbitration even exceeding the amount involved in the dispute;

Adjournments were granted with great ease.

No responsibilities on either side.

Page 49: Disputes and Arbitration- How to Avoid and Manage

On 23rd October 2015, the Government of India through an executive action promulgated the Arbitration and Conciliation Ordinance, 2015 bringing about large scale changes to the Arbitration and Conciliation Act, 1996.

The Arbitration and Conciliation (Amendment) Act, 2015 was passed by both houses of parliament in the winter session.

The Act was notified in the Gazette of India on 1st January 2016

Page 50: Disputes and Arbitration- How to Avoid and Manage

Strict Time limit for making award under Section 29A

The arbitral tribunal is statutorily obligated to deliver an award within 12 months from the date when arbitral tribunal enters into reference.

The explanation says that the arbitral tribunal is said to have entered upon the reference on the date on which the arbitrator(s) have received notice of their appointment.

Award within 12 months [29A(1)]

Maximum delay of 6 months [29A(3)] The award can be delayed by a maximum

period of 6 months only under the special circumstances where all parties give their consent to such extension.

Page 51: Disputes and Arbitration- How to Avoid and Manage

Where the award is not made out within the statutory period the mandate of arbitrators shall automatically terminate.

Unless the Court has, either prior to or after the expiry of the period so specified, extended the period.

While extending the period, if the Court finds that the proceedings have been delayed for the reasons attributable to the arbitral tribunal, then, it may order reduction of fees of arbitrator(s) by not exceding five per cent for each month of such delay.

Mandate of arbitrators to terminate automatically [29A(4)]

Additional Fess for faster disposal [29A(2)] Where the Arbitral Tribunal delivers the award

within of 6 months the arbitral tribunal shall be entitled to additional fees. The quantum of such additional fees shall be determined by the parties.

Page 52: Disputes and Arbitration- How to Avoid and Manage

Extension granted by the court [29A(5)]It is open for the courts to extend the time

period for making an award upon receipt of an application by any of the parties.Such extension is to granted only for sufficient cause and the court in its discretion has the power to:•Reduce the fees of arbitrators by up to 5% for each month of delay, [29A(4)]•Substitute one or all the arbitrators [29(6)]•Impose actual or exemplary costs on any of the parties [29A(8)]Again for the application field a time limit has been set and the same shall be disposed of as expeditiously as possible and endeavour shall be made to dispose of the matter within a period of sixty days from the date of service of notice on the opposite party. [29A(9)]

Page 53: Disputes and Arbitration- How to Avoid and Manage

Fast Track Procedure (Section 29B) The parties to an arbitration may choose to opt for

a new fast track procedure either before or after the commencement of the arbitration. (1)

The award in a fast track arbitration is to be made out within six months from the date the arbitral tribunal enters upon the reference. (4)The salient features of the fast

track arbitration are (3) Disputes are to be decided based on written

pleadings and documents only; Arbitral Tribunal shall have the power to call for

clarifications where it deems necessary. Oral hearing may be held only if all the parties

make a request or if the arbitral tribunal considers it necessary.

The arbitral tribunal may dispense with any technical formalities.

Page 54: Disputes and Arbitration- How to Avoid and Manage

Amendment to the A&C Act 1996 via Arbitration Ordinance 2015

Section 2(2) Section 8 (Reference of parties to the

dispute to arbitration) Section 9 (Interim Measures) Section 11 (Appointment of Arbitrations) Section 12 (Declaration by the

Arbitrators) Section 14 (Termination of mandate of

arbitration) Section 17 (Interim Measures by

Arbitration tribunal) Section 23 (Respondent can file counter

claim)

Page 55: Disputes and Arbitration- How to Avoid and Manage

Section 24 (Presentation of evidence or oral)

Section 29A and 29B (Time limit for arbitral award and Fast Track procedure)

Section 25 (Tribunal to treat Respondent’s failure to communicate statement of defence

Section 31 (Provision for levy of future internal)

Section 34 (Limiting the gamut of Public Policy of India)

Section 36 (Stay on enforcement of award)

Amendment to the A&C Act 1996 via Arbitration Ordinance 2015

Page 56: Disputes and Arbitration- How to Avoid and Manage

Positive step towards making Arbitration – Expeditious, Efficacious, Cost

effective Curb the practices leading to wastage of

time Declaration by the Arbitrator about his

independence and impartiality Making the Arbitrator responsible for delay

in the proceeding Likely to reduce the interference of the

court in proceedings.

Amendment to the A&C Act 1996 via Arbitration Ordinance 2015

Page 57: Disputes and Arbitration- How to Avoid and Manage

Bigger the Contractor, better and diplomatic handling is needed…….

Page 58: Disputes and Arbitration- How to Avoid and Manage

I Have Lost Everything due to greed to earn more through Arbitration

Contractor

Page 59: Disputes and Arbitration- How to Avoid and Manage

Ping-Pong b/w Ping-Pong b/w ContractorContractor & & Executive Executive

https://www.youtube.com/watch?v=KW_6Lzr47iU

Page 60: Disputes and Arbitration- How to Avoid and Manage

Play Play between between

Contractor and ExecutiveContractor and Executive has to be has to be FairFair and and as per as per

the provisions of the the provisions of the Contract AgreementContract Agreement

Page 61: Disputes and Arbitration- How to Avoid and Manage
Page 62: Disputes and Arbitration- How to Avoid and Manage

Quality of Food is important for him. Quality of Construction is important for us.

Page 63: Disputes and Arbitration- How to Avoid and Manage

63

Page 64: Disputes and Arbitration- How to Avoid and Manage

Dos & Don’ts by Parties

• Do not meet/try to meet arbitrator, in absence of other party

• All correspondence to Arbitrator be copied to the other party

• Send communication in writing in advance if not able to attend hearing

• On receipt of adverse award take legal advice

Page 65: Disputes and Arbitration- How to Avoid and Manage

It was a presentation It was a presentation made by made by Rajesh PrasadRajesh Prasad, ,

Executive Director Executive Director Rail Vikas Nigam LimitedRail Vikas Nigam Limited

Page 66: Disputes and Arbitration- How to Avoid and Manage

What is a Project?What is a Project?Means of converting Vision to Reality

A set of activities undertaken to meet specific objectives for changes

"A temporary endeavor undertaken to create a unique product, service or result "

Page 67: Disputes and Arbitration- How to Avoid and Manage

What is a Project?What is a Project?

• Temporary - have a definite beginning and an end• Unique - no two projects are identical• Predefined goals & objectives - financial/ social /economic• Budgets & schedules - prefixed budget and timeframe• Uses Resources & Manpower - both are limited• Quality / Performance - determined at beginning• Face Risks - known and unknown risks• Have a Project Life cycle - many phases from start to end

Projects can be defined as:

Page 68: Disputes and Arbitration- How to Avoid and Manage

Project ManagementProject ManagementWhat is Project Management (PM)?

Project Management is the processes & body of knowledge of specific skills, tools and techniques used to bring structure and planned order to deliver projects successfully

Project Management is the most efficient way for implementing unique changes

Page 69: Disputes and Arbitration- How to Avoid and Manage

Project Status Determination

Under Budget & Behind Schedule

Under Budget& Ahead of Schedule

Over Budget& Behind Schedule

Over Budget& Ahead of Schedule

2

1.5

1.0

.5

0

.5 1.0 1.5 2