Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010
30

Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Dec 24, 2015

Download

Documents

Clare Freeman
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Digital PECVD Machine Design and Construction

Zlatan Ceric

William Edwards

Timothy Gurtler

David Ogden

Quan Tran

Date:12/10/2010

Page 2: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Project Overview

Contracted by Nanotechnology Research Center Converted existing RIE to PECVD machine Automation of process eliminates the need for

constant human monitoring Cost of Hardware: $35,000 Built base model for NRC modification

Page 3: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Final Product

Page 4: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Design Objectives

Continuously monitor chamber vacuum pressure, RF power, and gas flow rate

Automated the polymer deposition process

Allows for future process modification through HMI

Page 5: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

RIE to PECVD Conversion

Removed turbo pump

Use one chamber pressure sensor instead of two

Removed old chamber heater

Remapped wires to integrate new design

Edited PLC and HMI code to reflect all changes

Page 6: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

System Hierarchy

HMI

RF Power

Mech Pump

MFC

Matching Network

Legend

Input to PLC

Output from PLC

Mech Conn.

PLC

Chamber

Page 7: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Mechanical Pump

Page 8: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Mass Flow Controllers

Page 9: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

RF Power System

Page 10: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Chassis Construction

Gator Jaw is the material used to build the stand

It is customizable and easily changed if needed

Plates can be mounted to the frame to provided a surface for components to mount

Page 11: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Component Mounting

Din rail provides a simple mounting solution

Standard 35mm width used widely in industrial control systems

PLC was designed to mount onto this type of rail

Power supply and terminal blocks also mount to it

Page 12: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Centralized Signal Testing

Over 70 signals are required for the PLC to manage

Having terminal blocks gives a convenient location to test the signals

Mounting them onto the din rail gives a clean look for the machine

Future manipulations of the machine will also be more convenient

Page 13: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Testing the Machine

Wire continuity was first check to ensure each component was properly connected

Each Input into the PLC was forced on to ensure each component was working properly

Feedback was compared between components and HMI Display

Page 14: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Set Point Feedback

• Pressure is required to stay within 10%

• Gas Flow Rate is required to stay within 1%

• RF Power is required to stay within 5%

Page 15: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

PLC Operational Flow Chart

Page 16: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

HMI Screen Capture

Page 17: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Recipe Input Capture

Page 18: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Power Input Capture

Page 19: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Coding Challenges Working with new programs and languages:

– RSLogix5000 with Ladder Logic– FactoryTalk View Studio

Interfacing with analog, digital, and serial connections

Inability to test and debug software before machine was fully assembled

Not able to implement “Trending” function due to time constraints

Page 20: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Subsystems Interaction

Subsystems need a way to interact with each other and PLC

Require customized cables

Page 21: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Problems with Pneumatics

Problem: No Documentation

Solution: Called Technical Support

Problem: Solenoid was not working properly

Solution: Craig Fox came out to

help solve the problems

Page 22: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Problems with RF Power

Problem: RF Power would not respond

Solution: Called Tech Support to resolve problem

Problem: High Power could not be achieved

Solution: Replaced RF Power Supply

Page 23: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Budget and Cost

Project is exclusively design for Ga Tech NRC and cannot be used for mass production

Parts were donated, salvaged, and funded by:– Ga Tech NRC– Rockwell Automation

A conservative estimate cost of $135,000 including hardware and labor/testing for completed project

Page 24: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Cost Breakdown

Labor & Testing Assume average GT ECE

graduate earns $65K annually

Project includes 5 design and implementation members

Estimated labor and testing of $100K

Hardware

Plasma Chamber $2,500

RF Power Supply $6,500

Frame $2,000

MFC x4 $8,000

Throttle Valve $5,000

• Major components

Page 25: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Future Work: Intended Machine Use

M. Bakir 2008

Options: •Deep UV lithography•Electron Beam Lithography•FEL/ARLP X-Ray Lithography•Nano Imprint Lithography

Page 26: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Topographic negative of structure will will be constructed with electron beam lithographyOrganic Gas will deposit non stick polymer on moldMold will be used as press to relief desired structureAntistick coating will have to be reapplied after several uses (~3)

Future Work: Additional Machine Use

Page 27: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Future Work: Diagnostic and Expansion

•Plasma Density Test •Additional internal real estate available:

•MFCs•Turbo•Heating System•Magnetic field module

Page 28: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Video Demonstration

Page 29: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.

Questions or Comments?

Page 30: Digital PECVD Machine Design and Construction Zlatan Ceric William Edwards Timothy Gurtler David Ogden Quan Tran Date:12/10/2010.