The Township Center Project - 2020 Daily Diary 07-17-2020 Page 1 SUBJECT: DAILY DIARY July 17, 2020 WEATHER: 80’s degrees, sunny. WORK DAY = 30. E. P. DOYLE: On-Site Tony all day. ENGINEERING SOLUTIONS TEAM: Ed on-site on and off. PREMIUM CONCRETE: Dustin + 2. on-site today. WALKER: Jose +1 on-site today. WATER PROOFING: 1 on-site today. Activities Today: • Premium worked on punch-list items today. • Walker on-site to establish the final sub-base finish grade for the basement. • Water proofer on-site to work on the elevator and the northeast corner. Activities Monday: • Concrete for the remaining basement walls is scheduled for Monday. Critical Path: • Status of Com Ed Truck and potential bracing? • Construction and delivery of the pre-cast floor planks. Pending Items: • How to backfill the NE corner of the building? Please advise if there are questions or if I missed anything. Thank you. Notes by Ed Kalina. / Please advise if there are any further thoughts or questions.