1 CORPORATE PRESENTATION June 10-12, 2014 CANADA’S INTERMEDIATE GOLD PRODUCER
Jun 19, 2015
1
CORPORATE PRESENTATION
June 10-12, 2014
CANADA’S INTERMEDIATE GOLD PRODUCER
2
Forward Looking Information This presentation contains certain forward-looking information and statements as defined in applicable securities law (referred to herein as
“forward-looking statements”). Forward-looking statements include, but are not limited to, statements with respect to Detour Gold’s future
financial or operating performance; guidance for production, total cash costs, capital costs, exploration costs; expected throughput, mining
and recovery rates; expected future production and mining activities; opportunities to optimize the mine operation; the updated mine plan
and economic analysis of the Detour Lake mine including, but not limited to, the life of mine plan, the waste to ore ratio, processing and
production rates, grades, metallurgical recovery rates, operating and sustaining capital costs, and the projected life of mine, opportunities to
optimize the mine operation; the success and continuation of exploration activities, the future price of gold, reclamation obligations,
government regulations and environmental risks.
Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause actual results, performance
or achievements to be materially different from any of its future results, performance or achievements expressed or implied by forward-
looking statements. These risks, uncertainties and other factors include, but are not limited to, assumptions and parameters underlying the
life of mine update not being realized, a decrease in the future gold price, discrepancies between actual and estimated production, changes
in costs (including labour, supplies, fuel and equipment), changes to tax rates; environmental compliance and changes in environmental
legislation and regulation, exchange rate fluctuations, general economic conditions and other risks involved in the gold exploration and
development industry, as well as those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour
Gold’s 2013 AIF and in the continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com.
Such forward-looking statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to,
assumptions about the following: the availability of financing for exploration and development activities; operating and sustaining capital
costs; the Company’s ability to attract and retain skilled staff; sensitivity to metal prices and other sensitivities; the supply and demand for,
and the level and volatility of the price of, gold; the supply and availability of consumables and services; the exchange rates of the Canadian
dollar to the U.S. dollar; energy and fuel costs; the accuracy of reserve and resource estimates and the assumptions on which the reserve
and resource estimates are based; market competition; ongoing relations with employees and impacted communities and general business
and economic conditions. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking
statements contained herein are made as of the date hereof, or such other date or dates specified in such statements.
All forward-looking statements in this presentation are necessarily based on opinions and estimates made as of the date such statements
are made and are subject to important risk factors and uncertainties, many of which cannot be controlled or predicted. Detour Gold and the
Qualified Persons who authored the associated Technical Report undertake no obligation to update publicly or otherwise revise any
forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be
required by law.
3
Notes to Investors
The mineral reserve and resource estimates reported in this presentation were prepared in accordance with Canadian National Instrument 43-
101Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities regulatory authorities. For United States reporting
purposes, the United States Securities and Exchange Commission (“SEC”) applies different standards in order to classify mineralization as a
reserve. In particular, while the terms “measured,” “indicated” and “inferred” mineral resources are required pursuant to NI 43-101, the SEC does
not recognize such terms. Canadian standards differ significantly from the requirements of the SEC. Investors are cautioned not to assume that
any part or all of the mineral deposits in these categories constitute or will ever be converted into reserves. In addition, “inferred” mineral resources
have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that
all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, issuers must not make
any disclosure of results of an economic analysis that includes inferred mineral resources, except in rare cases.
On February 4, 2014, Detour Gold announced an updated life of mine plan for the Detour Lake mine. The NI 43-101 compliant Technical Report for
this update was filed on SEDAR on February 4, 2014. The following QPs participated in this update: BBA Inc., under the direction of André Allaire,
Eng., Acting President and CEO and Patrice Live, Eng., Director Mining; SGS Canada Inc., under the direction of Yann Camus, Eng., Project
Engineer, and Maxime Dupéré, P.Geo., Senior Geologist; and AMEC Environment & Infrastructure, a Division of AMEC Americas Limited, David G.
Ritchie M.Eng., P.Eng, Senior Associate Geotechnical Engineer and Geotechnical Engineering Group Manager.
The scientific and technical content of this presentation has been reviewed, verified and approved by Drew Anwyll, P.Eng.,
Vice President of Operations, a Qualified Person as defined by Canadian Securities Administrators
National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.
Information Containing Estimates of Mineral Reserves and Resources
Non-IFRS Financial Performance Measures The Company has included “Total cash cost per gold ounce sold (TCC)” in this presentation which is non-IFRS measure. The Company believes
that these measures, in addition to conventional measures prepared in accordance with IFRS, provide investors an improved ability to evaluate the
underlying performance of the Company and its ability to generate operating earnings and cash flow from its mining operations. Refer to the MD&A
of March 31, 2014 or relevant period for reconciliation of these measures.
Detour Gold reports total cash costs on a sales basis. Total cash costs per gold ounce sold include production costs such as mining, processing,
refining, site administration, costs associated with providing royalty in-kind ounces, and costs for agreements with Aboriginal communities, but are
exclusive of depreciation and depletion, reclamation, non-cash share-based compensation and deferred stripping. Total cash costs are reduced by
silver sales and divided by gold ounces sold to arrive at total cash costs per gold ounce sold. Further details regarding total cash costs per gold
ounce sold and a reconciliation to the nearest IFRS measures are provided in our MD&A accompanying our financial statements filed on
www.sedar.com. Total cash costs plus capex per gold ounce sold includes TCC as calculated above plus sustaining capital and deferred stripping
divided by gold ounces sold. These non-IFRS measures are intended to provide additional information and should not be considered in isolation or
as a substitute for measures of performance prepared in accordance with IFRS. These measures do not have any standardized meaning
prescribed under IFRS, and therefore may not be comparable to other issuers. Other companies may calculate this measure differently.
4
Invest in Detour Gold
15.5 MILLION oz of gold
in proven and
probable reserves
600 average annual gold
production over next 10 years
~ THOUSAND oz / year 21
in mining-friendly
Ontario, Canada
+ YEAR mine life
A premier intermediate Canadian gold producer
and long-term investment opportunity
5
ONTARIO
Toronto
DETOUR LAKE MINE
Detour Lake mine investment thesis
Low-risk, safe mining jurisdiction
High-quality asset with long mine life
Production growth opportunities
Strong cash flow growth following ramp-up
completion
Leverage to gold price & weakening
Canadian dollar
Strong exploration upside on 100% owned
land package of 630 km2 on Greenstone Belt
Invest in Detour Gold
6
2014
INCREASE production
DECREASE costs
7
2014 Developments
22%
Positive developments to date:
Updated Life of Mine Plan
Closed equity financing for net
proceeds of US$149 million
Repaid US$40 million of debt in Q1
Secured 6-year power contract at
C$0.05/kWh
Q1 production of 107,154 oz
Next Milestones:
Complete ramp-up of Detour Lake
Generate positive cash flows in H2
8
Steady state production
& optimization
Mill throughput rates gradually
increase to 55,000 tpd in Q4
Quarterly production increase
expected as mine ramps up:
› H1 = 200,000-225,000 oz
› H2 = 250,000-275,000 oz
50% of overall mill feed from
higher grade ore zones
19 MT ore milled
3.3:1 WASTE:ORE strip ratio
0.87 G/T AU head grade
92 % gold recovery
(1)
1. Includes 7% dilution at 0.20 g/t.
2014 Targets
2014 Operating Plan
9
2014 Guidance
450-500 estimated gold production
THOUSAND oz
US$800-900 estimated total cash costs
TCC per oz sold
US$131 estimated capital expenditures
MILLION capex
Other
US$19 M Corporate G&A
US$3 M Exploration program
3
1. Refer to the section on Non-IFRS Financial Performance Measures on slide 3 of this presentation.
2. The following price and cost assumptions were used to forecast 2014 production and costs: diesel fuel price of
C$0.95 per litre; power cost of C$0.05 per kilowatt hour; and exchange rate of $1US:$1.05C.
3. Includes deferred stripping costs of US$35 M.
1, 2
second year
of operation
2014
10
Q1 2014 Operating Results - Mine
Q1’14 Performance:
4.9 Mt ore mined; strip ratio 2.9:1
Total of 19.2 Mt mined vs 20.9 Mt
planned; shortfall due to:
› In-pit rehandling for pit development
› Three shovels in overburden/till
Avg. mining rates of 213,000 tpd
Run-of-mine stockpiles of 2.8 Mt @
0.78 g/t at Q1 end
Dilution reduced to 4.6%
Next steps:
Q2 mining rates: 220,000 to 230,000 tpd
Complete mine development by summer
to access higher grade ore for H2
Higher Productivity in Q3-Q4’14
Q1’13 Q2’13 Q3’13 Q1’14 Q4’13
OB tpd
Q1 54,000
Q2E 86,000
Q3E 30,000
Q4E 7,500
Q3-Q4: Reduce # of shovels in
overburden (OB)
Mining rates
to go up
significantly
11
Q1 & Q2 Focus = ‘Open’ the Pit
South Ramp
Mine Development:
Complete south-wall pushback and final south ramp this summer
Prepare for Campbell pit breakthrough (open the pit to the east)
12
Q1 2014 Operating Results - Mill Q1’14 Performance:
4.1 Mt ore processed @ 0.90 g/t Au
Mill availability 80% vs 82% budget
Throughput rates at 45,282 tpd
› Avg. last 30 days +51,000 tpd
Recovery rates as planned
Reduction in cyanide, SO2 and
grinding media consumptions
Next steps:
Further improve mill availability
› Q2E: 82-85% availability
Reach nameplate capacity of 55,000
tpd in Q4
0
1
2
3
4
5
Q1'13 Q2'13 Q3'13 Q4'13 Q1'14
1.0
0.8
0.2
0.0
0.4
0.6
To
nn
es
Mil
led
(M
t)
Q1’13 Q2’13 Q3’13 Q1’14 Q4’13
80 82 85 92 91
Mill production
He
ad
Gra
de
(g
/t A
u)
Recovery %
13
Q1 2014 Operating Results - Costs
Total Cash Costs:
Q1’14 Q4’13
Gold oz sold 84,560 oz 95,000 oz
TCC/ oz sold1 US$976/oz US$1,174/oz
Q1 Progress:
Higher unit mining costs as a result
of ex-pit tonnes shortfall
Unit processing costs under budget
with lower reagents consumption
$-
$5
$10
$15
$20
$25
$30
G&A $3.57/t G&A $4.13/t
Processing
$11.13/t
Processing
$11.75/t
Mining
$2.87/t
mined
Mining
$2.60/t
mined
$28.22/t $29.15/t
1. Refer to the section on Non-IFRS Financial Performance Measures on slide 3 of this presentation.
Unit Costs (C$/t milled)
Q4’13 Q1’14
Next steps:
Downward trend to continue with
throughput and production increase
Total Cash Costs
$0
14
Strengthened Balance Sheet
Targeting $100 M cash at year-end 2014
› Cash & short-term investments of US$145.2 M at end of Q1
Increasing production profile in H2
Targeting reduction in debt levels in current gold price
environment
› US$80-100 M for the year
› US$40 M repaid in Q1
› CAT lease amortizations to add US$15 M in (Q3/Q4)
› Sculpt remaining pre-payments based on cash availability,
but retaining appropriate liquidity
Financial Review – 2014 Objectives
15
Gold hedge program
Tool used in 2014 to add protection
during the final ramp-up period
Policy only applicable to 2014 (up to
50% of gold ounces sold)
› 90,000 oz hedged at US$1,258/oz
› Management will determine in
Q3 if an extension is warranted
for Board approval
Price Protection During Ramp-up
16
NEAR-TERM
OPPORTUNITIES & Exploration Potential
17
Near-term Opportunities (2-5 yrs)
1. Increase throughput to 61,000 tpd for 2017
› Starts in 2014 with installation of 1
cyanide detox tank and 1 additional
oxygen plant
2. Block A project
› Bring to pre-feasibility study for reserve
definition in Q1 2015
3. Low-grade material (not in reserves)
› Heap leach
› Segregation of fines
4. Pebble circuit removal
5. Increase exploration activities on 630 km2
prospective property
18
TCC1
(C$/oz sold)
800
700
600
500
400
300
200
100
0
Gold Production
(‘000 oz)
Gold Production/Cost Profile
900
850
800
750
700
650
600
550
500
598,000 oz
C$759/oz
0.96 g/t
596,000 oz
C$762/oz
0.91 g/t
659,000 oz
C$778/oz
1.00 g/t
765,000 oz
C$639/oz
1.16 g/t
1. Refer to the section on Non-IFRS Financial Performance Measures on
slide 3 of this presentation.
600,000 oz/yr for first 10 yrs
19
Decouple PC and dome to
improve reliability Improve primary crusher
(PC) conveyor
Install 1 additional CN Detox
Add pumping capacities
Install 2nd oxygen plant
Opex down / availability up /
milling rate up
Reduce cyanide cost
Increase gold recovery
Install up to 4 additional
leach tanks
Increase or maintain gold
recovery; 61,000 tpd in 2017
Allow higher tonnage
58,000 tpd in 2016
(2014-17)
Projected
Costs:
C$45-65 M
H2
2014
2015
2016
2016?
2017?
Install another CN Detox 2015?
1. Throughput to 61,000 tpd
20
US$1,000/oz
US$1,200/oz
15.5 Moz
@ 1.02 g/t Au P+P
2.0 Moz
@ 1.15 g/t Au M+I
~5.5 km
Options being reviewed for:
› In-pit dumping and tailing deposition
› Best comingling options with Detour Lake
2. Block A Project
21
3&4. Low-grade Material & Pebbles
3. Currently stockpiling 0.4-0.5 g/t
mineralized material
Extra 1.5 M oz not accounted
for in LOM plan
Potential to process at end of
LOM - could easily cover closure
costs, even at US$1,200/oz gold
Evaluate potential for heap leach
and gold concentration by natural
segregation of fines
› Testing has started
4. Remove pebble circuit?
Pebbles appear to be barren
Reject pebbles and replace with
new feed?
Producing 700-800 tpoh of
pebbles. Replace with 40-60%
of new feed?
OR
pebbles
22
5. Exploration Focus – Lower Detour
Priority Target: Lower Detour area
Lower Detour area approx. 6-7 km south of mill
› Structural complexity: number of shear zones sub-parallel and
splaying from LDDZ
› Several gold mineralization styles encountered
2014 exploration program results:
› Mineralization extends for 450 metres
› High-grade gold intercepts in altered feldspar porphyry
intrusive containing quartz and/or quartz/tourmaline veins
› Results suggest that grade and continuity may improve at
depth
23
Lower Detour Area
15.5 M oz in Reserves
630 km2
5. Exploration Focus – Lower Detour
24
Lower Detour Area: 14,874 m of drilling completed in 2014
A B C
A’ B’ C’
5. Exploration Focus – Lower Detour
25
ADDITIONAL information
Shareholder Information
Analyst Coverage
Corporate Responsibility
Detour Lake Mine: LOM
Operating Costs
Detour Lake Mine: LOM
Sustaining Capital
Detour Gold: Reserves &
Resources
Derivative Instruments
Debt Repayment Schedule
Management & Directors
Contact Information
26
Shareholder Information
Paulson & Co.
>80% INSTITUTIONS TOTAL 11.2 M Share options
13.0 M Convertible notes 1
181.8 M FULLY DILUTED
157.6 M Issued & outstanding
Share Structure (03/31/2014) Top Shareholders
1. Conversion price for the Notes is US$38.50.
2. Cash position at March 31, 2014.
15%
C$1.7 BILLION market cap US$145.2 MILLION
cash position2
Share Structure (May 31, 2013) Top Shareholders
27
Analyst Coverage Initiating
Research Firm Analyst Target
at June 10, 2014
07.06.11 Haywood Kerry Smith $13.75
07.07.09 Paradigm Don Blyth/Don MacLean $14.50
07.08.07 Raymond James Phil Russo $16.00
07.11.26 National Bank Steve Parsons $14.00
07.12.20 Macquarie Mike Siperco $18.00
08.01.14 Canaccord Rahul Paul $11.00
08.07.14 TD Dan Earle $15.00
08.09.04 RBC Dan Rollins $16.00
08.11.06 BMO NB Brian Quast $15.00
09.06.17 Laurentian Eric Lemieux $10.75
10.05.19 CIBC World Markets Cosmos Chiu $14.00
10.07.22 Credit Suisse Anita Soni $12.00
13.04.16 Scotiabank Trevor Turnbull $17.00
13.08.14 Desjardins Michael Parkin $15.00
13.11.12 Beacon Securities Michael Curran $13.00
13.12.09 GMP Securities Ian Parkinson $13.50
14.02.06 Cormark Securities Richard Gray $15.00
14.04.22 Goldman Sachs Andrew Quail $10.50
Average target $14.00
28
Focus on health and safety of our employees, the well-being of
our community and the protection of the natural environment
Hiring in the region, giving priority to local Aboriginal communities:
670 full-time employees*
92% of workforce from region
23% are Aboriginals
Scholarship and job training
Supporting local communities
Business opportunities
Participation in municipal development
Corporate philanthropy
Northern
Ontario
39%
Cochrane
22%
Cochrane
Area
31% Rest of
Ontario
4%
4% Other
Corporate Responsibility
WORKFORCE ORIGIN
* At April 30, 2014. Excludes corporate office at 34 full-time employees.
29
LOM Plan 02/2014
Update
Proven & Probable Reserves (M oz) 1 15.5
Gold grade (g/t) 1.02
Strip ratio (waste:ore) 3.5
Estimated gold recovery (%) 92
Mine life (years) 21.7
Annual gold production (oz) 660,000
Total cash costs (TCC) (C$/oz sold) 2 $723
Sustaining capital (C$ billion) $1.14
TCC + capex (C$/oz sold) 2 $848
LOM Summary
1. Estimated using a gold price of US$1,000/oz. Includes stockpiles as of December 31, 2013.
2. Refer to the section on Non-IFRS Performance Measures on slide 3. Capex = sustaining capital expenditures + deferred stripping.
Main objective: Optimize first 5 years
30
09/12 02/14
Operating Costs C$/t
milled
C$/t
milled
C$/t
mined
C$/oz
sold 2
Mining costs 11.65 11.55 2.56 392
Processing costs 7.83 7.82 266
G&A 1.86 2.44 83
Total cash
operating costs 21.34 21.81 741
Other adjustments 1 (18)
Total cash costs 723
30
LOM Operating Costs
1. Other adjustments include costs for deferred stripping, agreements with Aboriginal communities, refining charges and are net
of silver by-product credits.
2. Refer to the section on Non-IFRS Financial Performance Measures on slide 3 of this presentation.
Maintenance
Labour &
Contractors Power
Diesel
G&A and
other
Consumables
30%
20%
26%
7%
11%
6%
2014 COSTS:
80% of costs in Cdn$
31
LOM Sustaining Capital
Description
5 years
2014 -2018
(C$ M)
Sustaining
Capital LOM
(C$ M)
Mining 168 1 535
Process Plant 71 2 126
TMA 203 3 454
G&A 14 28
Total 456 1,143
Deferred Stripping 225 614
Mine Closure 70
Higher capital in first 5 years:
1. Ramp-up to 38 trucks
2. Complete plant debottlenecking exercise
3. Prepare TMA foundation for 2nd and 3rd cell
50% of sustaining
capital costs in Cdn$
Mine
US$33 M
TMA
US$40 M Deferred
Stripping
US$35 M
2014 SUSTAINING CAPITAL: US$131 M
Other
US$5 M Mill
US$18 M
32
Effective December 31, 2013 Tonnes (Mt) Grade (g/t Au) Contained Gold
(koz)
Reserves
(1,2,3,4)
Detour Lake Mine Proven 94.4 1.29 3,901
Probable 379.7 0.95 11,585
P&P 474.0 1.02 15,486
Stockpiles 2.4 0.82 63
Total P&P 476.4 1.02 15,549
Resources (3,4)
Detour Lake Mine Measured (M) 16.4 1.37 725
Indicated (I) 65.9 1.01 2,150
M+I 82.4 1.09 2,874
Block A Measured (M) 1.5 1.21 57
Indicated (I) 52.5 1.15 1,934
M+I 53.9 1.15 1,991
Total M+I 136.3 1.11 4,866
Detour Lake Mine Inferred 19.2 0.75 465
Block A Inferred 2.5 1.23 99
Total Inferred 21.7 0.81 564
Detour Gold: Reserves & Resources
1. Mineral reserves calculated using a gold price of US$1,000/oz; mineral resources calculated using US$1,200/oz. Foreign exchange rate of
C$1.03 to US$1.00.
2. Mineral reserves estimated using a 4% dilution at 0.20 g/t Au (7% at 0.20 g/t Au for 2014) and 5% ore loss.
3. Based on an elevated cut-off grade of 0.5 g/t Au for Detour Lake and cut-off grade of 0.6 g/t Au for Block A.
4. Mineral resources are exclusive of mineral reserves. Mineral resources that are not mineral reserves do not have
demonstrated economic viability. Mineral reserves and resources are compliant with
CIM definitions.
33
Derivative Instruments
Currency Contracts at April 30, 2014 Ounces Notional Amount
US ‘000s
Contract
Rate/Price
Currency Collars $20,000 1.040
Currency Forwards (USD/CAD) $40,000 1.122
Total Derivative Assets $60,000
Currency Collars $20,000 1.085
Gold forwards 30,000 Cdn$1,329/oz
Gold forwards 85,000 US$1,273/oz
Total Derivative Liabilities 115,000 $20,000 US$1,256/oz1
January 2014 commenced gold sales risk management program;
continued FX risk management program throughout Q1
Hedging gains and losses are recorded in net finance income/costs
1. Using exchange rate of $1US:$1.10C.
34
Debt Repayment Schedule
At March 31, 2014 Revolving Credit
Facility (1) CAT Finance Lease Convertible Notes
Face Value US$30 M (1) US$150 M US$500 M
Maturity March 2016 Jan 2017-Dec 2018 (2) November 30, 2017
Interest Rate LIBOR + 3% LIBOR + 4% 5.5%
Payable Monthly Quarterly Semi-annually
Conversion Price n/a n/a $38.50
Payment schedule Principal Principal + Interest Principal Interest Total
(US$M)
2014 - $11.1 - $27.5 $38.6
2015 - $34.5 - $27.5 $62.0
2016 $30 $32.6 - $27.5 $90.1
2017 - $35.8 $500 $27.5 $563.3
Thereafter - $7.1 - - $7.1
Total (US$M) $30 $121.1 $500 $110.0 $761.1
1. The Revolving Credit Facility provides for borrowings of up to C$90 M and is subject to a completion test prior to September 30, 2014.
The Company intends to repay the Revolving Credit Facility within the next 12 months.
2. Includes multiple leases with maturities of 5 yrs from lease date.
35
Michael Kenyon Executive Chairman
Paul Martin President and CEO
Pierre Beaudoin COO
James Mavor CFO
Julie Galloway Sr VP General Counsel &
Corporate Secretary
Derek Teevan Sr VP Corporate &
Aboriginal Affairs
Drew Anwyll VP Operations
Pat Donovan VP Corporate Development
Jean-Francois Metail VP Reserves and Resources
Rachel Pineault VP HR & Aboriginal Affairs
James Robertson VP Environment &
Sustainability
Andrew Croal Director Technical Services
Laurie Gaborit Director Investor Relations
Alberto Heredia Controller
Bill Snelling Director Corporate Systems & Controls
Rickardo Welyhorsky Director Mineral Processing
Charles Hennessey General Manager Operations
Peter Crossgrove
Louis Dionne
Robert E. Doyle
André Falzon
Alex G. Morrison
Jonathan Rubenstein
Graham Wozniak
Ingrid Hibbard
Michael Kenyon
Paul Martin
Management & Directors
Management
Directors
36
Laurie Gaborit Director Investor Relations
Email: [email protected]
Phone: 416.304.0581
Paul Martin President and Chief Executive Officer
Email: [email protected]
Phone: 416.304.0800
www.detourgold.com
Contact Information