Development Programs
1. Annual Development Program (ADP) 2019-20
2. Community Development Program (CDP) 2018-19
3. Rural Accessibility Program (RAP) 2018-19
4. SDG Achievement Program (SAP) 2018-19
3
Annual Development Program
(2019-20)
ABSTRACT OF ON-GOING ADP (2019-20)
Sr.
NoSector
Executing
Agency
No
. o
f
Sc
he
me
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)Released
(2019-20)
Exp.
Upto
Date
Fin
an
cia
l
%
Cumu-
lative
Exp.
No. of
Schemes
Completed
1Sports & Youth
AffairsPMU
(Sports) 02 172.000 82.765 89.906 10.000 1.826 18% 84.591 --
2 HealthC&W
(Buildings) 01 72.247 34.131 4.466 1.117 0.815 73% 34.946 01
3Water Supply &
SanitationPHED 10 358.967 200.625 93.983 24.701 23.992 97% 224.617 --
4 Social WelfareC&W
(Buildings) 01 36.658 37.015 0.800 0.800 0.800 100% 37.815 01
5 LG&CD (Roads)XEN
LG&CD
Multan02 36.000 16.355 16.500 16.500 11.606 70% 27.961 02
6 RoadsC&W
(Highways) 08 10185.482 6194.347 489.146 246.984 245.484 99% 6439.831 03
7 Public BuildingsC&W
(Buildings) 01 1328.463 1263.385 65.078 30.000 30.000 100% 1293.385 01
SUB TOTAL (On-Going) 25 12189.82 7828.623 759.879 330.102 314.523 95% 8143.146 08
ABSTRACT OF NEW ADP (2019-20)
Summary of
Un-Approved
Scheme
Forum Sector Schemes
DDSC Public Buildings 01
Sr.
NoSector
Executing
Agency
No
. o
f
Sc
he
me
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Fin
an
cia
l
%
Cumu-
lative
Exp.
No. of
Schemes
Completed
1Higher
EducationC&W
(Buildings)01 34.623 --- 20.486 --- --- 0% --- ---
2Sports & Youth
AffairsPMU
Sports 01 69.498 --- 60.000 --- --- 0% --- ---
3 HealthC&W
(Buildings)01 23.892 --- 10.000 --- --- 0% --- ---
4 LG&CD (Roads)XEN
LG&CD
Multan02 27.264 --- 19.264 --- --- 0% --- ---
5 Roads C&W(Highways)
03 2233.649 --- 128.000 12.000 --- 0% --- ---
6 Public BuildingsC&W
(Buildings)02 30.000 --- 10.500 --- --- 0% --- ---
7Livestock & Dairy
DevelopmentC&W
(Buildings)01 300.000 --- 300.000 --- --- 0% --- ---
SUB TOTAL (New) 11 2718.926 --- 543.250 12.000 --- 0% --- ---
GRAND TOTAL 36 14908.75 7828.623 1308.129 342.102 314.523 92% 8143.146 07
ON-GOING PROVINCIAL ADP (2019-20)
Sr.
No
ADP
No.Name of Scheme
Executing
Agency
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Financial
%
Cumu-
lative
Exp.
Overall
Physical
%
Remarks
SPORTS & YOUTH AFFAIRS SECTOR (On-Going)
1 401
Establishment of NewStadium at DunyapurDistrict Lodhran
Project
Manageme
nt Unit
(PMU),
Sports
Board,
Lahore
77.000 26.557 52.168 5.000 1.826 37% 28.383 45% Work is in
progress.
Remaining
funds awaited
by FD.2 402
Establishment of NewStadium at KehrorPacca District Lodhran.
95.000R: 40.0
C: 16.2
T: 56.237.738 5.000 0.000 0% 56.208 35%
HEALTH SECTOR (On-Going)
3 703
Conversion of Existing oldDHQ Hospital Lodhran toFamily Hospital for Femaleand Children, Lodhran
C&W(Buildings)
72.247 34.131C: 4.466
R: 7.503
T:11.9691.117 0.815 73% 34.946 98%
Minor finishingunder progress.Procurement ofRevenuecomponent isunder process.
WATER SUPPLY & SANITATION SECTOR (On-Going)
4 1181
Water Supply DeraDogran Bhutta ColonyRukn Deen Pur, DistrictLodhran
PHED 39.263 20.138 10.00 2.500 2.500 100% 22.638 73%Work is in Progress.
5 1182
Water Supply SchemeKotli Wajjwah, DistrictLodhran
PHED 37.175 16.767 10.000 2.500 2.500 100% 19.267 68%Work is in Progress.
6 1183
Water Supply SchemeHaifzaabad DunyapurGharbi Remainig PortionDunyapur Sharqi, DistrictLodhran
PHED 49.805 24.218 10.000 2.500 2.500 100% 26.718 70%Work is in Progress.
ON-GOING PROVINCIAL ADP (2019-20)Sr.
No
ADP
No.Name of Scheme
Executing
Agency
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Financial
%
Cumu-
lative
Exp.
Overall
Physical
%
Remarks
7 1184
Water Supply Scheme inChak No.358/Wb DistrictLodhran
PHED 26.334 14.065 12.258 2.00 1.890 95% 15.955 71% Work is in Progress.
8 1185
Water Supply Scheme inChak No.13/M DistrictLodhran
PHED 28.934 14.654 12.274 2.855 2.855 100% 17.509 72% Work is in Progress.
9 2119water Supply / SewerageMouza Rawani.
PHED 29.450 25.463 3.977 3.977 3.700 93% 29.163 99% Under test operation.
10 2120
Rural water Supply SchemeChak No.12/M & 14/M (East& West) Tehsil Dunyapur,District Lodhran
PHED 29.922 23.526 6.388 1.597 1.597 100% 25.123 96%Scheme under test operation.
11 2121
Water Supply Scheme inChak No.359/Wb DistrictLodhran
PHED 19.309 12.215 7.086 1.772 1.750 99% 13.965 84% Work is in Progress.
12 2122
Water Supply Scheme inChak No.311/Wb DistrictLodhran
PHED 36.605 16.506 10.00 2.500 2.300 92% 18.806 66% Work is in Progress.
13 2325
Sewerage, Tuff Tiles inRemaining Portion of GailyWal City.
PHED 62.170 33.073 10.00 2.500 2.400 96% 35.473 77%
Work in Progress.Request made by XENPHED, Lodhran toCommissioner, Multanfor having NOC forLodhran-Shujabad roadcrossing through 15”dia RCC sewer.
SOCIAL WELFARE SECTOR (On-Going)
14 2551Construction of Building ofShelter Home at Lodhran.
C&W
(Buildings)36.658 37.015 0.800 0.800 0.800 100% 37.815 100%
Work completed and
handed over.
ON-GOING PROVINCIAL ADP (2019-20)
Sr.
No
ADP
No.Name of Scheme
Executing
Agency
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Financial
%
Cumu-
lative
Exp.
Overall
Physic
al
%
Remarks
LG&CD SECTOR (On-Going)
15 2649
Repair of Road alongwithBahishti Canal from Chak 45-M to N-5 (Bridge Bazari) 11km, District Lodhran
LG&CD 16.000 6.775 6.500 6.500 2.735 42% 9.511100
%Physically workcompleted.
16 2650
Repair of road alongwithCanal Gopal from N-5 bridgeGopal to Noor Shah Gillani,12 km, District Lodhran
LG&CD 20.000 9.580 10.000 10.000 8.871 89% 18.451100
%Physically work completed.
ROADS SECTOR (On-Going)
17 3052
Dualization of KhanewalLodhran Road Km No. 51.00to 94.00, Length 43.00 Kms.
C&W(Highways)
7684.917 5830.972 10.000 2.500 2.500 100% 5833.472 100% Work completed
18 3053Const: of Dhanote Bye Passroad, Length = 7.80 K.m
C&W(Highways)
120.011 11.003 5.000 5.000 5.000 100% 16.003 25% Work in progress
19 3054
Dualization of metalled roadfrom Girls College Chowk toKehror Pacca Chowk viaKazmi Chowk, Length 2.00Km.
C&W(Highways)
96.467 43.967 23.750 11.876 11.876 100% 55.843 90% Work in progress
20 3055
Widening / Improvement ofMetalled Road from THQKehror Pacca to Hasilwala,L=17.75 Km
C&W(Highways)
315.455 102.500 150.000 75.000 75.00 100% 177.500 90%
Group-IWork in progressGroup-IIWork completed.
ON-GOING PROVINCIAL ADP (2019-20)
Sr.
No
ADP
No.Name of Scheme
Executing
Agency
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Financial
%
Cumu-
lative
Exp.
Overall
Physic
al
%
Remarks
21 3056
Widening / Improvement ofroad from Lodhran toJalalpur-Pirwala connectingKLM via Bahadurpur, Length39.80 Km, District Lodhran
C&W(Highways)
1565.660 --- 286.576 143.288 143.288 100% 143.288 30%Work inprogress.
22 3646
Dunyapur Mailsi road fromHead Karianwala to Sardarpur Jhandir via Chowki SobayKhan and Manjha Kotla(Length = 18 Km)
C&W(Highways)
179.966 72.948 6.000 1.500 --- 0% 72.948100
%
Part-AWork completed.Part-BPC-I is Submitted toCE (South) on27.08.19 amountingto Rs. 179.958Million for approval.
23 3647
Dualization of LodhranKehror Pacca Road(Length=30 KM) DistrictLodhran (Phase-I 10 KM)
C&W(Highways)
199.999 113.557 4.000 4.000 4.000 100% 117.557 75%Work in progress
24 3648
Widening / Improvement ofKPR/Metalled road from N-5at Chak No.366/WB toDunyapur via Khagay walaLength =22.00 K.m DistrictLodhran (Phase-I K.m No.0.00 to 1.60 Km)
C&W(Highways)
23.007 19.40 3.820 3.820 3.820 100% 23.220100
%
Work completed.
PUBLIC BUILDINGS SECTOR (On-Going)
25 4320Construction of DistrictJail Lodhran
C&W(Buildings)
1328.4631263.
38565.078 30.000 30.000 100%
1293.
38598%
Work completed.
NEW PROVINCIAL ADP (2019-20)
Sr.
No
ADP
No.Name of Scheme
Executing
Agency
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Financial
%
Cumu-
lative
Exp.
Overall
Physical
%
Remarks
HIGHER EDUCATION SECTOR (New)
26 262
Provision of MissingFacilities at Govt.Degree College forWomen, Lodhran
C&W(Buildings)
C: 31.792R: 2.831T: 34.623
--- 20.486 --- --- 0% --- 0%
Tenders invited
on 24.10.2019
and under
process.
Funds awaited.
SPORTS & YOUTH AFFAIRS SECTOR (New)
27 507
Tehsil Sports Complexat Dunyapur, DistrictLodhran.
PMU Sports
69.498 --- 60.000 --- --- 0% --- 0%
DDSC:
28.08.2019.
AA:
06.11.2019
Tender:
10.12.2019
Funds awaited.
HEALTH SECTOR (New)
28 753
Establishment of
Dialysis Unit at THQ
Hospital Dunyapur
District Lodhran
C&W
(Buildings)
C: 16.531R: 7.361T: 23.892
--- 10.000 --- --- 0% --- 0%
The scheme
approved by
DDC on
24.10.2019.
Tender under
process.
NEW PROVINCIAL ADP (2019-20)Sr.
No
ADP
No.Name of Scheme
Executing
Agency
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Financial
%
Cumu-
lative
Exp.
Overall
Physical
%
Remarks
LG&CD SECTOR (New)
29 2710
Improvement / Repair forMetalled Road BastiMalook to Dunyapur Road,Adda Chak No. 356/WB toChak No. 354/WB, DistrictLodhran.
LG&CD 9.264 --- 9.264 --- --- 0% --- 0%
Schemes approvedby DDC on25.07.2019.Tender opened on17.09.2019 andunder process.Funds awaited byFD.
30 2714
Construction of M/R fromJora Mogha to 390/W.B via388/W.B, District Lodhran.
LG&CD 18.000 --- 10.000 --- --- 0% --- 0%
ROADS SECTOR (New)
31 3983
Dualization of LodhranKehror Pacca, Malsi VehariRoad District Lodhran(Phase-II) Remaining 20Km
C&W(Highways)
2025.649 --- 30.000 --- --- 0% --- 0%
Scheme approved
on 28.10.2019.
Detail Estimate
submitted to Chief
Engineer (South)
Highway, Lahore for
Technical sanction.
32 3984
Rehabilitation / Repair ofmetalled road fromMundhali Mor to ChowkMughal wala via Pul BaghWali. Length:12:00 Km
C&W(Highways)
48.000 --- 48.000 12.00 --- 0% --- 0%Work in
progress
33 3985
Carpeting of metalled road
from Lodhran Kehror Pacca
road Adda Daftar Chowk
via Danwran, Raja Pur,
Thathi Sameja to Lodhran
Khanewal Road N-5,
Length:10:00 Km
C&W(Highways) 160.000 --- 50.000 --- --- 0% --- 0%
Tender opened
on 07.11.2019.
Issuance of
Work order is
under process.
NEW PROVINCIAL ADP (2019-20)
Sr.
No
ADP
No.Name of Scheme
Executing
Agency
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Released
(2019-20)
Exp.
Upto
Date
Financial
%
Cumu-
lative
Exp.
Overall
Physical
%
Remarks
PUBLIC BUILDINGS SECTOR (New)
34 4278
Construction ofAssistant CommissionerOffice & Residence atTehsil Kehror Pacca,District Lodhran
C&W
(Buildings) 15.000 --- 7.000 --- --- 0% --- 0%
Tenders invited on
24.10.2019 & under
process.
Funds awaited.
35 4606
Construction ofBuilding for the officeof District PublicProsecutor Lodhran
C&W
(Buildings)
15.000Un/App.
--- 3.500 --- --- 0% --- 0%
The RCE estimate
amounting to
Rs.14.991 million
again submitted to
District Public
Prosecutor Lodhran
on 22.10.2019 for
arranging A.A and
funds.
LIVESTOCK & DAIRY DEVELOPMENT SECTOR (New)
36 4949
Strengthening ofVeterinary Servicesat Union CouncilLevel in DistrictsLodhran
C&W(Buildings)
300.000 --- 300.00 --- --- 0% --- 0%
Scheme approved
by Secretary,
L&DD Department
on 04.11.2019.
13
COMMUNITY DEVELOPMENT PROGRAM (CDP)
(2018-19)
ABSTRACT OF COMMUNITY DEVELOPMENT PROGRAM (CDP)
FOR THE YEAR 2018-19
14
Co
ns
tituen
cy
Executing
AgencyNo. of
Scheme
Approved
Cost
Exp.
Up to
06-2019
Allocation
(2019-20)
Release
(2019-20)Exp.
Financial
%
Physical
%
Cumulat
ive
Exp.
Scheem
Compl-
etedRemarks
PP
-22
4
C&W(Highways)
10 100.00 50.00 50.000 27.14 24.212 89% 90%74.21
210
Tender: 16.04.2019Work Order issued:
06.05.2019
Physically all works
Completed with saving.
PP
-22
8
PHED 01 10.000 4.998 5.002 5.002 3.710 74% 92% 8.708 ---
Work is in progress. 2-Nos.
Electric connection installed.
Direction have been given to
contractor to make the scheme
operational at the earliest.
LG&CD 9 90.000 45.000 45.000 16.400 15.402 94% 96%60.40
207
Tender: 10.04.2019 &
23.05.2019
Work Order issued
: 09/23.05.2019
Work is in progress.
GRAND
TOTAL20 200.00 100.00 100.00 46.542 43.324 93%
143.3
2217
ABSTRACT OF SAVING SCHEMES UNDER CDP (2018-19)
15
Co
ns
tituen
cy
Executing
AgencyNo. of
Scheme
Approved
Cost
Allocation
(2019-20)
Release
(2019-20)Exp.
Financial
%
Physical
%
Scheem
Compl-
etedRemarks
PP
-224
C&W(Highways)
01 14.160 14.160 --- --- 0% 0% ---Tender of scheme will be
opened on 23.11.2019.
PHED 01 5.000 5.000 --- --- 0% 0% ---
Scheme was approved against
saving on 23.10.2019.
Tender will be opened on
14.11.2019.
PP
-228
LG&CD 01 12.660 12.660 --- --- 0% 0% ---
Scheme was approved against
saving on 23.10.2019.
Tender will be opened on
21.11.2019.
GRAND
TOTAL03 31.820 31.820 --- --- 0% 0% ---
16
RURAL ACCESSIBILITY PROGRAM (RAP)
(2018-19)
ABSTRACT OF RURAL ACCESSIBILITY PROGRAM (RAP)
(PHASE-I) 2018-19
17
Sr.
NoName of Road Tehsil Constituency
Approved
Cost
Exp.
Up to
06-2019
Funds
Release
2019-20
Exp.
During
2019-20
Cumulative
Exp.Remarks
1
Widening / Improvement of Road
10’ to 12’ from Pull 50/M Pull
Malanhas via Jugu Minor, Tehsil &
District Lodhran. Length=7.00 Km
Lo
dh
ran
PP
-22
8
NA
-16
1
93.962
5.000
290.00
Million
Block
133.00
Million
Block
138.000Work in
progress.
2
Construction / Rehabilitation of
Carpeted road from Basti
Werheela Jhok Imam Bukhash to
Basti Elahi Bakhsh Wala via Basti
Saidi Wala, Mouza Chutala, Tehsil
& District Lodhran. Length=5.20
Km.
Lo
dh
ran
PP
-22
7
NA
-16
1
69.732
3
Widening / Improvement of road
10’ to 12’ from Jallah Arain, Ghani
Chowk to Chak No.365/WB via
Ibrahim Wala, Tehsil Dunyapur,
District Lodhran. Length=710 Km.
Du
nya
pu
r
PP
-22
4
NA
-16
1
95.208
4
Widening / Improvement of road
10’ to 12’ from Skindari More to
Pull 343/WB, Dunyapur–Basti
Malook road via Chak No.360/WB,
Chak No.359/WB and Chak
No.344/WB, Tehsil Dunyapur,
District Lodhran. Length=7.90 Km.D
un
ya
pu
r
PP
-22
4
NA
-16
1
105.902
GRAND TOTAL 364.804 5.000 290.00 133.00 138.00
ABSTRACT OF RURAL ACCESSIBILITY PROGRAM (RAP)
(PHASE-II) 2019-20
18
Sr.
NoName of Road Tehsil Constituency
Estimated
CostRemarks
1
Carpeting / Widening / Rehabilitation of
metaled road 10' to 12' from Jalal Pur Peer
Wala road Pacca Munna via Basti Saifal
Khan to Pull Bugrain, Length 6.50 Km,
Tehsil & District Lodhran
Lo
dh
ran
PP
-22
8
NA
-16
1
96.700
Schemes have been identified and
submitted to the Commissioner
Office on 25.10.2019 for clearance
by Divisional Coordination
Committee (DCC).
Later on, the cleared schemes by
DCC will be forwarded by the
Commissioner to Secretary, C&W
Department for further necessary
action.
2
Carpeting / Widening / Rehabilitation of
metaled road 10' to 12' from Adda Sikandari
(Amina School) via Mujahid Abad Station,
Chak 49/M to Mouza Sikandar Pur More,
Length 5.00 Km, Tehsil & District Lodhran.
Lo
dh
ran
PP
-22
7
NA
-16
1
71.500
3
Carpeting / Widening / Rehabilitation /
Construction of Road 10' to 12' from Chak
No 344/WB, to Pull Chak No. 341/WB Basti
Balochan Wali via Pull Chak No. 343/WB,
Length 7.00 Km, Tehsil Dunyapur, District
Lodhran.
Du
nya
pu
r
PP
-22
4
NA
-16
1109.00
4
Construction of Carpet Road 12’ wide from
Chak No. 43/M to Chak No. 34/M including
link Chak No. 42/M (Missing Link) Length
5.50 Km, Tehsil Dunyapur, District Lodhran.
Du
nya
pu
r
PP
-22
4
NA
-16
1
90.000
GRAND TOTAL 367.200
19
PRIME MINISTER’s SUSTAINABLE
DEVELOPMENT GOALS ACHIEVEMENT
PROGRAM (SAP)
(2018-19)
ABSTRACT OF PM’s SDG ACHIEVEMENT PROGRAM (SAP) FOR THE
YEAR 2018-19
20
Co
ns
tit
uen
cy
Executing
Agency
No. of
Scheme
Approved
Cost
Allocation
(2019-20)
Release
(2019-20)Exp.
Financial
%
Physical
%
No. of
Scheme
CompletedRemarks
NA
-16
1
C&W
(Highways)02 42.148 42.148 42.190 3.389 8% 55% --- Works in progress.
PHED 01 5.600 5.600 5.600 1.426 25% 45% --- Work in progress.
Village
Electrification
(MEPCO)136 102.100 102.100 102.10 102.10 100% 15% ---
Schemes approved on
05.08.2019 by PD,
MEPCO, Multan.
Cheque has been
issued on 20.08.2019.
Work in progress.
GRAND TOTAL 139 150.00 150.00 150.00106.91
571% ---