Developing Natural Gas Infrastructure in the Americas: the Mexican case NARUC Committee on Gas Francisco Salazar Diez de Sollano Chairman, CRE July 17, 2007
Developing Natural Gas Infrastructure in the Americas: the
Mexican case
NARUC Committee on Gas
Francisco Salazar Diez de SollanoChairman, CRE
July 17, 2007
Introduction: CRE
• CRE (Comisión Reguladora de Energía) was created in 1992 as a consulting body to the Secretary of Energy. Its objective was to prepare the rules that would regulate the relationship between the State’s utilities and the private investors in the power sector.
• In 1995, the Congress passed a reform opening the downstream activities in the natural gas sector. Then, CRE was also constituted as the formal regulator of the energy sector and was given operational and technical autonomy.
• CRE’s mandate is to promote the efficient development of the activities it regulates. In doing so, CRE looks for a balance between the interest of the consumers and that of the investors.
CRE’s regulation powers
Reserved to the State Open to private investment Regulated by CRE
Generation
CFE & LFC
National Transmission
Grid
Third Parties Others
ImportsImports / Exports
Power
Natural Gas Exploration
Marketing
Production
Processing.PMX Sales Transpo
rtStorage Distributio
n
LPG
Marketing
Production ProcessingPMX
Sales
Transmission
Generation Transmission
Distribution
PipelinePipeline
Distribution
Surface transport. Bottle Distribution
Storage
Natural gas demand
• According to the Ministry of Energy(1), natural gas demand was 6.549 bcfd in 2006 .
• 48% corresponded to the oil sector; 35.7% to the power sector; 14.6% to the industry (including Pemex Petrochemicals), and 1.6% to residential and other services.
• Natural gas demand is expected to increase at an overall annual rate of 3.9% over the next 10 years.
(1) Prospectiva del mercado de gas natural 2006-2015
Natural gas forecast 2005-2015
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
MM
CFD
Demand
Supply
3.9 %
2.8 %
Source: SENER 2006 – 2015 Prospectiva del Mercado de Gas Natural
Gross NG Balance 2005-2015
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
BC
FD
PEMEX PMX Internal flows Industrial Electricity Residential Production
5.72
6.11 6.65 6.617.05 7.58
7.908.28 8.69
9.11 9.49
Natural gas for power plants
• Power forecasts 2005-2015– 4.8% annual demand growth rate from 191
TWh in 2005 to 305 TWh in 2015– 24 GW of new capacity required to meet
demand (approx. 49% of current capacity)– CFE will install 23,545 MW during the next
decade– Combined cycle power plants will grow from
33% to 51% of the total capacity by 2015• 7.3% average annual natural gas
growth over the next decade (for power)
Natural gas imports 2005-2015
0
500
1000
1500
2000
2500
2005 20062007 2008 2009 20102011 2012 20132014 2015
MM
CFD
Imports Exports Imports will peak by 2015 at 2.2 BCFD
Source: SENER 2006 – 2015 Prospectiva del Mercado de Gas Natural
How to face increasing demand?
• Continue promoting private investment in– Development of LNG terminals along both
the Pacific and the Gulf coasts– Pipeline infrastructure both to strengthen
cross-interconnections and access to new LNG plants
• Start exploiting coal bed methane reserves• Focus Pemex’s investment in areas of
paramount interest such as exploration and production of oil and gas
CRE’s regulation objective
CRE’s regulation must:• Ensure technical engineering excellence through
modern standards and third-party auditing procedures
• Approve general terms of service that satisfy user’s needs and reflect current practice in industry
• Approve rates that are competitive and allow fair rates of return to investors
• Lead to predictable and stable regulatory conditions with adequate flexibility
Permits granted by CRE
Type Licenses Length (km)
Capital
Investment (MM USD)
Transport 155 12,354 1,979
Open Access
20 11,501 1,744
Non-Open Access
135 853 235
Distribution 22 35,494 1,669
LNG terminals 5 n.a.* 2,000
TOTAL 182 47,848 5,648
* LNG total storage capacity of 1,250,000 cubic metres
Mexico’s natural gas transport network
GULF OF MEXICO
CA
RIB
BEA
N S
EA
ISLASMARIAS
PACIFIC OCEAN
NACO
SantaAna
Hermosillo
Guaymas
Anahuac
Chihuahua
Delicias
Cd.Camargo
Jiménez Químicadel Rey
Monclo
va
SaltilloTorreón
Gómez P.
SAN LUISPOTOSI
SalamancaGuadalajara
Uruapan
Morelia
Toluca
Tula
Pachuca
Puebla
Jalapa
PozaRica
Verac
ruz
T. BlancaC.P
.Q.
Paja
ritos
Minatitlán
Nvo. TeapaVillahermosa
C.P.Q.Cd. Pemex
Atasta
Campeche
MéridaTlalchinol
Cactus y Nuevo Pemex
C.P.Q
.
La V
enta
Qro.
Cd. Juárez
Cd.
Mendoza
Cd. Lerdo
L. Cárdenas
Matamoros
Piedras Negras
S.L. Río ColoradoMexicali
NuevoLaredo
Imports Imports
Imports
Imports
Cd. MaderoTampico
Cuernavaca
Escalón
Durango
Castaños
Cad
erey
ta
Hidalgo
Parras
Camarg
oPandura
MiguelAlemán
Sn. Fernando
CampoTam.
C.F.E.Colinas
C.P.Q.Poza R.
C.P.Q.Matapionchi
C.F.E. El Verde
ALTAMIRA
MAZATLAN
911
10 2
1 6
3
5
7
8M
onte
rrey
Sta. Ana
Valladolid
4
PRIVATE PIPELINES
Kinder MorganGasoductos de ChihuahuaIgasamex BajíoEnergía MayakánTejas Gas de TolucaFINSA EnergéticosTransportadora de Gas ZapataGasoductos del BajíoTransportadora de Gas Naturalde Baja CaliforniaDuctos de NogalesGasoducto BajaNorteSan FernandoGasoductos del RíoAgua PrietaConceptos Energéticos MexicanosTransportadora La HuastecaTejas Gas de la PenínsulaTerranova Energía
123456789
101112131415161718
AGUASCALIENTES
Nogales
Sn Juan
del Río
Cancún
Cananea
AguaPrieta
13
14
12
TAMAZUN
CHALE16
15
17
TOPOLOBAMPO
LEGENDPEMEX transmission systemPrivate open access Project under evaluation at CREFeasible projectFeasible LNG terminalCityNatural gas injection pointPetrochemical plant
MANZANILLO
230 km
LIBERTAD
18Reyno
sa
Zacatecas
Developing LNG terminals
• LNG project solutions are varied – Having a predictable and transparent regulation
gives investors and developers the flexibility to structure their projects in a variety of ways
– Terminal Developers (TD) can participate in acquisition of LNG through different schemes
– TD can sign long-term contracts with utilities and shippers and/or assign all or a fraction of the terminal capacity to a marketing function
– Shippers can arrange for their LNG deliveries or have the terminal/marketer do it.
– CRE has resolved all LNG applications in approximately 12 – 18 months
Developing LNG Terminals
• Leading times are currently very long for LNG projects
• Construction time is typically 3 years • There is an increasing demand of LNG
terminals, especially in North America • Costs of steel and concrete have
increased significantly • Additionally, liquefaction plants have
been delayed in several countries
LNG regasification plants
Cd. Pemex
Cd Juarez
Chihuahua
MonterreyReynosa
Cd Madero
TolucaD.F.
PR
MexicaliTijuana
Naco
• Six applications submitted, 5 permits granted
• Commercial operation: Sep 30th, 2006 (Altamira)
• ECA (Sempra): operation in March 2008
Baja California1. ECA (Sempra)
• 160,000 m3 x 2
• 1.0 – 1.3 BCFD
2. Shell Baja
• 170,000 m3 x 2
• 1.0 – 1.3 BCFD
Manzanillo
AltamiraShell-Total
• CFE bid
• 140,000 m3 x 2
• 0.5 - 1.1 BCFD
Topolobampo
Libertad
Problems…
• Private projects associated to private industry and LDC’s have had limited success– Large consumers are reluctant to sign long term
contracts– Pemex’ supply and services are preferred– Competing fuels are priced with non-market criteria
• As a result, most transport and LNG infrastructure is tied to CFE’s need for CC generators and Pemex’ requirements
• Most of the new combined cycle power plants are located near Pemex’ transmission system or LNG terminals
• Both companies dominate the gas market
Towards a new transport model
• CRE is currently reviewing PEMEX SNG (national pipeline system) rates, the methodology to calculate them and the corresponding tariffs.
• The idea is prepare SNG to be the main part of a National Integrated Transport System (SNI)
• Issues being discussed include using a postage stamp instead of a mcf mile methodology, desired levels of central planning and expansion of the system, roll-in criteria, desired degree of competition, etc.
• Although SENER is responsible for energy policy and planning, CRE’s opinion is central in this issue.
Conclusions
• Natural gas foreseen demand’s growth in Mexico will require infrastructure to secure supply.
• So far, CRE has developed a predictable, transparent regulation that can accommodate flexibility to investors.
• Current infrastructure in Mexico has been mainly linked to CFE and PEMEX through long term contracts.
• New infrastructure to allow regional growth and active private participation in new projects poses regulatory challenges to the CRE.