Est. cost crores Agency LOI Sch comp Survey Foundation Erection Stringing 1 400 kv s/s Gonda (PPP I) 220 kv dc Gonda400- Gonda220 DC inter- connector 13.45 11.17 Trading Engineers 13.45 03/46 0/46 0/13.45 11.6 1. Stubs & Templates delivered at site. 2. 03 nos. FDN gang to be deployed shortly. The proposed date of complition is 31.03.16. 2 400kV Hardoi Road(Lucknow) 400kV Hardoi Road(Lucknow) S/s- 220kV Hardoi Road DC Interconnector 9.25 7.4 18.07.14 22.07.14 26.07.14 5.18 Unitech Comp 0/35 0/35 0/9.25 10 profile submitted for approval.The proposed date of complition is 22.06.16. 1 220 kv s/s Tanda (RNNSAS) 220 kv DC Sohawal(400) -Tanda TD- 329 113.24 72.47 PNC 16.09.10 15.09.11 Comp 336/348 217/ 348 12/ 113.24 69.3 FDN, ROW at 10 locs loc no- 11,12,23,29,157,183,190,248, 249,250 Er ROW at loc no 145, Str ROW at loc no.-92, crop compensation cases paid. The proposed date of complition is 31.10.15. 132 kv sc Tanda220- Tanda132 TD- 348 11.8 2.42 Aster 06.04.11 05.04.12 Comp 50/54 45/54 7.92/ 11.8 86.6 As per local representative ROW at loc 8/0 & 6/1 for Erection and at loc 8/0 to 13 for Stringing work and EE, ETD, Faizabad to meet DM today, 01 no Erection gang working at site at loc 12 & 13 WIP, 01 no Stringing gang working at Tanda Gantry & Dead End Tower WIP, Stringing work at loc 3-4 completed, Foundation work could not be started due to standing sugarcane & paddy crop. Foundation work likely to start by next week. The proposed date of complition 12.10.15. 2 220 kv s/s Nighasan (RNNSAS) Work Progress ED % Prog. DETAILS OF ONGOING LINES UNDER TRANSMISSION CENTRAL Sl. No. Name of work Tend. No. Length Km. TWC BOD ETF Loan (in Cr.) Remarks
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
1400 kv s/s Gonda
(PPP I)
220 kv dc Gonda400-Gonda220 DC inter-
connector13.45 11.17
Trading Engineers
13.45 03/46 0/46 0/13.45 11.6
1. Stubs & Templates delivered at site. 2. 03 nos. FDN gang to be deployed shortly.
The proposed date of complition is 31.03.16.
2400kV Hardoi
Road(Lucknow)400kV Hardoi
Road(Lucknow) S/s- 220kV Hardoi Road DC Interconnector
As per local representative ROW at loc 8/0 & 6/1 for Erection and
at loc 8/0 to 13 for Stringing work and EE, ETD, Faizabad to meet DM today, 01 no Erection gang working at site at loc 12 & 13
WIP, 01 no Stringing gang working at Tanda Gantry & Dead End Tower WIP, Stringing work at
loc 3-4 completed, Foundation work could not be started due to standing sugarcane & paddy crop. Foundation work likely to start by next week. The proposed date of
complition 12.10.15.
2220 kv s/s Nighasan
(RNNSAS)
Work ProgressED
% Prog.
DETAILS OF ONGOING LINES UNDER TRANSMISSION CENTRAL
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
220 kv sc Sitapur-Nighasan
TD-329
110 55 15.19 SEW 23.03.10 22.09.11 Comp 335/336 317/ 33681.92/
11092.4
Row in Foundation at loc no. 84, under court case. River xing work to be taken up after receeding of
water.S/s Ready.The proposed date of complition 31.12.15.
220 kv sc Shahjahanpur-
Nighasan
TD-329
121 60.5 SEW 23.03.10 22.09.11 Comp 368/369 358/ 369104.18/
12195.9
ROW at 1location -32/2, matter in court ,River xing work to be
taken up after receeding of water..S/s Ready.The proposed
submitted, Pile fdn to be built on River crossing, No gang working at site since last one month, in the review meeting dt 23.09.15 firm assured to start the work earliest. The proposed date of
2 rly xing one already approved & one under approval.2 loc forest clearence required, on line NOC applied to forest department for approval.The proposed date for
the complition is 31.10.15.
13 132 kV Neri (Sitapur)
132 kv LILO of Sitapur-Shahjahanpur@Neri
4 1.95 06.07.12 18.07.12 12.12.12
REC 047-2012-6596 1.75
Local 12th Plan
14 132 kV s/s Bandaa
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
132 kV SC Puwanyan - Bandaa
20 6.202 Aravali
Land finalized, no work yet started, in the review meeting dt 23.09.15 firm assured to start the work earliest. The proposed date
of complition is 31.03.2016.
133 kV SC Gola - Bandaa
45 13.955 Aravali
Land finalized, no work yet started, in the review meeting dt 23.09.15 firm assured to start the work earliest. The proposed date
of complition is 31.03.2016.
15 132 kv s/s Haidargarh
132 kv LILO of sc jagdishpur-Haidergarh
Sugar Mill @ Haidergarh
20 6.59 30.4.11 18.7.12
REC 047-2012-6631 05.93
Accord 03.07.16 0/62 0/62 0/20
Route survey completed, profile approved, no gang present at
site, firm debared for a period of one year.
132 kv dc Sultanpur Rd. Lko (400)-
Haidergarh 30 9.89 30.4.12 18.7.12
REC 047-2012-6631 08.90
Accord 03.07.16 0/93 0/93 0/30On hold,firm debared for a