-
- 1 -
Executive 30 November 2010, Progress report 1 on the One Council
Programme Annex 2
Detailed Summary of Progress with One Council Projects
OCP1 Customer First
Project Sponsor Rob Dickson
Project Manager Dylan Champion
Review Headline Indicator GREEN
Headline Commentary
OCP1 continues to progress with the implementation of BPR
decisions to achieve service improvements and realise individual
savings. Environment, Housing and Culture & Lifelong Learning
continue their implementation of the BPR process, and are
progressing to the point of considering closure of their respective
workstreams. The key areas for implementation are now Transforming
Social Care and Income, Revenues and Benefits. It is currently the
view of the project team that the 2011/12 target will be achieved,
and that above target savings will be made in 2012/13. Fortnightly
coordination meetings of the Implementation group address this and
other issues, especially interdependencies with OCP3 Commissioning
and OCP6 ICT. The three principle ICT issues being addressed
are:
• The replacement of the Contact Management system (UCCX)
• A work package for diagnostic remedial CRM work followed by
development work.
• Development of a business requirements document for Website
development - work initial decision with potential suppliers to
develop a specification to undertake the upgrade. The web
development work is critical since it enables the achievement of
50% of customer Contact by 31 March 2011, fundamental to the
Customer First strategy.
-
- 2 -
Customer Contact continues to improve with the new Information
and Advice Centre being ranked amongst the top performing council
receptions areas in a recent London wide satisfaction survey. The
survey, conducted by the Customer Services for London Group
measured customer satisfaction with face-to-face services during
May 2010. 96% of Kingston’s 245 respondents were either ‘Satisfied
or ‘Very satisfied’ with the service they received at the Guildhall
2 Information and Advice Centre – the fourth highest score of the
19 participating London boroughs. Furthermore, 99% of Kingston
respondents said that the person they spoke to was knowledgeable
and helpful, and 98% said the environment was welcoming. As more
activities become mainstreamed, the final phases of OCP1 are now
being planned. The current project team will be re-organised in
November 2010 to meet the demands of the work ongoing. Governance
with be maintained by the OCP1 Project Board, which will continue
to ensure measures are in place for closure and mainstreaming into
service areas.
OCP2 Community Hubs
Project Sponsor Rob Dickson
Project Manager Gary Walsh
Review Headline Indicator GREEN
Headline Commentary
This project is progressing well. Work has continued to build on
the experience gained over the last year and with the
implementation of Strategic Business the project is now ready begin
to transition with remaining activity being mainstreamed into the
Community functions of Strategic Business.
The Kingston concept of Community Hubs is developing well beyond
the original focus on buildings, and more towards the concept of
clusters, community networks and community activity taking place
within local communities.
Our aim is to facilitate the creation and development of
clusters of services that are offered in local settings. These new
arrangements would make services more accessible, networked and
improve the customer experience. The services offered in hubs could
be provided by the Council, health, voluntary organisations and
other Partners.
-
- 3 -
The Neighbourhood Managers are working closely with all
communities on a neighbourhood basis. Neighbourhood Community Plans
are being developed with the aim of developing residents’
priorities and presenting local objectives, identifying where
services are delivered and where there are gaps in service
provision.
OCP3 Commissioning
Project Sponsor Rob Dickson
Project Manager Nick Mathews
Review Headline Indicator Green
Headline Commentary
OCP3 is progressing well and is now the focus of significant
transformation activity in preparing the options for recommissioned
services for the future. The OCP3 Board is working with Directors
and Service Management Teams to support the Executive
recommissioning our services for the future. The OC3 Commissioning
Programme has been agreed by SLT and is monitored and led by the
board arrangements which include the Transforming Social Care
Board. The Procurement Diagnostic implementation work has been
agreed by SLT and is underway focusing on supporting our in year
activity to close the budget gap. Significantly gateway
arrangements are now in place for major spend areas and continued
joint working with the financial community through OCP4 is
essential through the 2010/11 financial year and to influence
2011/12. The Performance Plus project is now being prepared for
transition into the Strategic Business service and planning is
underway for the full roll out of the system as part of the work
develop the components of our Strategic Business Cycle to be fit
for the One Kingston future. The project will need to manage a
significant range of work and embedding adequate resources in all
commissioning projects and appropriate risk management as the work
is designed and implemented will be critical. The support of the
Strategic Business service is critical and is in place. Transition
planning is now underway to embed our future commissioning and
procurement approach into the Strategic Business service.
-
- 4 -
OCP4 Finance
Project Sponsor Leigh Whitehouse
Project Manager Jane Hurt
Review Headline Indicator Amber
Headline Commentary
A new sponsor took over OCP4 before the last review and since
August, there has been a new project manager in place. Workshops
have taken place with board members to establish a high level
finance model and staff seminars to engage with all staff over the
vision and the agreed model for finance, have taken place in
September. There is also a high level project plan outlining
further “to be” design work until April 2011, with consultation and
implementation by June 2011. SLT have approved the way forward (at
their meeting on 2 September 2010) and a newly constituted Board
and refreshed governance structure should ensure that momentum is
maintained. The transitional structure for finance will also aid
the progress of both the project and Finance “business as usual” so
that the project does not have an adverse effect on this.
Additionally, several work streams have been established to cover
the priority areas such as Agresso development necessary to support
other One Council projects. There is every indication now that by
the next quarterly review, the project will be well on target.
OCP5 Assets
Project Sponsor Roy Thompson
Project Manager Peter Cordy
Review Headline Indicator Green
Headline Commentary
OCP5 has gathered considerable momentum in recent months, and is
addressing the wide scope of Asset management with appropriate
project management direction and discipline. The Project Manager
has established the project team and project support, and Project
Board governance is in place. Activities described in the initial
PID are now complete; however the twelve work streams represent a
very ambitious programme with clear resource constraints requiring
a careful process of prioritising work. A report was taken to SLT
on 10 August 2010 which updated on work in
-
- 5 -
progress. It described the findings of each of the topic
identified in the PID, including the baseline phase based upon the
topic areas. OCP5 presented a report to SLT on User Requirement and
the Office Accommodation Strategy for the future. The
organisational review now underway is critical to establishing the
new structure for Asset management, the Corporate Landlord
function. The project has been engaging with Neighbourhoods on the
Asset Management Plan (AMP), having consulted with partners and
stakeholders. There has been a very positive response. The AMP was
adopted by Executive on 29 September 2010. OCP5 has is reviewing
the Repairs and Maintenance contract, and once the Building
Maintenance Strategy is developed, will consider how the contract
fits with it including the extended supply chain. The contract
review includes benefits realisation with OCP3 Commissioning &
Performance Management to undertake a thorough examination of the
relevant contracts and identify a better gate keeper approach and
agree the way forward. This includes the scope and performance of
existing contracts. Work is also underway with the Repairs and
Maintenance regarding Compliance and Business Continuity to provide
assurance re compliance. The savings position marketing strategy
has been put forward for disposals, and those already identified
will proceed for disposal as planned. The project is also
progressing other work strands such as Sustainability, ensuring
appropriate links to the Low Carbon Management Plan and Carbon
Reduction Commitment
OCP6 ICT
Project Sponsor Roy Thompson
Project Manager Mike Fogaty
Review Headline Indicator Green
Headline Commentary
Good progress has been made. OCP6 ICT is now closing as a
project. Implementation of the agreed structure has taken place,
bringing together the previously dispersed resource from across the
Organisation, with the few remaining vacancies being filled. The
new strategic direction for the One Council Team is in place with
work begun to implement the new ICT Strategy and to carry out work
required on other One Council projects, most notably OCP1. A new
governance structure for ICT decisions and development has been
approved by SLT and is starting to be rolled out and communicated
across the Organisation.
-
- 6 -
Additionally, work is underway on succession planning to ensure
that when the interim head of IT leaves, the new service will
continue to be run effectively. The new One Council ICT Team is in
place and will take forward the programme of ICT work required for
the future.
OCP7 Organisational Dynamic
Project Sponsor Sheila West
Project Manager Jonathan Smale
Review Headline Indicator GREEN
Headline Commentary
The Project is on track and delivering a substantial programme
of work. OCP7 Organisational Development has completed the
implementation of Phase 1. OCP7 Strategic Business has now reached
the implementation stage with recruitment complete and the
Strategic Business Team now in place. OCP7 communications continues
to operate and is planning for the adjustment of its remit to the
One Kingston Programme environment. OCP7 Change Management
continues to provide a HR change management function for the One
Council Programme and has now supported the review of the majority
of roles in the organisation. OCP7 Strategic Business Phase 2 is
now underway with the PID agreed by SLT and the Project Team
meeting, and the first engagement workshops with staff in scope
held and the ‘As Is’ stage of the review begun. OCP7 Organisational
Development Phase 2 is now underway; however the complexity of the
budget realignment from Phase 1 has left significant challenges in
achieving the targeted levels of savings.
-
- 7 -
OCP8 One Council Manager
Project Sponsor Sheila West
Project Manager Jonathan Smale
Review Headline Indicator GREEN
Headline Commentary
The project is progressing well and SLT have now approved a
revised approach to addressing the role of managers. The Leadership
Academy, Leadership Development Programme and Evolve training and
development opportunities are now in place. Organisational Reviews
are addressing management roles in line with the new approach.
OCP9 SLT
Project Sponsor Bruce McDonald
Project Manager Andy Holder
Review Headline Indicator GREEN
Headline Commentary
OCP9 continues to make appropriate progress with the future role
of SLT. SLT have continued to attend regular development sessions
and there has been a seamless transition with the arrival of the
new Director of Finance.
-
- 8 -
OCP10 PMO
Project Sponsor Roy Thompson
Project Manager Kevin Mitchell
Review Headline Indicator GREEN
Headline Commentary
The project is now in closing, having progressed in line with
the SLT brief and delivered the key outputs set. A closure report
is due to go to SLT in November 2010. The PMO have supported SLT in
leading the design and delivery of the One Council Programme, the
Strategic Housing Project and developing our Programme and Project
Management Approach. Action to embed our Risk Management Approach
is progressing well with the approach in place but requiring
ongoing support. The PMO have supported SLT to enable One Council
Projects to catch up where required and the One Council Programme
is now fully underway and beginning to reach the closure stage for
key components. The PMO function is now being transitioned to the
Strategic Business service to support our transformation and
programme activity.