1 DETAILED PROJECT REPORT ON SELAI GADADHAR INTEGRATED WATERSHED MANAGEMENT PROJECT OF DHUBRI DISTRICT UNDER THE DEPARTMENT OF LAND RESOURCES MINISTRY OF RURAL DEVELOPMENT GOVERNMENT OF INDIA NEW DELHI PREPARED & SUBMITTED TO STATE LEVEL NODAL AGENCY INTEGRATED WATERSHED MANAGEMENT PROGRAMME GOVERNMENT OF ASSAM BY BS CONSULTANTS 128, RAJGARH ROAD, 2 nd FLOOR, GUWAHATI-781 007
83
Embed
detailed project report on selai gadadhar integrated watershed ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1
DETAILED PROJECT REPORT
ON SELAI GADADHAR INTEGRATED WATERSHED
MANAGEMENT PROJECT OF DHUBRI DISTRICT
UNDER
THE DEPARTMENT OF LAND RESOURCES MINISTRY OF RURAL DEVELOPMENT
GOVERNMENT OF INDIA NEW DELHI
PREPARED & SUBMITTED
TO
STATE LEVEL NODAL AGENCY INTEGRATED WATERSHED MANAGEMENT
PROGRAMME GOVERNMENT OF ASSAM
BY
BS CONSULTANTS 128, RAJGARH ROAD, 2nd FLOOR,
GUWAHATI-781 007
2
PROJECT AT A GLANCE 1. Name of project : Selai Gadadhar Integrated Watershed Management Project Code No: 3A1E3 2. Name of the State : Assam (Code No. 18) 3. Name of the State Level Nodal Agency: Department of Soil Conservation, Government of Assam 4. Name of the District : Dhubri (Code No: 2) 5. Name of the Development Block :1. Debitola Development Block 2. Rupsi Development Block 6. Name of Gaon Panchyats : 1. Uttar Geramari, 2. Alomganj, 3. Chapgarh
4. Madhusoulmari 5. Selairpar, 6. Folimari,
7. Asharikandi
7. Numbers of villages covered : 30 Nos. 8. Name of Micro Watershed : 1. Selai
2. Gadadhar 3. Tiamari 9. Total Geographical area of the project : 5392 ha. 10. Area proposed to be treated : 3160.88 ha. 11. Total project cost : Rs. 379.31 Lakh 12. Name & Address of PIA : Divisional Soil Conservation Officer, Barpeta
3
CONTENTS
Sl. No. Chapter Particulars Page No
1 INTRODUCTION 1
2 METHODOLOGY 2-3
3 CHAPTER –I GENERAL DESCRIPTION OF THE DHUBRI DISTRICT 4 - 10
Location & Geographical units 4
Climate & Soil 4
Physiography & Drainage 5
Demographic profile 6
Land use & Land Holdings 6
IWMP projects in the District MIS M(SP)2
Prioritized list of Proposed projects Table DPR 1
8
8
Vision & Strategy 9
4 CHAPTER –II GENERAL DESRIPTION OF THE SELAI GADADHAR IWM PROJECT AREA
11 - 14
Location 11
Climate 11
Rainfall with Table: DPR 2 & 3 11-13
Soil 13
Physiography, Relief & Drainage 14
5 CHAPTER-III PRESENT STATUS OF THE PROJECT AREA 15 - 27
Objectives 15
Present Land Use & Land Cover, Table: DPR 4 17
Details of Areas of Micro Watersheds Table: M (SP) 2 17
Details of Types of Areas Covered under IWMP, Table (SP) 3
18
4
Details of Physiography Relief & Drainage. Table: M (SP) 4
19
Agro-Climatic Zone, Soil types, Average Rainfall & Major Crops., Table M (SP) 5
19
Details of Flood & Drought in Project Area., Table M (SP) 6
20
Details of Soil Erosion, Table M (SP) 7. 20
Details of Infrastructure, Table M (SP) 8 21
Details of Land Holdings pattern, Table M (SP) 9 22
Details of Common Property Resources Table M (SP) 10
23
Details of Kharif Crop Area, Table M(PO) C1 23
Details of Rabi Crops Area, Table M (PO) C2 24
Details of Zaid Crop Area, Table M (PO) C3 25
Details of Fund Flow of Watershed Committee Account, Table M(FM) 4
Table-M (SP) 2: Details of areas of micro-watersheds covered under the watershed programme (ha) of DoLR in the State(A) pre-IWMP, (B) under IWMP, (C ) under other Ministries and (D) Total area (ha) covered under the watershed programme of DoLR. 1 2 3 4 5 6
Sl. No.
Names of
States
Names of
Districts
Total micro-watersheds in the
District
Micro-watersheds# covered so far Net watersheds to be
covered Dept. of Land Resources
Other Ministries/ Depts.
Total watersheds
covered Pre-IWMP projects
IWMP projects
Any other watershed project
No. Area (ha.) No. Area (ha.) No.
Area (ha.) No. Area
(ha.) No. Area (ha.) No. Area (ha.)
1 Assam Dhubri 62 130034 ha 32 16000 ha - - - - 30 16000 30 122658 ha
24
Table-M (SP) 3: Details of the types of areas covered under the IWMP:
1 2 3 4 5 6 7 8 9 10
Sl. No.
Name of State
Name of District
Names of projects
Year of sanction
Project duration (dd/mm/ yyyy)
Area of the
projects
Type of terrain Hilly (H)/ Desert (D)/ Others (O)
Project cost (Rs. In
lakh)
Names of micro watersheds and Code Nos.# (as per DoLR’s unique codification)
1 Assam Dhubri Selai Gadadhar
2009 2009 2014 3160.88 Others 379.30 3A1E3
11 12
Cultivated and wasteland area of the projects Area details (ha) (Falling within the projects)
Cultivated
rainfed area
Cultivated
irrigated area
Uncultivated wasteland Pvt. Agri. Land Forest Land
Comm. land
Others (river/wate
r body)
Total area (ha) a) Temporary
Fallow b)
Permanent
3491 ha 102 361 517 Gen SC ST OBC Total
Nil 361 5 5393 1300 240 0 1951 3491
25
Table-M (SP)4: Details of physiography and relief of the project areas
1 2 3 4 5 6 7 8 9
Sl. No.
Names of
States
Name of District
Names of
projects
Elevation (meters)
Slope range (%)
Order of watershed Sub/micro-watershed
Major streams
Top sequence (Soil series)
1. Assam Dhubri Selai Gadadhar
40-50 0.5 Selai Gadadhar Gadadhar
& Selai
Recent Alluvium and older Alluvium
(Coarse Loamy and Fine Loamy)
Table-M (SP) 5: Agro-climatic zone, soil types, average rainfall and major crops in the project area
1 2 3 4 5 6 7 8 9
Sl. No
Name of
State
Name of the Agro-climatic zone
Area in ha
Name of the
District
Names of the projects
Major soil types Average rainfall in mm (preceding 5
years’ average)
Major crops
a) Type b) Area (ha)
a) Name b) Area (ha)
1. Assam Lower Brahmaputra valley
5150 Dhubri
Selai Gadadhar
Sandy loam 5150 2299.06 Paddy,
Jute
2900 650
26
Table-M (SP) 6: Details of flood and drought in the project area
1 2 3 4 5 6 7 8 Sl. No.
Names of
States
Names of
Districts
Names of
projects
Particulars Villages Periodicity Not affected Annual Any other
(please specify) 1 Assam Dhubri Salai
Gadadhar Flood 14 nos. Occasionally flooded
during the rainy seasons i.e July &
August
Nil 14 nos.
Drought Nil. Nil. Nil Nil.
Table-M (SP) 7: Details of soil erosion in the project areas
1 2 3 4 5 6 7 8 9 Sl. No.
Name of State Name of District
Name of project Cause Type of erosion
Area affected (ha)
Run off (mm/ year)
Average soil loss (Tones/ ha/ year)
1 Assam Dhubri Selai Gadadhar Water erosion:
a. Sheet 755 176.18 41.48 b. Rill 215 117.88 c. Gully 377 137.78
Sub-Total: 1347 Wind erosion: - Nil -
Total for the project: 1347
27
Table-M SP) 8: Details of infrastructure in the project area
1 2 3 4 5 6
Sl. No. Name of State
Name of
District
Name of
project Parameters Status
1.
Ass
am
Dhu
bri
Sela
i Gad
adha
r
(i) No. of villages connected to the main road by an all-weather road 28
(ii) No. of villages provided with electricity 28
(iii) No. of households without access to drinking water Nil
Total for the Project: - 282 - - - 4665 12 260 - - 1540 4150 300 200 - - 30250 10375
* From column no.2 total number of States, from column no.3 total no. of Districts; from column no.4 total no. of projects; from column no.5, total no. of crops; from column no.6 to 8, the totals for the area, average yield per ha and total production, category-wise, for the entire country may be given at the end of the Table.
Irri. – Irrigated Rf. – Rainfed
31
Table-M(PO)C3: Details of Zaid crop area and yield in the project area
Total for the project: - 71 53 675 70 87 1245 176 87 2223
32
Table-M(FM)4: Details of Fund flow of Watershed Committee Accounts in the Country: State-wise* (Amount in Rs.)
1 2 3 4 5 6 7 8 9 10
Sl. No.
Nam
e O
f Sta
te
Nam
e of
Dis
tric
t
Nam
e of
Pro
ject
Nam
e of
wat
ersh
ed
com
mitt
ee
Opening Balance
Deposit Withdrawal Interest accrued
Closing balance
DRDA/ ZP Cheque No./date
Amount
/ Date of deposit in
WC Account
Total amount
available in WC Account
Amount withdrawn
by Cash/ Cheque
Date of with-
drawal
Purpose
of
withdrawal
1
Ass
am
Dhu
bri
Sela
i Gad
adha
r
Sela
i Gad
adha
r
To be maintained with the progress of execution.
* From column no.2 total number of States, from column no.3 total number of Districts; from column no.4 total number of projects; from column no.5 total no. of watershed committees; from column no. 6 total amount of opening balance; from column no.7, total amount deposited in WC accounts and total amount available in WC accounts; from column no.8 total amount withdrawn, category-wise; from column no.9 total interest accrued and from column no.10 total closing balance for WCs, for the entire country may be mentioned at the end of the table.
33
Table-M(FM)5: Details of pending UCs.
1 2 3 4 5 6 7 8 9 10 11 12
Sl. No.
Stat
e
Dis
tric
t
Proj
ect
Instal-ment no.
Financial year of
release of fund
Amount released (Rs. in lakh)
Amount utilized (Rs.in lakhs)
Submission of UC@
Date of Submission of
UC
Reasons for not
submitting/ delayed
submission of UC
Pending UCs
Due date
Amount (Rs. In lakhs)
Date Amount (Rs.
In lakhs)
Period Amount (Rs. in lakhs)
1
Ass
am
Dhu
bri
Birsing Jarua (IWDP)
3rd 2003-2004
209.71 154.93 Mar/04 154.93 July/04 154.93 Does not arise
Emphasis should also be given adequately at imparting training and environmental
motivation programme to all users group and self help groups as such it is proposed to
make the people conscious and develop skill specially among womenfolk who are
traditionally an important constituent of the society particularly in respect of economic
activity and thereby improving access of the poor, specially women to the benefits and
ensuring access to usufructs right from common property resources for the resource poor.
The schemes proposed in the project area are basically on the basis on the participatory
rural appraisal (PRA) exercises conducted in the project area. The needs of the villagers
are taken into consideration and compromising on the availability of fund and magnitude
of the requirement of the villagers the schemes are proposed.
Entry Point Activities: With a view to establish credibility of the project implementing
agency as well as watershed development team and to create a rapport with the village
community some important entry point activities have been proposed as envisaged in the
guidelines of the Govt. of India. The schemes/projects are selected and proposed by the
PIA/Project Manager in consultation with the beneficiaries, the gram panchyats, the
watershed committee as well as the watershed development team.
A. Agricultural Strategy proposed:
Production of rice will have to be raised through improving productivity of winter and
summer rice through use of quality seeds, high yielding varieties, hybrid inputs and
irrigation potential. Area under rice with very poor productivity should be diverted to
summer rice with creation of irrigation potential.
However there is need to bridge the gap between research and extension for which the
Watershed Committee, Project Implementing Agency, The District Agricultural
39
Machinery as well as District Watershed Development Unit should Co-ordinate; not only
to increase agricultural production but also on agri. processing, input availability, and
marketing as well as overall transfer of technology from lab to land.
More over it is proposed that one no of Central Nursery with different suitable
horticultural species be raised under entry point activities as well as 0.5 ha of
Horticultural Nursery under work phase, so as to enable to distribute seedlings to the
people to supplement in their home stead garden and orchards. Crop demonstration
activities like paddy, vegetables and potato etc. are also proposed in the project area for
benefit of the beneficiaries.
B. Protective Afforestation:
Forest are important natural resources and they influence climate, soil conditions
particularly soil and water balance, erosion, floods, maintenance of bio-sphere, ecology
as well as wild flora and fauna etc. In this project it is proposed to create additional forest
coverage of 15.4 ha. in and around Selai Gadadhar with suitable species. In areas with
sandy soil in reverine environment Khair Sisso and Simul etc. should be planted while in
other areas plantation of bamboo be stressed as it is not only poor man’s timber but are
also needed for paper industries.
Moreover, it is proposed that one nos. of central nursery with around 3.00 lakhs planting
stock be raised with important forest species suitable for the locality under entry point
activity so that seedlings can be given to the people within the project area as well as
planting can be undertaken in road sides river bank and institutional campus.
C. Development of Pasture and Animal Husbandry:
The project area has good potential for development of animal husbandry, which needs
special attention. The rural people rear livestock and poultry as important source of
income.
40
Grasess like Gunea, Napier, Para and other locally available grass species may be
considered for being raised in the proposed area. It is proposed that two hectares of area
with fodder grass to be raised in the project area under entry point activity and output to
be sold to or may be distributed to the beneficiaries as the watershed committee /District
Watershed Development Unit feel proper.
As many as 234 units of Self Help Groups (SHGs) are selected in the project area to take
up schemes of rearing of milch cow, poultry, piggery and duckery, beekeeping etc.
D. Pisciculture:
Pisciculture is one of the important developmental schemes, which helps in improving
life style of the people. In one hand creation of water bodies helps in recharging of
ground water level and improves in soil moisture regime. On the other hand pisciculture
in water bodies like Farm Pond, fisheries etc. gives additional income to the farmers. In
general this would meet the nutrient requirement of the people in the project area and
others.
E. Soil and Water Conservation Activities:
In situ-conservation, utilization of soil and water within the Project is the prime criteria
for sustaining agricultural and horticultural production in the cultivated land for which
proper soil and water conservation activities are to be taken on priority basis. Therefore
considering the necessity for comprehensive in situ soil and water conservation measures
in the project area the following soil conservation engineering measures are
recommended as detailed in the work plan.
Water harvesting structures - To store runoff water and to check gully erosion as well as
sheet and rill erosion construction of R.C.C. check dams or drop spill ways, earthen
check dam, farm ponds, earthen embankments, water distribution channel etc. are
proposed in the project area which will give benefit to arrest soil loss, improve soil
41
moisture regime and increase production of crops of kharif as well as rabi crops in the
project area 7 nos. of water distribution canal are proposed to be constructed in the
project area. Further by using water pumps kharif crops can also be cultivated in nearby
areas.
F. Land Development:
To protect the land from erosion as well as to arrest the runoff water in the project area 16
nos. of earthen bunds with and without core wall involving 24420 m3 of earthworks are
proposed to be created in the project area to give benefit in about 900 hectares of
cultivated field.
These earthen bunds will also protect the paddy fields from inundation by the floodwater
of the adjoining Selai Gadadhar river and to give strength to the dykes boulder pitching is
also proposed in areas where it is felt needed.
G. Surface Water Storage / Ground Water Recharge:
To create facility for storage of runoff water and to facilitate rearing of fish construction
of RCC check dams, farm ponds, fishery ponds as well as reclamation of marshy lands
are also proposed in the project area. The water from the farms dug out ponds and ring
wells in agricultural fields and homestead garden will recharge the ground water level
about 3 mts. And can be utilized in paddy fields, orchards including vegetables gardens
can be utilized by using water pumps.
Moreover 14 nos. of open wells and 10 nos. of tube wells are also proposed in the project
area under EPA to recharge ground water level as well as for meeting up requirement of
drinking water of the people of the project area.
For effective implementation of the project activities in the project area all concerned
must share the overall responsibilities from the District Water Shed Development Unit
42
(DWDU) level to the Users Groups (UG) and Self Help Group (SHG) Level. For proper
and fruitful implementation of the Project the responsibility of the Project Implementing
Agency and that of the Watershed committee is maximum. The watershed Development
Team must co-ordinate with the watershed committee and Project Implementing Agency
for effective implementation of the water shed works. Proper Training to the Users
Groups (UG) and Self Help Groups (SHG) is most required for effective implementation
of the project activities.
43
Chapter IV- Project Activities
Table-M(PA)A1: Entry point activities (EPA)
IV. A. Preparatory phase: Treatable Area: 3161 ha. Financial Outlay; Rs. 15.17 lakhs
1 2 3 4 5 6 7 8 9 10 11
S. N
o.
Stat
e
Dis
tric
t N
ame
of
proj
ect
Am
ount
ea
rmar
ked
for
EPA
Entry Point Activities planned with Name of villages ***
Est
imat
ed c
ost
Exp
endi
ture
in
curr
ed
Bal
ance
Exp
ecte
d ou
tcom
e
Rem
arks
1
Ass
am
D
hubr
i
Sela
i Gad
adha
r
15.1
7
Selairpar I 1) Installation of HTW=3No. 22500.00 - - For drinking purpose.
The
sche
mes
and
est
imat
ed c
ost a
s pro
pose
d by
Pro
ject
Man
ager
. Det
aile
d es
timat
es a
re to
be
prep
ared
and
sanc
tione
d by
the
SLN
A/D
WD
U.
Selairpar II (Charjogipara) 1) Installation of HTW=3Nos. 22500.00 -do- Shyamcharanerkuti I 1) Installation of HTW=2Nos. 15000.00 - - -do- Shyamcharanerkuti II 1) Installation of HTW=2No. 15000.00 - - -do- Shyamcharanerkuti III 1) Installation of HTW=2Nos. 15000.00 - - -do- Sajuarkuti 1) Installation of HTW=4Nos. 30000.00 - - -do- Kheraj Daobhangi 2) Plantation at Daobhangi Junior
College 50000.00 - - To conserve ecological
balance. Daobhangi 1) Installation of HTW=5Nos. 37500.00 - - For drinking purpose. Geramari I *** 2) Boundary wall and Office
repairing of Gauripur S.C. Range Alomganj 335500.00
- - To protect public property
1) Installation of HTW=2Nos. 15000.00 - - For drinking purpose. Geramari II
1) Installation of HTW=2Nos. 15000.00 - - -do- 2) Boundary wall of GP Office Uttar Geramari
50000.00 - - -do-
Geramari III 1) Installation of HTW=2Nos. 15000.00 - - -do- Geramari VI 1) Installation of HTW=2Nos. 15000.00 - - -do- Modaikhali 1) Installation of HTW=2Nos. 15000.00 - - -do- Beguntali 1) Installation of HTW=2Nos. 15000.00 - - -do- Asharikandi
1) Installation of HTW=2No. 15000.00 - - -do- 2) Nursery at Asharikandi 50000.00 - - Seedlings to be distributed 1) Installation of HTW=2No. 15000.00 - - -do-
44
Folimari I 2) Repairing of Janakalyan Society Club
49500.00 - - To protect public property
-
do-
Folimari II 1) Installation of HTW=2Nos. 15000.00 - - For drinking purpose. Dubirchar 1) Installation of HTW=4Nos. 30000.00 - - -do- Chapgarh I 2) Plantation of Chapgarh ME School &
High School 80000.00 - - To conserve ecological
balance. Charaldanga 1) Installation of HTW=3Nos. 22500.00 - - For drinking purpose. Bhelakoba 1) Installation of HTW=3Nos. 22500.00 - - -do- Tiamari I 1) Installation of HTW=2No. 15000.00 - - -do- Tiamari II 1) Installation of HTW=2No. 15000.00 - - -do-
2) Plantation at High Madrassa 30000.00 - - To conserve ecological
balance. Brahmattar Selairpar 1) Installation of HTW=3No. 22500.00 - - For drinking purpose. Fulkumari 1) Installation of HTW=4Nos. 30000.00 - - -do- Hariarkuti 2) Plantation at Hariarkuti LP School 30000.00 - - -do- Bhouspuri 1) Installation of HTW=2Nos. 15000.00 - - -do- Khudimari I
1) Horticultural Nursery 347000.00 - - Seedlings to be
distributed 2) Installation of HTW=2No. 15000.00 - - For drinking purpose.
Khudimari II 1) Installation of HTW=2No. 15000.00 - - -do- Grand Total: 15,17,000.00
*** The work of boundary wall and office repairing of Gouripur Range is to be taken up only with specific approval from the SLNA /DWDU as such works are not generally undertaken under entry point activities.
45
Table-M(PA)A2: Other activities of preparatory phase
* from column no. 2, no. of States; from column no. 3, no. of Districts; from column no. 4, total no. of Projects; from column no. 5 to 14 category wise totals, from column no. 15, total cost incurred, for the entire country may be indicated at the end of the table # One of the following may be entered in columns 5 to 14 , Completed (ii) in progress (iii) just started (iv) not started
46
IV. B. Watershed Works phase
Table DPR 5 Livelihood Activities (Asset less)
Name of Scheme Physical
Target Unit cost
Year wise Phasing 2nd year (4%) 3rd year (3%) 4th year (3%) Total
Livelihood Activities (Asset less) Nos Amonut Nos Amonut Nos Amonut Livestock Development Works by S.H.G.(1 unit to each SHG Group) A. Piggery – Breaded 2 nos 1.20 1 nos 1.20 1 nos 1.20 nil 0.00 2.40 B. Duck Rearing 12 nos 0.12 1 nos 0.12 6 nos 0.72 5 nos 0.60 1.44 C. Milch Cow 10 nos 1.20 4 nos 4.80 3 nos 3.60 3 nos 3.60 12.00 Other Activities 0.00 A. Bicycle Repairing 7 nos 0.40 4 nos 1.60 1 nos 0.40 2 nos 0.80 2.80 B. Handloom 8 nos 0.50 3 nos 1.50 2 nos 1.00 3 nos 1.50 4.00 C.Pottary Making 2 nos 0.44 nil 1 nos 0.44 1 nos 0.44 0.88 D. Fruit Processing 4 nos 0.50 2 nos 1.00 1 nos 0.50 1 nos 0.50 2.00 E. Carpenter 7 nos 0.24 3 nos 0.72 2 nos 0.48 2 nos 0.48 1.68 F. Mobile Repairing 2 nos 0.30 1 nos 0.30 nil 1 nos 0.30 0.60 G. Bike Repairing 2 nos 0.50 2 nos 1.00 1.00 I. Vermi Compost 3 nos 0.225 2 nos 0.45 1 nos 0.225 nil 0.00 0.68 J. Fishery Dev./ Fish Farming (25 x 30) m2 6 nos 0.60 2 nos 1.20 1 nos 0.60 3 nos 1.80 3.60 K. Bamboo Craft 2 nos 0.55 1 no 0.55 1 nos 0.55 1.10 L. Wood Craft 1 nos 0.55 1 nos 0.55 0.55 M. Blacksmith 2 nos 0.40 2 nos 0.80 0.80 N. Jaru Making 1 nos 0.30 1 nos 0.30 0.30 O. Tarja Making 3 nos 0.50 1 nos 0.50 2 nos 1.00 1.50 P. Bee-Keeping 3 nos 0.20 1 no 0.20 1 nos 0.20 1 nos 0.20 0.60
Total : 77 nos 29 nos. 15.24 24 nos. 11.37 24 nos. 11.32 37.93
Contd………..
47
Production System & Micro Enterprises 5% 4% 4% A. Piggery – Breaded 16 nos 1.20 1 nos 1.20 1 nos 1.20 1 nos 1.20 3.60 B. Duck Rearing 20 nos 0.12 3 nos 0.36 3 nos 0.36 3 nos 0.36 1.08 C. Milch Cow 16 nos 1.20 5 nos 6.00 3 nos 3.60 2 nos 2.40 12.00 D. Bicycle Repairing 8 nos 0.40 4 nos 1.60 1 nos 0.40 3 nos 1.20 3.20 E. Handloom 26 nos 0.50 6 nos 3.00 4 nos 2.00 4 nos 2.00 7.00 F.Pottary Making 3 nos 0.44 2 nos 0.88 1 nos 0.44 1.32 G. Fruit Processing 10 nos 0.50 4 nos 2.00 3 nos 1.50 2 nos 1.00 4.50 H. Carpenter 8 nos 0.24 3 nos 0.72 3 nos 0.72 2 nos 0.48 1.92 I. Mobile Repairing 3 nos 0.30 2 nos 0.60 nil 0.00 nil 0.00 0.60 J. Bike Repairing 2 nos 0.50 2 nos 1.00 1.00 K. Vermi Compost 6 nos 0.225 2 nos 0.45 1 nos 0.23 3 nos 0.675 1.35 L. Fishery Dev./ Fish Farming (25 x 30) m2 18 nos 0.60 2 nos 1.20 3 nos 1.80 4 nos 2.40 5.40 O. Bamboo Craft 3 nos 0.55 1 no 0.55 nil 0.00 1 nos 0.55 1.10 P. Wood Craft 2 nos 0.55 nil 0.00 2 nos 1.10 1.10 R. Blacksmith 2 nos 0.40 1 nos 0.40 nil 0.00 nil 0.00 0.40 S. Jaru Making 2 nos 0.30 nos 0.30 nil 0.00 nil 0.00 0.30 T. Tarja Making 6 nos 0.50 1 nos 0.50 2 nos 1.00 2 nos 1.00 2.50 U. Bee-Keeping 6 nos 0.20 4 nos 0.80 1 nos 0.20 1.00
Total : 18.88 15.49 15.01 49.37
48
Table-M(PA)B1: Activities related to Surface water resources in the project areas.
Table- M(PA)B2: Activities related to recharging ground water resources in the project area
1 2 3 4 5 6 7
8 9
S. No.
Nam
e of
Sta
te
Nam
e of
Dis
tric
t
Nam
e of
pro
ject
Typ
e of
stru
ctur
e
Pre-project Proposed target Achievement due to project
Change in
irrigated
area (Col. 8-6) (ha)
No.
Are
a Ir
riga
ted
(ha)
Augmentation/ repair of existing recharging
structures
Construction of new recharging structures
Total target Augmentation/ repair of existing recharging
structures
Construction of new recharging structures
Total
achievement
No.
Are
a to
be
irri
gate
d (h
a)
Est
imat
ed
cost
N
o.
Are
a to
be
irri
gate
d (h
a)
Est
imat
ed
cost
Are
a to
be
irri
gate
d (h
a)
Est
imat
ed
cost
No.
irri
gate
d
(ha)
E
xp.
incu
rred
No.
Are
a ir
ri-
gate
d (h
a)
Exp
.
incu
rred
irri
gate
d
(ha)
Exp
. To
be
incu
rred
1
Ass
am
Dhu
bri
Sela
i Gad
adha
r
(i)Open wells
8 For drinking purpose
- - - 14 280 From EPA
280 From EPA
- - - 14 280 From EPA
280 From EPA 280
(ii)Bore wells
- - - - - - - - - - - - - - - - - - -
(iii)Any others
- - - - - - - - - - - - - - - - - - -
Total for the project: 8 For drinkin
g purpose
- - - 14 280 From EPA
280 From EPA
- - - 14 280 From EPA
280 From EPA
280
51
Table M(PS)B3: Activities proposed for Users groups (UGs) in the project area (Rs. In Lakhs)
1 2 3 4 5 6 Sl
. No.
Nam
e of
Sta
te
Nam
e of
Dis
tric
t
Nam
e of
pro
ject
Nam
e O
f MW
S Major Activities of the UGs-targets Nos. of UGs
proposed
Estimated Cost
Amount of WDF to be collected
Structure /Activity proposed Sl. No.
Type No. Treatment (ha.)
1
Ass
am
Dhu
bri
Sela
i Gad
adha
r
Sela
i MW
S 1 Boulder Spur (In RM) 30 60 1 0.87 0.044 2 Distributional Canal (In RM) 3200 150 3 3.07 0.154 3 Earthen embankment without
Core wall (In RM) 7000 220 5 14 0.7
4 Boulder Revetment (In RM) 1274 120 3 25.78 1.289 5 Nulla Bund (with provision of
slab culvert) In RM 1000 60 1 6.27 0.314
6 Protective Afforestation (In Ha) 5.4 5.4 3 1.48 0.074 7 Afforestation Regeneration (In
Ha) 3 3 1 0.55 0.025
8 Crop Demo (Paddy) In Ha 16.5 16.5 4 2.48 0.124 9 Crop Demo (Potato/ Veg) In Ha 9.5 9.5 5 2.28 0.114
Sub Total 644.4 26 56.78 2.699
Gad
adha
r
1 Excavated Pond ( In M3) 1200 25 1 0.68 0.034 2 Distribution Channel (In RM) 3010 150 2 2.89 0.145 3 Earthen Embankment without
core wall (In RM) 4475 200 4 8.95 0.448
4 RCC Check Dam (In m2) 20 180 1 7.10 0.36 5 Boulder Revetment (In RM) 366 100 3 7.42 0.371 6 Boulder Spur (In RM) 411 70 1 11.92 0.60 7 Crop Demo (Potato/ Veg) In Ha 9.5 9.5 4 2.28 0.114 8 Crop Demo (Paddy) In Ha 14 14 3 2.10 0.105 9 Protective Afforestation (In Ha) 5 5 1 1.36 0.068 Sub Total 753.50 20 44.70 2.245
52
Tia
mar
i MW
S
1 Boulder Revetment (In RM) 1093 200 3 22.13 1.11
2 Earthen Embankment without core wall (in RM)
12945 450 7 25.89 1.29
3 Distribution Channel (In RM) 5533 250 3 5.92 0.296
4 Earthen Chek dam (In M3) 1000 50 1 1.22 0.061
5 Excavated Pond (In M3) 15017 50 1 8.56 0.428
6 Earthen embankment with core wall (In RM)
2324 100 2 11.15 0.56
7 Boulder Pitching (In M2) 331 60 2 2.84 0.142
8 Boulder Spur (In RM) 200 60 1 5.80 0.29
9 Protective Afforestation (In Ha) 10 10 5 2.74 0.137 10 Crop Demo (Potato/ Veg) 5.5 5.5 2 1.32 0.066 11 Crop Demo (Paddy) In Ha 14 14 3 2.1 0.105 12 Nursery Raising (Horticulture) In
Ha 0.5 0.5 1 1.5 0.075
Sub Total 1250 31 91.17 4.56 Grand Total 2647.90 77 189.65 9.504
53
Table- M(PA)B4: Activities related to livelihoods by Self Help Group (SHGs) for Asset less people in the project area
(Rs. in lakhs)
1 2 3 4 5
SL. No.
Name of State
Name of District
Name of Project
Major activities of the SHGs
Name of activity No. of SHGs
involved Average annual income
1
Ass
am
Dhu
bri
Sela
i Gad
adha
r
1 Piggery – Breaded 2 nos 0.8 2 Duck Rearing 12 nos 0.5 3 Milch Cow 10 nos 0.8 4 Bicycle Repairing 7 nos 0.5 5 Handloom 8 nos 0.8 6 Pottary Making 2 nos 0.5 7 Fruit Processing 4 nos 0.8 8 Carpenter 7 nos 0.5 9 Mobile Repairing 2 nos 0.5
10 Bike Repairing 2 nos 0.5 11 Vermi Compost 3 nos 0.5 12 Fishery Dev./ Fish
Farming (25 x 30) m2 6 nos 0.8
13 Bamboo Craft 2 nos 0.5 14 Wood Craft 1 nos 0.5 15 Blacksmith 2 nos 0.5 16 Jaru Making 1 nos 0.5 17 Tarja Making 3 nos 0.5 18 Bee-Keeping 3 nos 0.5
Total: 77 Contd..........
54
Table-M(PA)B4: Activities related to livelihoods by Self Help Groups (SHGs) for Asset less people in the project area
6 7 8 9 10 11 12 No. of SHGs to be given training
Total assistance received by the SHG Total annual Income
generated
Total No. of SHGs Total Amount of Loan Sanctioned
by banks
No. of SHGs
Federated
Loan from revolving fund
Training Material Others I II III (pl.specify)
02 nos 0.2 0.2 1.0 1.6 0.2 Not graded Not yet process 2 nos 12 nos 1.2 1.2 2.4 6.0 1.2 Not graded Not yet process 11 nos 10 nos 1.0 1.0 5.0 8.0 1.0 Not graded Not yet process 10 nos 7 nos 0.7 1.4 2.1 5.6 1.4 Not graded Not yet process 7 nos 8 nos 0.8 0.8 1.6 4.0 0.8 Not graded Not yet process 8 nos 2 nos 0.2 0.2 0.8 1.6 0.4 Not graded Not yet process 2 nos 4 nos 0.4 0.4 0.8 2.0 0.4 Not graded Not yet process 2 nos 7 nos 0.7 0.7 1.4 3.5 0.7 Not graded Not yet process 7 nos 2 nos 0.2 0.2 0.4 1.0 0.2 Not graded Not yet process 2 nos 2 nos 0.2 0.2 0.2 1.0 0.4 Not graded Not yet process 2 nos 3 nos 0.3 0.3 0.9 2.4 0.9 Not graded Not yet process 3 nos 6 nos 0.6 0.6 1.2 3.0 0.6 Not graded Not yet process 5 nos 2 nos 0.2 0.2 0.3 1.0 0.3 Not graded Not yet process 2 nos 1 nos 0.1 0.1 0.2 0.5 0.2 Not graded Not yet process 1 nos 2 nos 0.2 0.2 0.3 1.0 0.3 Not graded Not yet process 2 nos 1 nos 0.1 0.1 0.2 0.5 0.2 Not graded Not yet process 1 nos 3 nos 0.3 0.3 0.5 1.5 0.5 Not graded Not yet process 3 nos 3 nos 0.3 0.3 0.3 1.5 0.6 Not graded Not yet process 2 nos
77 nos 7.70 8.40 19.50 45.70 10.20 72 nos
55
Table-M(PA)B4: Activities related to livelihoods by Self Help Groups (SHGs) Under Production System & Micro Enterprises in the project area
1 2 3 4 5
SL. N
o.
Nam
e of
the
Stat
e
Nam
e of
the
dist
rict
Nam
e of
the
proj
ect
Major activities of the SHGs Name of activity No. of
SHGs involved
Average annual income
from activity per SHG
1 Assam Dhubri Selai Gadadhar
1 Piggery – Breaded 16 nos 0.8
2 Duck Rearing 20 nos 0.5
3 Milch Cow 16 nos 0.8
4 Bicycle Repairing 8 nos 0.5
5 Handloom 26 nos 0.8
6 Pottary Making 3 nos 0.5
7 Fruit Processing 10 nos 0.8
8 Carpenter 8 nos 0.5
9 Mobile Repairing 3 nos 0.5
10 Bike Repairing 2 nos 0.5
11 Vermi Compost 6 nos 0.5
12 Fishery Dev./ Fish Farming (25 x 30) m2 18 nos 0.8 13 Bamboo Craft 3 nos 0.5
14 Wood Craft 2 nos 0.5
15 Blacksmith 2 nos 0.5
16 Jaru Making 2 nos 0.5
17 Tarja Making 6 nos 0.5
18 Bee-Keeping 6 nos 0.5
Total: 157
56
Table-M(PA)B4: Activities related to livelihoods by Self Help Groups (SHGs) Under Production System & Micro Enterprises in the project area
6 7 8 9 10 11 12 No. of
SHGs to be given
training
Total assistance received by the SHG (Rs. In Lakh)
Total annual Income
generated (Rs. In Lakh)
Total Annual
Savings (Rs. In Lakh)
No. of SHGs Graded as
Total Amount of loan
sanctioned by the banks (s)
No. of SHGs
federated
Loan from revolving
fund
Training Material Others (pl.specify)
I II III
16 nos 1.60 1.60 8.00 - 12.80 1.60 Not graded Under process 16 nos 20 nos 2.00 2.00 4.00 - 10.00 2.00 Not graded -do- 20 nos 16 nos 1.60 1.60 8.00 - 12.80 1.60 Not graded -do- 16 nos 8 nos 0.80 0.80 1.60 - 4.00 0.80 Not graded -do- 8 nos 26 nos 2.60 5.20 7.80 - 20.80 5.20 Not graded -do- 26 nos 3 nos 0.30 0.30 0.60 - 1.50 0.30 Not graded -do- 3 nos 10 nos 1.00 1.00 2.00 - 5.00 1.00 Not graded -do- 10 nos 8 nos 0.80 0.80 1.60 - 4.00 0.80 Not graded -do- 8 nos 3 nos 0.30 0.30 0.60 - 1.50 0.30 Not graded -do- 3 nos 2 nos 0.20 0.20 0.40 - 1.00 0.20 Not graded -do- 2 nos 6 nos 0.60 0.60 1.20 - 3.00 0.60 Not graded -do- 6 nos 18 nos 1.80 1.80 3.60 - 9.00 1.80 Not graded -do- 18 nos 3 nos 0.30 0.30 0.60 - 1.50 0.30 Not graded -do- 3 nos 2 nos 0.20 0.20 0.40 - 1.00 0.20 Not graded -do- 2 nos 2 nos 0.20 0.20 0.40 - 1.00 0.20 Not graded -do- 2 nos 2 nos 0.20 0.20 0.40 - 1.00 0.20 Not graded -do- 2 nos 6 nos 0.60 0.60 1.20 - 3.00 0.60 Not graded -do- 6 nos 6 nos 0.60 0.60 1.20 - 3.00 0.60 Not graded -do- 6 nos
157 Nos. 15.70 18.30 43.60 95.90 18.30 157 Nos.
57
Table-M(PA)B5: Other activities of watershed works phase*
Table-M(PA)B6: Details of engineering structures in watershed works*
1 2 3 4 5 6 7 8 9
Sl. No.
Stat
e
Dis
tric
t
Proj
ect/
MW
S
Name of Structures
Type of treatment Type of land Executing
Agency Target
(i) R
idge
are
a (R
)
(ii) D
rain
age
line
(D)
(iii)
Lan
d de
v. (L
)
(i) P
riva
te
(ii) C
omm
unity
(iii)
Oth
ers (
pl. s
peci
fy) (i) UG
(ii)SHG
(iii) Others
(pl. specify)
No. of units (No./ cu.m./ Rmt)
Estimated cost (Rs. in lakh) Expected month & year
of completion (mm/yyyy)
M W O T
1
Ass
am
Dhu
bri
Sela
i Gad
adha
r Se
lai M
WS
Boulder Spur (In RM) Y Y UG 30 0.61 0.22 0.04 0.87 3RD Year
Distribution Channel (In RM)
Y Y UG 3200 0.46 2.46 0.15 3.07 2ND & 3rd Year
Earthen embankment without core wall (In RM)
Y Y UG 7000 2.10 11.20 0.70 14.00 1st , 2nd , 3rd & 4th Year
Boulder Revetment (In RM)
Y Y UG 1274 18.05 6.45 1.28 25.78 3rd & 4th Year
Nulla Bund with provision of slab culvert (In RM)
Y Y UG 1000 3.76 2.19 0.32 6.27 4th year
Sub Total 24.98 22.52 2.49 49.99
Gad
adha
r
Excavated Pond (In M3) Y Y UG 1200 0.10 0.54 0.04 0.68 4th Year
Distribution Channel (in RM)
Y Y UG 3010 0.43 2.31 0.15 2.89 1st & 3rd Year
Earthen embankment without core wall (In RM)
Y Y UG 2975 0.89 4.76 0.30 5.95 1st , 2nd , 4th Year
59
RCC Check Dam (In M2) Y Y UG 20 4.26 2.48 0.36 7.10 3rd year
Boulder Revetment (In RM)
Y Y UG 366 5.19 1.85 0.38 7.42 2nd , 3rd & 4th Year
Boulder Spur (In RM) Y Y UG 411 8.34 2.98 0.60 11.92 1st Year
Sub Total 19.21 14.92 1.83 35.96
Tia
mar
i
Boulder Revetment (In RM)
Y Y UG 1093 15.49 5.53 1.11 22.13 2nd Year
Earthen Embankment without core wall (In RM)
Y Y UG 12945 3.80 20.71 1.38 25.89 1st , 2nd , 3rd & 4th Year
Distribution Channel (In RM)
Y Y UG 5533 0.89 4.74 0.29 5.92 2nd , 3rd & 4th Year
Earthen Check dam (In M3)
Y Y UG 1000 0.18 0.98 0.06 1.22 3rd Year
Excavated Pond (In M3) Y Y UG 15017 1.28 6.85 0.43 8.56 1st Year
Earthen embankment with core wall (In RM)
Y Y UG 2324 5.57 5.02 0.56 11.15 3rd & 4th Year
Boulder Pitching (In M2) Y Y UG 331 1.99 0.71 0.14 2.84 2nd & 3rd Year
Boulder Spur (In RM) Y Y UG 200 4.06 1.45 0.29 5.80 2nd Year
Sub Total 33.26 45.99 4.26 83.51
Grand Total 77.45 83.43 8.58 169.46
60
Table-M(PA)B7: Details of activities connected with vegetative cover in watershed works*
1 2 3 4 5 6 7 8 9
Sl. N
o.
Stat
e
Dis
tric
t
Proj
ect/
MW
S Name of structure/ work
Type of treatment Type of land Executing ancy Target
(i) Ridg
e area (R)
(ii) Drainage line (DL)
(iii) Lan
d dev. (L)
(i) Pvt.
(ii) Comm.
(iii) Others (pl. specif
y)
(i) UG (ii) SHG (iii) Others (IB)
Area (ha)
No. of plants
Estimated cost
(Rs. In Lakh)
Expected month & year of
completion (mm/ yyyy)
1
Ass
am
Dhu
bri
Sela
i Gad
adha
r
Sela
i
Afforestation (stamp planting)
Y - - Y Y - UG 5.40 5400 1.48 1st & 4th Yr
Aff. Regenaration y - - - Y - UG 3.00 3000 0.55 3rd year Crop Demo (Paddy) - - y y - - IB 16.50 - 2.48 2nd Year
Crop Demo (Potato/ Veg) - - y y - - IB 9.50 - 2.28 2nd Year
Sub Total 34.40 8400 6.79
Gad
adha
r Crop Demo (Potato/ Veg) - - y y - - IB 8.50 - 2.28 2nd Year Crop Demo (Paddy) - - Y y - - IB 14.00 - 2.10 2nd Year Afforestation (stamp planting)
y - - - y - UG 5.00 5000 1.36 4th Year
Sub Total 27.50 5000 5.74
Tia
mar
i
Afforestation (stamp planting)
y - - y y - UG 10.00 10000 2.74 2nd,3rd &4th
Horticulture Nursery Raising y - - y - - UG 0.50 100000 1.50 1st year Crop Demo (Potato/ Veg) - - y y - - IB 5.50 - 1.32 2nd Year Crop Demo (Paddy) - - y y - - IB 14.00 - 2.10 2nd Year Sub Total 30.00 110000 7.66
Grand Total 91.90 123400 20.19
61
Table-M(PA)B8: Details of allied / other activities
1 2 3 4 5 6 7 8 Sl. No.
State District Project Name of activity@
Type of land Executing agency Target (i)
Pvt. (ii)
Comm. (iii) Others (pl.
specify) (i) UG (ii)SHG (iii) Others (pl. specify)
PROPOSED ACTION PLAN UNDER ENTRY POINT ACTIVITIES (EPA)
Treatable Area: 3161 ha. Financial Outlay; Rs. 15.17 lakhs
Table-M(PA)A1: Entry point activities (EPA). (Rs. in lakh)
1 2 3 4 5 6 7 8 9 10 11
S. N
o.
Stat
e
Dis
tric
t N
ame
of
proj
ect
Am
ount
ea
rmar
ked
for
EPA
Entry Point Activities planned with Name of villages ***
Est
imat
ed c
ost
Exp
endi
ture
in
curr
ed
Bal
ance
Exp
ecte
d ou
tcom
e
Rem
arks
1
Ass
am
D
hubr
i
Sela
i Gad
adha
r
15.1
7
Selairpar I 1) Installation of HTW=3No. 22500.00 - - For drinking purpose.
The
sche
mes
and
est
imat
ed c
ost a
s pro
pose
d by
Pro
ject
Man
ager
. D
etai
led
estim
ates
are
to b
e pr
epar
ed a
nd sa
nctio
ned
by th
e SL
NA
/DW
DU
.
Selairpar II (Charjogipara)
1) Installation of HTW=3Nos. 22500.00 -do-
Shyamcharanerkuti I 1) Installation of HTW=2Nos. 15000.00 - - -do- Shyamcharanerkuti II 1) Installation of HTW=2No. 15000.00 - - -do- Shyamcharanerkuti III 1) Installation of HTW=2Nos. 15000.00 - - -do- Sajuarkuti 1) Installation of HTW=4Nos. 30000.00 -do- Kheraj Daobhangi 2) Plantation at Daobhangi Junior
College 50000.00
To conserve ecological balance.
Daobhangi 1) Installation of HTW=5Nos. 37500.00 For drinking purpose. Geramari I *** 2) Boundary wall and Office
repairing of Gauripur S.C. Range alomganj 335500.00
To protect public property
1) Installation of HTW=2Nos. 15000.00 For drinking purpose. Geramari II
1) Installation of HTW=2Nos. 15000.00 -do- 2) Boundary wall of GP Office Uttar Geramari
50000.00
-do-
Geramari III 1) Installation of HTW=2Nos. 15000.00 -do- Geramari VI 1) Installation of HTW=2Nos. 15000.00 -do- Modaikhali 1) Installation of HTW=2Nos. 15000.00 -do-
64
Beguntali 1) Installation of HTW=2Nos. 15000.00 -do- Asharikandi
1) Installation of HTW=2No. 15000.00 -do- 2) Nursery at Asharikandi 50000.00 Seedlings to be distributed 1) Installation of HTW=2No. 15000.00 -do-
*** The work of boundary wall and office repairing of Gouripur Range is to be taken up only with specific approval from the SLNA /DWDU as such works are not generally undertaken under entry point activities.
Folimari I 2) Repairing of Janakalyan Society Club
49500.00
To protect public property
-do-
Folimari II 1) Installation of HTW=2Nos. 15000.00 For drinking purpose. Dubirchar 1) Installation of HTW=4Nos. 30000.00 -do- Chapgarh I 2) Plantation of Chapgarh ME
School & High School 80000.00
To conserve ecological balance.
Charaldanga 1) Installation of HTW=3Nos. 22500.00 For drinking purpose. Bhelakoba 1) Installation of HTW=3Nos. 22500.00 -do- Tiamari I 1) Installation of HTW=2No. 15000.00 -do- Tiamari II 1) Installation of HTW=2No. 15000.00 -do-
2) Plantation at High Madrassa 30000.00
To conserve ecological balance.
Brahmattar Selairpar 1) Installation of HTW=3No. 22500.00 For drinking purpose. Fulkumari 1) Installation of HTW=4Nos. 30000.00 -do- Hariarkuti 2) Plantation at Hariarkuti LP
School 30000.00
-do-
Bhouspuri 1) Installation of HTW=2Nos. 15000.00 -do- Khudimari I 1) Horticultural Nursery 347000.00 Seedlings to be distributed
2) Installation of HTW=2No. 15000.00 For drinking purpose. Khudimari II 1) Installation of HTW=2No. 15000.00 -do-
Grand Total: 15,17,000.00
65
Table DPR 6: Year wise phasing of Selai Gadadhar IWM Project for 5 (five) years Plan (IWMP)
Name of the District: Dhubri Name of watershed:-Selai Godadhar
Total project area:- 5393 ha Treatable area:- 3160.80 ha Project cost:- 379.30 Lakh
Component 1st Year 2nd Year 3rd Year 4th Year 5th Year