Top Banner
1 | Page
134

Design Report Final

Jan 20, 2023

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Design Report Final

1 | P a g e

Page 2: Design Report Final

© 2010, Calvin College and Chris Crock, Aaron Lammers, Brent Long, Aaron Raak.

Page 3: Design Report Final

Abstract

Carabuela is a small village located in northern Ecuador that currently has a flawed wastewater treatment

system. Working alongside the organization Heralding Christ Jesus Blessings (HCJB), WasteWatchers

designed a new wastewater treatment system for Carabuela. Throughout the project, the team considered

three design norms: cultural appropriateness, stewardship and transparency. Using these norms as a guide,

the team designed a bar rack system, grit chamber, Imhoff Tank, lagoon system, and drying beds as part

of the new wastewater treatment system. The amount of BOD, TSS and pathogens removed were

acceptable to standards for irrigation. Effluent BOD levels were reduced by 97% down to 2.6 mg/L. The

faecal coliform levels were reduced by 4 log removal (~99.995%) to 915 faecal coliforms per 100 mL.

The helminth egg levels were reduced by 4 log removal down to 0.1 eggs per liter.

The estimated total construction cost for the project would be $31,000. Operations and maintenance

would cost approximately $14,000 per year. We hope to obtain some grant funds for the initial

construction and ongoing operations and maintenance. It is the intention of this project that the system be

constructed in the village once the people approve it.

Page 4: Design Report Final

i | P a g e

Table of Contents

1. Introduction ............................................................................................................................................... 7

1.1 The Team ...................................................................................................................................... 7

1.2 The Project .................................................................................................................................... 7

1.3 Project Background ....................................................................................................................... 8

2 Project Management ............................................................................................................................. 9

2.1 Team Organization ........................................................................................................................ 9

2.2 Schedule ...................................................................................................................................... 10

2.3 Budget ......................................................................................................................................... 11

2.4 Method of Approach ................................................................................................................... 11

3 Requirements ...................................................................................................................................... 11

3.1 Performance Requirements ......................................................................................................... 11

3.1.1 Water Effluent ..................................................................................................................... 11

3.1.2 Sludge Effluent ................................................................................................................... 12

3.2 Functional Requirements ............................................................................................................ 12

3.3 Team Deliverables ...................................................................................................................... 13

4 Task Specifications and Schedule ....................................................................................................... 13

5 System Architecture ............................................................................................................................ 15

6 Design Criteria .................................................................................................................................... 17

6.1 Bar Rack...................................................................................................................................... 17

6.2 Grit Chamber .............................................................................................................................. 18

6.3 Imhoff tank .................................................................................................................................. 18

6.4 Lagoon System ............................................................................................................................ 19

6.5 Sludge Treatment ........................................................................................................................ 19

7 Design Alternatives ............................................................................................................................. 19

7.1 Bar racks ..................................................................................................................................... 19

Page 5: Design Report Final

ii | P a g e

7.1.1 Introduction: ........................................................................................................................ 19

7.1.2 Design Considerations for Inclined Bar Racks ................................................................... 20

7.2 Grit Chamber .............................................................................................................................. 25

7.2.1 Introduction: ........................................................................................................................ 25

7.2.2 Vortex Grit Chamber .......................................................................................................... 25

7.2.3 Modified Vortex Chamber .................................................................................................. 25

7.2.4 Old Septic Tank .................................................................................................................. 26

7.2.5 Rectangular Open Channel ................................................................................................. 26

7.2.6 Design Considerations: (Vesilind, 2003) ............................................................................ 27

7.3 Imhoff Tank ................................................................................................................................ 28

7.3.1 Septic Tank ......................................................................................................................... 28

7.3.2 Imhoff Tank ........................................................................................................................ 30

7.3.3 Primary Lagoon System ...................................................................................................... 31

7.4 Lagoon System ............................................................................................................................ 31

7.4.1 Aerated Ponds ..................................................................................................................... 31

7.4.2 Anaerobic Ponds ................................................................................................................. 32

7.4.3 Aerobic Ponds ..................................................................................................................... 32

7.5 Sludge Treatment Design Alternatives ....................................................................................... 32

7.5.1 Mechanical Alternatives ..................................................................................................... 33

7.5.2 Drying Lagoons................................................................................................................... 33

7.5.3 Drying Beds ........................................................................................................................ 33

8 Design Decisions ................................................................................................................................ 35

8.1 Bar racks ..................................................................................................................................... 35

8.2 Grit Chamber .............................................................................................................................. 37

8.3 Imhoff Tank ................................................................................................................................ 39

8.4 Lagoon System ............................................................................................................................ 40

8.5 Sludge Drying Beds .................................................................................................................... 41

Page 6: Design Report Final

iii | P a g e

9 Hydraulic Analysis .............................................................................................................................. 42

10 Environmental Design..................................................................................................................... 44

10.1 Bar Racks and Grit Chamber ...................................................................................................... 44

10.2 Imhoff Tank ................................................................................................................................ 45

10.3 Waste Stabilization Lagoons ....................................................................................................... 48

10.4 Sludge Drying Beds .................................................................................................................... 50

11 Structural Design ............................................................................................................................ 50

11.1 Bar Racks .................................................................................................................................... 50

11.2 Grit Chamber .............................................................................................................................. 51

11.3 Imhoff Tank ................................................................................................................................ 53

11.4 Waste Stabilization Lagoons ....................................................................................................... 54

11.5 Sludge Drying Beds .................................................................................................................... 55

12 Grant Proposal ................................................................................................................................ 56

12.1 Executive Summary .................................................................................................................... 56

12.2 Background Information ............................................................................................................. 57

12.3 Problem Statement ...................................................................................................................... 57

12.4 Project Detail .............................................................................................................................. 59

12.4.1 Goals and Objectives .......................................................................................................... 59

12.4.2 Clientele .............................................................................................................................. 60

12.4.3 Methods ............................................................................................................................... 60

12.5 Staff/Administration ................................................................................................................. 60

12.6 Needed Resources ....................................................................................................................... 61

12.7 Goal #1—Design a wastewater treatment system ....................................................................... 62

12.8 Goal #2—Plan with cultural appropriateness ............................................................................. 62

12.9 Strategy for evaluation of effectiveness ...................................................................................... 63

13 Conclusion ...................................................................................................................................... 63

14 Future Work to be Completed ......................................................................................................... 64

Page 7: Design Report Final

iv | P a g e

15 Works Cited .................................................................................................................................... 66

16 Acknowledgements ......................................................................................................................... 68

17 Appendices ...................................................................................................................................... 69

Page 8: Design Report Final

v | P a g e

Table of Figures

Figure 1: Wastewater Treatment Process ...................................................................................................... 8

Figure 2: Organization Chart ...................................................................................................................... 10

Figure 3: Task Specifications and Schedule ............................................................................................... 14

Figure 4: System Architecture .................................................................................................................... 16

Figure 5: Example of Manually Raked Bar Screen .................................................................................... 24

Figure 6: Sutro Weir ................................................................................................................................... 26

Figure 7: Long narrow grit chamber where heavier inorganics are removed ............................................. 28

Figure 8: Septic Tank Schematic ................................................................................................................ 29

Figure 9: Imhoff Tank Schematic ............................................................................................................... 30

Figure 10: Several Lagoon System Schematics .......................................................................................... 31

Figure 11: System Flow Rate during Rainfall ............................................................................................ 43

Figure 12: Weir Design ............................................................................................................................... 45

Figure 13: Imhoff Cone Depth .................................................................................................................... 47

Figure 14: General Bar Rack Design .......................................................................................................... 50

Figure 15: Grit Chamber General Design ................................................................................................... 51

Figure 16: Plan View .................................................................................................................................. 55

Figure 17: Side View .................................................................................................................................. 56

Page 9: Design Report Final

vi | P a g e

Table of Tables

Table 1: Channel Width Calculations ......................................................................................................... 22

Table 2: Typical Design Criteria for Coarse Screening Equipment............................................................ 23

Table 3: Typical Design Properties for coarse Screenings ......................................................................... 23

Table 4: Table of bar types and their respective shape factors ................................................................... 24

Table 5: Grit Chamber Calculations and Dimensions ................................................................................. 28

Table 6: Estimated grit quantities for a Detritus tank ................................................................................. 28

Table 7: Drying Bed Materials.................................................................................................................... 34

Table 8: Drying Bed Costs .......................................................................................................................... 35

Table 9: Bar Rack Decision Matrix ............................................................................................................ 36

Table 10: Grit Chamber Decision Matrix ................................................................................................... 37

Table 11: Lagoon Decision Matrix ............................................................................................................. 41

Table 12: Sludge Drying Decision Matrix .................................................................................................. 41

Table 13: Side Overflow Weir flows .......................................................................................................... 44

Table 14: Design Criteria for Unheated Imhoff Tanks ............................................................................... 46

Table 15: Bar rack and grit chamber cost estimate ..................................................................................... 53

Table 16: Imhoff Tank Cost Estimate ......................................................................................................... 54

Page 10: Design Report Final

7 | P a g e

1. Introduction

1.1 The Team

Proper sanitation facilities are denied to over two-thirds of the world‘s

population—including the rural village of Carabuela, Ecuador. In the

mountainous region of northern Ecuador, residents of Carabuela face the

problem of inadequate wastewater treatment. WasteWatchers, comprised

of four civil/environmental engineers, worked in conjunction with

Heralding Christ Jesus Blessings (HCJB) to design a wastewater

treatment facility for this village. We chose this project because of our

passion for water quality in underdeveloped regions. The goal of our

project was to design an effective system that included cultural

appropriateness, transparency, and stewardship. We designed a treatment

process and facility using proven technologies, requiring no electricity with minimal maintenance, and

involving low complexity.

1.2 The Project

Over 80% of Ecuador‘s wastewater goes untreated, and one example of this is the village of Carabuela, a

community of 200 homes near the Pan American highway about two hours‘ drive from the capital, Quito.

At present, wastewater goes mostly untreated into a nearby stream. We are connected to Carabuela

through HCJB (Heralding Christ Jesus Blessing), a group that works to bring water sanitation and

hygiene to rural communities.

For this project we designed a water treatment system to reduce the pathogen content of the effluent, use

the effluent water for irrigation, and to possibly use the treated sludge for fertilizer. The design involved

the use of a bar rack and grit chamber to remove large objects and solids in the waste stream, an Imhoff

tank for primary settling and biological digestion, waste stabilization ponds to reduce Biochemical

Oxygen Demand (BOD) and pathogens, and sludge drying beds that treat the sludge produced from the

Imhoff tank and the grit chamber. The effluent water was treated sufficiently to be routed to nearby fields

as irrigation water.

Page 11: Design Report Final

8 | P a g e

Figure 1: Wastewater Treatment Process

We chose this project because it has the potential to enhance public safety, to promote a sustainable use of

the land, and to improve stewardship of the earth in this locality. Water-borne diseases are a major health

concern; according to the World Health Organization (WHO), ―Globally improving water, sanitation, and

hygiene has the potential to prevent at least 9.1% of the disease burden‖. One important method is

wastewater treatment, which can drastically cut the spread of cholera, dysentery, and many other

diseases., Diarrhea, a common symptom of these diseases, is responsible for the deaths of 1.8 million

people every year. At present a stream is polluted with human waste. Sanitized wastewater can safely

irrigate crops helping agriculture while reducing the amount of water taken from the environment and

avoiding contamination of an important local resource.

1.3 Project Background

Our design included the typical processes used in developed countries—screening, sedimentation,

anaerobic digestion, sludge handling, and waste stabilization—however, the components of the system

were far less complex and costly. The screening process used a system of bars that removes large objects

floating in the waste stream. Sedimentation and anaerobic

digestion both occur in the Imhoff tank, which also separates

solids from the stream. The sludge (solids removed by the

Imhofff) was then moved to in-ground beds for drying and

inactivation of possible pathogens. Then, waste stabilization,

the final process before irrigation reuse, used manmade ponds

to remove and inactivate any remaining pathogens in the

stream.

Page 12: Design Report Final

9 | P a g e

Issues faced by our team were: communicating cross culturally, determining quality standards without

"overkill", gathering data from long distances, and applying design norms that were suitable for our

customer. We overcame these problems with conference calls, consultations with industrial mentors,

researching similar case studies, and learning the culture of our customer. Involvement with this project

exemplified our ability to research unfamiliar technologies, interpret data, and understand cultural

differences and values of people we work with.

2 Project Management

2.1 Team Organization

The team consisted of four senior civil engineering students who each designed one of the four major

components of the wastewater treatment system. The following describes the roles of each team member.

Christopher Crock‘s role was to research various types of grit chambers and bar racks that would be best

for the project‘s situation. He then sized the grit chamber and bar racks he deemed appropriate, and Aaron

Lammers tackled the structural design of both components using the ACI metric code and moment

analyses. Aaron Lammers‘ role was to research the Imhoff Tank and design its environmental parameters

pertaining to Carabuela‘s situation. After Aaron Lammers calculated the necessary dimensions of the

Imhoff Tank, Chris Crock undertook the structural design of the Imhoff Tank, while still collaborating

with Aaron Lammers, using the ACI metric building code and finite element analyses in STAADPro.

Brent Long‘s role was to examine various stabilization ponds. After determining which pond system to

use, he developed structural drawings of the pond system that showed a plan view and cross sectional

views. Also, Brent calculated the amount of storm water that would enter the system from roof drains

during heavy storm period events so that fluctuating flow rates would be accounted. Aaron Raak‘s role

was to decide an appropriate size for the drying beds. He constructed the layout of the drying beds using

computer software. His role also included calculating the storm water that would enter the system and

calculated the TSS removal in the system.

Page 13: Design Report Final

10 | P a g e

Figure 2 is an organizational chart that shows the structure of the working relationships within this

project. At the top is the client, followed by the team‘s consultant and advisor, and finally the team

members. The team‘s main priority was to follow the client‘s recommendations. Whenever there was

information that was not communicated between the client and team members, the team would meet with

the team consultant and advisor.

The team met every other day from 3:30 pm to 4:20 pm on Monday, Wednesday and Friday to give a

project update. The team collaborated at this time to discuss any problems that they encountered during

their design process and possible solutions to resolve them. Because each team member designed a

component of the system, it was important that everyone communicated to each other about their

approach to strengthen the integrity of the project. After the meetings, the team would segregate, and

members accomplish their specific tasks according to a team decision. All important documents were kept

on a shared server space on the network. It was organized so that each team member could upload their

data in their specific component‘s folder so that could be easily accessed in an organized manner. The

location of this information can be found at the following address on Calvin College‘s server:

/NetStorage/DriveS@SHARED/Engineering/Teams/Team05 - WasteWatchers

2.2 Schedule

At the beginning of the project, the team met to discuss a schedule by which they would follow during the

remainder of the project. The schedule consisted of major deadlines given by the team advisor and

personal team goals that needed to be completed at certain times. Overall, the team was on schedule with

an exception of a few times when deadlines would be pushed back a couple of days because they

required more time to complete. Most of the changes to the schedule occurred when there were smaller

Team Member: Christopher Crock

Team Member: Aaron Lammers

Team Member: Brent Long

Team Member: Aaron Raak

Consultant: Tom Newhof

Client: Bruce Rydbeck

Advisor: Leonard DeRooy

Figure 2: Organization Chart

Page 14: Design Report Final

11 | P a g e

tasks that needed to be completed prior to the week or weeks they were to be delivered. Everyone

adjusted to the schedule well and the team never fell behind. No single person was in charge of the

schedule, but instead the team as a whole decided the schedule and kept everyone accountable. The

average amount of work each person put into the project was 10-15 hours a week. More work was put

into the project during the end of the semester and less at the beginning.

2.3 Budget

For this project there was not a budget specified by the customer. The, but HCJB did request the

wastewater treatment system to be economically feasible. See the section 3 Requirements for full details.

For every design decision, cost was a major factor. Although there was not a budget to follow, the team

addressed the necessity for a low cost system as much as possible.

2.4 Method of Approach

One of the requirements mentioned in section 3 Requirements is that the wastewater treatment system

must be a proven technology. That is to say, the design could not be created from scratch but based off

technologies that have already been implemented in the real world. The team approached the design by

researching various wastewater treatment systems in the world. There are several different constituents to

a wastewater system, so the team decided which ones were appropriate for the village of Carabuela. After

deciding which constituents were necessary, each team member took a specific part and researched

various types of units for their constituent. Remembering the design norms, the team agreed uponwhich

element would be used in the system. After all parts were decided, the next phase was to design a way to

unify the components as one complete system

3 Requirements

3.1 Performance Requirements

3.1.1 Water Effluent

The wastewater produced and discarded by the community needs to be treated to acceptable

levels. The effluent was treated to be used to irrigate a field of alfalfa, a crop not consumed

by humans. The relevant standards of the Ecuadorian government for wastewater effluents

used for agricultural purposes are zero helminth eggs and a coliform count of 1,000/100 mL.

The World Health Organization (WHO) sets the E. coli limit for leafy crops at 104 E. coli/

100mL; at this level of treatment, other pathogens are assumed to be treated as well (World

Health Organization, 2006).

Page 15: Design Report Final

12 | P a g e

1. Coliform count of <1000/100mL

2. BOD under 2.0 mg/L

3. <1 helminth eggs/100mL

3.1.2 Sludge Effluent

1. The sludge was to be treated until it could be used as fertilizer

1000 E. coli/g solids and <1 helminth egg/g solids satisfy WHO safety requirements (World

Health Organization, 2006). However, if the sludge is to be used for alfalfa, it needed only

to meet lesser requirements, as Class B sludge. Due to the limited amount of research in the

area, the US Environmental Protections Agency has determined that if the sludge has gone

through one of 6 processes for the significant reduction of pathogens (PSRPs) it may be

applied to crops with certain restrictions.

3.2 Functional Requirements

1. The design must handle the amount of wastewater produced by the entire population as it will be

in 20 years

Currently it has about 1700 people, but after 20 years at projected growth rates it will

contain about 2700 people.

2. None of the treatment methods may use electricity.

Utilities are unreliable at best in Carabuela.

3. The system must fit onto 0.5 hectares.

Land is limited in the hill country, and arable land is valuable and generally claimed already.

4. The system should not require any chemical additives.

This keeps the system sustainable, independent of outside vendors, and easier to operate.

5. The design should have no moving parts during normal operation.

It may have to run for years with haphazard maintenance.

6. The design should not require experts from outside the village to build it.

The local population can construct any required structures of wood or reinforced concrete

structures. They are described as resourceful and skilled in construction.

Page 16: Design Report Final

13 | P a g e

3.3 Team Deliverables

PPFS

Final Report

Design notebooks

Team website

Operations and maintenance manual

4 Task Specifications and Schedule

The tasks for this project can be summarized into 8 sections including: deciding and defining the project,

alternate research, preliminary design, environmental design, hydraulic design, structural design,

operation and maintenance and physical model. The general order of completion and task division can be

seen in Figure 3.

Page 17: Design Report Final

14 | P a g e

Figure 3: Task Specifications and Schedule

The task of deciding and defining the project was a full group task. Each member initially contacted

different non-profit organizations and gathered potential projects. The team met and decided on the most

feasible project. From that point the team was in contact with Bruce Rydbeck with HCJB to define what

Page 18: Design Report Final

15 | P a g e

the project entailed. The team was able to define the general plan for treatment. With this plan, the team

was then able to divide the process into four components that each member began to research. Chris

Crock worked on preliminary treatment, Aaron Lammers worked on primary treatment Brent Long

worked on tertiary treatment and Aaron Raak worked on sludge treatment. After much research, the team

met again and discussed the alternatives and chose components for the preliminary design. Each member

then started the preliminary design on the component they researched. The combination of the alternative

research and the preliminary design culminated in the Project Plan and Feasibility Study (PPFS). The

PPFS summarized all of the research and made recommendations as to the proposed components.

Directly following the PPFS, the team wrote a design memo that outlined how the project was going to be

completed in the next semester.

The next step in the design process was to complete the environmental designs and hydraulic analysis.

For this task the team broke into two sub-teams to better utilize time a resources. Chris Crock and Aaron

Lammers worked on the environmental design while Brent Long and Aaron Raak worked on the

hydraulic analysis. Out of this environmental work, the sizes for all environmental components were

completed along with a detailed hydraulic analysis of the impact of rainfall on the influent flows. Next the

group once again divided up the components to complete the structural designs and drawings for each

component. Chris Crock worked on the Imhoff tank (with help from Aaron Lammers), Aaron Lammers

worked on the bar racks and grit chamber, Brent Long worked on the lagoon system and Aaron Raak

worked on the sludge drying beds. To complete the wastewater system, it was necessary to create a

maintenance and operations manual to be given to the residents of Carabuela. This task was divided into

each component, and each member wrote the section that they had initially researched. The final

component of this project was the physical model. This model was constructed to increase the

understanding about the design and to test simple hydraulics. This task was completed at various times

throughout the spring semester. A final design report and plan set was sent to Bruce Rydbeck at HCJB to

be presented to the residents of Carabuela as an alternative solution to their current wastewater problem.

5 System Architecture

The system architecture shown in Figure 4 presents the process of the proposed wastewater treatment

facility and its flow organization along with the output characteristics of each component. The bar racks

and grit chamber remove only the larger particles and objects in the wastestream; therefore, the effluent

properties of these components are unchanged from the input. The Imhoff Tank then removes 50% of

BOD, based on proven research (Sasse, 1998) and TSS is reduced by 66%. The sludge from the grit

chamber was designed to be treated in the sludge drying beds, and the effluent stream from the Imhoff

Page 19: Design Report Final

16 | P a g e

Tank was routed to stabilization lagoons where pathogen and BOD levels are further reduced to levels

acceptable for irrigation reuse. The final effluent from the stabilization ponds was treated for irrigation of

a nearby alfalfa field for animal consumption.

Figure 4: System Architecture

Page 20: Design Report Final

17 | P a g e

6 Design Criteria

Carabuela, Ecuador required a specific wastewater treatment system that appropriately treated their

wastewater with the effluent to be used for irrigation. For Carabuela, the approach for design followed

specific design norms that fit with the customer. WasteWatchers developed seven criteria that resolve the

challenges in the design of the wastewater treatment facility:

1. Effective Treatment

a. Appropriate BOD levels

b. Reduction in TSS

c. Appropriate pathogen removal for irrigation reuse

2. Culturally Appropriate

a. Local materials used for construction

b. Local construction methods and practices

c. Proven Technology - similar wastewater treatment cases

3. Sustainability

a. No electricity

b. Lower levels of sophistication

4. Site Appropriate

a. Plan view footprint

b. Required equipment for construction

5. Low Cost

a. Cost of construction

b. Cost of maintenance

6. User Friendliness

a. Transparency

b. Trustworthiness

c. Simplicity in operation

7. Life of Design

6.1 Bar Rack

Although the screening process of wastewater treatment is fairly simple (even more so for manually

cleaned screens), the design norms and criteria of WasteWatchers heavily affected the design of this unit

process because of the importance in removal of screenings in the waste stream. Design norms were the

same for each unit process, but the details within each norm and criteria differ for each component.

Page 21: Design Report Final

18 | P a g e

Within the bar rack component, certain criteria were weighted heavier than others, these being: cultural

appropriateness, user-friendliness, and effective treatment. Cultural appropriateness was important

because of the simplicity of a bar rack. The user-friendliness of the bar rack was important, as

maintenance for this component should be simple and easy to maintain. As with all components, the

effective treatment was also important for the design.

6.2 Grit Chamber

As the second unit process in the treatment facility, the grit chamber is crucial for removing settleable

solids, yet scouring organics so that they will continue downstream. This stage of the process was

designed using the same criteria as the screening but with changes in the scoring and alternatives. Again,

the system was designed with the customer in mind, and the design norms were a major component in the

design of the grit chamber.

Because the grit chamber is important in preliminary treatment, the design decisions were heavily

weighted by the effectiveness of the design, user-friendliness, and low cost. With these criteria most

heavily weighted, the design decisions were influenced.

6.3 Imhoff tank

The essential design criteria for choosing a primary treatment method for this location were effective

treatment, cultural appropriateness, sustainability, and site appropriateness. Effective treatment was

crucial because if the system does not effectively treat the water its benefit would not outweigh the

necessary cost to construct. Cultural appropriateness was crucial to the decision of a primary treatment

method because of the capital cost associated with its construction and the necessity of a proven

technology. Primary treatment alternatives were typically expensive and required intricate construction.

It was necessary to design a component that can be built by the local people with materials that are also

local. Local workers and materials would lower the construction cost significantly as compared to the

alternative. Sustainability is vital because of the remoteness of the location. The design must not require

electricity because of the limited access to electrical power. Because of the rural nature of the location,

there are no major electrical sources near enough to provide constant power to a wastewater treatment

facility. The design must also have a low level of sophistication so that the local residents can be easily

trained to operate and maintain the system. Site appropriateness is crucial because some alternatives for

primary treatment are very effective and lower costs but would not be possible to construct based on land

Page 22: Design Report Final

19 | P a g e

availability and terrain. These four design criteria were the most crucial but all design criteria were

considered when deciding the optimal alternative.

6.4 Lagoon System

The criteria that were used in selecting the lagoon system consists the following: effective treatment,

cultural appropriateness, sustainability, site appropriateness, low cost, user friendliness and its length of

life. Out of these criteria, the most important ones that were considered were effective treatment and

cultural appropriateness. Because this is the last step in the treatment process before wastewater is

discharged, it is important that the waste is well treated. Cultural appropriateness plays in when deciding

the sophistication of the system. The lagoon system should not comprise any electrical equipment as this

would conflict with the culture of the people.

6.5 Sludge Treatment

For sludge treatment, sustainability and cultural appropriateness took precedence because in Carabuela

the largest danger of poor treatment comes from not having any treatment system in place. If the design

was not appropriate to the site, it could not be built, so all systems must fit onto the land available for

water treatment and be constructed with local materials. Effective treatment was also one of the most

important criteria; in this case, treatment means drying the sludge out until it can be handled like a solid,

and preferably used as fertilizer. Low cost was important to a relatively poor village, but if HCJB or the

government of Ecuador can be persuaded to fund the project in part or in whole then cost becomes

slightly less important. It is important that the sludge treatment be simple to use, but transparency was

less than vital. All the systems feasible for sludge treatment in rural use will easily last through the design

life of the overall system.

7 Design Alternatives

7.1 Bar racks

7.1.1 Introduction:

The first unit process in the treatment of wastewater is screening. In this unit process, larger, coarse solids

are removed through a system of bars or screens, and units that use parallel bars or rods are usually called

bar racks or bar screens. Because screening is the first unit process in wastewater treatment, it is

important that the system works properly, so processes further downstream are not inhibited by

screenings that would otherwise be allowed through the system. Screening helps to prevent the systems

Page 23: Design Report Final

20 | P a g e

downstream from being corrupted by ―rags and floatables‖ (wood, trash, large rocks, plastic, etc.), or

screenings, and help to produce the most effective treatment of wastewater. The screening process uses

either coarse or fine bar screens that can be mechanically or manually raked. Because mechanically raked

bar screens require power, the recommended technology for Carabuela, Ecuador would be a manually

raked, coarse bar screen, which would remove ―rags and floatables‖ in the range of 25-50 mm (Vesilind,

2003).

Three different components were considered in the design of the bar racks. These components were a

mesh screen fitted to the inlet of the grit chamber, a mesh cage that would lie on the bottom of the grit

chamber to catch ‗rags and floatables‘, and finally a set of racks made from rebar in a separate chamber

from the grit chamber. The decision matrix, , shows that the open channel with rebar bar racks as the

selected component.

7.1.2 Design Considerations for Inclined Bar Racks

The design of bar screens does not involve complex equations, but the understanding of the factors and

considerations are important to a design which requires little maintenance, no power, and long life. Listed

below are considerations that need to be thoroughly accounted for in the design of bar screens.

Manually cleaned screens demand frequent cleaning, so as to prevent clogging and the possibility

of flow surges when debris is removed.

A flow surge could cause ineffective grit removal and organics downstream.

The angle of incline is important as to provide effective area that minimizes headloss, while

maximizing the ease of cleaning.

Maximum approach velocities must be within the range 0.3 - 0.6 m/s for maximum flows in order

to prevent dislodgment or disintegration of larger particles.

Maximum velocities through the bar screen should be < 1 m/s to prevent dislodgment or

disintegration of larger particles.

Clear openings between bars are the most important factor in the design for removal quantities.

The purpose of screening is not to remove the organic matter, rather the large inorganics, wood,

trash, etc. because processes downstream will perform the organic removal process.

Accepted practice calls for a minimum headloss through a manually cleaned bar screen of 150

mm (fairly clean) and a maximum of 760 mm (clogged).

A drainage area for screenings is needed before shoveling and burial or delivery to the drying

beds.

Page 24: Design Report Final

21 | P a g e

o Nonslip platforms deserve special attention for cleaning and removal of screenings for

the workers.

o The drainage area must provide enough volume to store screenings long enough for

dewatering. (Vesilind, 2003)

Manually cleaned screens require frequent cleaning to prevent any clogging and excessive headloss, and

the frequency of cleaning will depend on the flows and also the quantity of screenings that are present in

the raw wastewater. The clear space of the bar rack was important in determining the amount of

screenings that will be removed and the characteristics of the screenings. Table 2 provides that the

openings between parallel bars would be 20 - 50 mm. The screening of excreta may create hygiene issues

with workers who must manually rake the rack and in the disposal of the screenings, therefore a proper

size that allows excreta to flow through but stops ―rags and floatables‖ should be considered. Quantities

and characteristics of coarse screenings can be seen in Table 2, and these values would be used to

calculate volume needs for treatment beds of sludge and also for the short-term storage on the drainage

area for screening.

Table 2 shows that the velocities through the screens should be limited to 0.6 m/s to prevent deposition or

displacement of any grit or rags and floatables (Mara, 2004), and due to the low flow system of Carabuela

(8 m3/person/month) this velocity was met with a minimum cross-section area of the influent channel of

only a couple centimeters. Because of the small required cross-sectional area of the channel, it was

suggested to use the designed channel height with a freeboard, the distance between the maximum water

surface elevation (WSE) and the top edge of the channel, of 0.5 meter, 0.76 meters for headloss, 0.037

meters for required minimum height of the wetted perimeter. The total height of the channel is suggested

to be 1.3 m. The channel width requires a total of 0.3 m, which includes the clear space and the bar

widths. The calculations used for determining the width of the channel can be seen in Table 1.

Page 25: Design Report Final

22 | P a g e

Table 1: Channel Width Calculations

98 m3/day Flow Rate (est.)

196 m3/day Max. Flow (est.)

0.00269 m3/s Max Flow

0.579 m/s Maximum approach velocity

207.6 cm^2 Flow Area for Approaching Channel (bars not accounted)

10.38 cm Channel Height (headloss and freeboard not accounted)

20.0 cm Channel Width (bars not accounted)

11.13 mm Bar thickness (#3 rebar)

20.0 mm Clear Spacing

6 #3 Rebar Required number of bars

155 mm Appropriate headloss for clean screens

760 mm Appropriate headloss for clogged screens

0.50 m Freeboarding

0.60 m Channel Height (w/ freeboard and headloss)

0.20 m Channel Width (bars accounted for)

207.6 cm^2 Cross Sectional Area of Approaching Channel

The clear space of the bar rack is important in determining the amount of screenings that will be removed

and the characteristics of the screenings. Table 2 provides that the openings between parallel bars would

be 20—50 mm. In the calculation for channel width, 20 mm was used (the minimum) so as to minimize

rags and floatables that flow through, but also to minimize the excreta that would be blocked from

passage. The screening of excreta may create hygiene issues with workers who must manually rake the

rack and in the disposal of the screenings, therefore a proper size that allows excreta to flow through but

stops ―rags and floatables‖ should be considered. Quantities and characteristics of coarse screenings can

be seen in Table 3, and these values would be used to calculate volume needs for treatment beds of sludge

and also for the short-term storage on the drainage area for screenings.

Page 26: Design Report Final

23 | P a g e

Table 2: Typical Design Criteria for Coarse Screening Equipment

Item Range* Comment

Trash Rack Commonly used with a combined

sewer system Openings 38—150

Manually Cleaned Screen Used in small plants and bypass

channels Openings 20-50 mm

Approach Velocity 0.3—0.6 m/s

Mechanically Cleaned

Openings 25—50 mm

Approach Velocity, Maximum 0.6—1.2 m/s

Approach Velocity, Minimum 0.3—0.6 m/s

Continuous Screen

Openings 6—38 mm Ineffective in the 6—18 mm

range

Approach Velocity, Maximum 0.6—1.2 m/s

Approach Velocity, Minimum 0.3—0.6 m/s

Allowable Headloss 0.15—0.6 m *Values from US EPA 1979, 1987; WPCF, 1989

Table 3: Typical Design Properties for coarse Screenings

Item Range* Comment

Quantities

Separate Sewers

Average screenings per

1000 m3 wastewater

3.5—35L/1000m3 Function of the screen opening

space

Peaking Factor (hourly flow) 1:1—5:1

Combined Sewers

Average screenings per

1000 m3 wastewater

3.5—84L/1000m3 Function of the screen opening

space

Peaking Factor (hourly flow) 2:1-- > 20:1

Solids Content 10-20 %

Bulk Density 640—1100 kg/m3

Volatile Content 70-95 %

Fuel Value 12,600 kJ/kg *Values from US EPA 1979, 1987; WPCF, 1989

The shape and size of the parallel bars are important in calculating the headloss through the bar screen,

and Table 4 provides the shape factor required for Kirschmer‘s headloss equation below (Equation 1).

This headloss is used in finding the headloss for a given bar screen, where h is the headloss upstream, W

is the width of the bar, hv is the headloss through the screen and θ is the angle of the bar with respect to

the channel.

Equation 1: Kirschmer's equality for partially clogged bar screens

Page 27: Design Report Final

24 | P a g e

Table 4: Table of bar types and their respective shape factors

Bar Type β*

Sharp edged rectangle 2.42

Rectangular with semicircular side upstream 1.83

Circular 1.79

Rectangular with semicircular upstream and downstream 1.67 *Kirschmer‘s bar shape factors for Kirschmer‘s headloss equation

In order to accommodate the manual raking of the screen, it was advised to incline the screen or bars at a

maximum angle of 60 degrees from the channel. When higher flows (>1000 m3/day) are common, it is

preferred to use mechanically raked screens, so they can be raked every 10-30 minutes (Mara, 2004), but

average flow rates of that magnitude will not be expected in Carabuela, so it was fitting to use manually

cleaned bar screens with twice daily rakings of the screen. Also, as a precaution for a damaged bar screen,

an extra bar screen should be available to quickly replace the damaged screen. A simple bar rack fitted to

the incoming channel can be seen in Figure 5.

* http://www.urbanwater.co.za/

Figure 5: Example of Manually Raked Bar Screen

Page 28: Design Report Final

25 | P a g e

7.2 Grit Chamber

7.2.1 Introduction:

Grit Removal follows the unit process of screening and removes grit (heavy metals and sand) as to

prevent any unnecessary abrasion of equipment downstream and accumulation of grit in the biological

processes downstream. With the high presence of grit in combined sewer, it is necessary to achieve the

appropriate levels of removal for our customer (Vesilind, 2003). Grit materials have a greater settling

velocity than do organic materials and therefore can be removed without removing organics, which are

needed for the digestion process downstream in the Imhoff tank or waste stabilization lagoons.

Grit quantities and attributes are important considerations in design to have minimum negative effects on

processes downstream. Because attributes differ among treatment facilities and other requirements such

as: headloss, space, removal efficiency, organic content, and economics, a number of processes exist.

Some of these are: Aerated grit chambers, Vortex-type, Detritus tank, and Hydroclonic (Vesilind, 2003).

The alternatives that were considered are the vortex grit chamber, a modified vortex grit chamber, the old

septic tank, and a rectangular grit chamber.

7.2.2 Vortex Grit Chamber

A vortex grit chamber uses the similar principles of a cyclonic air filter used in coal burning plants; the

similarity is how the vortex facilitates the settling of heavier grit particles to a sump, while returning the

lighter organic matter to the effluent flow. The benefits of this design would be a low headloss in the

system and an efficient removal of grit from the stream. However, the design would not be sufficient

unless electricity was used because of the need for pumps to remove the grit and also to create a vortex.

7.2.3 Modified Vortex Chamber

Using the same principle of the electrically powered vortex chamber, the modified chamber would

function without the need of electricity. Multiple fifty gallon drum barrels could be used to create a grit

chamber that manipulates the in-flow stream to create a low flow vortex without the need of pumps.

Baffles would be used to control the geometry of the flow into a circular, vortex pattern. The hope would

be to provide enough scour to allow organic material to continue suspended, while providing enough

residence time for grit to settle and be collected in a sump. The grit could then be removed by opening a

valve connected to the sump. This design allowed for the use of a vortex grit chamber with slight

modifications; however, this chamber has not been used and is not ‗proven‘.

Page 29: Design Report Final

26 | P a g e

7.2.4 Old Septic Tank

With sustainability being an important criterion, recycling the old septic tank was attractive to

WasteWatchers‘ design; otherwise, the septic tank would be left unused. The length to width ratio was

already appropriate for a grit chamber, but the cross sectional area was larger than needed. The design of

a grit chamber from a recycled septic tank would involve removing the top concrete so that access to the

chamber would be easier, allowing maintenance of the chamber. The principles for grit removal in a

septic tank is similar to that of an open channel used to remove grit, large particles settle because of

decreased velocity of the water, while leaving organics in the stream because of scour. WasteWatchers

concluded that the septic tank was too large to function as a grit chamber (scour could not be provided to

create lift and allow organic matter to remain in the flow stream).

7.2.5 Rectangular Open Channel

The design of a new grit chamber was the most favored because of WasteWatchers ability to provide

appropriate functionality for the level of wastewater flow from Carabuela. The new chamber was

designed with a weir that would maintain the velocity of the water through the chamber no matter the

flows. Because of the varying flows from Carabuela, the new grit chamber design was more attractive to

WasteWatchers. The weir design was a sutro weir (a plate with two parabolic openings in which the water

flows through Figure 6), and it allowed for the design of a specific chamber that would remove only grit.

As with all the design alternatives, the grit needed to be removed manually after it collected on the bottom

of the channel. The appropriate technology for our customer, , was a Detritus tank (short term

sedimentation or the rectangular grit chamber), so as to minimize costs and maintenance and also to

eliminate the dependency on electricity. The Detritus tanks acts as a detention tank with a constant level

of grit removal.

Figure 6: Sutro Weir

Page 30: Design Report Final

27 | P a g e

7.2.6 Design Considerations: (Vesilind, 2003)

The basis of design for the grit chamber was the settling velocity of grit and the surface loading rate. The

velocities of minimum sizes of grit are 0.02 m/s (Vesilind, 2003). With this velocity the cross-sectional

area is 0.836 m2, where the width is 0.46 m, and the length is 1.8 m. This design allowed for all particles

with a settling velocity of 0.02 m/s or grater to be removed from the stream. The calculation for settling

velocity used Equation 2 and Equation 3 where Vs is the settling velocity, g is the acceleration due to

gravity, CD is the drag coefficient, ρs is particle density, ρ is the water density, d is diameter of particle

settling, and Re is the Reynolds number. Transitional flow was assumed in the grit chamber because the

Reynolds Number was within the transitional range of 1—106.

Equation 2: settling velocity in transitional flow

Equation 3: Coefficient of drag for transitional flow

Typical particle sizes include particles > 0.21 mm sp. gravity 2.65 (EPA, 1987)

Removal of 95% has been traditionally target removal

Modern remove 75% of 0.15 mm

Removal of grit manually requires at least one redundant tank for cleaning purposes

Velocity or turbulence in grit chamber may be designed to allow the displacement of organic

materials but not grit (this could be achieved with the proportional weir)

The Detritus Tank was a tank with a length to width ratio of 4:1 to meet the minimum cross-sectional

areas as can be seen in Table 5. This was a concrete tank that consisted of a baffle to evenly distribute the

flow along the channel and will be manually cleaned with a shovel. In order to allow for cleaning while

continuing treatment, a second tank of the same specifications was suggestedto be constructed. This shall

be constructed in parallel with the channeling to the grit chamber so flow can easily be shut-off from the

chamber being cleaned to the tank that will take its place in grit removal. As with the screenings from the

bar screen, the disposal of the grit from the grit chamber will be transferred to the drying beds for further

treatment. The quantities of grit can be estimated as seen in Table 6. It is important to regularly clean the

Page 31: Design Report Final

28 | P a g e

tank so that it will not be overloaded causing further problems downstream. An example of a simple

square Detritus tank can be seen in Figure 7.

Table 5: Grit Chamber Calculations and Dimensions

0.305 m/s Minimum settling velocities

0.120 m2 Cross-sectional area

1.5 M Length

0.20 M Width

*chautauqua.ny.us

Figure 7: Long narrow grit chamber where heavier inorganics are removed

Table 6: Estimated grit quantities for a Detritus tank

Type of system Average Grit Quantity

(m3/1000m

3 wastewater)

Ratio of max day to average day

Separate 0.004-0.037 1.5—3.0:1

Combined 0.004—0.18 3.0—15:1

7.3 Imhoff Tank

Primary treatment for wastewater treatment systems in developing regions primarily rely on simple

methods that do not require extensive equipment or highly trained personnel. Some typical alternatives

for similar locations include Imhoff tanks, septic tanks and anaerobic lagoons. These alternatives have

been considered as the most appropriate methods for primary treatment.

7.3.1 Septic Tank

The septic tank is the most common, small scale and decentralized treatment plant, worldwide. It is

compact, robust and in comparison to the cost of its construction, extremely efficient. It is basically a

Page 32: Design Report Final

29 | P a g e

sedimentation tank in which settled sludge is stabilized by anaerobic digestion (Sasse, 1998). A cross

section of a typical septic tank can be seen in Figure 8.

Figure 8: Septic Tank Schematic

Dissolved and suspended matter leaves the tank more or less untreated. Two treatment principles, namely

the mechanical treatment by sedimentation and the biological treatment by contact between fresh

wastewater and active sludge, compete with each other in the septic tank. Optimal sedimentation takes

place when the flow is smooth and undisturbed. With turbulent flow, degradation of suspended and

dissolved solids starts more quickly because of intensive contact between fresh and already active

substrate. However, since there is not enough ―calmness‖ for sedimentation, more suspended solids are

discharged with the effluent due to the turbulence. The effluent odor is foul because active solids that are

not completely fermented leave the tank. The main advantages of a septic tank are that they are simple,

durable, and require little space because of being underground. The main disadvantages of septic tanks

are the low treatment efficiency and the effluent not being odorless (Sasse, 1998). Another disadvantage

of using a septic tank is that the septic tank that is currently used in Carabuela has lost all treatment ability

because of the difficulty to desludge the tank. Also the confidence of local residents in septic tank

effectiveness has most likely been reduced to a point in which septic tanks are no longer appropriate to

the location.

Page 33: Design Report Final

30 | P a g e

7.3.2 Imhoff Tank

The Imhoff tank was invented and patented by a German engineering named Karl Imhoff in 1906

(Seeger, 1999). The tank combines two wastewater treatment processes, sedimentation and biological

digestion, into one physical system. A schematic of a typical Imhoff tank can be seen in Figure 9.

Figure 9: Imhoff Tank Schematic

The tank is typically a two-story system in which simple sedimentation and anaerobic digestion are used

to treat the influent wastewater. The tank consists of a settling compartment above the digestion chamber.

Funnel-like baffle walls prevent up-flowing foul sludge particles from mixing with the effluent and from

causing turbulence. The effluent remains fresh and odorless because the suspended and dissolved solids

do not have an opportunity for contact with the active sludge to become sour and foul. The main

advantages of an Imhoff tank are durability, small space requirement because of being underground, and

odorless effluent (Sasse, 1998). An additional advantage for this location is that maintenance and

desludging of the tank can be made more accessible. A simple pipe with a control valve can draw the

sludge out without fully draining the tank. The main disadvantages of an Imhoff tank are that it is less

simple than a septic tank, and it requires a regular desludging interval (Sasse, 1998).

Page 34: Design Report Final

31 | P a g e

7.3.3 Primary Lagoon System

Lagoons are artificial lakes. What happens in lagoons closely represents treatment processes which take

place in nature. Several examples of different types of lagoons can be seen in Figure 10.

Figure 10: Several Lagoon System Schematics

The main advantages of lagoon systems were that they were simple in construction, flexible with respect

to degree of treatment, and required little maintenance. The main disadvantages of lagoon systems were

that the stabilization ponds occupied open land, there was always some odor, , and that mosquitoes could

be difficult to control. The main disadvantage for this location was that lagoons required large, open, flat

land which was difficult to find in the mountainous region of Carabuela. Since separate lagoon systems

were required for tertiary treatment, implementing another lagoon system would not be an effective use of

the available resources.

7.4 Lagoon System

7.4.1 Aerated Ponds

Aerated ponds differ from aerobic or anaerobic ponds by the fact they are equipped with mechanical

aerators or submerged pipes that supply oxygen. This is an advantage over aerobic ponds, which uses

oxygen from photosynthesis and surface re-aeration; moreover, BOD is removed (60 to 90%) as well as

COD (70 to 90%) and TSS (70 to 90%) (Martin & Martin, 1991). Another advantage of this system is that

it required less land because it had a higher oxygen content to degrade organic matter. In the case of our

wastewater system, constructing an aerated lagoon would be troublesome because of its complexity, need

Page 35: Design Report Final

32 | P a g e

for electricity, and cost. The people of Carabuela do not have the necessary resources or funds to operate

such a design. They are more interested in a design that is simpler and easier to operate and maintain.

7.4.2 Anaerobic Ponds

Anaerobic ponds are deeper than aerobic ponds, heavily loaded with strong organic waste, and contain

large amounts of anaerobic microorganisms that quickly deplete any oxygen that might be available in the

influent (Okun, 1975). These ponds are often used to treat strong organic industrial wastes. We would not

be interested in this type of stabilization pond because it is not as efficient as the other two. You would

see this types of pond used to convert methane gas into energy, which is a highly sophisticated process.

7.4.3 Aerobic Ponds

Aerobic ponds operate off microbial reactions. Organic materials are bio-oxidized, giving off CO2, NH3

and inorganic radicals. Algae use CO2, inorganic radicals and sunlight to produce dissolved oxygen in a

cyclic-symbiotic relationship (Reynolds & Richards, 1996). The principle advantage of this pond was that

it removed pathogens at a much lower cost than any other forms of treatment (Martin & Martin, 1991).

The deeper the lagoon, the less oxygen there will be at the bottom; therefore, designing a lagoon with a

shallow depth is optimal because more sunlight can penetrate throughout the pond creating a stronger

photosynthesis reaction. Carabuela is located high up in the mountains and achieves warm climate year-

round (50 – 72 degrees Fahrenheit). This is a great place to use an aerobic lagoon, which thrives off warm

temperature climates. There are two types of aerobic ponds. They differ by the total depth with one being

approximately 15 to 46 cm and the other being 1.5 meters deep. The shallow depth pond contains high

populations of algal growth and the other contains a high population of bacteria (Martin & Martin, 1991).

Aerobic ponds should be cleaned periodically. It is important to remove grass and other plant growth

from the surrounding area and in the pond itself. Floating scum on top of the lagoons should be removed,

or oxygen transfer is impaired. If large amounts of scum are either black or brown, this is an indication

that the lagoon is being overloaded (Martin & Martin, 1991).

7.5 Sludge Treatment Design Alternatives

After each treatment process, the sludge produced will need to be treated. Often this involves aerobic or

anaerobic digestion, but with an Imhoff tank this is done during the settling stage. The sludge will be

piped to the dewatering stage. This decreased the volume by up to three-quarters and makes the sludge

handle as a solid, ready for disposal. Dewatering can be done in dewatering beds, in drying lagoons, or

with mechanical systems including belt filters, centrifuges, and heat drying.

Page 36: Design Report Final

33 | P a g e

7.5.1 Mechanical Alternatives

The mechanical choices include belt filters, centrifuges, and heat drying. Belt filters use two moving

belts to squeeze water out of the sludge. Centrifuges use rotating chambers to separate the solid mass

from water. The various forms of heat drying use heat from electrical systems to dry the sludge. All of

these required complex machinery with trained operators, frequent maintenance, and electrical power.

They were thus not appropriate to Carabuela‘s situation.

7.5.2 Drying Lagoons

Drying lagoons operate simply, with little maintenance or operator input required. Sludge from the

primary treatment and digestion flows down into a lagoon 60-120 cm deep, and then dries by drainage

and evaporation. This can take from 1-3 years, with 10 years recommended by one source. Relatively

little research has been done into drying lagoons. The long drying time, with its requirement for new

lagoons, and the comparative lack of research disqualified this option, though otherwise it could be

suitable for decentralized wastewater operations such as the one in Carabuela.

7.5.3 Drying Beds

There are several types of dewatering beds: open-air sand beds, covered sand beds, and several more

recent types such as vacuum-assisted beds, paved drying beds, and wedge wire or plastic-bottomed beds.

Vacuum-assisted drying, wedge wire-bottomed beds, and plastic-bottomed beds all require substantial

energy inputs, chemical inputs, sophisticated equipment, and trained operators. They were therefore not

appropriate to the situation. This left open-air sand beds and covered sand beds as the practical choices.

Sand drying beds typically consist of a layer of gravel with underdrains, a layer of sand, and vertical

partitions. The gravel layer is typically 20-35 cm thick. The sand layer on top of it is typically 15-25 cm

thick. The pipes are no less than 10 cm in diameter and no more than six meters apart. The walls should

be watertight and extend at least 40 cm above and 15 cm below the sludge. Drying occurs by way of two

processes: percolation and evaporation. During percolation water from the sludge drains through the sand

and gravel layers and is carried out by the underdrains to the treatment lagoons. Percolation is complete

after one to three days, while evaporation takes from weeks to months, depending on the climate. The

sludge dries until it is approximately thirty-five percent solids, at which point it handles like a solid; it is

then manually removed and transported to land disposal or incineration. Covered drying beds have glass

over the beds, protecting them from rain and quickening evaporation. According to one older source,

covered drying beds generally cost about twice as much as open beds. This is only an approximation, and

the data comes from the 1930s, but construction methods have not significantly changed since then.

Page 37: Design Report Final

34 | P a g e

Relative prices of construction materials may have changed, but it gave a general view of the relative

costs of the alternatives.

The land area required by drying beds varied based on temperature and humidity. One academic source

contained a rational method for determining land area, but for most agencies (WHO, EPA, Mississippi

DEQ, Bremen Overseas Research and Development Agency, United States Army and Air Force) and

textbooks (Wastewater Treatment by Liu and Liptak, Unit Operations and Processes in Environmental

Engineering, 2nd

edition by Reynold and Richards) the required area is usually determined by a rule of

thumb based on the population to be served. These rules vary somewhat by the agency involved; the

areas range from 0.10-0.20 m2 per capita for open beds, and 0.075-0.15 m

2 per capita for covered beds.

Because Carabuela has a relatively cool climate with moderate rainfall, this team uses a conservative

number. The equations used follow the EPA guidelines of 0.20 m2 per capita for open beds and 0.15 m

2

for closed beds, so if Aopen is the required land area for open beds, Aclosed is area for covered beds, and P is

the population,

Aopen (m2) = 0.2P

Acovered (m2) = 0.15P

Planning for a sand layer 20 cm thick and a gravel layer 25 cm thick gives the equations

Vsand (m3) = 0.2A

and

Vgravel (m3) = 0.25A

Table 7: Drying Bed Materials

Open bed Closed bed

Area (m^2) 960 720

Solids Handled (kg/yr) 81600 93600

Sand required (m^3) 192 144

Gravel required (m^3) 240 180

It was determined to be useful for fertilizer if the level of pathogens were acceptable. Digested sludge

generally provides lower levels of nutrients than chemical fertilizers, but costs very little or nothing.

According to the World Health Organization (WHO), sludge treated by anaerobic digestion and drying

beds has reduced pathogen levels, but requires further prolonged storage before it is safe to use on crops.

Page 38: Design Report Final

35 | P a g e

According to the US Environmental Protection Agency, the sludge should qualify as Class B sludge ready

for restricted application after a process to significantly reduce pathogens, such as anaerobic digestion or

air drying for more than 3 months. This team recommended that if the sludge is to be used as fertilizer, it

should be left on the bed for as long as feasible before use. This will probably mean six months, the

typical digestion period of the Imhoff tank. To qualify as Class B, the crops should not be harvested less

than thirty days after fertilizer application. If the sludge cannot be applied to alfalfa or another feed crop,

it should not be applied to human food crops, though it could be applied to fallow fields. Alternatively,

the waste could be sent to a landfill or incinerator, if one is feasibly close.

Most of the cost of a drying bed comes from construction. The only maintenance cost was the labor cost

for the operator to shovel off the dried sludge. As shown in Table 8, the layers of sand and gravel added

small amounts to the cost. Land was the most expensive requirement for an open bed; a closed bed

required less area, but the glass made it approximately twice as expensive as the open bed system.

Table 8: Drying Bed Costs

Cost Open bed Covered bed

Land $ 1,920 $ 1440

Sand $ 290 $ 220

Gravel $ 360 $ 270

Glass $ - $ 7200

Labor $ 2880 $ 3600

Total Cost $ 5450 $ 12700

8 Design Decisions

8.1 Bar racks

WasteWatchers decided to use an inclined bar rack made from rebar, and it was prioritized with

simplicity, low cost, and effectiveness in mind. These three criteria were scored for each alternative in the

screening process, along with others, . Because screening is a fairly simple process, WasteWatchers

hoped to keep the design as simple as possible. Effectiveness and low cost were the other of the three top

priorities for the screening design. Captured by these top three priorities of the screening design,

WasteWatchers chose to use and design an inclined bar screen made from small diameter rebar.

Page 39: Design Report Final

36 | P a g e

Table 9: Bar Rack Decision Matrix

Alternative Designs

Weighting

Inclined Bars Mesh Catchment Mesh Grid Screen

Score

Weighted Score

Score Weighted

Score Score

Weighted Score

Cri

teri

a

Effective treatment 16 15 24 15 24 12 19.2

Culturally Appropriate 16 15 24 10 16 14 22.4

Sustainable 16 10 16 10 16 8 12.8

Site Appropriate 15 13 19.5 10 15 13 19.5

Low Cost 13 10 13 11 14.3 13 16.9

User friendly 12 7 8.4 8 9.6 4 4.8

Long Lasting 12 9 10.8 9 10.8 4 4.8

Total: 100

115.7

105.7

100.4

From the decision matrix (, it can be seen that the criteria were best met by the Inclined Bar Screen. The

effectiveness of treatment for the bar screen involves the removal of larger solids in the waste stream,

while the simplicity of cleaning the bar screen meets the design norms of cultural appropriateness,

sustainability, and user friendliness. Because redundancy is a requirement in wastewater treatment and

Inclined Bar Racks need an open channel, the costs in construction for two concrete open channels and

two Inclined Bar Racks were higher than the other alternatives. Capturing most of the design norms, the

inclined bar rack was most suitable.

Within the design of the bar screen, more detailed decisions were made such as, the clear space between

the bars, the design velocity of the water through the bars, and the dimensions of the open channel where

the screening takes place. Through research and flow calculations, we chose the clear space to be the

minimum allowable spacing for manually cleaned bars Table 2. The minimum spacing tolerated smaller

solids and particulate to remain in the waste stream to be later removed by other components, while

screening out the larger, damaging solids and particulate. The design velocity of the water flowing

through the bar rack was chosen because research showed that a range of 0.3—0.6 m/s to be most

effective in screening and maintenance. With higher velocities, screenings would be dislodged, and lower

velocities would cause particles, that were otherwise settle in another process component, to settle in the

bar rack channel. Finally, the dimensions of the open channel where the bar racks would be contained had

Page 40: Design Report Final

37 | P a g e

to be designed. Using Equation 4, we calculated the required cross-sectional area, Table 1, for the bar rack

open channel at a velocity less than the required 0.6 m/s.

Equation 4: Cross Sectional Area Calculation

The requirement of redundancy in wastewater treatment design was considered in this process as well.

Because of the necessary cleaning and maintenance of a bar rack, two open channels were designed

identical so that ether could be used while the other is being cleaned or repaired. Redundancy was an

important design consideration factored into every component.

8.2 Grit Chamber

The decision to use and design a rectangular open channel grit chamber was mostly prioritized with

effectiveness, proven technology, low cost, and simplicity. A decision matrix was created to score each of

the different alternatives for a grit chamber design with these previous four criteria weighted more

heavily, . Because grit removal can effectively remove much of the grit in a waste stream without much

complexity in design, effectiveness and proven technology was an important priority in the chamber

design. Simplicity and low cost are the other two criteria that were considered in deciding on the grit

chamber design. Because the system was simple, it was also low cost.

Table 10: Grit Chamber Decision Matrix

Alternative Designs

Weighting

Rectangular Open Channel

Vortex Grit Chamber

Modified Vortex Grit Chamber

Old Septic Tank

Score

Weighted Score

Score Weighted

Score Score

Weighted Score

Score Weighted

Score

Cri

teri

a

Effective treatment

16 15 24 16 25.6 8 12.8 7 11.2

Culturally Appropriate

16 15 24 8 12.8 14 22.4 8 12.8

Sustainable 16 12 19.2 8 12.8 11 17.6 13 20.8

Site Appropriate

15 13 19.5 6 9 11 16.5 13 19.5

Low Cost 13 10 13 7 9.1 8 10.4 13 16.9

User friendly

12 10 12 7 8.4 5 6 4 4.8

Long Lasting

12 9 10.8 7 8.4 6 7.2 5 6

Total: 100

122.5

86.1

92.9

92

Page 41: Design Report Final

38 | P a g e

In the decision matrix, the rectangular open channel (this is basically an expansion in the pipe to slow the

velocity of water) met the requirements and agreed with WasteWatchers‘ design norms. The

effectiveness of the grit chamber was based on its ability to remove smaller solids (sand, soil, small rocks,

grit, and etc.), while also providing scour to allow the organic matter to continue downstream. The

cultural appropriateness of the grit chamber design involved its simplicity and ease of maintenance; the

rectangular channel proved to be easily cleaned with redundant chambers and is a simple component of

the system. Because the entire system was designed without the need of electricity, the grit chamber

would be sustainable in the sense of maintenance and no power needs; however, it would need to be built

anew (the drawback of not using a recycled septic tank as the grit chamber). Because of its relatively

small size, the grit chamber was site appropriate; furthermore, it had a relatively low construction cost.

User friendliness was achieved by the grit chamber by means of simplicity, but there may be some

drawback in manually shoveling the sludge from the bottoms of the chambers (foul smells will most

likely be present). As with the entire system, the grit chamber was designed for a 20 year life and has the

ability to last longer if the increase of population does not extend above our estimates.

The design of the grit chamber surprisingly had many decisions needed to be made. The velocity of water

through the grit chamber was an important factor in the design of the open channel chamber. Research

showed (Reynolds & Richards, 1996), that the design velocity for grit removal was 0.305 m/s. Because of

the heavily varying flows from Carabuela, it was decided to design a weir that could control the velocity

at different flow rates. Many weirs were considered but the most consistent weir to keep velocities

constant was the sutro weir. The design of the weir was a sutro weir (or proportional weir), where the

openings were parabolic. This decision to keep the velocity constant was important so that organic

material would be scoured and remain in the flow stream while grit would settle and be collected in the

bottom of the channel. The weir was designed so that it could be placed at the end of the channel to

control the velocity upstream. The cross sectional area was designed so that the channel could handle the

max flow of the waste stream with an appropriate freeboard (0.5 meters from Table 1), Equation 5.

Equation 5: Cross Sectional Area Calculation

As with the rest of the wastewater treatment system, the grit chamber was also designed with redundancy.

The second chamber was identical to the first, and the ability to change flows from one to the other was

captured in the design.

Page 42: Design Report Final

39 | P a g e

8.3 Imhoff Tank

For the primary treatment of the wastewater, several alternatives including an Imhoff tank, a septic tank,

an anaerobic lagoon and conventional sedimentation were considered.

The Imhoff tank scored highly because it was culturally appropriate in that it is abundantly used in many

developing nations and regions, site appropriate in that it does not take excessive land space, sustainable

in that it has a low level of sophistication and requires no electricity. The main drawbacks of the Imhoff

tank are the high level of maintenance, the high capital cost, and the possible limited lifespan. Overall the

Imhoff tank was the best option for this situation. With the Imhoff tank several options were considered

for construction methods. The Imhoff tank could be built and designed several ways. Two construction

alternatives are possible and vary in construction materials used. A new tank made of typical concrete

could be built or a new tank made of ferrocement could be used.

Building a typical concrete tank could pose some problems when it comes to construction. Forming the

tank could be a problem because the walls of the tank would be high and would require concrete to be

pumped up to the top of the forms. Concrete pumps and cranes which would typically be used in

construction in the United States might not be available in the remote regions of Ecuador. Construction of

the tank could be difficult depending on the availability of skilled concrete workers. Also the tank would

require a significant number of reinforcing steel bars which would add to the construction cost. The main

advantage of using typical concrete for the construction is that it is a very proven and well known

technology that is durable and dependable. The alternative to typical concrete construction is using

ferrocement.

Ferrocement is a type of thin wall reinforced concrete commonly constructed of hydraulic cement mortar

reinforced with closely spaced layers of continuous and relatively small size wire mesh (Naaman, 2000).

The main advantages of using ferrocement as compared to typical reinforced concrete are as follows:

Thinner material

Ferrocement has a high reinforcement ratio in both tension and compression

Smaller crack widths which provide excellent leakage characteristics for water tanks

Good durability under various environmental exposure

Can accommodate lower levels of technology because it requires less mechanization and

less heavy equipment

Easy to repair and maintain

Page 43: Design Report Final

40 | P a g e

A decision on the construction method was made after research into the village of Carabuela and typical

construction methods to the area. According to many images of the village, typical concrete construction

is standard to their major structures. Also some of the younger generation of the village has spent time in

the capital city of Quito working as construction workers (Meier & Villalobos, 1996). This expertise can

be utilized in the construction of typical concrete. Because of this familiarity with concrete and the

standard nature of concrete construction to the area, typical concrete construction will be used for all

structures to be built.

8.4 Lagoon System

In below, there is a design matrix that lists each of these criteria along with possible alternatives.The

facultative pond was selected over the other alternatives for a number of reasons. It best suited the design

norms for this project: cultural appropriateness, stewardship and transparency. The facultative pond was

considered better than the aerated pond because it does not require a power source such as electricity or

gas that would provide extra costs to the system and complexity. Aerated ponds need power to provide

more oxygen to the pond by the use of blowers or mechanical paddles. This power would not be easily

accessible to its location and would drain the energy resources in that area. The people of Carabuela want

a system that is easy to operate. The aerated pond would be hard to operate. Another reason why aerated

ponds were not considered appropriate was because they are not very transparent. An aerated pond

requires mechanical equipment that is not easily understood. The team wants the people of Carabuela to

be able to operate their system and be able to fix problems when they occur. It would be very hard to fix

an aerated system without the proper education about them. Besides the aerated pond, the anaerobic pond

was not selected. The anaerobic pond was not selected because they are generally used to capture

methane gas from anaerobic microbial reactions, a byproduct that the people are not interested about. Its

depth is much deeper, which would add to construction costs. It does not treat the waste as efficiently as

facultative ponds because not enough sunlight is able to penetrate through the entire pond. Overall, as

shown in the decision matix, the facultative pond is the best decision. It provides the best treatment at the

lowest cost and it is culturally appropriate and transparent.

Page 44: Design Report Final

41 | P a g e

Table 11: Lagoon Decision Matrix

Alternative Designs

Weighting

Aerated Lagoon Facultative

Lagoon

Anaerobic

Lagoon

Score

Weighted

Score Score

Weighted

Score Score

Weighted

Score

Cri

teri

a

Effective treatment 16 9 14.4 8 12.8 7 11.2

Culturally

Appropriate 16

5 8 9 14.4 9 14.4

Sustainable 16 7 11.2 8 12.8 8 12.8

Site Appropriate 15 3 4.5 3 4.5 3 4.5

Low Cost 13 3 3.9 5 6.5 4 5.2

User friendly 12 4 4.8 8 9.6 8 9.6

Long Lasting 16 7 11.2 7 11.2 7 11.2

Total: 104 58 71.8 68.9

8.5 Sludge Drying Beds

The treatment of the sludge must also fit with our design norms; preferably, the sludge can be used to

fertilize nearby fields, but at the least it must be treated well enough for disposal.

Table 12: Sludge Drying Decision Matrix

Alternatives

Uncovered Beds Covered Beds

Criteria Weight Score Weighted

Score Score Weighted

Score

Effective Treatment 17 9 15.3 6 10.2

Sustainability 17 8 13.6 4 6.8

Cultural Appropriateness 15 7 10.5 8 12

Site Appropriate 14 4 5.6 6 8.4

Low Cost 13 8 10.4 5 6.5

User Friendly 12 8 9.6 8 9.6

Long Lasting 12 7 8.4 7 8.4

Total 100 51 73.4 44 61.9

For the calculated areas, the covered and uncovered beds would both dry the sludge well enough, but the

covered beds‘ covering gives them the edge in wet weather and preventing odor. The glass covers would

have to come from outside Carabuela, hauled from the factories over Ecuadorian roads. They also,

Page 45: Design Report Final

42 | P a g e

however, require ventilation; for consistent good performance, the covered beds need fans to move air

over the beds, so they are not as appropriate for Carabuela. The glass doubles the cost of the system,

despite the reduced land requirement. Neither system requires much thought or ingenuity from the

operator, but some caution and basic equipment is required to reduce exposure to pathogens. Both open

and covered beds require significant amounts of land, but the covered sand beds require 25% less. The

open beds would require 570 m2, whereas the covered beds would take 400 m

2 out of a total of 5000 m

2

available for all systems. Each system will last 20 years without significant trouble; they have no

machinery to break down.

When all factors are considered, the uncovered beds are a better choice. Their advantages in cost, local

sustainability, and cultural appropriateness outweigh the covered beds‘ slight edge in performance and

land requirements.

9 Hydraulic Analysis

The majority of the influent entering the wastewater treatment system comes from homes, but another

source is stormwater. It was important for the team to perform a stormwater analysis in order to get an

accurate reading of the flow rate entering the system. This process was not as easy as it sounds. The first

step was to gather precipitation data for Carabuela. Although only six years of precipitation data was

collected, it was enough to give extrapolate some of the worst rain events occurring in a year. Figure 11

shows the months for the past six years and the amount of rainfall that occurred during that period. The

max amount of rainfall during this six-year period was 52 mm. knowing the intensity of the worst rain

event (52 mm) and the average area of a typical roof (60 square meters), the team was able to calculate

the average flow of stormwater per roof. An EPA SWMM model of the town generated a maximum

outflow of 3200 m3/day, far beyond the ability of the system to handle. In consequence, an overflow weir

was needed to prevent storm events from flushing the system.

Page 46: Design Report Final

43 | P a g e

Figure 11: System Flow Rate during Rainfall

The design of the side-overflow weir was based on the equation provided by Engel (Engels, 1921). Using

his equation, the WasteWatche was able to calculate the amount of flow exiting over the side-overflow

weir for various flows. Table 13 shows the actual amount of flow entering the system as well as the

percentage breakup of the total amount of flow entering and exiting over the weir. The length of the side-

overflow weir crest was 900 mm and had a depth of 550 mm. Its location was on a side wall upstream the

bar racks. Although the weir does not remove all the wastewater at high flows, it does remove a large

percentage of it that could cause severe damage to the system.

Page 47: Design Report Final

44 | P a g e

Table 13: Side Overflow Weir flows

Total flow into system

% into system

Flow over weir

% over weir

Total Flow

150 100% 0 0% 150

174 100% 0 0% 174

198 100% 0 0% 198

221 100% 0 0% 221

245 92% 21 8% 266

269 80% 66 20% 335

293 69% 131 31% 423

316 60% 211 40% 527

340 53% 306 47% 646

364 47% 415 53% 779

388 42% 537 58% 925

411 38% 672 62% 1083

435 35% 818 65% 1253

459 32% 975 68% 1434

482 30% 1143 70% 1626

506 28% 1322 72% 1828

530 26% 1511 74% 2041

554 24% 1710 76% 2264

601 22% 2137 78% 2738

10 Environmental Design

10.1 Bar Racks and Grit Chamber

Because the bar racks and grit chamber are in the beginning stages of the treatment facility, removal of

organic material and pathogens are not as important in the design; however, the removal of grit and large

solids and floatables.

The design of the bar racks depended mostly on the clear space between the bars (20 mm, Table 2). The

disposal of the screenings was considered in design, where a depressed steel plate with drainage would be

placed over the open channel for the screenings to dewater. The screenings could then either be stored and

taken to a landfill or incinerated.

The environmental design of the grit chamber involved the removal of grit and scour of organic matter.

Grit from the grit chamber would be shoveled during maintenance periods and then taken to the sludge

drying beds for treatment. These two factors were based on the velocity of the water flowing through the

grit chamber. The ideal velocity of water through the grit chamber was 0.25-0.30 m/s. In order to keep a

constant or near constant velocity in this range, WasteWatchers designed a sutro weir (proportional weir).

This weir showed that it could handle a wide range of flows while maintaining a constant water velocity.

The equation of a parabola was used to determine the dimensions of the weir, Figure 12.

Page 48: Design Report Final

45 | P a g e

Figure 12: Weir Design

Although these two unit processes did not have much environmental design in them, it was important

that they were effective in their treatment so that downstream unit processes functioned properly. The

final design proved appropriate removals of contaminants upstream when downstream components were

analyzed and designed.

10.2 Imhoff Tank

The environmental design of the Imhoff tank was based off of both basic sedimentation principles and

recommendations from experience based design guides. The first design guide we used gave many typical

design parameters and can be seen in Table 14 below.

-0.05

0

0.05

0.1

0.15

0.2

0.25

-0.15 -0.1 -0.05 0 0.05 0.1 0.15

Hie

igh

t Fr

om

Re

ctan

gula

r W

eir

(cm

)

Width From Neutral Axis (cm)

Page 49: Design Report Final

46 | P a g e

Table 14: Design Criteria for Unheated Imhoff Tanks

Value

Design Parameter Unit Range Typical

Settling Compartment

Overflow rate peak hour gal/ft2 ∙ d 600 - 1,000 800

Detention time h 2 - 4 3

Length to Width ratio 2:1 - 5:1 3:1

Slope of settling compartment ratio 1.25:1 to 1.75:1 1.5:1

Slot opening in 6 - 12 10

Slot overhang in 6 - 12 10

Scum Baffle

Below surface in 10 - 16 12

Above surface in 12 12

Freeboard in 18 - 24 24

Gas vent area

Surface area % of total

surface area 15 - 30 20

Width of openinga in 18 - 30 24

Digestion Section

Volume (unheated) Storage

capacity

6 months

of sludge

Volumeb ft

3/capita 2 - 3.5 2.5

Sludge withdrawal pipe in 8 - 12 10

Depth below slot to top of sludge ft 1 - 3 2

Tank Depth

Water surface to tank bottom ft 24 - 32 30

a Minimum width of opening must be 18 in to allow for a person to enter for cleaning.

b Based on a six-month digestion period.

Note: gal/ft2 ∙ d x 0.0404 = m

3/m2 ∙ d

in x 25.4 = mm

ft3 x 2.8317 x 10

-2 = m

3

ft x 0.3048 = m

* (Tchobanoglous, 1991; Metcalf & Eddy, 1935)

This guide showed ranges and typical values for many of the critical components of the Imhoff tank. The

first design criterion from this table that was considered was the overflow rate. Recommended overflow

rates for unheated Imhoff tanks range from 600 to 1000 gal/ft2 day (Tchobanoglous, 1991). This design

used the minimum value of 600 gal/ft2 day to assume the worst case with the least efficient overflow rate.

Using the design flow, a required plan view area for the sedimentation chamber was able to be calculated.

The required plan view area was 7.854 square meters and represents the minimum required plan area of

sedimentation for optimal operation of the Imhoff tank. Values for length and width of the sedimentation

Page 50: Design Report Final

47 | P a g e

chamber were then chosen to be in excess of the required area. The length of the tank was chosen to be 8

meters and the width of the tank was chosen to be 1 meter. The total sedimentation plan view area was

then 8 square meters which is larger than the minimum required area.

Next the retention time of the tank was chosen to be two hours. Retention times of much longer than two

hours during peak hours in the flow portion of the tank would jeopardize the effect of the effluent

remaining fresh and odorless because the suspended and dissolved solids not having an opportunity to get

in contact with the active sludge and become sour and foul (Sasse, 1998). Using the design flow, the

retention time and plan view area, the depth of the sedimentation area can be calculated. To calculate the

dimensions of the Imhoff cone, first the general depth of the sedimentation area if it were rectangular.

This depth would be 2 meters. This depth needs to be adjusted because the actual Imhoff sedimentation

chamber has a cone shape as shown in Figure 13.

The depth of the sedimentation chamber can be broken into two components: the top vertical section and

the bottom sloped section. The top vertical section depth can be calculated using Equation 6.

Equation 6: Depth of top sedimentation walls

In this equation the slope equals the slope of the bottom section walls and the width equals the width of

the sedimentation chamber. The bottom sloped section can be calculated using Equation 7.

Equation 7: Depth of bottom sedimentation walls

The slope of the bottom walls was chosen based off of advice from Ms. Anne Mikelonis through email

correspondence. Ms. Mikelonis completed her master‘s thesis on upgrades to an Imhoff tank in Honduras.

Her expertise on Imhoff tanks was used to optimize the design. The Imhoff tank that was being upgraded

had particular problems with scum accumulating on the sedimentation chamber walls due to insufficient

Rectangular general

Actual Imhoff Cone

Figure 13: Imhoff Cone Depth

Page 51: Design Report Final

48 | P a g e

slope of the bottom walls. For this design, the bottom wall slope was chosen to be 2:1 to reduce this

possibility.

Another safety consideration that was used was a horizontal overlap of the bottom sedimentation walls.

This overlap was chosen to be 0.5 meters and keeps the cleaned water untainted by reducing the

possibility of tainted water, carried upward by gas bubbles or other conditions, to enter the sedimentation

chamber. This horizontal overlap translates to a depth increase of 1 meter because of the 2:1 slope. To

further separate the settled sludge and cleaned water, the vertical clearance between the bottom of the

sedimentation chamber and the maximum depth of settled sludge was chosen to be 0.5 meters.

The anaerobic nature of the digestion in the sludge compartment creates significant levels of methane gas.

This methane gas moves from the sludge upward and requires an open space to exit into the air. On both

sides of the sedimentation chamber a 1 meter wide gas vent was added to accommodate for this gas

release. A width of 1 meter was chosen to allow for passage of a person for maintenance purposes.

The sludge storage compartment was designed to hold 0.053m3 of sludge per resident. This value was

derived based on the dimensions of a similar Imhoff tank currently in operation in Honduras (Mikelonis,

2007). Since the Imhoff tank is designed for redundancy and there are two tanks in the one structure, each

tank only is required to hold half of the total sludge volume. The volume of sludge that each tank is

designed to hold is 47.7 cubic meters. This volume corresponds to a maximum sludge depth of 2 meters.

Now that each section of the Imhoff tank has been constrained and dimensioned the total tank dimensions

can be calculated. The total redundant Imhoff tank has a length of 8 meters, a width of 6 meters and a

depth of 6 meters. The full calculations for the design of the Imhoff tank can be seen in entirety in

Appendix A.

10.3 Waste Stabilization Lagoons

As the fourth component of the wastewater treatment facility, the waste stabilization lagoons were

designed to reduce the BOD and pathogens in the waste stream. WasteWatchers used various case studies

and sources for research on wastewater treatment in developing countries to complete the environmental

design of the wastewater treatment facility for Carabuela, Ecuador. Many standards for BOD, E. coli,

TSS, Giardia, and Helminth eggs were either not found in Ecuadorian government agencies or they were

unattainable for any Ecuadorian treatment system.

In order to meet requirements for unrestricted irrigation, three waste stabilization ponds were designed

(two being maturation ponds and one being a facultative ponds). Using kinetics, temperature factors, and

hydraulic residence times, WasteWatchers designed and sized the ponds. The facultative pond is partly

Page 52: Design Report Final

49 | P a g e

anaerobic and partly aerobic. This digestion will heavily reduce the BOD levels in the waste stream. The

last two maturation ponds mostly reduce the pathogen content through inactivation with high residence

times.

The calculations of the lagoons assume a max flow of wastewater to be twice the average flow of

wastewater. WasteWatchers assumed (through help of HCJB contact, Bruce Rydbeck) the flow to be 8

m3/month/household with the average of five people per household. The assumed BOD concentration for

the beginning of the system was 200 mg/l (32 kg/day), and it was reduced by the Imhoff tank to 100 mg/l

(19.6 kg/day) before the flow entered the facultative pond. The assumed concentration of Helminth eggs

in the flow was 1000/L and the E. coli coliforms were assumed to be 2x107 coliforms per 100 mL (Mara,

2004).

The BOD loading rate was calculated to be 167 kg/(hectare-day) with temperature effects accounted for

(Mara, 2004). The inflow for using the BOD loading rate, max flow rate, and the BOD concentration, the

area of the facultative pond was calculated to be 0.115 hectares. Because temperature was a factor in the

amount of BOD removed, the worst case temperature was used for the calculation of the BOD loading

rate. The depth of the pond was suggested to be 1.5 meters (Mara, 2004). The final BOD concentration

from the facultative pond was calculated to be 2.7 mg/l (0.52 kg/day), showing a 1.6 log removal of BOD.

The Helminth eggs and E. coli removal rates were also calculated for the facultative pond, being 9.93

eggs/L and 3.5x105 E. coli coliforms. Because these concentrations did not yet meet unrestricted

irrigation standards, two maturation ponds were designed to further reduce Helminth eggs and fecal

coliforms.

As with the facultative pond, the two maturation ponds were designed using hydraulic residence times

and biokinetics (Mara, 2004). The effluent concentrations of pathogens and BOD were used for the

influent of the two maturation ponds in series. Temperature was a factor with the maturation ponds, and

the worst case temperature for pathogen removal was used. Assumed hydraulic residence time was 3 days

for both maturation ponds. The removal of Helminth eggs and E. coli were the only pollutants taken into

consideration into the design of the maturation ponds, since BOD was reduced to already acceptable

levels.

The final results of BOD, Helminth eggs, and E coli concentrations were 2.7 mg/L, 0.10 eggs/L, and

915 Fecal Coliforms/100 mL, respectively. The removal rates are 1.6 log removed, 4.0 log removed, and

4.3 log removed respectively. These results were produced in order for the effluent water to be used for

unrestricted irrigation; however, the actual use of the effluent will depend on cultural values and actual

test data of the effluent water.

Page 53: Design Report Final

50 | P a g e

10.4 Sludge Drying Beds

The sludge drying beds are an essential part of the Imhoff treatment system. The sludge drying beds are

designed to handle the maximum level of sludge from one side of the Imhoff tank. The depth of the

sludge was chosen to be 20 cm to maximize infiltration and evaporation. The required area to dry the

sludge was 238.5 square meters. The beds were divided into four sections so that the sludge could be

added at four different times and dry at different schedules. Four tanks were necessary so that the sludge

would have up to a year to dry before being removed. This one year length is sufficient to kill off any

pathogens present in the sludge. The pathogens are killed off so that the dried sludge can be reused for

fertilizer. The width of each drying bed was 8.916 meters, the length of each bed is 26.79 meters and the

total width of the all the beds was 35.665 meters.

11 Structural Design

11.1 Bar Racks

The structural design for the bar racks can be broken up into five components: the concrete design, the

steel reinforcing design, the bar design, the drying plate design and the isolation plate design. Each

component of the design is unique but also connected to the every other component. The general design

of the tank can be seen in Figure 14.

The concrete wall and foundation design was inherently tied to the requirements for steel reinforcing. For

concrete that was earthen formed or is in contact with the weather or water the minimum steel reinforcing

cover is 75 mm (American Concrete Institute, 2005). Since both sides of the tank meet this requirement,

the minimum concrete wall thickness was 150 mm. The thickness was increased to 200 mm to

accommodate for the bending of the steel at the bottom of the tank. Typical 3000 psi strength concrete

was designed to be used.

Bar racks Influent

channel

Effluent

channel

Figure 14: General Bar Rack Design

Page 54: Design Report Final

51 | P a g e

The steel reinforcing design was governed by the minimum required steel to insure that the concrete does

not hold any tensile force. The minimum reinforcing steel for the bar rack is based on ACI 318M 14.3.2

(American Concrete Institute, 2005, p. 238) is 120 mm2. The reinforcing steel was spaced at 300 mm

apart in order to keep a consistent spacing throughout the entire length. The bend in the steel was set at 4

times the diameter of the bars according to ACI 318M 7.2.2 (American Concrete Institute, 2005, p. 79).

All bars are to be typical #4 rebar and are to be bent as shown in the specifications.

The bar design was chosen to reduce complexity and to increase the ease in which the system was used.

The bars are placed into the concrete foundation 100 mm and are angled at 60° from horizontal. The bars

then extend 730 mm. The bars then bend with a radius of 43.5 mm for 109°. The bars are also to be

typical #4 rebar. There are seven bars spaced at 20 mm apart.

The drying plate design was connected to the bar design. The bend in the bars was designed to end in

contact with the drying plate. The drying plate is 10 mm thick steel assembled as can be seen in the

specifications. The drying plate was designed for the edges to sit on the top of the wall and the center to

drop down into the channel. The drying plate is designed to be anchored to the top of the wall to maintain

its correct location.

The isolation plates were designed to allow for complete isolation of one bar rack. The isolation plates are

10 mm thick steel that is 24 mm wide and 22 mm tall. The plates were designed to slide down a 10 mm

wide notch in the concrete which runs down the height of the channel and also into a 10 mm deep notch

in the floor.

11.2 Grit Chamber

The structural design for the grit chamber was similar to the design for the bar racks and has been

designed to be completely connected to the bar racks. The structural design for the grit chamber was

broken up into four components: the concrete design, the steel reinforcing design, the sutro weir design

and the isolation plate design. The grit chamber has a similar general layout to the bar racks and can be

seen in Figure 15.

Sutro Weirs

Influent

channel

Effluent

channel

Figure 15: Grit Chamber General Design

Page 55: Design Report Final

52 | P a g e

The concrete wall and foundation design were inherently tied to the requirements for steel reinforcing.

For concrete that is earthen formed or is in contact with the weather or water the minimum steel

reinforcing cover is 75 mm (American Concrete Institute, 2005). Since both sides of the tank meet this

requirement, the minimum concrete wall thickness was 150 mm. The thickness was increased to 200 mm

to accommodate for the bending of the steel at the bottom of the tank. Typical 3000 psi strength concrete

was designed to be used.

The steel reinforcing design was governed by the minimum required steel to insure that the concrete does

not hold any tensile force. The minimum reinforcing steel for the bar rack was based on ACI 14.3.2

(American Concrete Institute, 2005, p. 238) is 120 mm2. The reinforcing steel was spaced at 300 mm

apart in order to keep a consistent spacing throughout the entire length. The bend in the steel was set at 4

times the diameter of the bars according to ACI 7.2.2 (American Concrete Institute, 2005, p. 79). All bars

are to be typical #4 rebar and are to be bent as shown in the specifications.

The sutro weirs design was based on hydraulic engineering principles for weir controls. The main purpose

of the sutro weirs was to back the water up and to keep the velocity in the channel relatively constant. The

sutro weirs were designed to be made from 10 mm thick steel with a width of 24 mm and a height of 22

mm. The weir cut in the weir follow the details as shown in the specifications.

The isolation plates were designed to allow for complete isolation of one bar rack. The isolation plates are

10 mm thick steel that is 24 mm wide and 22 mm tall. The plate was designed to slide down a 10 mm

wide notch in the concrete which runs down the height of the channel and also into a 10 mm deep notch

in the floor.

The total cost for the combined bar rack and grit chamber system can be seen in . Steel and concrete were

the majority of costs in the pricing estimate, and U.S. prices were used because of a lack of pricing for

steel and concrete in Ecuador.

Page 56: Design Report Final

53 | P a g e

Table 15: Bar rack and grit chamber cost estimate

Rebar

Total Length: 118313.1 mm

Total Length: 118.31 m

Total Weight: 92.8757835 kg

Price: 0.9 $/kg

Rebar Cost: $83.59 Concrete

Total Volume: 2.807 m3

Concrete Price: 65 $/m3

Concrete Cost: $182.46 Steel Plates

Total Area: 639800 mm2

0.6398 m2

Steel Plate Price 215.28 $/m2

Steel Plate Cost: $ 137.74 Manufacture Cost $68.87 Steel Plate Cost: $206.60 Labor

Total Labor 40 hrs

Steel Plate Price 4 $/hr

Steel Plate Cost: $ 160.00

Total Cost: $ 632.65

11.3 Imhoff Tank

The Imhoff tank is a large tank that has three long walls and two short walls, and the structural design of

this tank was somewhat complicated. Although the design was complicated, Carabuela, Ecuador does

have construction companies that have experience in masonry work. The design consists of framework,

steel work, and masonry work with concrete. The assumed design constants for design are 3000 psi

concrete and 40,000 psi steel.

Appropriate loads for the Imhoff conic section and concrete beams were assumed for a strong design. The

conic section was assumed to have two people standing on the section in the strength calculations along

with the self weight. The beam that supports the conic section was designed for three people to be

standing on the beam, the self weight of the beam, and the load of the conic section.

Page 57: Design Report Final

54 | P a g e

The loads from the beam were then transferred to the side walls, where both vertical spans were used to

design the walls. The water pressure and earth pressure were designed for worst case moments within the

wall, and calculations were based on the ACI manual for construction. A finite element analysis was run

on the various load cases to look at the worst case stress points within the design. Reinforcing steel

spanned only one direction in the walls because of the ratio of length to width (also to help optimize the

cost and strength of the tank), and a horizontal span was designed for the steel in the conic sections of the

tank. Calculations for steel and concrete were completed using both the finite element analysis and

normal structural design with ultimate moments.

Accompanying the design calculations was the completion of structural drawings and a . A cost estimate

was also calculated give a final cost estimate on the entire system, Table 16. Steel and concrete were the

majority of costs in the pricing estimate, and U.S. prices were used because of a lack of pricing for steel

and concrete in Ecuador.

Table 16: Imhoff Tank Cost Estimate

Amount Costs

Concrete (m^3) Steel (m) Labor (hr) Concrete Steel Labor

Interior Wall 19.2 1160 50 $1,027.56 $719.20 $150.00

Exterior Walls 38.4 2320 50 $2,055.11 $1,438.40 $150.00

Front and Back Walls 28.8 1740 50 $1,541.33 $1,078.80 $150.00

Floor Slab 28.8 1160 40 $1,541.33 $719.20 $120.00

Conic Section 24 536 40 $1,284.44 $332.15 $120.00

Total 139.2 6916 230 $7,449.78 $4,287.75 $690.00

Total Cost $12,427.53

Pricing

Labor ($/hr)

Concrete ($/m3)

Steel ($/m)

$3.00 $53.52 $0.62

11.4 Waste Stabilization Lagoons

The pond system includes one secondary facultative pond and two maturation ponds. The facultative

pond is 1.5 meters in depth with 0.5 meters of freeboard. The maturation ponds are 0.5 meters in depth

with 0.5 meters of freeboard. The influent enters each pond through an 8‖ PVC pipe to the center of the

pond. An outlet pipe is located 1 foot below the surface of the water in each pond. For redundancy, there

are two ponds for each type of pond. Gate valves are placed before and in-between ponds for the purpose

Page 58: Design Report Final

55 | P a g e

of directing the flow of wastewater. In order to protect the groundwater from contaminants in the

wastewater, 0.3 meters of clay lines the bottom of each stabilization pond.

11.5 Sludge Drying Beds

The drying beds will have a layer of 20 cm of sand on top of a graded layer of gravel, starting at 20 cm in

thickness and increasing to 25 cm. The bed retaining walls can be constructed of concrete or an earth

berm. The walls shall be 45 cm high to retain the sludge without shading it. Under the gravel layer, in

the center of each bed, shall run an underdrainage system. These shall be PVC pipes 15 cm in diameter,

on a 1% grade.

There shall be three beds, seven meters wide and thirty meters long. Each shall have an influent gate 15

cm in diameter leading from the Imhoff tank, with a shear gate over the end of each pipe to control flow.

Below each shear gate will be a 5 cm- thick concrete slab to prevent sand erosion.

Figure 16: Plan View

Page 59: Design Report Final

56 | P a g e

Figure 17: Side View

12 Grant Proposal

12.1 Executive Summary

Carabuela is a small village in Ecuador that is currently facing issues with its wastewater treatment

system. The system is not working properly for a number of reasons. First, its septic tank and infiltration

basin are both being overloaded. Second, the system is not being cleaned routinely. Third, the untreated

effluent is being discharged directly into a nearby stream. These issues have been brought to our attention

and it is our hope to develop a new wastewater treatment system that would be feasible to the people

living in Carabuela. We are working alongside Heralding Christ Jesus Blessings (HCJB), who has

provided us with important information about the project. This project requires a significant capital

investment. Because there is a limited amount of resources, the people of Carabuela, they would not be

able to fund the entire project without outside assistance. To avoid overburdening the residents of

Carabuela, this grant hopes to secure funding for the initial capital investment while additional operations

and maintenance costs would be funded by the residents of Carabuela.

Page 60: Design Report Final

57 | P a g e

12.2 Background Information

Carabuela is a small village located in the northern part of Ecuador outside Otavalo. Currently, the village

consists of approximately five hundred homes with an average of five people living per residence. Only

two huindred of these homes are currently connected to the wastewater system. Obviously population

growth will continue to expand so our design must meet future demands. Based on a recent analysis of the

village, the population of Carabuela is expected to reach 2700 occupants through the year 2029. Of this

total population only 1800 occupants would be connected into our system. This is the target population

that our design will be based upon. The village has recently constructed a drinking water system that

provides clean water to the majority of the residents. Not every residency that connects into the drinking

water system is currently connected into the wastewater system. To create a system that the village can

rely on, the design accounts for every residency connected into the system.

The residents of Carabuela are creative people who work in occupations such as weaving, knitting, dyeing

or farming with weaving and knitting being the primary occupations. The people rely on the quality of

their hand woven products in order to compete against cheaper woven products that are mass-produced.

The village‘s proximity to Otavalo, a larger economic city, allows for significantly higher financial

opportunities.

The geography of the area consists of a large knoll, which divides the village into two: one side being

farmland and the other side being the main village. The effluent wastewater will need to be routed around

this knoll to the farmland where it will be released. Since no energy sources such as pumps will be used,

gravity will be the only force that will move the wastewater.

12.3 Problem Statement

Contamination of water supplies is an important issue that affects many developing countries and regions.

In Latin America, for example, less than 15 percent of wastewater collected in sewered cities and towns is

treated prior to discharge1. Initially, Carabuela was one of the 15% who treated their collected wastewater

but as their system deteriorated, no longer adequately treated the water. Contaminated water supplies

impact public health by releasing pathogens which cause many diseases which will fall in the range of

excreted infections: non-bacterial faeco-oral diseases (category I), bacterial faeco-oral diseases (category

II), geohelminthiases (category III), taeniases (category IV), water based heliminthiases (category V), and

excreta rodent-vector diseases (category VI) (Mara, 2004).

Category I infections should consider the removal of Rotoviruses, which cause 350,000 to 600,000 deaths

per year. Category II infections are non-latent, have a medium-high persistence, have the ability to

Page 61: Design Report Final

58 | P a g e

multiply, and have a medium-low infectivity. E coli, Salmonella, Shigella and Vibrio Cholera are some

of the infections that are found in Category II infections. Category III infections are latent, very persistent,

unable to multiply, and have a high infectivity. Common infections can be caused by the Roundworm

(200,000 eggs/day), Hookworm (200,000 eggs/day), and Whipworm (5,000-20,000 eggs/day). Category

IV infections are latent, persistent, have the ability to multiply, have a very large infectivity, and have

either a cow or pig intermediate host. One parasite has the ability to produce 106—10

5 eggs/day. Some of

the common examples of parasites in Category IV are the Beef tapeworm and the Pork tapeworm.

Category V infections can be caused by the Trematode worms. Category VI infections can either be

insect-vector or rodent-vector diseases. Insect-vector diseases result from poorly maintained systems and

are transmitted by mosquitoes. Elephantitis is often a result of diseases transmitted by mosquitoes.

Rodent-vector diseases are usually spread by brown rats and result from the rat‘s contact with urine. A

common disease from brown rats is Leptospirosis, which is fatal if not treated. All these emerging

diseases need to be considered for the design of a wastewater treatment system in a developing country

(World Health Organization, 2006).

Engineers must also consider essential microbiology that involves the treatment for certain viruses and

Archaea. Viruses are parasitic microbes that have a DNA or RNA protein coating and range from 20—

200 nm. Archaea are usually a few micrometers and must grow in a 15—40 degree Celsius environment.

They thrive in near neutral or slightly alkaline environments. The design of Carabuela‘s wastewater

system must consider the environment and chemical properties of waste being delivered into the system.

The above considerations are needed for an appropriate design for Carabuela, and effluent qualities are

needed to set at an appropriate removal level to have an effective system while reducing the possibility of

―over kill‖ in the system.

As of now, the current system consists of sewage pipes that lead to a main manhole and a septic tank and

infiltration basin, which are both being overloaded. Storm water and wastewater both enter the system. It

is possible to separate the two but for now the original intent is to design with consideration of a

combination of both streams. The current system has deteriorated due to lack of maintenance to the level

that the septic tank no longer adequately treats the water and the infiltration basin has been clogged. The

effluent of the septic was rerouted to discharge straight into a nearby stream. The effluent water has

serious negative impacts on water quality in the receiving stream. The water from this stream is used for

later downstream irrigation.

Page 62: Design Report Final

59 | P a g e

Implementation of a wastewater treatment system can provide a vast increase in the health and safety of

both the residents of Carabuela and also any inhabitants downstream. The system rural nature of the

community brings about a different set of design standards and design requirements.

Some requirements of the system are that it must not be highly sophisticated and it must be proven. Any

design that is developed must be simple enough that persons in Carabuela can operate it easily. It should

be simple because there will be no one there to guide them in case any sudden problems should arise.

Along these lines the system should only have components that have already been tested. A system that is

based on developing theories should not be implemented. The system must be designed with cultural

appropriateness in mind. For example, the system should not operate using any energy sources because

the people would not be able to finance it for an extended period of time without outside funding.

12.4 Project Detail

12.4.1 Goals and Objectives

There are two major goals for the ―Carabuela Wastewater Treatment‖ Project and specific objectives

within each of the goals.

Goal #1 – To design a wastewater treatment system

Objective #1.1 – To analyze the amount of waste that will flow into the system

Objective #1.2 – To determine the amount of storm water that will enter the system from

roof drains

Objective #1.3 – To size the elements of the system

Goal #2 – To plan with cultural appropriateness

Objective #2.1 – To devise a system that is low cost, requires little maintenance, and

needs no electrical components

Objective #2.2 – To build a wastewater treatment system that can be easily operated

Objective #2.3 – To design according to Carabuela‘s culture

Page 63: Design Report Final

60 | P a g e

The primary goal is to design a wastewater treatment system. Along with this goal it has to be culturally

appropriate. The people of Carabuela are not interested in a sophisticated system, but more so a system

that has been proven. The wastewater treatment standards in the United States are not the same for

Carabuela, so the design will be based off their cultural standards.

12.4.2 Clientele

There is one clientele group for this project.

The clientele are the people of Carabuela. They anticipate a new wastewater treatment system

that will effectively treat their waste to acceptable standards. The people are sponsored by an

organization called Heralding Christ Jesus Blessings (HCJB) whom we have contacted for the

past six months. HCJB has given us the data necessary to design a wastewater treatment system

and has given feedback to a few of our designs. It is up to the governing agency of Carabuela to

decide if our design will be implemented. That is why it is in our best interest to be as culturaly

appropriate with all design decisions.

12.4.3 Methods

The primary methods for achieving the goals and objectives of the ―Carabuela Wastewater Treatment‖

Project will be:

• The development of calculations that will prove the system‘s effectiveness in

treating the waste, and the creation of a bench scale prototype to demonstrate

the system‘s hydraulics

• The writing of a manual guide that will help the people of Carabuela to operate the

system

12.5 Staff/Administration

The ―Carabuela Wastewater Treatment‖ Project will employ three full-time staff members.

• Environmental Systems Director (ESD) - responsible for the overall operation of the

wastewater system. The ESD consults with the chief operator to set the treatment parameters for

process control and general operation of the department

• Chief Operator - responsible for the day-to-day operation of the wastewater department. He

assigns the daily work tasks and insures that the normal, routine tasks are performed

Page 64: Design Report Final

61 | P a g e

• Plant Operator - checks the plant for proper operation of equipment and process

12.6 Needed Resources

Personnel:

o Operations: 3 full-time workers

Environmental Systems Director- Makes operations decisions- $6000/year

Chief Operator- Day-to-day operation of plant; assigns tasks- $5000/year

Plant Operator- Day-to-day operation of plant- $3000/ year

o Construction: About 10 constructions workers; at least 2 skilled in concrete pouring

o Quechua translator (possibly but probably not necessary)

Materials:

o Reinforced concrete for Imhoff tank

o Sand, gravel, wood for drying beds

o Steel for grit chamber

o Shovels, trowels, construction tools, etc.

Land:

o Lagoon: 5000 m2- have to buy

o Drying beds: 960 m2- built on existing treatment site

o Imhoff tank: 70 m2- built on existing treatment site

o Total: 5500 m2 or 0.55 ha

Budget

o Land: $10,000

5,000 m2 @ $2/m

2

o Materials: $13,250

Imhoff tank: $12,050

Concrete: $7,500

Pipes: $250

Steel: $4,300

Drying beds: $500

Sand: $170

Gravel: $210

Grit Chamber: $700

o Labor: $4,000

Skilled labor: $3/hour

Page 65: Design Report Final

62 | P a g e

Unskilled labor: $2/hour

Imhoff tank: $690

230 hours skilled labor

Drying beds: $5,450

Lagoon: $2,000

o Construction Total: $31,000

o Operation:

Labor: 3 full-time workers: $14,000/year

Test effluent quality 2x/ month for first year

Test quality every other year thereafter

Total: $14,000/year

12.7 Goal #1—Design a wastewater treatment system

Designing a wastewater treatment system involves complicated calculations, lengthy research, and

knowledge of how wastewater is properly treated. To ensure a proper design, a certified engineer will

guide and supervise the design, while signing off on all final plans to ensure correct standards are met. A

group of four senior engineering students have developed models of the system that show the necessary

levels of contaminants that are removed by the proposed system, and are being advised and consulted by

two professional engineers.

The method of designing an appropriate system uses engineering software and research of similar case

studies to develop sizes for the components of the wastewater system. The proposed system also uses

technology that has been proven to work by many communities that have a similar situation to Carabuela.

12.8 Goal #2—Plan with cultural appropriateness

Within the proposed design, cultural appropriateness is a major factor in choosing the components of the

system. The system will be inexpensive, require minimal maintenance and no electrical components. Ease

of operation was also considered in order to empower the people of Carabuela to operate the system

without outside resources. This strategy of having a culturally appropriate design will allow for the

citizens of Carabuela to take pride and ownership in their wastewater facility, increasing the community

involvement of maintenance and operation.

The ease of operation and maintenance will be accomplished by the creation of a manual for the entire

system. This manual will include structural drawings for construction, maintenance and operations

Page 66: Design Report Final

63 | P a g e

recommendations, evaluation reports for day to day maintenance, and resources to provide knowledge

about the system in order to have a transparent design.

12.9 Strategy for evaluation of effectiveness

The effluent from each component will be tested for the first year on a bimonthly basis to ensure

proper treatment.

o If treatment is meeting the set standards, operation and maintenance will continue as

before

o If treatment is not meeting the set standards, the operations will be double checked to

make sure all maintenance and operation recommendations are being followed.

o If treatment is not meeting the set standards, and operations are following the

recommendations the system maintenance and operation will be altered until all standards

are met.

After the first year of effective operation, water quality tests will only need to be made on a

biannual basis.

The structural integrity of components will be inspected on a biannual basis.

o If leaks or cracks are found in a component, the component will be immediately patched

or fixed

o If all components are structurally sound, the maintenance and operation will continue as

recommended.

The day to day maintenance of the system will be recorded when completed.

Evaluation reports will be done through the compilation of the day to day maintenance of the

system.

13 Conclusion

In conclusion, we determined that a system consisting of bar racks, grit chambers, an Imhoff tank,

lagoons, and sand drying beds can adequately treat the wastewater of Carabuela without using either

electricity or chemical additives. Wastewater will flow from the gathering system through bar racks,

which will strain out the larger objects in the stream. It will proceed through a grit chamber which will

settle out sand and larger particles. Then it will flow to an Imhoff tank which is a modified septic tank

that settles out organic matter and traps the sludge in an anaerobic digester. From there the remaining

water will go through a series of lagoons for its final treatment before release into a stream or irrigation

canal. The sludge will go to sand drying beds to reduce its water content and pathogen count; if suitable

Page 67: Design Report Final

64 | P a g e

fields are available, the treated sludge may serve as fertilizer. Since many houses connect their roof

drains to the sanitary sewers, an overflow weir will be needed to prevent flushing out the system during

heavy events. The estimated total cost is $31,000 for construction and $14,000 per year for maintenance

and operation. Since this is probably beyond the capacity of the villagers, we hope to obtain funding from

HCJB Global and from the government of Ecuador.

The largest problem with designing a wastewater treatment system for the village was gathering data

about the area. Because Bruce Rydbeck (our contact in the area) had worked on a previous project to

provide drinking water to the town, we could get fairly good topographical maps and layouts of the town,

but we could not get specific information on waste flow volumes, pathogens, or contaminant. We

designed our system using rules of thumb based on organizations that do similar work, case studies, and

the field experience of our contact.

If the people of Carabuela approve the system and funds are found for construction, the greatest worry

becomes for the future functioning of the components. Although the design does not require exhaustive

maintenance, sloppy or infrequent care can ruin it. If the town grows faster than 3% for 20 years the

system may be swamped before its design life is finished. Likewise, if the people maintain the system so

that it works well past the design life, continued growth may swamp the system. However, that is not

particularly likely; if the situation in Ecuador is like that the one in Honduras according to reports from

Anne Mikelonis, the largest problem with Imhoff tank operation is lack of maintenance. With proper

upkeep, however, our system should satisfactorily treat Carabuela‘s wastewater for the next twenty years.

14 Future Work to be Completed

In order for this project to be ready for implementation some additional work must be completed. The

first additional analysis that must be completed is a hydraulic analysis of the system and location.

Because of the limited amount of site topographic data, it was not possible to include a site plan of

elevation requirements or a piping and connection plan. To complete this portion, a survey of the area will

need to be completed to determine the topography of the treatment facility. This will be necessary to

determine the proper location and elevation for each component of the design to insure that the water will

flow by gravity. Included in this analysis would be calculations of headloss in the piping, valves and other

connections. From this hydraulic analysis all component locations can be specified.

The second additional analysis that would need to be completed would be a design of the overflow

channel to the river. Once again, due to the limited data the scope of this project could not include this

Page 68: Design Report Final

65 | P a g e

part of the system. A channel would need to be designed to safely convey the overflow water from the

preliminary treatment structure to the river.

The final additional analysis that would need to be completed would be a review of the work that

WasteWatchers has completed. Because of the sensitive nature of the project and its potential impacts on

the residents of Carabuela and the surrounding environment it is highly recommended that professional

engineers in the fields of environmental and structural engineering review the entirety of the project

including the assumptions and design guide material used. It is also recommended that an engineer

familiar with the location reviews the system to insure the accuracy of the assumptions and to adjust the

system based on the experience and input of the people of Carabuela.

Page 69: Design Report Final

66 | P a g e

15 Works Cited

American Concrete Institute. (2005). Building Code Requirements for Structural Concrete and

Commentary. Farmington Hills: American Concrete Institute.

Mara, D. D. (2004). Domestic Wastewater Treatment in Devloping Countries. Sterling, VA: Earthscan

Publications.

Martin, E. T., & Martin, E. J. (1991). Technologies for Smalle Water and Wastewater Systems. New

York: Van Nostrand Reinholf.

Meier, P. C., & Villalobos, F. (1996).

. Quito: Banco Central Del Ecuador.

Metcalf, L., & Eddy, H. P. (1935). American Sewerage Practice. New York: McGraw Hill.

Mikelonis, A. M. (2007). Chemically Enhanced Primary Treatment of Wastewater in Honduran Imhoff

Tanks. Massachusetts Institute of Technology, Civil and Environmental Engineering.

Naaman, A. E. (2000). Ferrocement and Laminated cementitious composites. Ann Arbor: Techno Press

3000.

Okun, D. A. (1975). Community Wastewater Collection and Disposal. Geneva: World Health

Organization.

Reynolds, T. D., & Richards, P. A. (1996). Unit Processes in Environmental Engineering. Stamford, CT,

USA: Cengage.

Sasse, L. (1998). Decentralised Wastewater Treatment in Developing Countries. Delphi: Bremen

Overseas Research and Development Association.

Seeger, H. (1999). The history of German waste water treatment. European Water Management , 2 (5).

Tchobanoglous, G. a. (1991). Wastewater engineering: Treatment, disposal, and reuse (Third Edition

ed.). New York: McGraw-Hill.

Vesilind, A. (2003). Wastewater Treatment Plant Design. Alexandria, VA: Water Environment

Federation.

Page 70: Design Report Final

67 | P a g e

World Health Organization. (2006). Guidelines for the Safe Use of Wastewater, Excreta and Greywater

(Vol. Volume 2: Wastewater Use in Agriculture). World Health Orgainization.

World Health Organization. (2006). Guidelines for the Safe Use of Wastewater, Excreta and Greywater

(Vol. Volume 4: Excreta and Greywater Use in Agriculture). World Health Organization.

Page 71: Design Report Final

68 | P a g e

16 Acknowledgements

We would like to take this time to express our thanks to all those who helped us, and without whom we

could not have completed this project.

Professor Leonard De Rooy, was our team advisor, monitored our project and gave us suggestions where

our design fell short. Mr. Thomas Newhof, of Prein & Newhof,Inc. was our industrial consultant and

provided us with advice and direction at several key points. Professor David Wunder provided us with

advice and manuals on wastewater treatment.

Bruce Rydbeck of HCJB International was our contact in Ecuador. He connected us with the project, and

sent us the data from Carabuela. Anne Mikelonis and Janice Skadsen, contacts of Mr. Rydbeck with

wastewater experience in Latin America, also contributed suggestions to our project.

Phil Jasperse contributed time, expertise, and materials for our model, and Christie Pasek sacrificed part

of her weekend to help build it. Sandra Chang Garcia translated our Operations & Maintenance Manual

into Spanish.

Thanks again, and God bless you all.

Page 72: Design Report Final

69 | P a g e

17. Appendices

Appendix A: Calculations

Appendix B: Operations and Maintenance Manual

Appendix C: Structural Drawings

Page 73: Design Report Final

Appendix A. Calculations

Bar Rack Design Table

Max flow 0.008 m3/s Channel Width 0.2 m spacing between

bars 20 mm bar diameter 11.13 mm

Number of bars 6 # 3 rebar

Max Depth 0.10 m

10.38 cm

Velocity 0.579 m/s

must be less than 0.6 m/s

Page 74: Design Report Final

Grit Chamber Sutro Weir

Over Flow Weir Calculations

Weir Lip 2

Rectangle Base (cm) 1

Width (cm) 20

Zoom Factor Top

20 0.1

20

Total flow into

system

Half Width Base Height Head Half Gap Width Half Gap Width Gap Width Total Head

w(m) a(m) y(m) x(m) x(m) x(cm) H(m) K Q(m3/s) Q(m3/day) V(m/s)

0.1 0.01 -0.01 0.1 -0.1 20 0.02000 0.027462571 0.00000 0 0.0000 Length of

Overflow Weir

-0.0075 0.1 -0.1 20 0.02250

0.00005 4 0.0100

-0.005 0.1 -0.1 20 0.02500

0.00013 11 0.0255 0.9

-0.0025 0.1 -0.1 20 0.02750 0.00023 20 0.0425

0.000 0.1000 -0.1000 20.0000 0.03000

0.00146 127 0.2441 % into system Flow over weir % over weir Total Flow

0.005 0.0567 -0.0567 11.3303 0.03500

0.00174 150 0.2485 100% 0 0% 150

0.010 0.0436 -0.0436 8.7162 0.04000

0.00201 174 0.2517 100% 0 0% 174

0.015 0.0369 -0.0369 7.3776 0.04500

0.00229 198 0.2543 100% 0 0% 198

0.020 0.0330 -0.0330 6.6028 0.05000

0.00256 221 0.2563 100% 0 0% 221

0.025 0.0305 -0.0305 6.1089 0.05500

0.00284 245 0.2580 92% 21 8% 266

0.030 0.0289 -0.0289 5.7702 0.06000

0.00311 269 0.2594 80% 66 20% 335

0.035 0.0276 -0.0276 5.5248 0.06500

0.00339 293 0.2605 69% 131 31% 423

0.040 0.0267 -0.0267 5.3394 0.07000

0.00366 316 0.2615 60% 211 40% 527

0.045 0.0260 -0.0260 5.1946 0.07500

0.00394 340 0.2624 53% 306 47% 646

0.050 0.0254 -0.0254 5.0786 0.08000

0.00421 364 0.2632 47% 415 53% 779

0.055 0.0249 -0.0249 4.9836 0.08500

0.00449 388 0.2639 42% 537 58% 925

0.060 0.0245 -0.0245 4.9045 0.09000

0.00476 411 0.2645 38% 672 62% 1083

0.065 0.0242 -0.0242 4.8375 0.09500

0.00503 435 0.2650 35% 818 65% 1253

0.070 0.0239 -0.0239 4.7801 0.10000

0.00531 459 0.2655 32% 975 68% 1434

0.075 0.0237 -0.0237 4.7304 0.10500

0.00558 482 0.2659 30% 1143 70% 1626

0.080 0.0234 -0.0234 4.6870 0.11000

0.00586 506 0.2663 28% 1322 72% 1828

0.085 0.0232 -0.0232 4.6487 0.11500

0.00613 530 0.2667 26% 1511 74% 2041

0.090 0.0231 -0.0231 4.6147 0.12000

0.00641 554 0.2670 24% 1710 76% 2264

0.100 0.0228 -0.0228 4.5569 0.13000 0.00696 601 0.2676 22% 2137 78% 2738

Page 75: Design Report Final

Imhoff Tank

Site characteristics

Influent water characteristics

Overflow Rate

(Tchobanoglous, 1991)

Sedimentation Chamber Calculations

Tank dimensions

Sedimentation area

(DEWATS, SASSE 1998)

months 30day

households 360 micro 106

4hrpopulation households 5

Slope 2

Qavg 8m

3

monthshouseholds Qavg 96

m3

day

Qmax 2Qavg

Qdesign 150m

3

day

water 1000kg

m3

0.001Pa s

v 600gal

ft2

dayv 2.83 10

4 m

s

Areaplanreq

Qmax

vAreaplanreq 7.854m

2

Length sed 8m Widthsed 1m

Areap lansed Length sed Widthsed Areaplansed 8m2

retention 2hr

volume retention Qmax

Depthsedvolume

AreaplansedDepthsed 2m

Page 76: Design Report Final

Cone area

Gas vent area

Clearance area

Total Upper Chamber dimensions

Storage compartment

Total 2 Tank system dimensions

Depthsedtop Depthsed 0.5 SlopeWidthsed

2 Dep thsedtop 1.5m

Depthsedbot

Widthsed

2Slope Depthsedbot 1m

Depthsedoverlap Slope 0.5m Dep thsedoverlap 1m

Widthspace 1m Widthspace 1m

Widthspace 39.37 in

Depthclearance 0.5m

Widthhalf Widthsed 2 Widthspace

Widthhalf 3m

Depthsed 2m

Length sed 8m

Volumestorage0.053m

3population

2Volumestorage 47.7 m

3

Depthstorage2

Volumestorage

Length sed WidthhalfDepthstorage2 1.987m

Depthtotal Depthstorage2 Depthsedtop Depthsedbot Depthsedoverlap Depthclearance

Length total Length sed

Width total 2Widthhalf

Length total 8m Length sed 8m

Width total 6m Widthsed 1m

Dep thtotal 5.987m

Page 77: Design Report Final

Settling Velocity

(Mara, pg. 140, Table 12.3 Settling velocity for paracite eggs and cysts)

Parasite and cyst sizes

Cryptospridium

Giardia

Hookworms

Trichuris

Ascaris

dcryp to 6micro m

crypto 1.08 water

vcryp to

g cryp to water dcryp to2

18vcryp to 0.006

m

hr

dgiardia 14micro m

giardia 1.05 water

vgiardia

g giardia water dgiardia2

18vgiardia 0.019

m

hr

vhookworm 0.39m

hr

vtrichuris 1.53m

hr

vascaris 0.65m

hr

vsed

Qmax

Length sed Widthsedvsed 1

m

hr

Page 78: Design Report Final

Sludge Drying Bed

Depthdrying 20cm

Ratiodrying 3

Areadrying0.053m

3population

2 Depthdrying

Areadrying 238.5m2

Widthdrying

Areadrying

3Widthdrying 8.916m

Length drying 3 WidthdryingLength drying 26.749m

totalwidth 4 Widthdrying totalwidth 35.665m

Page 79: Design Report Final

Pond Systems

Site characteristics

Influent water characteristics

Design of Secondary Facultative Pond

Surface Loading Rate

(assumption based averages in case studies)

BOD Loading Rate

(Mara, pg. 119, Eqn 11.3)

Secondary Facultative Pond Area

(Mara, pg. 118, Eqn 11.1)

Hydraulic Residence Time

(evaporation rate) (http://www.inamhi.gov.ec/anuarios/am2000.pdf, Ecaudor meteroligical data)

(pond depth) (Mara, pg. 120, Typical Facultative Pond Depth)

households 360

population households 5

Qavg 8m

3

30dayhouseholds flow Qavg 96

m3

day

Qmax 2 Qavg

water 1000kg

m3

0.0001Pa s

Li 100mg

l

T 15 Celsius

s 350kg

hectare day1.107 .002 T( )

T 25s 166.691

kg

hectare day

Af

Li Qmax

s

Af 0.115hectare

e1 7mm

day

Df 1.5m

Page 80: Design Report Final

(Mara, pg. 120, Eqn. 11.7)

BOD Removal

(Mara, pg. 135)

(Mara, pg. 60, Eqn. 5.9)

(Mara, pg. 59, Eqn. 5.8)

(Mara, pg. 59, Eqn. 5.7)

(unfiltered BOD, includes Algal BOD)

Egg Removal

(Mara, pg. 59, Table 12.4, Egg removal in WSP in NE Brazil case study)

(Mara, pg. 124, Eqn. 11.12)

E coli Removal

units

(influent Ecoli) (Mara, pg. 59, Table 12.2, Bacterial in WSP in NE Brazil case study)

(Mara, pg. 142, Eqn. 12.2)

(Mara, pg. 141, Eqn. 12.1)

f

2 Af Df

2 Qmax 0.001e1 Af f 8.999day

k20 0.1 day1

1.107 0.002T( )T 25

k1 k20 ( )T 20

k1 4.081day1

Le

Li

1 k1 f

Le 2.651mg

l

T 25

eggs i1000

L

f 8.999day f1f

day

Rf 1 0.41 e0.49 f1 0.0085 f1

2

Rf 0.99

eggs ef 1 Rf eggs i eggs ef 9.9251

L

FC1

100mL

Nif 2 107

FC

kB 2.6 day1

1.19( )T 20

kB 6.205day1

Nef

Nif

1 kB f

Nef 3.519 105

FC

Page 81: Design Report Final

Maturation Pond #1 Design

(Depth of maturation pond)

Hydraulic Residence Time

(set variable)

Helminth Eggs

E coli Removal

Maturation Pond #2 Design

Hydraulic Residence Time

Helminth Eggs

Dm 0.5m

m 3day

m1m

day

Rm1 1 0.41 e0.49 m1 0.0085 m1

2

Rm1 0.898

eggs em1 1 Rm1 eggs ef eggs em1 0.101FC

sm

Le Dm

msm 4.418

kg

hectare day

Am1

Qmax m

DmAm1 0.115hectare

Nem1

Nef

1 kB m

Nem1 1.794 104

FC

m2m

day

Rm2 1 0.41 e0.49 m2 0.0085 m1

2

Rm2 0.898

eggs em2 1 Rm2 eggs em1 eggs em2 0.1031

L

sm

Le Dm

msm 4.418

kg

hectare day

Page 82: Design Report Final

E coli Removal

Removal of contaminants

Am2

Qmax m

DmAm2 0.115hectare

Nem2

Nem1

1 kB m

Nem2 914.766FC

Lremoval 100 1Le

LiLremoval 97.349

LogBOD 2 log 100 Lremoval LogBOD 1.577

eggs removal 100 1eggs em2

eggs i eggs removal 99.98972204

Logegg 2 log 100 eggs removal Logegg 3.988

Ecoliremoval 100 1Nem2

Nif Ecoliremoval 99.995426

Logecoli 2 log 100 Ecoliremoval Logecoli 4.34

Page 83: Design Report Final

TSS Removal

Imhoff Tank

TSSin 250mg

L

Qin 192m

3

day

f750 .05 d750 750 m

f375 .05 d375 375 m

f175 .30 d175 175 m

f75 .15 d75 75 m

f29 .25 d29 29 m

f5 .15 d5 5 m

f1.5 .05 d1.5 1.5 m

Length sed 8m

Width sed 1m

Dep thsed 2m

tretention 2hr

tretention 7.2 103

s

vflow

Length sed

tretention

vflow 1.111 103 m

s

vsed 1m

hr

0.01185gm

cm s

pf 1000kg

m3

pp 1600kg

m3

Page 84: Design Report Final

Lagoons

Facultative Ponds

Dp

18 vsed

g pp pf

0.5

Dp 3.173 105

m

Dp 31.733 m

fremoved 1 f1.5 f5

Dp 8 m

50 m 8 mf29

fremoved 0.659

Dm 1.5m

f 9day

vsedfac

Dm

f

vsedfac 1.929 106 m

s

Dpfac

18 vsedfac

g pp pf

0.5

Dpfac 2.644 106

m

fremoved1

Dp 8 m

50 m 8 mf29

8 m Dpfac

8 m 2 mf5

fremoved1 0.275

ftotalremoved1 fremoved fremoved1

ftotalremoved1 0.934

TSSefac 1 ftotalremoved1 TSSin

TSSefac 16.527mg

L

Page 85: Design Report Final

Maturation Ponds

Dm 0.5m

m 3day

vsedm

Dm

m

vsedm 1.929 106 m

s

Page 86: Design Report Final
Page 87: Design Report Final
Page 88: Design Report Final
Page 89: Design Report Final
Page 90: Design Report Final
Page 91: Design Report Final
Page 92: Design Report Final

Imhoff Tank Wall Design Beam Section

Dead Load, psi Fluid Pressure, psi DL

388 1240 250 388

Horizontal Moment Coeff Earth Pressure, psi Beta Φ Cs

99 0 0.85 0.9 0.5

Steel Rebar Design (Vertical) Layer 1 a (height) 19.685 ft

# of bars 8 b (length) 26.247 ft

spacing 1.500 in 3.81 cm Fluid level inside tank 19.685 ft

Clear Space 3.00 in 7.62 cm Ground level with tank 8 ft

6 Bar size (diameter,#) 0.750 in 1.905 cm Ground water table level 0 ft

Bar size (area) 0.440 in2Sludge Density 100 pcf

79 thickness 31.00 in 78.74 cm Soil Pressure 0 psf

bw 12.00 in 30.48 cm Water Pressure 63 pcf

d 27.625 in 70.1675 cm f'c 3500 psi

Ag 372.0 in2fy 40000 psi

A.steel 3.520 in2

c 4.640 in 11.78553 cm Interior wall

Mn 300995 lb-ft/ft Mu (flexure) 1.3(1.4D + 1.7F + 1.6H) 3447 psf

ΦMn 270896 lb-ft/ft Pu (direct tension) 1.65(1.4D + 1.7F + 1.6H) 4375 psf

K.tr 1 Pu (direct compression) 1.0(1.4D + 1.7F + 1.6H) 2651 psf

l.d 14 in 36.49698 cm Vu (shear by concrete) 1.0(1.4D + 1.7F + 1.6H) 2651 psf

Vu (shear beyond concrete) 1.3(1.4D + 1.7F + 1.6H) 3447 psf

Steel Rebar Design (Vertical) Layer 2

# of bars 0 Vertical Moment (moment coeff * qu * a^2) /1000

spacing #DIV/0! #DIV/0! cm 333918 lb-ft/ft

Bar size (diameter,#) 0.750 in 1.905 cm Vertical Moment kN*m

6 Bar size (area) 0.440 in2260507 lb-ft/ft 353.2

thickness 24.00 in

61 bw 12.00 in 30.48 cm

d 19.875 in 50.4825 cm

Ag 288.0 in2

A.steel 0.000 in2

c 0.000 in 0 cm

Mn 0 lb-ft/ft

ΦMn 0 lb-ft/ft

K.tr #DIV/0!

l.d #DIV/0! in #DIV/0! cm

Total A.steel 3.520 in2

Total Mn 300995 lb-ft/ft

Total ΦMn 270896 lb-ft/ft Pass

Minimum Flexural Steel

(200*bw*d)/fy 1.658 in2Pass

ACI 350-06 10.5.1 3*sqrt(fc)*bw*d/fy 1.471 in2Pass

ACI 350-06 10.5.1 Minimum Vertical Wall Steel

.003*Ag 1.116 in2Pass

ACI 350-08 14.3.2 Minimum Steel for Temp and Shrink

.002*Ag 0.744 in2Pass

ACI 350-06 14.3.2 Maximum Flexural Steel

(.0019125*B1*bw*d*fc)/((0.003+fy/Es)*fy) 10.84 in2Pass

Steel Rebar Design (Horizontal)

# of bars 2

6 Bar Size, Diameter 0.750 in 1.905 cm 0.0191 m

Bar size (area) 0.440 in2

A.steel 0.88 in2Pass

Spacing 5.25 in 13.335 cm 0.1334 m

Vertical Moment Coeff

Interior Wall

Page 93: Design Report Final

Imhoff Tank Wall Design Section 1 - 0 to 2 m

Beta Φ

0.85 0.9 f'c 3500 psi

Steel Rebar Design (Vertical) Layer 1 fy 40000 psi

# of bars 8

spacing 1.500 in 3.81 cm Vertical Moment kN*m

Clear Space 3.00 in 7.62 cm 260507 lb-ft/ft 353.2

6 Bar size (diameter,#) 0.750 in 1.905 cm

Bar size (area) 0.440 in2

61 thickness 24.00 in 60.96 cm

bw 12.00 in 30.48 cm

d 20.625 in 52.39 cm

Ag 288.0 in2

A.steel 3.520 in2

c 4.640 in 11.79 cm

Mn 218862 lb-ft/ft

ΦMn 196976 lb-ft/ft

K.tr 1

l.d 14 in 36.5 cm

Steel Rebar Design (Vertical) Layer 2

# of bars 4

spacing 3 7.62 cm

Bar size (diameter,#) 0.750 in 1.905 cm

6 Bar size (area) 0.440 in2

thickness 24.00 in

61 bw 12.00 in 30.48 cm

d 19.875 in 50.48 cm

Ag 288.0 in2

A.steel 1.760 in2

c 2.320 in 5.893 cm

Mn 110815 lb-ft/ft

ΦMn 99734 lb-ft/ft

K.tr 2

l.d 9 in 23.89 cm

Total A.steel 5.280 in2

Total Mn 329677 lb-ft/ft

Total ΦMn 296710 lb-ft/ft Pass

Minimum Flexural Steel

(200*bw*d)/fy 1.238 in2 Pass

ACI 350-06 10.5.1 3*sqrt(fc)*bw*d/fy 1.098 in2 Pass

ACI 350-06 10.5.1 Minimum Vertical Wall Steel

.003*Ag 0.864 in2 Pass

ACI 350-06 14.3.2 Minimum Steel for Temp and Shrink

.002*Ag 0.576 in2 Pass

ACI 350-06 14.3.2 Maximum Flexural Steel

(.0019125*B1*bw*d*fc)/((0.003+fy/Es)*fy) 8.09 in2 Pass

Steel Rebar Design (Horizontal)

# of bars 2

6 Bar Size, Diameter 0.750 in2

Bar size (area) 0.440 in2

A.steel 0.88 in2 Pass

Spacing 5.25 in 13.34 cm

Page 94: Design Report Final

Imhoff Tank Wall Design Section 2 - 2 to 4 m

Beta Φ

0.85 0.9 f'c 3500 psi

Steel Rebar Design (Vertical) Layer 1 fy 40000 psi

# of bars 8

Clear Space 3.00 in Vertical Moment kN*m

6 Bar size (diameter,#) 0.750 in 173652 lb-ft/ft 235.44

Bar size (area) 0.440 in2

61 thickness 24.00 in

bw 12.00 in

d 20.625 in

Ag 288.0 in2

A.steel 3.520 in2

c 4.640 in

Mn 218862 lb-ft/ft

ΦMn 196976 lb-ft/ft

K.tr 1

l.d 14 in

Steel Rebar Design (Vertical) Layer 2

# of bars 0

Bar size (diameter,#) 0.750 in

6 Bar size (area) 0.440 in2

thickness 24.00 in

61 bw 12.00 in

d 19.875 in

Ag 288.0 in2

A.steel 0.000 in2

c 0.000 in

Mn 0 lb-ft/ft

ΦMn 0 lb-ft/ft

K.tr #DIV/0!

l.d #DIV/0! in

Total A.steel 3.520 in2

Total Mn 218862 lb-ft/ft

Total ΦMn 196976 lb-ft/ft Pass

Minimum Flexural Steel

(200*bw*d)/fy 1.238 in2Pass

ACI 350-06 10.5.1 3*sqrt(fc)*bw*d/fy 1.098 in2Pass

ACI 350-06 10.5.1 Minimum Vertical Wall Steel

.003*Ag 0.864 in2Pass

ACI 350-06 14.3.2 Minimum Steel for Temp and Shrink

.002*Ag 0.576 in2Pass

ACI 350-06 14.3.2 Maximum Flexural Steel

(.0019125*B1*bw*d*fc)/((0.003+fy/Es)*fy) 8.09 in2Pass

Steel Rebar Design (Horizontal)

# of bars 2

6 Bar Size, Diameter 0.750 in2

Bar size (area) 0.440 in2

A.steel 0.88 in3Pass

Spacing 5.25 in

Page 95: Design Report Final

Imhoff Tank Wall Design Section 3 - 4 to 6 m Beta Φ

0.85 0.9

f'c 3500 psi

Steel Rebar Design (Vertical) Layer 1 fy 40000 psi

# of bars 4

Clear Space 3.00 in Vertical Moment kN*m

6 Bar size (diameter,#) 0.750 in 86864 lb-ft/ft 117.772

Bar size (area) 0.440 in2

61 thickness 24.00 in

bw 12.00 in

d 20.625 in

Ag 288.0 in2

A.steel 1.760 in2

c 2.320 in

Mn 115215 lb-ft/ft

ΦMn 103694 lb-ft/ft

K.tr 2

l.d 9 in

Steel Rebar Design (Vertical) Layer 2

# of bars 0

Bar size (diameter,#) 0.750 in

6 Bar size (area) 0.440 in2

thickness 24.00 in

61 bw 12.00 in

d 19.875 in

Ag 288.0 in2

A.steel 0.000 in2

c 0.000 in

Mn 0 lb-ft/ft

ΦMn 0 lb-ft/ft

K.tr #DIV/0!

l.d #DIV/0! in

Total A.steel 1.760 in2

Total Mn 115215 lb-ft/ft

Total ΦMn 103694 lb-ft/ft Pass

Minimum Flexural Steel

(200*bw*d)/fy 1.238 in2Pass

ACI 350-06 10.5.1 3*sqrt(fc)*bw*d/fy 1.098 in2Pass

ACI 350-06 10.5.1 Minimum Vertical Wall Steel

.003*Ag 0.864 in2Pass

ACI 350-06 14.3.2 Minimum Steel for Temp and Shrink

.002*Ag 0.576 in2Pass

ACI 350-06 14.3.2 Maximum Flexural Steel

(.0019125*B1*bw*d*fc)/((0.003+fy/Es)*fy) 8.09 in2Pass

Steel Rebar Design (Horizontal)

# of bars 2

6 Bar Size, Diameter 0.750 in2

Bar size (area) 0.440 in2

A.steel 0.88 in3Pass

Spacing 5.25 in

Page 96: Design Report Final

Imhoff Tank Bottom Design

f'c 3500 psi

fy 40000 psi

Vertical Moment kN*m

69042 lb-ft/ft 93.608

Beta Φ

0.85 0.9

Steel Rebar Design (Vertical) Layer 1

# of bars 4

Clear Space 3.00 in 7.62 cm

Spacing 3.00 in 7.62 cm

6 Bar size (diameter,#) 0.750 in 1.91 cm

Bar size (area) 0.440 in2

45 thickness 17.72 in 45.01 cm

bw 12.00 in 30.48 cm

d 14.345 in 36.44 cm

Ag 212.6 in2

A.steel 1.760 in2

c 2.320 in 5.89 cm

Mn 78373 lb-ft/ft

ΦMn 70536 lb-ft/ft

K.tr 1

l.d 10 in 26.15 cm

Steel Rebar Design (Vertical) Layer 2

# of bars 0

Bar size (diameter,#) 0.750 in

6 Bar size (area) 0.440 in2

thickness 24.00 in

61 bw 12.00 in

d 19.875 in

Ag 288.0 in2

A.steel 0.000 in2

c 0.000 in

Mn 0 lb-ft/ft

ΦMn 0 lb-ft/ft

K.tr #DIV/0!

l.d #DIV/0! in

Total A.steel 1.760 in2

Total Mn 78373 lb-ft/ft

Total ΦMn 70536 lb-ft/ft Pass

Minimum Flexural Steel

(200*bw*d)/fy 0.861 in2Pass

ACI 350-06 10.5.1 3*sqrt(fc)*bw*d/fy 0.764 in2Pass

ACI 350-06 10.5.1 Minimum Vertical Wall Steel

.003*Ag 0.638 in2Pass

ACI 350-06 14.3.2 Minimum Steel for Temp and Shrink

.002*Ag 0.425 in2Pass

ACI 350-06 14.3.2 Maximum Flexural Steel

(.0019125*B1*bw*d*fc)/((0.003+fy/Es)*fy) 5.63 in2Pass

Steel Rebar Design (Horizontal)

# of bars 2

6 Bar Size, Diameter 0.750 in2

Bar size (area) 0.440 in2

A.steel 0.88 in2Pass

Spacing 6 in 15.2 cm

2

Strength of Materials

Page 97: Design Report Final

Appendix B. Operations and Maintenance Manual

Page 98: Design Report Final

B-1 | P a g e

Wastewater Treatment System

Operations and Maintenance

Manual

Page 99: Design Report Final

B-2 | P a g e

Table of Contents Bar Rack and Screening Operations and Maintenance ................................................................................. 3

Typical Maintenance Required of the Operator ....................................................................................... 3

Grit Chamber Operations and Maintenance .................................................................................................. 4

Typical Maintenance Required of the Operator ....................................................................................... 4

Safety Measures ........................................................................................................................................ 4

Troubleshooting Certain Symptoms ..................................................................................................... 5

Quantity of Grit Removed ......................................................................................................................... 6

Volatile Solids Content .............................................................................................................................. 6

Imhoff Tank: ................................................................................................................................................. 7

Operation and Maintenance .......................................................................................................................... 7

Starting the Imhoff tank ............................................................................................................................ 8

Operating instructions .............................................................................................................................. 8

Troubleshooting ...................................................................................................................................... 10

Symptom A: Foaming .......................................................................................................................... 10

Symptom B: Sludge Does Not Flow through Draw-off ....................................................................... 11

Pond System Operation and Maintenance .................................................................................................. 19

Background ............................................................................................................................................. 19

The Pond System ..................................................................................................................................... 19

Maintenance ........................................................................................................................................... 20

Drying Beds Operations and Maintenance ................................................................................................. 21

Page 100: Design Report Final

B-3 | P a g e

Operations and Maintenance Manual

Bar Rack and Screening Operations and Maintenance

Typical Maintenance Required of the Operator Screening is one of the simplest processes in the treatment of wastewater; however, foul odor may be

involved because of its contact with the raw sewage in the early stages. To ensure proper operations,

debris in the wastewater stream trapped in the bar racks must be removed properly. Most often, repairs

are needed due to poor performance of the bar rack. Typical procedures to correct the maintenance

problems are seen below:

1. Obnoxious odors, flies, and other insects around the bar rack indicate prolonged storage of

screenings. The frequency of cleaning the screenings from the bar racks should be increased

2. Excessive screen clogging indicates one of the following: (a) an unusual amount of debris in the

wastewater, (b) too low of velocity through the bar racks, or (c) the bar racks are not frequently

cleaned enough.

3. Excessive grit in the chamber is due to low velocities in the channel. Some solutions are to re-

slope the channel bottom, decrease the cross-sectional area, rake the channel, or regularly flush

the channel with a hose.

4. Because screenings attract flies and other insects and are odorous, screenings should be emptied

daily and stored in covered containers. The screenings should then be properly disposed of.

5. The raking of the bar screen to clean the screenings from the racks should be done as follows:

rake the screen upwards until the screenings fall into the depression the steel plate, Allow for

dewatering, and then transfer the screenings into a sealed container for proper disposal.

Page 101: Design Report Final

B-4 | P a g e

Grit Chamber Operations and Maintenance

Typical Maintenance Required of the Operator Although the removal of grit is a fairly uncomplicated process in wastewater treatment, it will require

proper maintenance with ingenuity and resourcefulness. The ideal conditions for operation can be

achieved with two or more channels, but this grit chamber for Carabuela, Ecuador will need only two

channels because of the low capacity needed. The proper maintenance of the grit chamber will reduce any

unnecessary odors and combats corrosion. Below are procedures that will help to ensure proper grit

removal:

1. Measure the depth and location of grit in the collecting channels

2. When grit accumulates to half the water’s depth or two-thirds the channel’s length (whichever

comes first) bypass the channel in operation to the channel that is unused (the clean channel).

3. Dewater the ‘dirty’ channel with dewatering lines and allow the runoff to continue flowing

through the treatment system.

4. After dewatering, use shovels to remove the grit. Measure the amount of grit by estimating the

volume or weight and record this. Fill a wheelbarrow with the grit, and empty the grit into the

sludge drying beds, shallow trenches, or an appropriate landfill.

5. Flush out the channels after the grit is removed, and then the unit or channel is clean for full

service again.

6. If analyzed for volatile solids and a high percent is found, undertake corrective measures as seen

in Symptom A, excessive organic materials.

7. Check for unusual quantities of grit in the treatment units which follow the grit removal process.

8. Remove grit from other units in the system if found in substantial quantities and undertake

corrective measures as seen in Symptom B, carryover of grit.

Safety Measures Grit removal has the ability to produce and accumulate toxic gasses contained in the sewage, which could

possibly cause an explosive atmosphere when mixed with air. If the grit chamber is not fully exposed to

the atmosphere then the following precautions need to be taken:

1. The grit chamber and surrounding area should be thoroughly ventilated at all times.

2. The area should be considered as explosive and protected as such.

3. Consider the area as a toxic zone and protect it as such. Adequate measures should be taken to

protect the workers and operators from any such dangers of contamination while working with

the units.

Page 102: Design Report Final

B-5 | P a g e

Troubleshooting Certain Symptoms

Problems may occur in the grit channel and they should be corrected as soon as possible if they occur.

Some typical problems that occur are Excessive organic materials in the grit chamber and the carryover of

grit into other units downstream of the grit chamber. These are important to realize and correct if and

when present.

Symptom A—Excessive Organic Material in the Grit Chamber

Cause: The velocity of the water is too low or the detention time for the channel is too long.

Prevention and Cure:

Reduce the cross sectional area of the chamber occupied by the flowing sewage.

1. One may install bricks, planks, or tile along the sides of the channel.

2. One may reshape the outlet weir to proportionally reduce the depth of flow for all normal and

present flow rates.

3. Decrease the number of channels used.

4. Reduce the length of the channel by moving the outlet weir further upstream in the grit chamber.

Symptom B—Carryover of Grit

Cause: The velocity of the water is too high and the detention period is too short.

Prevention and Cure:

1. Remove the grit more frequently.

2. Increase the number of channels used. If only two channels are available construct another

channel for standby while the other two channels are in operations. This will allow for the sewage

to bypass to a clean channel while the ‘dirty’ channels shall be cleaned.

3. Increase the cross-sectional area of the channels.

It is important to keep an accurate record of the quality and quantity of grit removed from the chambers.

Fairly simple test may be done in order to detect any unwanted symptoms in the system. An accurate

tracking of records will help to warn the operator, through comparison of the history of quantities and

qualities, of any change in the source of grit and locating any troubles.

Page 103: Design Report Final

B-6 | P a g e

Quantity of Grit Removed Each time the grit chamber is manually clean, a record should be kept of the quantity of grit that is

removed. The quantity of grit should be calculated in terms of flow that has passed through the unit. For

example: if 550 L is removed and the total sewage flow has been 19,000 m3 since the last time the

chamber was cleaned then the grit removed should be recorded as 0.0289 liters of grit removed per 1

m3 of sewage flow.

Volatile Solids Content The percent of volatile solids should be determined regularly if laboratory facilities are available.

Page 104: Design Report Final

B-7 | P a g e

Imhoff Tank:

Operation and Maintenance

Page 105: Design Report Final

B-8 | P a g e

Starting the Imhoff tank

It is necessary to initially seed the Imhoff tank sludge chamber. If digested sludge is not available from

another plant, substitutes include rotted leaves, decomposed manure, cesspool cleanings or other

stabilized organic material (Martin, 1937, pp. 995-1000). Place the materials in the bottom of the Imhoff

tank before opening the tank to water flow. When starting the flow through the tank, make sure that the

seeding material does not move from the sludge chamber into the sedimentation chamber. If seeding

material starts to move into the sedimentation chamber, cease flow into that tank and wait to commence

flow until the material has settled to the bottom of the tank again.

Operating instructions (Daniels, 1945, pp. 105-107)

I. Care of Channels – 2 to 3 times a week

All channels should be kept open and free of solid material, such as grease, scum, grit, etc. Scrub

the channels with a broom or brush.

II. Care of Flowing-through Chambers 2-3 times a week

1. All floating material, such as matches, sticks, grease, etc., should be skimmed off daily and

thrown into the gas vents. Bottles, rags, and other large material should be removed and

buried. No scum or decomposing material should be allowed to accumulate in the flowing-

through chambers or offensive odors may result. As this material does not readily respond to

bacterial digestion, it should be burned or buried after skimming the tank(Beaumont, 1929).

The skimmer may be easily constructed from the attached plan seen in Figure 7.

2. The walls and sloping bottoms should be scraped down with the squeegee at least twice

weekly, and the solid material pushed through the slot. Scraping should be done carefully in

order that no solid material will be stirred up to pass on through the outlet. In case the

squeegee cannot be pushed through the slot it will be necessary to clean the slot by dragging a

chain through it, using a saw-like motion. The walls of the flowing-through chambers above

the water line should be washed or scrubbed down in order to remove any clinging material.

The squeegee and slot cleaner may be easily constructed from the attached plan seen in

Figure 7.

III. Reversing the Flow – 2 times a month or every other week

Page 106: Design Report Final

B-9 | P a g e

In some plants provision is made for reversing the flow of sewage through the tank. This is

necessary in order to permit even deposition of the sludge and to obtain sludge of more uniform

composition. The flow should be reversed at least once a month and preferably every 15 days.

Diagrams for how to reverse the flow can be seen in the following figures. Figure 1 shows

operation of both tanks in direction 1. Figure 2 shows operation of tank #1 only in direction 1. This

flow path is used for maintenance of tank #2. Figure 3 shows the operation of tank #2 only in

direction 1. This flow path is used for maintenance of tank #1. Figure 4 shows operation of both

tanks is direction 2. Figure 5 shows operation of tank #1 in direction 2. This flow path is used for

maintenance of tank #2. Figure 6 shows operation of tank #2 in direction 2. This flow path is used

for maintenance of tank #1.

IV. Care of Gas Vents – 2 to 3 times a week

The scum in the gas vents must be broken up with the churner. This is necessary in order that the

floating material, which has been raised by gas formed during sludge digestion, may settle to the

bottom. If this is not done consistently the scum will accumulate to a depth of several feet, resulting

in considerable odor nuisance. It may even be necessary to remove the material from the tank and

bury it, an expensive and disagreeable process.

V. Measurement of Sludge – 2 to 3 times a month

In order that the operator may know the rate at which sludge is being deposited, it is necessary that

the depth of sludge be measured at intervals not exceeding two weeks. This may be done by the use

of a sounder, constructed of a flat conical pan with a weight at the center. The depth of the sludge

may be measured from the top of the tank. In no case should the sludge be allowed to rise higher

than within two feet of the slots in the bottom of the flowing-through chamber.

VI. Removing Sludge – Once a month

Sludge should usually be drawn about once a month when the tank is operating about to capacity.

During the winter months it will probably not be necessary to remove sludge unless trouble is

experienced or the sludge rises to within two feet of the slot. Well-digested sludge is black and has

very little odor. Only this well digested sludge should be removed. It is better to draw a small

amount of sludge at frequent intervals than to draw a large amount in frequently. Undigested sludge

is gray and none of this material should be drawn. As soon as the first gray color appears no more

of the material should be removed. It is necessary that some digested sludge be left in the tank in

order to assist digestion of the remainder. Sludge should always be removed slowly or the heavier

Page 107: Design Report Final

B-10 | P a g e

undigested sludge may be forced out of the tank. Flow may be started by rodding the discharge

pipe.

VII. General – As necessary

The plant should be in closed within a suitable fence in order to pre vent accidents and

depredations. All valves, gates, and other appurtenances should be tested regularly to see that they

are in good operating condition.

Troubleshooting (Imhoff Tanks, 1961)

Symptom A: Foaming

Causes: Generally, foaming, as characterized by large amounts of fluffy scum rising from the gas vents

and overflowing the tank, is caused by a very high rate of digestion. There is too much undigested sludge

present compared with the well-digested material. This lack of balance may cause violent biological

activity in an acid stage, with high rates of gas production of high carbon dioxide content. Conditions

creating foaming include:

1. Starting a new plant with large quantities of raw sludge without sufficient quantities of "seed",

sludge;

2. Rising temperatures in the sludge digestion zone in spring or early summer following long, cold

winter periods with very slow digestion rates;

3. Large quantities of organic materials in the sewage, such as milk products, or cannery wastes; or

4. Insufficient sludge digestion capacity for the organic loading.

Prevention and Cure:

1. Start operation of a new Imhoff tank in spring or summer.

2. Reduce quantity of sludge in the tank to a safe minimum level during fall months to provide

sufficient space for sludge to be added during winter.

3. Withdraw sludge frequently in low quantities, but maintain a sufficient quantity of well-digested

sludge in the tank.

4. When foaming has started, it may be corrected by:

(a) Temporarily removing tank from service.

Page 108: Design Report Final

B-11 | P a g e

(b) High-pressure spraying to break up gas bubbles in the foam. The quantity of water should be

kept to minimum. Sometimes a gentle spray of either water or sludge liquor directed at the

foam is effective.

(c) Agitating scum mechanically or manually to help release gas bubbles.

(d) Adding hydrated lime to adjust pH to 7.0 or slightly higher. Samples of sludge should be

collected from several points in the tank to determine the quantity of lime to be added. The

total amount may be fed in a dissolved condition at slow rates and in a manner which will

distribute it uniformly to all portions of the digestion zone and gas vents. An alternate method

is to add it in dry form to the gas vents and thoroughly mix and distribute it by plunging and

hosing. Usually, adjustment of the pH is effective in preventing continuance of foaming, once

addition of lime has been discontinued. Correction of the condition causing the foaming is

generally necessary.

Symptom B: Sludge Does Not Flow through Draw-off

Causes:

1. Sludge too viscous; or

2. Obstruction at end of pipe, such as sand, consolidated sludge, rags, sticks, etc.

Prevention and Cure:

1. Rod-out draw-off hole using long pole;

2. Repair valve if broken;

3. When large quantities of grit have accumulated, it may be necessary to dewater tank and remove

grit through gas vents.

Page 109: Design Report Final

B-12 | P a g e

Figure 1: Flow Path #1 & #2

Page 110: Design Report Final

B-13 | P a g e

Figure 2: Flow Path #1

Page 111: Design Report Final

B-14 | P a g e

Figure 3: Flow Path #2

Page 112: Design Report Final

B-15 | P a g e

Figure 4: Flow Path #3 & #4

Page 113: Design Report Final

B-16 | P a g e

Figure 5: Flow Path #3

Page 114: Design Report Final

B-17 | P a g e

Figure 6: Flow Path #4

Page 115: Design Report Final

B-18 | P a g e

Figure 7: Skimmer, Slot cleaner, and squeegee (Imhoff Tanks, 1961)

Page 116: Design Report Final

B-19 | P a g e

Pond System Operation and Maintenance

Background The purpose of this operation and owner’s manual is to familiarize the operator with the pond system by

explaining the setup of the pond system and describing how it functions. Also, this manual will detail how

to fix common problems about the pond system so that the operator can restore it back to working

condition. It is very important that the operator read this manual prior to the start of the treatment process.

The Pond System The pond system is shown below in Figure 8.

Figure 8: Pond System

The effluent, which comes from the Imhoff Tank, enters the facultative pond through a 200mm PVC pipe.

As shown in Figure 8, the 200mm PVC pipe splits into two 200mm PVC pipes. The reason is so that if

one side of the pond needs to be cleaned or repaired, the wastewater can be routed to the other side. The

method for controlling which pipe the wastewater flows through involves gate valves. These gate valves

work by turning the handle, which closes off a section of the pipe preventing any fluid from flowing

through it. A total of 8 gate valves are situated in the pond system. The depth of the facultative pond is 1.5

meters and the depth of the maturation pond is 0.5 meters. The floor of both ponds is made up of a 300

Page 117: Design Report Final

B-20 | P a g e

mm layer of clay soil. The clay soil prevents the wastewater from seeping into the water table, which can

cause negative environmental impacts. In addition to these depths there is an additional 0.5 meters of

freeboard. This freeboard is needed in case there is any extra substantial amount of wastewater that enters

both ponds. In addition to the freeboard, a weir is constructed for both ponds on the side parallel to the

Rio Carabuela for the purpose of directing the flow of wastewater should there be any overflowing.

Maintenance This section discusses the maintenance involved while taking care of the pond system. If the pond system

is not taken care of, the efficiency of the system declines. The pond should be monitored on a regular

basis in order for the treatment process to go properly.

One of the most important things to monitor is the amount of scum buildup on top of the pond. A buildup

of scum will prevent the penetration of sunlight into the pond creating a deficiency in oxygen transfer

between algae and organic materials. Organic materials are bio-oxidized, giving off CO2, NH3 and

inorganic radicals. Algae use CO2, inorganic radicals and sunlight to produce dissolved oxygen in a

cyclic-symbiotic relationship. If there is a strong odor coming from the ponds, check to see if there is

enough sunlight penetration into the ponds.

It is important to monitor the amount of sludge buildup on the bottom of both ponds. At some point there

will be too much sludge and dredging will be required. Dredging involves scooping the bottom of the

pond either by hand or machine and removing any settled sludge after the pond has been drained.

Dredging will have to be performed every 20 years, but may be earlier depending on the quantity of

sludge entering the pond system.

For safety, be sure to fence off the lagoon to prevent livestock and humans from entering the pond area.

Page 118: Design Report Final

B-21 | P a g e

Drying Beds Operations and Maintenance

When the sludge is drained from the Imhoff tank, it should flow down to the sludge drying beds.

1. Hold open a shear gate to let sludge flow into the bed. Let the sludge fill to a depth of 20 cm,

then close gate.

2. If more sludge needs to be drained, shut the open shear gate and open the shear gate to a different

bed. Then, after sludge has stopped flowing, open the other gates long enough to let any

remaining sludge in the pipes drain out.

3. Wait until sludge has dried to the point where it can be removed. This time can vary widely,

depending on the weather. If the temperature is in the high 20s and the air is not humid, the time

may be 3 to 4 weeks. If the air is cold, it may take more than 12 weeks. To check if the sludge is

ready to be shoveled out, try handling it with a shovel.

4. When the sludge is dried out, shovel it out. Use boots and gloves while handling sludge, and

wash with soap afterwards. The sludge can be used for fertilizer, removed to a landfill, or

brought to an incinerator.

As necessary

5. Lay down some sand to replace the sand lost when the sludge was shoveled out.

6. Inspect the shear gates for rust and proper operation. Spray WD40 or similar lubricant in the

hinges if they squeak when opened. Use sand brush or sandpaper to remove rust.

If odors are a problem, first check to make sure that no undigested sludge drains from the Imhoff tank.

Adding potassium permanganate, calcium hypochlorite, and ferrous chloride can reduce odors.

Page 119: Design Report Final

Appendix C. Structural Drawings

Title Page

System Layout

Bar Rack and Grit Chamber Structural Drawings

Imhoff Tank Structural Drawings

Lagoon System Structural Design and Layout

Drying Bed Structural Drawing and Layout

Page 120: Design Report Final
Page 121: Design Report Final
Page 122: Design Report Final

2

3

4

1

5

6

H I J K L M N

A

P-103

B

P-1034

P-105

5

P-105

1P-105

F GD E 6P-104

CBA

1

P-103

2

3

4

1

5

6

1P-104

H I J K L M N

A

P-103

B

P-103

F GD ECBA

611 mm 600 mm600 mm

200 m

m

1500 mm 906 mm 821 mm

1

P-103

900 mm

https://knightvision.calvin.edu/bbcswebdav/orgs/ENGR/senior-projects/2009_10/team05/web/index.html

Scale

Checked by

Drawn by

Date

Project number 2010:05

7 May 2010

1 : 15

Plan View

WasteWatchers

Aaron Lammers

P-101

1 : 15

Level 22

No. Description Date

1 : 15

Level 11

Page 123: Design Report Final

Level 1

-600

Level 2

0

2 3 41 5 6

Level 1

-600

Level 2

0

HIJKLMN

A

P-103

B

P-103

4

P-105

5

P-105

FG DE C B A1

P-103

Level 1

-600

Level 2

0

H I J K L M N

A

P-103

B

P-103

4

P-105

5

P-105

F GD ECBA 1

P-103

Level 1

-600

Level 2

0

234 156 https://knightvision.calvin.edu/bbcswebdav/orgs/ENGR/senior-projects/2009_10/team05/web/index.html

Scale

Checked by

Drawn by

Date

Project number 2010:05

7 May 2010

As indicated

Elevation Views

WasteWatchers

Aaron Lammers

Checker

P-102

1 : 10

East1

1 : 15

North2

1 : 15

South3

No. Description Date

1 : 10

West4

Page 124: Design Report Final

Level 1

-600

Level 2

0

#4 rebar @ 26.35 mm O.C.Top End bent at 100mm Dia

F E

100 m

m

Level 1

-600

Level 2

0

2 3 4 5

200 mm

#4 rebar @ 300mm O.C.

#4 rebar spaced as specified

Level 1

-600

Level 2

0

2 3 41 5 6

#4 rebar @ 300mm O.C.

#4 rebar spaced as shown

50 m

m

200 m

m

https://knightvision.calvin.edu/bbcswebdav/orgs/ENGR/senior-projects/2009_10/team05/web/index.html

Scale

Checked by

Drawn by

Date

Project number 2010:05

7 May 2010

1 : 5

Sectional Views

WasteWatchers

Aaron Lammers

Checker

P-103

1 : 5

Bar RacksC

1 : 5

Section AA

1 : 5

Section BB

1 : 5

Section C1

No. Description Date

Page 125: Design Report Final

2

3

4

1

5

6

M

110mm Slot Depth

https://knightvision.calvin.edu/bbcswebdav/orgs/ENGR/senior-projects/2009_10/team05/web/index.html

Scale

Checked by

Drawn by

Date

Project number 2010:05

7 May 2010

1 : 5

Slot Details

WasteWatchers

Aaron Lammers

Checker

P-104

1 : 5

Typical Isolation Slot Detail1

1 : 5

Drying Plate Slot Detail6

No. Description Date

Page 126: Design Report Final

600 mm

391 m

m

Isolation Half PlateInserted into dryingplate slot

105 m

m10 m

m

105 mm 180 mm

10 mm

105 mm

240 mm

120 m

m

200 mm

10 m

m

43 mm

30 m

m

20 mm

240 mm

220 m

m

https://knightvision.calvin.edu/bbcswebdav/orgs/ENGR/senior-projects/2009_10/team05/web/index.html

Scale

Checked by

Drawn by

Date

Project number 2010:05

7 May 2010

1 : 2

Steel PlateDetails

WasteWatchers

Author

Checker

P-105

1 : 2

Drying Plate Detail1

1 : 2

Drying Plate Cross Section2

1 : 2

Isolation Half Plate Detail3

1 : 2

Sutro Weir Detail4

1 : 2

Isolation Plate Detail5

No. Description Date

Page 127: Design Report Final

https://knightvision.calvin.edu/bbcswebdav/orgs/ENGR/senior-projects/2009_10/team05/web/index.html

Scale

Checked by

Drawn by

Date

Project number 2010:05

7 May 2010

Isometric View

WasteWatchers

Aaron Lammers

Checker

P-106

No. Description Date

Page 128: Design Report Final

https://knightvision.calvin.edu/bbcswebdav/orgs/ENGR/senior-projects/2009_10/team05/web/index.html

Scale

Checked by

Drawn by

Date

Project number 2010:05

7 May 2010

Steel ReinforcingSkeleton

WasteWatchers

Author

Checker

P-107

No. Description Date

Page 129: Design Report Final
Page 130: Design Report Final
Page 131: Design Report Final
Page 132: Design Report Final
Page 133: Design Report Final
Page 134: Design Report Final