BTEC HND in QS Unit / Module Design Principles & Application Assessment Assignment 1–Application of Principles of Building Design and Sustainable Construction Concepts in new building construction Lecturer Mr. Mahinda Padmasiri Student Name ID Date Handed Over 2015-06-30 Date Due 2015-08-09 Initial Submission Date Re- Submission Date Student to Tick if Grading Opportuni ty Criteria Met? Assessor Feedback Initi ally On Resubmissio n LO 1.1 LO 1.2 LO 1.3 LO 1.4 LO 2.1 LO 2.2 LO 2.3 LO 2.4 LO 2.5 Design Principles & Applicatins – Assignment 01 International College of Business and Technology
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
BTEC HND in QS
Unit / Module Design Principles & Application
AssessmentAssignment 1–Application of Principles of Building Design and Sustainable Construction Concepts in new building construction
Lecturer Mr. Mahinda Padmasiri
Student Name ID
Date Handed Over 2015-06-30 Date Due 2015-08-09
Initial Submission Date
Re-Submission Date
Student
to
Tick if
Grading Opportunity
Criteria Met?
Assessor FeedbackInitially
On Resubmission
LO 1.1
LO 1.2
LO 1.3
LO 1.4
LO 2.1
LO 2.2
LO 2.3
LO 2.4
LO 2.5
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
BTEC HND in QS
LO 2.6
LO 3.1
LO 3.2
LO 3.3
LO 4.1
LO 4.2
M1
M2
M3
D1
D2
D3
Assessed By(Name):
Signature: Date:
Student Signature & Comments:
Important Information for Students
The criteria each task relates to are shown against that taskwhere possible.
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
BTEC HND in QS
Please note that plagiarism is treated as a serious offence andtherefore the work you produce must be individual and originalalthough may work in groups in some instances (Please refer toStudent Handbook on Plagiarism & Cheating).
All sources of information must be referenced using “Harvardreferencing” where a reference list/Bibliography should beincluded at the end of the assignment.
Please note that the submission date given for this assignment isthe final date that you can hand over the assignment. A one weekgrace period maybe extended with prior approval from the ProgramManager – Undergraduate.
Assignments returned to students for re-working must be re-submitted within 10 days (Please refer to Student Handbook onAssignments – Re-submission).
Failure to re-submit the previously marked assignment with there-submitted assignment will mean that results cannot be releasedfor the respective unit.
Please read, follow and reference both the contents of the unitoutline and the grading criteria of the assignment beforecompleting this assignment.
Plagiarism:While research and discussion are an essential part of an assignment,
the deliberate copying of someone else’s work or unacknowledged
copying from printed or electronic sources is NOT permitted. You may
be subject to disciplinary procedure if you do this. You should sign
this sheet to show that you comply with these regulations.
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
Mr. Marceline Fernando wasservice as a High courtJudge for last 15 years andnow with his retirement hehas decided to build newhouse in Kandy after theunique and wonderfulexperience he got in havingthree day meditation programin Nillambe meditation
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
BTEC HND in QS
centre in Kandy. He selected a land through a local broker in the areaand they bought the land recently in close proximity to Nillambemeditation centre, Kandy. The land is in a small hilltop of an area of18 perches which is originally a part of age old tea plantation. Thesurrounding is quiet unspoiled landscape of tea planation. The sitehas breathtaking panoramic view to the East.
Mr. Marceline Fernando hired an architect to design his house as pertheir requirement for a peaceful living. The client specifically needsa lot of privacy, so client wants a nice house that will match withthe environment that will enhance their living quality. The clientwants four bedrooms, and an open roof terrace. But their main concernis building maintenance, they need their house to be one that is easyto maintain with all necessary facilities.
There is an access road to land. Existing width of the road is 1.2m(5’), need to expand up to 2m and paving with a suitable paving.
The contract includes both building house and the access road.According to the client brief the architect develops a design concept.And he selects some building materials which make the building and itsfinishes easy to maintain and give a good look resembling the cottagearchitecture suitable for upcountry with touch of Kandyan style.
According to the client brief the architect develops a design concept.And he selects some building materials which make the building and itsfinishes easy to maintain and give a good look. At the same time theproject Engineer suggest the client to develop a Rainwater Harvesting(RWH) System to utilize rainwater for extensive gardening andlandscaping to reduce long-term maintenance costs.
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
Proposed Land
BTEC HND in QS
Note: Based on the above information you can develop the projectfurther where it is necessary as per the client’s requirement.
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
BTEC HND in QS
Tasks:
1.Identify and describe clearly the planning process of building thehouse and the access road. (Lo 1.1)
2.Briefly explain what are the similarities and differences of thedesign process of this two building works? (Lo 1.2)
3.Describe in detail the main stages of the production (construction)phase of this house. (Lo 1.3)
Note: You can assume & develop a design concept for above house.Based on that concept you can describe the production process.
4.Explain in brief, how do you manage and co-ordinate the design andplanning process of the house to meet above requirements of theclient. (Lo 1.4)
Part 02
Task 05:
If you are the architect, how you interpret the client brief and theother factors that may affect the selection of materials, systems andequipment in different architectural design elements that will enhancethe aesthetics in this project? Give examples and sketches where it isnecessary. (Lo 2.1)
Task 06:
Using following information draw complete detail Plan manually.. (Lo4.1)
Space Item Size Qty
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
BTEC HND in QS
Bedroom 3000mm x 3000mm about 04Living Can decide 01
Dining and kitchen Can decide 01Bath 2000mm x 4000mm 02Toilet 2000mm x 2000mm 02
Internal Open space ( Open Can decideTV lobby Can decideGarage Can decide
Note: Apply the material effects and produce minimum 02 shots ofstandard views of the 3D model. Use the standard door and windowsizes.
Task 07:
Produce Detailed finishing schedule for bath room iving room kitchendining and one bed room . (Lo 4.2)
Task 08:
Architect is now selecting the materials for this house. For both loadbearing and non-load bearing walls of the house, the architectsuggests:
1. Fire burnt bricks or2. Compressed Earth Bricks
Explain & evaluate the environmental efficiencies – notably thethermal insulation efficiency, recyclability, durability and costeffectiveness of above building materials. (Lo 2.4)
Note: In this case you may study the climate and weather condition in Kandy for past ten years.
Task 09:
Explain what are the Safe disposal methods for the waste producedduring construction. (Lo 2.5)
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
BTEC HND in QS
Part 03
Task 10:
Architect already suggested a Rainwater Harvesting Tank for abovehouse in order to increase the resource efficiency to make this housemore sustainable. Now he wants to pump water from the RWH tank to thefountain of the proposed reflection pond in the South West corner ofthe land. Explain briefly how you integrate this system andrequirements with overall design of this house. Produce flow diagrams,sketches where it is necessary. (Lo 2.2)
Task 11:
For interior floors of the house, the architect suggests: Terra cotta or
Terrazzo
Do a cost study and compare the financial implications of adopting
above finishing materials. Give reasons for your recommendation. (Lo
2.3)
Design Principles & Applicatins – Assignment 01 International College of Business and Technology
BTEC HND in QS
Task 12:
Having facing a huge open environment the architect suggests to uselarge windows as the day-light maximizing strategy. Explain and assessthe benefits of this design element in terms of energy efficiency ofthis house. (Lo 2.6)
Part 04
Task 13:
Identify and explain in brief the roles & responsibility of all parties involved in the designing & planning processes of a building construction project. (Lo 3.1) (Lo 3.2)
Task 14:
Identify and assess the particular responsibilities and liabilities ofall parties who are responsible for:
1. Health Safety & Welfare at work
2. Adopting Construction Design and Management (CDM) Regulations
(Lo 3.3)