Top Banner
DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM W. T. Weng Brookhaven National Laboratory APS Neutrino Study Superbeam Working Group January 29-30, 2004, FNAL
24

DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Feb 01, 2016

Download

Documents

Madhavi Mehta

DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM. W. T. Weng Brookhaven National Laboratory APS Neutrino Study Superbeam Working Group January 29-30, 2004, FNAL. AGS Upgrade (1MW): Beam loss considerations 1.2 GeV Superconducting Linac H - injection study - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

DESIGN OF THE BNL PROTON DRIVERfor SUPER NEUTRINO BEAM

W. T. Weng

Brookhaven National Laboratory

APS Neutrino Study

Superbeam Working Group

January 29-30, 2004, FNAL

Page 2: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

OUTLINE

AGS Upgrade (1MW):

Beam loss considerations

1.2 GeV Superconducting Linac

H- injection study

2.5 Hz AGS power supply and rf system

Target and Horn system

AGS Upgrade (4MW)

Conclusion

Page 3: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Total Accelerated Protons at the AGSAGS Accelerated Protons 1/1/1993 to 9/30/2002

0.0E+00

2.0E+19

4.0E+19

6.0E+19

8.0E+19

1.0E+20

1.2E+20

Jan

-93

Jan

-94

Jan

-95

Jan

-96

Jan

-97

Jan

-98

Jan

-99

Jan

-00

Jan

-01

Jan

-02

date

acce

lera

ted

pro

ton

s (

red

= S

EB

, b

lue

= F

EB

)

0.8 1020

0.6 1020

0.4 1020

0.2 1020

0

Tot

al a

ccel

erat

ed p

roto

ns 1.0 1020

1.2 1020

Slow extracted beam (Kaon decay) Fast extracted beam (g-2)Note: Lower total accelerated protons in later years due to much shorter running time

Page 4: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

AGS Intensity History

1 MW AGS

Page 5: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

AGS Upgrade to 1 MW

200 MeV Drift Tube Linac

BOOSTER

High Intensity Sourceplus RFQ

Superconducting Linacs

To RHIC

400 MeV

800 MeV

1.2 GeV

To Target Station

AGS1.2 GeV 28 GeV

0.4 s cycle time (2.5 Hz)

0.2 s 0.2 s

200 MeV

1.2 GeV superconducting linac extension for direct injection of ~ 1 1014 protonslow beam loss at injection; high repetition rate possiblefurther upgrade to 1.5 GeV and 2 1014 protons per pulse possible (x 2)

2.5 Hz AGS repetition ratetriple existing main magnet power supply and magnet current feedsdouble rf power and accelerating gradientfurther upgrade to 5 Hz possible (x 2)

Page 6: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

AGS Proton Driver Parameters

present AGS 1 MW AGS 4 MW AGS J-PARC

Total beam power [MW] 0.14 1.00 4.00 0.75

Beam energy [GeV] 24 28 28 50

Average current [A] 6 36 144 15

Cycle time [s] 2 0.4 0.2 3.4

No. of protons per fill 0.7 1014 0.9 1014 1.8 1014 3.3 1014

Average circulating current [A] 4.2 5.0 10 12

No. of bunches at extraction 6 24 24 8

No. of protons per bunch 1 1013 0.4 1013 0.8 1013 4 1013

No. of protons per 107 sec. 3.5 1020 23 1020 90 1020 10 1020

Page 7: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

1.2 GeV Superconducting Linac

Beam energy 0.2 0.4 GeV 0.4 0.8 GeV 0.8 1.2 GeV

Rf frequency 805 MHz 1610 MHz 1610 MHz

Accelerating gradient 10.8 MeV/m 23.5 MeV/m 23.4 MeV/m

Length 37.8 m 41.4 m 38.3 m

Beam power, linac exit 17 kW 34 kW 50 kW

Page 8: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Layout of the 1.2 GeV SCL

Page 9: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Beam Loss at H- Injection Energy

AGS Booster PSR LANL SNS 1 MW AGS

Beam power, Linac exit, kW 3 80 1000 50

Kinetic Energy, MeV 200 800 1000 1200

Number of Protons NP, 1012 15 31 100 100

Vertical Acceptance A, m 89 140 480 55

23 0.57 4.50 6.75 9.56

NP /23 A), 1012 m 0.296 0.049 0.031 0.190

Total Beam Losses, % 5 0.3 0.1 3

Total Loss Power, W 150 240 10001440

Circumference, m 202 90 248 807

Loss Power per Meter, W/m 0.8 2.7 4.0 1.8

Page 10: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

AGS Injection Simulation

Injection parameters:

Injection turns 360

Repetition rate 2.5 Hz

Pulse length 1.08 ms

Chopping rate 0.65

Linac average/peak current 20 / 30 mA

Momentum spread 0.15 %

Inj. beam emittance (95 %) m

RF voltage 450 kV

Bunch length 85 ns

Longitudinal emittance 1.2 eVs

Momentum spread 0.48 %

Circ. beam emittance (95 %) 100m

Page 11: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Halo in AGS as Function of Linac Emittance

For acceptable operation, the linac emittance has to be less than 1.5

Page 12: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Linac Emittance Improvement

Emittance at source 0.4 pi mm mr (rms,nor)

Page 13: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Options Layout

Page 14: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

New AGS Main Magnet Power Supplypresently:

Repetition rate 2.5 Hz 1 Hz Peak power 110 MW 50 MW Average power 4 MW 4 MW Peak current 5 kA 5 kA Peak total voltage 25 kV 10 kV Number of power converters / feeds 6 2

Page 15: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Eddy Current Losses in AGS Magnets

For 2.5 (5.0) Hz:In pipe: 65 (260) W/mIn coil: 225 (900) W/m

Page 16: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

AGS RF System Upgrade

Use present cavities with upgraded power supplies

Upgrade Present

• Rf voltage/turn 0.8 MV 0.4 MV• RF voltage/gap 20 KV 10 KV• Harmonic number 24 6 (12)• Rf frequency 9 MHz 3 (4.5) MHz• Rf peak power 2 MW 0.75 MW• Rf magnetic field 18 mT 18 mT• 300 kW tetrodes/cavity 2 1

Page 17: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Neutrino Beam Production

•1 MW He gas-cooled Carbon-carbon target

•New horn design•Target on down-hill slope forlong baseline experiment

•Beam dump well above ground water table to avoid activation

Page 18: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Super Neutrino Beam Geographical Layout

BNL can provide a 1 MW capable Super Neutrino Beam for $104M FY03 (TEC) dollars

the neutrino beam can aim at any site in the western U.S. the Homestake Mine is shown here)

there will be no environmental issues if the beam is produced atop the hill illustrated here and the beam dumped well above the local water table construction of the Super Neutrino Beam is essentially de-coupled from AGS and RHIC operations

Page 19: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Path Towards 4 MW

Upgrade I Upgrade II Upgrade III

Linac intensity/pulse 1.0 1014 2.0 1014 2.0 1014

Linac rep. rate 2.5 Hz 2.5 Hz 5.0 HzLinac extraction energy 1.2 GeV 1.5 GeV 1.5 GeV23 9.6 14.9 14.9Beam power 54 kW 144 kW 288 kW

AGS intensity/pulse 0.9 1014 1.8 1014 1.8 1014 AGS rep. rate 2.5 Hz 2.5 Hz 5.0 HzRf peak power 2 MW 4 MW 8 MWRf gap volts/turn 0.8 MV 0.8 MV 1.5 MVAGS extraction energy 28 GeV 28 GeV 28 GeVBeam power 1 MW 2 MW 4 MW

Page 20: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

4 MW AGS Proton Driver Layout

200 MeV Drift Tube Linac

BOOSTER

High Intensity Sourceplus RFQ

Superconducting Linacs

To RHIC

400 MeV

800 MeV

1.5 GeV

To Target Station

AGS1.2 GeV 28 GeV

0.2 s cycle time (5 Hz)

0.1 s 0.1 s

200 MeV

Page 21: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Additional Work Planned

1. Reduction of the Linac Emittance2. Cryogenic System Design3. LLRF Tuning and Feedback of SCL4. Transition Crossing in the AGS5. Beam Collimation6. Optimization of the Target and Horn System7. Improvement of Upgrade Path

Page 22: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Preliminary Cost Estimate of the BNL - SNBF

A) Accelerator Systems B) Neutrino Production Systems

1.2 GeV SC Linac:

Front End $ 2.5 M

LE SC Linac $ 38.3 M

ME SC Linac $ 30.7 M

HE SC Linac $ 28.1 M

AGS Upgrades:

AGS Power Supply $ 32.0 M

AGS RF Upgrade $ 8.6 M

AGS Injection Channel $ 3.7 M

Full Turn Extraction $ 5.5 M

Shielding $ 3.2 M

Direct Cost $156.8 M

Item Cost

Proton Transport $14.8 M

Target/Horn $ 5.5 M

Shielding/Dump $ 5.8 M

Decay Tunnel $ 0.4 M

Hill. Construction $13.0 M

Near Detector Vault $ 7.3 M

Conventional Facility $ 7.5 M

Other Construction $ 2.2 M

Installation $ 5.2 M

Direct Cost $61.7 M

Total Direct Cost = $218.5 M$

Page 23: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Preliminary Cost Estimate – Continued

Total Direct Cost = $218.5 M

Add ED&I, 15%

Contingency, 30%

BNL Project Overhead, 13%

Total Estimated Cost = $369 M

Page 24: DESIGN OF THE BNL PROTON DRIVER for SUPER NEUTRINO BEAM

Conclusions

1. The feasibility has been demonstrated for a 1MW upgrade for the AGS

2. It is possible to further upgrade the AGS to 2~4MW

Such a high power proton driver is essential for very long base line neutrino experiment and also for the neutrino factory.