Top Banner

of 40

Design of Cofferdam

Apr 06, 2018

Download

Documents

ajiboyd
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/2/2019 Design of Cofferdam

    1/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    Cofferdams

    Lecture 9

  • 8/2/2019 Design of Cofferdam

    2/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    1

    Cofferdams

    A cofferdam is a temporarystructure designed to keep waterand/or soil out of the excavationin which a bridge pier or otherstructure is built.

    - Standard Handbook of HeavyConstruction

  • 8/2/2019 Design of Cofferdam

    3/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    2

    Cofferdams Cofferdams are temporary enclosures to keep out

    water and soil so as to permit dewatering andconstruction of the permanent facility (structure) inthe dry.

    A cofferdam involves the interaction of thestructure, soil, and water. The loads imposedinclude the hydrostatic forces of the water, as wellas the dynamic forces due to currents and waves.

    Because cofferdams are typically constructedunder adverse conditions in a marine environment,

    and because significant deformations of elementsmay occur at various stages of construction, it isdifficult to maintain close tolerances. Ampleprovisions must be made for deviations indimensions so that the finished structure may be

    constructed according to plan.

  • 8/2/2019 Design of Cofferdam

    4/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    3

    Cofferdams

    The loads imposed on the cofferdam structureby construction equipment and operationsmust be considered, both during installation ofthe cofferdam and during construction of thestructure itself.

    Removal of the cofferdam must be plannedand executed with the same degree of care asits installation, on a stage-by-stage basis. Theeffect of the removal on the permanent

    structure must also be considered. For thisreason, sheet piles extending below thepermanent structure are often cut off and leftin place, since their removal may damage the

    foundation soils adjacent to the structure.

  • 8/2/2019 Design of Cofferdam

    5/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    4

    Cofferdams

    In cofferdam construction, safety is aparamount concern, since workers will beexposed to the hazard of flooding and collapse.

    Safety requires:

    good design

    proper construction

    verification that the structure is being constructed asplanned

    monitoring the behavior of the cofferdam and

    surrounding area

    provision of adequate access

    light and ventilation, and

    attention to safe practices on the part of all workers

    and supervisors.

  • 8/2/2019 Design of Cofferdam

    6/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    5

    Cofferdams

    Types of cofferdam:

    Braced

    Earth-Type

    Timber Crib

    Double-Walled Sheet Pile

    Cellular

  • 8/2/2019 Design of Cofferdam

    7/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    6

    Cofferdams

    Braced CofferdamsFormed from a single wall of sheetpiling

    Driven into the ground to form abox around the excavation site

    The "box" is then braced on theinside

    Interior is dewatered

    Primarily used for bridge piers inshallow water (30 - 35 ft depth)

  • 8/2/2019 Design of Cofferdam

    8/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    7

    Cofferdams

    Cofferdam Design ConsiderationsScouring or undermining by rapidlyflowing water

    Stability against overturning or tiltingUpward forces on outside edge due totilting

    Stability against vertical shearEffects of forces resulting from:

    Ice, Wave, Water, Active Earth and Passive

    Earth Pressures

  • 8/2/2019 Design of Cofferdam

    9/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    8

    Cofferdams

    Advantages of CofferdamAllow excavation and construction of

    structures in otherwise poorenvironment

    Provides safe environment to work

    Contractors typically have designresponsibility

    Steel sheet piles are easily installedand removed

    Materials can typically be reused on

    other projects

  • 8/2/2019 Design of Cofferdam

    10/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    9

    Cofferdams

    Items needed for installationPile driving hammer

    Vibratory orImpact

    Crane of sufficient size

    Steel sheet piles are typicallyused

    H-piles and/or wide-flange beamsfor wales and stringers

    Barges may be required

  • 8/2/2019 Design of Cofferdam

    11/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    10

    CofferdamsTYPES OF IMPOSED LOADS

    Hydrostatic pressure The maximum probable height outside the

    cofferdam during construction and the waterheight inside the cofferdam during various stagesof construction need to be considered. These

    result in the net design pressure shown below:

    Hydrostatic forces on

    partially dewatered cofferdam

  • 8/2/2019 Design of Cofferdam

    12/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    11

    CofferdamsTYPES OF IMPOSED LOADS

    Forces due to Soil LoadsThe soils impose forces, both locally

    on the wall of the cofferdam and

    globally upon the structure as awhole. These forces are additive tothe hydrostatic forces.

    Local forces are a major component

    of the lateral force on sheet-pile walls,causing bending in the sheets,bending in the wales, and axialcompression in the struts

  • 8/2/2019 Design of Cofferdam

    13/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    12

    CofferdamsTYPES OF IMPOSED LOADS

    Forces due to Soil Loads (Contd)

  • 8/2/2019 Design of Cofferdam

    14/40

  • 8/2/2019 Design of Cofferdam

    15/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    14

    CofferdamsTYPES OF IMPOSED LOADS

    Wave forces

    Waves acting on a cofferdam are

    usually the result of local windsacting over a restricted fetch andhence are of short wavelength andlimited to height.

    Waves can also be produced bypassing boats and ships,especially in a restricted waterway.

  • 8/2/2019 Design of Cofferdam

    16/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    15

    CofferdamsTYPES OF IMPOSED LOADS

    Ice forces These are of two types:

    the force exerted by the expansion of a closed-in solidly frozen-over area of water surface

    (static ice force) and the forces exerted by the moving ice on

    breakup (dynamic ice force).

    As an example, for static ice force, a value

    of 4000 lb/ft2

    has been used on cofferdamsand structures on the great Lakes, whereasthe value due to dynamic ice force on acofferdam-type structure are often taken at12,000 to 14,000 lb/ft2 of contact area.

  • 8/2/2019 Design of Cofferdam

    17/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    16

    CofferdamsTYPES OF IMPOSED LOADS

    Seismic Loads These have not been normally considered

    in design of temporary structures in thepast. For very large, important, and deep

    cofferdams in highly seismically activeareas, seismic evaluation should beperformed.

    Accidental loads

    These are the loads usually caused byconstruction equipment working alongsidethe cofferdam and impacting on it under theaction of waves.

  • 8/2/2019 Design of Cofferdam

    18/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    17

    Cofferdams Scour

    Scour of the river bottom or seafloor alongthe cofferdam may take place owing to rivercurrents, tidal currents, or wave-inducedcurrents. Some of the most serious and

    disastrous cases have occurred when thesecurrents have acted concurrently.

    A very practical method of preventing scouris to deposit a blanket of crushed rock or

    heavy gravel around the cofferdam, eitherbefore or immediately after the cofferdamsheet piles are set. A more sophisticatedmethod is to lay a mattress of filter fabric,

    covering it with rock to hold it in place.

  • 8/2/2019 Design of Cofferdam

    19/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    18

    Cofferdams

    Cofferdam Components

    Sheet piling

    Bracing frame

    Concrete seal

    Bearing piles

  • 8/2/2019 Design of Cofferdam

    20/40

  • 8/2/2019 Design of Cofferdam

    21/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    20

    Cofferdams

    The structure inside may be foundeddirectly on rock or firm soil or mayrequire pile foundations. In thelatter case, these generally extendwell below the cofferdam.

    In order to dewater the cofferdam,the bottom must be stable and able

    to resist hydrostatic uplift.Placement of an underwaterconcrete seal course is the fastestand most common method.

  • 8/2/2019 Design of Cofferdam

    22/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    21

    Cofferdams An underwater concrete seal course may

    then be placed prior to dewatering in orderto seal off the water, resist its pressure, andalso to act as a slab to brace against theinward movement of the sheet piles in order

    to mobilize their resistance to uplift underthe hydrostatic pressure.

  • 8/2/2019 Design of Cofferdam

    23/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    22

    Cofferdams Construction Sequence For a typical cofferdam, such as for a

    bridge pier, the constructionprocedure follow the listed pattern.

    1. Pre-dredge to remove soil or soft

    sediments and level the area of thecofferdam.

  • 8/2/2019 Design of Cofferdam

    24/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    23

    Cofferdams Construction Sequence

    2. Drive temporary support piles3. Temporarily erect bracing frame on the

    support piles.

  • 8/2/2019 Design of Cofferdam

    25/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    24

    Cofferdams Construction Sequence

    4. Set steel sheet piles, starting at all fourcorners and meeting at the center of each side

    5. Drive sheet piles to grade.

    6. Block between bracing frame and sheets, and

    provide ties for sheet piles at the top asnecessary.

  • 8/2/2019 Design of Cofferdam

    26/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    25

    Cofferdams Construction Sequence

    7. Excavate inside the grade or slightlybelow grade, while leaving the cofferdam

    full of water.

  • 8/2/2019 Design of Cofferdam

    27/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    26

    Cofferdams Construction Sequence

    8. Drive bearing piles.9. Place rock fill as a leveling and support

    course.

  • 8/2/2019 Design of Cofferdam

    28/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    27

    Cofferdams Construction Sequence

    10. Place tremie concrete seal.

  • 8/2/2019 Design of Cofferdam

    29/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    28

    Cofferdams Construction Sequence

    Tremie concrete seal.

  • 8/2/2019 Design of Cofferdam

    30/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    29

    Cofferdams Construction Sequence

    Tremie concrete seal.

  • 8/2/2019 Design of Cofferdam

    31/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    30

    Cofferdams Construction Sequence

    11. Check blocking between bracing and sheets.12. Dewater.

    13. Construct new structure.

  • 8/2/2019 Design of Cofferdam

    32/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    31

    Cofferdams

    Cofferdam for the Sidney Lanier Bridge, Oregon

  • 8/2/2019 Design of Cofferdam

    33/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    32

    Cofferdams Construction Sequence

    13. Construct new structure.14. Flood cofferdam.

  • 8/2/2019 Design of Cofferdam

    34/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    33

    Cofferdams Construction Sequence

    15. Remove sheet piles.16. Remove bracing.

    17. Backfill.

  • 8/2/2019 Design of Cofferdam

    35/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    34

    Cofferdams Traditional Sheet Pile Shapes

    Z-Type (Z)Used for intermediate to deep

    wall construction

    Larson / U Type (U)Used for applicationssimilar

    to Z - Type

    Flat / Straight Type (SA), (S)

    Used for filled cell constructionArch shaped & lightweight

    Used forshallower wall

    construction

  • 8/2/2019 Design of Cofferdam

    36/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    35

    Cofferdams Typical types of interlocks

    Ball & Socket (BS) Single Jaw (SJ) Double Jaw (DJ)

    Hook & Grip (HG) Thumb & Finger

    one point contact (TFX)

    Double Hook (DH) Thumb & Finger

    three point contact (TF)

  • 8/2/2019 Design of Cofferdam

    37/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    36

    Cofferdams Braced Cofferdam Construction

    Install Wale and Strut System forFramework /Template

  • 8/2/2019 Design of Cofferdam

    38/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    37

    Cofferdams Braced Cofferdam Construction

    Install Wale and Strut System for Framework /Template (Contd)

  • 8/2/2019 Design of Cofferdam

    39/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    38

    Cofferdams Tips for installing Sheet piles:

    Always set-up a template system

    Rule of thumb: Crane Boom length shouldbe twice that of the sheets

    Drive the Sheets with the "male" interlockleading in order to avoid soil plugs

    If the "female" interlock must lead, place abolt or other object at the bottom to avoid

    debris filling the slot Align and plumb the first two sheets and

    drive carefully and accurately

    Drive sheets in pairs when possible placing

    the hammer in the center of the pair

  • 8/2/2019 Design of Cofferdam

    40/40

    Temporary StructuresCM 420CM 420CM 420CM 420CM 420CM 420

    39

    Cofferdams

    Tips for installing Sheet piles (Contd): Some contractors recommend not driving a

    sheet more than 1/3 its length beforedriving the adjacent pile

    Letting the sheets "freefall" and drop inorder to aid in penetration will generallycause the sheets to fall "out of plumb"

    Cellular cofferdams require that all sheets

    are set and "closed" before any driving isdone

    Finally never rush the Pile Foreman!!