Design Exceptions 101 Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer
28

Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Dec 24, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Design Exceptions 101Design Exceptions 101

Ed Fischer, State Traffic-Roadway EngineerMike Morrow, FHWA Field Operations EngineerKent R. Belleque, Senior Interchange Engineer

Page 2: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Items to Cover TodayItems to Cover Today

• Design Exception Background• Key Items in Design Exceptions

– Timelines– Evaluation Criteria– Justification– Helpful Tools

• Planning Level Design Exceptions• Case Studies (Helpful Hints)• Expectations from Ed and Mike• Q & A

Page 3: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Chief Engineer’s RoleChief Engineer’s Role

• Authority for Design Standards• Outlined in Title 23 CFR 625• Oregon Highway Design Manual (HDM)

Approval of Exceptions to Standards• Delegated to State Roadway Engineer

• Contact with FHWA on Process

Page 4: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Expectations from ODOTExpectations from ODOT

• Provide Enough Information that Convinces the Reviewer to Approve not Achieving the Standard

Can we get to Yes?

Page 5: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

When Should the Process Begin?When Should the Process Begin?

• Start Discussion ASAP with ODOT• Allow Sufficient Time for Review• May also Require Approval by FHWA• Insufficient Data will Require More Time

Page 6: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

What Should be Included?What Should be Included?

• General Discussion on the Design Exception• Evaluation of the Exception• Justification• Review and Approval (Tech Center and FHWA

Level)

Page 7: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Areas of Special NoteAreas of Special Note

• Vertical Clearance and Motor Carrier Contact

Page 8: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Areas of Special NoteAreas of Special Note

• 3R- Roadside Design- Documented @ Region

Page 9: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Areas of Special NoteAreas of Special Note

• Form has been updated– Top 10% SPIS– Interchange Spacing

Page 10: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Other Available ToolsOther Available Tools

• Highway Safety Analysis Tools – http://www.oregon.gov/ODOT/HWY/TRAFFIC-ROAD

WAY/highway_safety.shtml– Crash Data– SPIS/SIP– Crash Reduction Factors

Page 11: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Flexibility in Design-FHWAFlexibility in Design-FHWA

• Design Exceptions– Consideration of Safety

and Operations– Consideration of Crash

History and Roadway Character

– Cost to Attain Full Standard and Impact on Environmental Features

– Degree of Reduction• Impact on other

Standards• Mitigation

Page 12: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Flexibility in Design-AASHTOFlexibility in Design-AASHTO

• Similar to FHWA Guidance– Proper Justification– Crash analysis, Rationale

for Exception

• Stresses Importance of Documentation

Page 13: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Flexibility in Design- 1R and SFFlexibility in Design- 1R and SF

• TRB Special Report 214- 3R Practices

• 1R and Single Function Impact on Design Exceptions?????

Page 14: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Design Exceptions on a National Design Exceptions on a National Level Level • Dealing with Same

Issues as ODOT– Why are Design

Exceptions Done?• 42%- Reduces Liability• 40%- Design

Exception Documentation

• Number of Exceptions Varies

Page 15: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

NCHRP Synthesis 316NCHRP Synthesis 316

• Type of Exceptions Similar

Page 16: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Planning Design ExceptionsPlanning Design Exceptions

• Planning Studies Need to Follow Design Standards– Design Elements Need to Meet Standard or Get an

Exception– If Elements are Unknown, don't Show Specific Dimensions

• Timing of Planning Design Exceptions– Construction in 5 years-Process the Exception Before

Putting in Planning Document– Construction in 5-10 years-Submit Draft Design Exception

and Obtain Written Indication of Approval/Denial

Page 17: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Non-Design Exceptions IssuesNon-Design Exceptions Issues

• PLA01-Review Process for Design Concepts on ORS 366.215 Routes– Vehicle Carrying Capacity

and Lane Reductions

Page 18: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Tech Services- To Do List Tech Services- To Do List

• Design Speed• Horizontal and Vertical Angle Points• 3R- Criteria A & B• Others??

Page 19: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Real Life Examples: Case 1Real Life Examples: Case 1

Specifically it is requested that the following design features not be further evaluated: horizontal alignment, vertical alignment, grades, lane width, shoulder width, bridge width and the correction of deficient bridge rails and missing ADA sidewalk features, roadway cross slopes, cut/fill/ditch slopes, access, and clear zone.

Page 20: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Case 2: Reasons for Not Attaining Case 2: Reasons for Not Attaining StandardStandard

Page 21: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

The Request: Case 3The Request: Case 3

Page 22: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Case 3 (Continued)Case 3 (Continued)

Page 23: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

The Request: Case 4The Request: Case 4

Page 24: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.
Page 25: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Items to RememberItems to Remember

• Look at Crash Data• Number and Type of Exceptions• Cost by Itself is not a Good Justification• Look for Ways to Mitigate

– Striping– Signing– Illumination

Page 26: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Items to RememberItems to Remember

• Identify Design Exceptions ASAP• Work with Design Exception Review Team in

Salem– Christopher Henson Rural Roadway Engineer– Rich Crossler-Laird Urban Roadway Engineer– Kent Belleque Interchange Engineer– Dan MacDonald Roadside Safety Engineer– Dave Polly Standards Engineer– And Others

• Allow Sufficient Time for Processing

Page 27: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Web Page LinksWeb Page Links

• Design Exceptions– http://egov.oregon.gov/ODOT/HWY/ENGSERVICES/de

sign_exceptions.shtml– Request Form Instructions– Required Signatures

• Technical Bulletins– http://egov.oregon.gov/ODOT/HWY/ENGSERVICES/

tech_bulletin.shtml

Page 28: Design Exceptions 101 Ed Fischer, State Traffic-Roadway Engineer Mike Morrow, FHWA Field Operations Engineer Kent R. Belleque, Senior Interchange Engineer.

Comments from ODOT and FHWAComments from ODOT and FHWA

• Ed Fischer and Mike Morrow

• Q and A