    Objective

    The Design Development phase is a refinement of the Scope of Work

    identified during Schematic Design. As required, large-scale drawings,

    mock-ups, and detailed plans are developed to present a coordinated,

    clear view of the projects major elements with respect to architectural,

    structural, mechanical, electrical, plumbing, equipment, civil, landscape,

    and utility infrastructure.

    The Project Teams key objective during this phase is to integrate all

    design elements in order to provide the General Contractor and/or

    Construction Manager with information sufficiently comprehensive to

    support a project Design Development estimate and guaranteed maxi-

    mum price for the project scope of work. Inconsistencies between the

    budget previously developed during Predesign and revised in subsequent

    phases should be reconciled for scope and budgetary adjustments. While

    the client may provide design input during this phase, any changes in a

    projects scope during Design Development will more than likely impact

    the budget and schedule.

    For large projects completed Design Development documents (both

    electronic and hardcopy), final review comments, a refined cost estimate,

    schedule, and MN B3 documentation are summarized in a project report

    for ratification by the Universitys Capital Oversight Group and Project

    Executive Committee.

    jec t In i t iat ion

    Scoping

    Feas ibi l i t y

    Programming

    Schemat ic Des ign

    i i

    Const ruc t ion Documents

    Const ruc t ion

    Closeout

    DESIGN DEVELOPMENT

    I i i i

    i

    i i l i

    i

    i i i

    i

    l

    l

    l

    I i i i

    i

    i i l i

    i i l

    i

    i

    l

    I i i i

    i

    i i l i

    i i l

    i l

    i

    l

    i iI i i i

    i

    i i l i

    i i l i

    ii iI i i i

    i

    i i l i

    i i l i

    ii iI i i i

    i

    i i l i

    i i l i

    Design Development

    TasksProject TeamPrior Phase Review CommentsProject Delivery MethodExternal Peer Review

    Constructability ReviewProject ScheduleSustainability ComponentsSite DesignBuilding Design

    *General

    *Architectural

    *Hazardous Materials

    *MEP/FP Systems Design

    *Verify Coordination of Drawings and SpecsCommissioning Strategy PlanBudget ReviewCommunity Outreach PlanPublic Art

    Jurisdictional ReviewCommunications PlanProcedures and Administration

    DeliverablesDesign Development documentsCompleted review commentsExceptions to StandardsMonthly project summary for CPPM man-

    agement and Project Executive CommitteeMN B3 documentationProject Delivery Readiness IndexBenchmark ReportCM-GMPTotal project budgetProgress meeting minutesProject report for COG and Project

    Executive Committee ratificationBoard of Regents notification of

    construction awards over $5,000,000

    ApprovalsProject Team (review only)CPPM Management (review and approval)COG and Project Executive Committee

    Project Delivery Model 69

  • 8/13/2019 Design Development score

    2/22

    Design Development Phase Checklist

    Task Task Notes

    Determine if additional project team members should be

    added during Design Development.

    Project Team

    Task Task Notes

    Gather outstanding review comments from prior design

    phases and determine whether the comments have been

    satisfactorily resolved. Where comments have not been

    resolved, investigate and document conclusions.

    Prior Phase Review Comments

    Task Task Notes

    Confirm project delivery method previously selected in

    Schematic Design.

    Confirm contract provisions and insurance requirements for

    project delivery method selected.

    Project Delivery Method

    Task Task Notes

    Forward final external peer review comments to design

    professionals for action and written response.

    External Peer Review

    Task Task NotesConfirm constructability review in cases where

    Construction Manager is under contract.

    Constructability Review

    70

  • 8/13/2019 Design Development score

    3/22

    Design Development

    Task Task Notes

    Identify long lead time items to develop pre-purchase

    strategy, if necessary.

    Include detailed construction schedule in Master Project

    Schedule (refer to Schematic Design checklist for project

    schedule tasks).

    Confirm approval steps.

    Project Schedule

    Task Task Notes

    Confirm sustainability goals and objectives. See: www.

    uservices.umn.edu/sustainableu/future.html.

    Review status of projects energy consumption analysis,

    code compliance, and efficiency goals. See MN state B3

    guidelines at http://www.csbr.umn.edu/B3/.

    Review energy asset program with utility company.

    Develop solutions and treatments for sustainability

    components.

    Sustainability Components

    Project Delivery Model 71

  • 8/13/2019 Design Development score

    4/22

    Design Development Phase Checklist

    72

    Task Task Notes

    Review setback requirements and impact on fire resistive

    requirements.

    Review storm water management plans:

    Construction

    Permanent

    Review utility capacity connection points and invert

    elevations.

    Review site lighting, location, schematic circuitry.

    Review tree and other site elements protection plan.

    Review landscape, hardscape, and grading plan.

    Confirm historical preservation requirements See: www.

    cppm.umn.edu/docs/preservationplan.pdf.

    Review traffic control during construction.

    Further develop parking plan.

    Confirm loading dock location and access.

    Review vehicular, bike, and pedestrian access.

    Confirm fire apparatus and emergency vehicles access and

    staging.

    In collaboration with the Contractor and client, confirm the

    need for a security plan at the construction site. For ex:

    Fencing

    Webcam

    Security officers

    Security cards

    Confirm issues of public art implications (both interior and

    exterior).

    Confirm recycling/refuse collection.

    Confirm contractor staging.

    Confirm emergency generator location (if applicable).

    Confirm area of safe refuge (exterior).

    Confirm geotechnical and/or environmental soil boring

    data.

    Site Design (Construction and Permanent)

  • 8/13/2019 Design Development score

    5/22

    Design Development

    Task Task Notes

    Review and update design intent, as necessary (inclusive

    of documents by design disciplines).

    Coordinate all building systems.

    Structural systemsconsider the impact of the followingto surrounding spaces:

    Noise

    Vibration

    Review exterior wind analysis for public safety.

    Review building components with permanent storm water

    plans.

    Review demolition plans. See guidelines in Schematic

    Design phase.

    Review and confirm applicable UM Construction and

    Exterior Standards.

    Confirm written design intent narrative (inclusive of allassumptions and variations) provided in Schematic Design

    phase for:

    Architecture

    Structural

    Mechanical

    Electrical

    Telecom

    Landscape

    Other

    Expand outline specification to integrate systems, products

    and procedures for architecture, civil, and landscape.

    Confirm utility loads and capacity at the projected site.

    Confirm code compliance/update summary.

    Confirm project keying security plan expectations.

    Confirm structural loading requirements.

    Building DesignA. General

    Project Delivery Model 73

  • 8/13/2019 Design Development score

    6/22

    Design Development Phase Checklist

    74

    Task Task Notes

    Develop historical preservation requirements into a treat-

    ment. See Secretary of the Interior Federal guidelines.

    Review exterior skin materials and colors.

    Confirm roof systems, gutters, and downspouts.

    Confirm screening and sightlines.

    Review Life Safety Plans for:

    Egress and exiting

    ADA access

    Areas of rescue

    Fire and emergency vehicle apparatus access and staging

    Fire wall ratings and types

    Confirm location and size of mechanical, electrical rooms

    (stack), telecom rooms (stack), custodial closets, and

    toilets.

    Review floor plans (adjacencies).

    Review building circulation system, entrances, horizontal,

    and vertical.

    Reconfirm square footage.

    Confirm compliance with University numbering system for

    room names.

    Confirm doors, windows, and all fenestration/openings.

    Confirm overall dimensions and floor to floor heights.

    Confirm Non-Ionizing Radiation Shielding (magnetic, RF,

    laser, etc.) of MRI, NMR, Class 3b and 4 lasers, microwave

    transmitters, and UV sources.

    Confirm Ionizing Radiation Shielding of X-ray/Accelerator

    rooms (walls, doors, control barriers, etc).

    Determine mockups, renderings, and presentation

    requirements.

    Establish classroom standards (including lighting and

    acoustics).

    Verify material testing requirements.

    Building DesignB. Architectural

  • 8/13/2019 Design Development score

    7/22

    Design Development

    Project Delivery Model 75

    Task Task Notes

    Confirm hazardous materials assessment for removal.

    Confirm Hazardous Materials Inventory (chemical, radiation,

    and biological) and define hazardous chemical control zones.

    Building DesignC. Hazardous Materials

    Task Task Notes

    Verify maintenance access to mechanical and electrical

    systems.

    Review mechanical equipment.

    Review exhaust stacks/air intake.

    Determine that the type, size, and weight of equipment fit

    into space; review floor and ceiling loading.

    Determine structural loading for MEP/FP equipment,

    piping, etc.

    Provide system calculations for MEP/FP.

    Refine MEP/FP systems design.

    Confirm code requirements.

    Coordinate all utilities and systems (system integration).

    Refine drawings for security, telecom/data, and audio/visual.

    Refine routing and racking strategy for process piping.

    Develop equipment schedules.

    Review equipment numbering for determination that it is in

    accordance with University standards.

    Refine ceiling/wall space strategy for MEP/FP.

    Locate each MEP fixture/device.

    Building DesignD. MEP/FP Systems Design

  • 8/13/2019 Design Development score

    8/22

    Design Development Phase Checklist

    76

    Task Task Notes

    Site Utilities:

    Steam

    Sanitary sewer

    Storm water

    Site electrical

    High voltage

    Domestic water

    Fire water

    Irrigation

    Telecom

    Natural gas

    Chilled water

    Building Systems:

    HVAC systems

    Plumbing systems

    Medical gases

    Laboratory services

    Site lightingElectrical power

    Electrical lighting

    Fire sprinklers

    Fire alarm

    Telecommunications

    Natural gas

    FFE

    Audio/Visual

    Security/Access

    Call out in specifications for coordination above ceiling

    Grounding and lighting protection

    Architectural Elements:

    Site grading

    Building foundations

    Structural system

    Building envelope (walls, fenestration, roof)

    Landscape design with building and utility systems.

    Building DesignE. Verify Coordination of Drawings and Specifications

  • 8/13/2019 Design Development score

    9/22

    Design Development

    Task Task Notes

    Reconfirm University participants for commissioning.

    Continue commissioning plan review.

    Continue process document review.

    Review project specific training plans developed in

    Schematic Design and revise, if necessary.

    Commissioning Strategy Plan

    Task Task Notes

    Review and reconfirm total budget originally developed

    in Programming phase, and revised and reviewed during

    Schematic Design.

    Reconcile budget variances.

    Review lump sum or not-to-exceed budget amount.

    Review proposed VE items, if over budget.

    Review final strategy and reconcile variances.

    Finalize contractors GMP. Confirm costs for:

    Construction costs (labor and materials)

    Allowances

    Construction contingency

    Bond cost

    Insurance cost

    Contractor fee

    Labor burden

    General conditions

    Review/execute internal service level agreements.

    Confirm financing agreement.

    Budget Review

    Project Delivery Model 77

  • 8/13/2019 Design Development score

    10/22

    Design Development Phase Checklist

    Task Task Notes

    Continue review of Construction Impact checklist.

    Review process for construction site notifications.

    Reconfirm outreach requirements.

    Community Outreach Plan

    Task

    Confirm the project process: schedule, payment,

    specifications, contracts, etc.

    Revisit issues of public art implications (both interior and

    exterior).

    Confirm artistic programmatic criteria.

    Confirm public art budget.

    Public Art

    Task

    City and county governments

    Code Office and DEHS

    Elevators

    High-pressure steam

    MN Department of Health

    MPCA:

    Air

    Environmental

    Sewer/water

    MetCouncilstorm water

    NIH

    Other civic groups

    Park Board

    SHPO review

    Utility providers: power, sewer, water and gas

    Jurisdictional Review: (review goals established in Schematic Design for each entity)

    78

  • 8/13/2019 Design Development score

    11/22

    Design Development

    Task Task Notes

    Confirm and continue communication steps developed in

    Predesign.

    Communications Plan

    Task Task Notes

    Review Construction Documents Guidelines.

    Maintain project in CPPM project management information

    system.

    Provide monthly project report to CPPM project

    management.

    Procedures and Administration

    Project Delivery Model 79

  • 8/13/2019 Design Development score

    12/22

    Design Development Phase Checklist

    Task Task Notes

    Design Development documents:

    Project Manual:

    *Products

    *Installation

    *Process

    *Drawings, sketches, and other graphic presentationmaterials

    *E-files

    Completed review comments

    Exceptions to Standards

    Monthly project summary for CPPM Management and

    Project Executive Committee

    MN B3 documentation

    Project Delivery Readiness Index (as needed)

    Benchmark Report:

    Program elements by GSF

    BudgetSchedule

    Funding

    Quality

    CMGMP (as needed on a project-by-project basis)

    Total project budget as revised in this phase

    Progress meeting minutes

    Project report for COG and Project Executive Committee

    ratification

    Board of Regents Project Update Form (prior to award of

    GMP in excess of $5 Million)

    Deliverables

    80

  • 8/13/2019 Design Development score

    13/22

    Design Development

    Task Task Notes

    Project Team: (review only)

    Client contact

    Facilities Management

    DEHS

    Building Code Division

    Office of Classroom ManagementCPPM Project Manager

    CPPM Management: (review and approval)

    Ratification by COG and Project Executive Committee

    Review and Approval of Deliverables

    Project Delivery Model 81

  • 8/13/2019 Design Development score

    14/22

    Construction Documents Guidelines

    General Information

    Applicable References (current editions)1. University of Minnesota Campus Master Plan

    2. University of Minnesota Standards and Procedures for Construction1

    3. University of Minnesota Exterior Design Standards1

    4. University of Minnesota Historic Preservation Plan1

    5. University of Minnesota CAD Data Standards

    6. University of Minnesota Building Code Division Policies and Procedures Manual with Appendix

    7. American Institute of Architects (AIA) CAD Layer Guidelines

    8. Construction Specifications Institute (CSI) Uniform Drawing System and Master Format

    Required For All Sheets1. University Project Name and University Number

    2. Project Team including contact information (also insert team member titles)

    3. Drawing issue date

    4. Signature certification block

    5. Key Plan

    6. North arrow for plans

    7. Scale, Notes, Symbols, and call-out identification systems

    8. CAD Layer Matrix for large or complicated projects

    9. Plotting information

    Civil Engineering

    Civil Survey1. Civil survey with confirmed benchmarks, right-of-ways, easements, property lines, required setbacks, bearing and

    distance labels, and construction controls

    Environmental Site Plan1. Coordinated environmental containment and mitigation plan

    Grading Plan1. Proposed contour lines and building footprints

    Roads and Topography Plan1. Proposed pedestrian and vehicular circulation and parking lot plans

    Utility Plan1. Coordinated fire protection and utilities plan

    821See www.cppm.umn.edu

  • 8/13/2019 Design Development score

    15/22

    Design Development

    Landscape Architecture

    Landscape Site and Planting Plan1. Coordinated landscape site plan as applicable

    Plant and Landscape Materials1. Existing trees to remain

    2. New trees

    3. Trees to be removed4. Other plant materials

    5. Rock, bark, mulch

    6. Lawn areas

    Irrigation System1. Sprinklers

    2. Piping

    3. Equipment

    4. Coverage

    5. Controls

    Site Improvements1. Walks and Steps

    2. Fencing

    3. Walls

    4. Decks and Plazas

    5. Site furnishings

    6. Other structures

    7. Scaled layouts, elevations, sections, details, and coordination plans for individual landscape items as applicable

    Structural Engineering

    Foundation Plan1. Piles and drilled piers

    2. Foundation layout and reinforcing

    3. Slab layout, reinforcing, and control joints

    Framing Plan1. Grid pattern, dimensions, and key tags

    2. Framing Plan (columns, beams, and joists)

    3. Structural bearing and shear walls

    4. Scaled layouts, elevations, sections, details, and coordination plans for structural systems as applicable

    Project Delivery Model 83

  • 8/13/2019 Design Development score

    16/22

    Construction Documents Guidelines

    Architectural

    Title Page1. Project building name, University number, and official street address

    2. Sheet Index

    3. University Project Number (all sheets)

    4. Project Team (all sheets)

    5. Drawing issue date (all sheets)

    6. Signature certification block (all sheets)

    7. Location Plan

    8. Key Plan (all sheets)

    9. Scale, Notes, Symbols, and call-out identification systems (all sheets)

    10. Materials, hatching, and other pattern identification symbols key

    11. CPPM project Web address: http://www.cppm.umn.edu/active-projects.html

    12. Comprehensive Code Data Block:

    a. List all applicable current codes

    b. Occupant groups and loads

    c. Plumbing fixture analysis (actual and minimums)

    d. WAC/SAC analysis

    e. Required separation of occupanciesf. Floor area and height/number of stories

    g. Allowable square footage and actual square footage

    h. Types of construction

    i. Fire-resistive rated construction

    j. Design loads

    k. Frost depth

    l. Interior wall and ceiling finish (sprinklered/unsprinklered)

    Coordinated Architectural Site Plan1. Confirmed property lines and required setbacks

    2. Comprehensive utility plans

    3. Emergency apparatus access and staging plan4. Life Safety Plan with egress routes and ADA accessibility

    5. Construction access, loading, and circulation

    6. Construction staging and storage areas

    7. Crane and other equipment locations

    8. Temporary fencing

    9. Storm water and silt controls

    84

  • 8/13/2019 Design Development score

    17/22

    Design Development

    10. Construction parking types and locations (obtain Parking and Transportation approval)

    11. Landscaping coordination plan

    12. Permanent access, loading, and circulation

    13. Site lighting coordination plan

    14. Permanent fencing coordinated with Landscape Plans

    15. Retaining walls coordinated with Landscape Plans

    16. Permanent parking stall types and locations (obtain Parking and Transportation approval)

    17. Enlarged site details and sections

    18. Site signage

    Building Plans1. Demolition plans and details (where required)

    2. Selective demolition plans and details (where required)

    3. Testing/investigative location plans (where required)

    4. Structural plan with column spacing and shear wall locations

    5. Scaled floor and roof plans with appropriate dimensions and University room numbers

    6. Utility main and entrance locations

    7. Mechanical, Electrical, and Telecom Room layouts and coordination plan

    8. Recycling Room(s)

    9. Janitor Room(s)

    10. Door locations with swings

    11. Vertical circulation locations and sizes

    12. Reflected ceiling plans

    13. Show fire separation rated walls on reflected ceiling plans

    14. Room materials, casework, and equipment layouts

    15. Furniture Plan

    16. Lab Equipment Plan

    17. Kitchen and Specialty Equipment Plan

    18. Classroom requirements and specifications

    Elevations1. Exterior elevations indicating:

    a. location of fixed and operable windows

    b. curtain walls and specialty partitions

    c. doors and access panels

    d. overall dimensions and floor-to-floor heights

    e. air intakes and exhausts

    f. fire apparatus connections and hose bibs

    g. utility connections and meters

    Project Delivery Model 85

  • 8/13/2019 Design Development score

    18/22

    Construction Documents Guidelines

    2. Exterior cladding systems, finish materials, and colors

    3. Exterior architectural lighting and locations

    4. Roof profile and finish material(s)

    a. roof top equipment and screening

    b. roof access and safety barriers

    c. rainwater distribution systems

    5. Interior elevations of restrooms, major/complicated spaces (e.g. auditoriums, classrooms)

    Sections1. Building sections showing floor-to-floor heights and space relationships (including instructional space elevations)

    2. Exterior wall sections

    3. Stair, elevator, and shaft sections

    4. Sections of major complicated spaces

    5. Tunnels

    Scaled Details and Schedules1. Exterior wall details

    2. Roof details

    3. Floor and floor finish details

    4. Wall types

    5. Casework details6. Ceiling details

    7. Interior details

    8. Significant structural details

    9. Door and door frame types

    10. Window types

    11. Door and window details

    12. Door and window schedule

    13. Room finish schedule

    14. Restroom and plumbing fixture details

    15. ADA-required details

    16. Specialty walls

    17. Specialty equipment

    86

  • 8/13/2019 Design Development score

    19/22

    Design Development

    Mechanical

    Mechanical Site Plan1. Coordinated mechanical site plan where applicable

    Controls and Instrumentation Plan1. Control/Energy Management system equipment layout plan

    2. Thermostats and low-voltage wiring

    HVAC Plan1. HVAC Equipment Plan

    2. HVAC Ductwork Plan

    3. HVAC Piping Plan

    Dust and Fume Collection Systems1. Dust and Fume Collection Equipment Plan

    2. Dust and Fume Ductwork Plan

    Steam Systems1. Steam systems equipment

    2. Steam systems condensate piping

    3. Steam systems low-pressure piping4. Steam systems high-pressure piping

    Refrigeration Systems1. Refrigeration equipment

    2. Refrigeration piping

    Electric Heat and Other Specialty Equipment1. System description, layout, and coordination plans for specialty systems

    Elevations, Sections, Details1. Scaled layouts, elevations, sections, details, and coordination plans for individual mechanical systems as applicable

    Project Delivery Model 87

  • 8/13/2019 Design Development score

    20/22

    Construction Documents Guidelines

    Plumbing

    Site Plan1. Coordinated plumbing site plan where applicable

    Plumbing Plan1. Acid, alkaline, and oil waste systems

    2. Domestic hot and cold water systems

    3. Sanitary drainage4. Storm drainage system

    5. Miscellaneous plumbing equipment

    6. Plumbing fixtures

    7. Scaled layouts, elevations, sections, details, and coordination plans for individual plumbing systems as applicable

    8. Medical gases and tanks

    9. Laboratory services

    Electrical

    Electrical Site Plan1. Coordinated electrical site plan where applicable

    Communication Plan1. Auxiliary systems (e.g. bell, call, clock, paging, intercom, security, etc.)

    2. Sound systems, AV equipment, TV, and other classroom equipment schedules and plans

    Grounding Plan1. Lightning protection systems

    Lighting Plan1. Special, emergency, and exit lighting plans

    2. Ceiling, wall, and floor-mounted lighting plans

    3. Luminaire identification and schedules

    4. Lighting, switching, and circuiting plans

    Power Plan1. Site power plan

    2. Power panels and grounding system

    3. Power equipment

    4. Power switchboards

    5. Power circuits, floor raceways, under-carpet, and other power distribution

    6. Cable trays, feeders, and bussways

    7. Wall, ceiling, special receptacle, and device plans

    8. Emergency power systems

    88

  • 8/13/2019 Design Development score

    21/22

    Design Development

    Telecommunications

    Site Plan1. Coordinated telecommunications site plan where applicable

    Data Plan1. Data equipment, distribution, and outlet plan

    Telephone Plan1. Telephone equipment, distribution, and outlet plan

    Fire Protection

    Sprinkler Plan1. CO2 system

    2. Halon system

    3. Standpipe system

    4. Sprinkler head and piping system

    5. Fire system equipment (hoses and extinguishers)

    6. Fire alarm system (including detectors and sensors)

    7. Scaled layouts, elevations, sections, details, and coordination plans for individual fire protection systems as applicable

    Project Manual

    Project Manual1. University Project Name and Number (all pages)

    2. Project Team (all pages)

    3. Contract Document issue date (all pages)

    4. Signature certification block by professional discipline

    5. CPPM Consultant Instructions for Front End Documents (see http://www.cppm.umn.edu/aedocs/Instructions.doc)

    6. General Requirements with Bidding Documents

    7. Owner provided information available to bidders/proposers where applicable

    8. Design Intent Statements for all disciplines (C/S/A/M/E/P/FP etc.)9. Specifications by current CSI divisions and format

    10. Appropriate language for project labor agreement (if necessary)

    Project Delivery Model 89