ICCSD Liberty High School Design Development Phase Meeting Board of Education Presentation: November 11, 2014 AGENDA: Design Development Committee Input Process MidAmerican Energy/Weidt Group CNC Program Review Updated Site Master Plan Design Development Floor Plans 3-D Visualization and Animation Update on Project Schedule
12
Embed
Design Development Phase Meeting Board of Education ...€¦ · Board of Education Presentation: November 11, 2014 AGENDA: Design Development Committee Input Process MidAmerican Energy/Weidt
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ICCSD Liberty High School
Design Development Phase Meeting
Board of Education Presentation: November 11, 2014
AGENDA:
� Design Development Committee Input Process
� MidAmerican Energy/Weidt Group CNC Program
� Review Updated Site Master Plan
� Design Development Floor Plans
� 3-D Visualization and Animation
� Update on Project Schedule
Design Development & Committee Input Process Design Development & Committee Input Process Design Development & Committee Input Process Design Development & Committee Input Process
� 09-09-2014 Introductory Meeting, MidAmerican Energy CNC/Weidt Group
� 09-23-2014 Departmental Design Input Meetings
• Athletics, Family Consumer Science, and Kitchen • Athletics, Family Consumer Science, and Kitchen
� 10-01-2014 Departmental Design Input Meetings
• Administration Office, Special Education, Art, PLTW, Library, Business
• Science Departments, General Education, Drama, Music Departments
� 10-07-2014 Design Team Consultant Coordination Meeting
� 10-21-2014 Design Development Progress Meetings
•MidAmerican Energy/Weidt Group Bundle Results Meeting
• Nurse Area & General Building Review
� 10-28-2014 Design Development Updates Review
• Phase-II Athletic Complex & Indoor Athletics, Band, Performing Arts
• Art, PLTW, Library, General Ed., FCS, Science, Business, Administration• Art, PLTW, Library, General Ed., FCS, Science, Business, Administration
� 11-04-2014 Design Development Input Meetings
• Kitchen, Commons & Food Service Equipment
• Auditorium, Music Departments, Acoustics & Audio Visual Equipment
• City of North Liberty Planning & Zoning Meeting
MidAmerican Energy & The Weidt GroupMidAmerican Energy & The Weidt GroupMidAmerican Energy & The Weidt GroupMidAmerican Energy & The Weidt Group
Commercial New Construction ProgramCommercial New Construction ProgramCommercial New Construction ProgramCommercial New Construction ProgramFinal Report Summary Final Report Summary Final Report Summary Final Report Summary –––– November 3, 2014November 3, 2014November 3, 2014November 3, 2014
Top Integrated Utility Savings Strategies Top Integrated Utility Savings Strategies Top Integrated Utility Savings Strategies Top Integrated Utility Savings Strategies –––– Included in Bundle #2Included in Bundle #2Included in Bundle #2Included in Bundle #2
1. Ground coupled geothermal HR Chillers and zonal heat pumps
2. Variable frequency drives decreasing motor speed during times
of reduced load
3. Low wattage lighting design that increases lighting system
efficiency
4. Max Envelope with increased insulation and window
characteristics
5. Dimming daylighting with automatic dimming controls that
responds to daylighting levels
6. Demand ventilation with CO2 sensors that adjust the demand for
outside air flow based on occupant demand
7. Total Heat Recovery that recaptures heat from building exhaust
8. Occupancy/Vacancy sensor control of lighting
3D Visualization – Aerial View of Building Massing
3D Visualization –View of South Elevation
3D Visualization –View of Main Entrance
3D Visualization – Interior View of Main Entrance Commons
3D Visualization –Interior View of Commons
3D Visualization –Aerial View Phase II Outdoor Athletic Complex
ICCSD Liberty High School – Design Development Phase Presentation