Build 165 — April/May 2018 — 31 Steps 1–2 – Roof/wall junction construction sequence. Figure 2 wall framing (insulation omitted for clarity) upper wall underlay lapped over upturned roof underlay Step 2 – self- adhesive flexible flashing membrane fitted around junction and folded across the roof underlay turn-down lower wall underlay Step 1b – roof underlay turned down over lower wall underlay wall framing (insulation omitted for clarity) purlin roofing Step 1a – roof underlay turned up under upper wall underlay Roof-to-wall junction detail The BRANZ helpline has been asked recently about how best to detail the tricky junction between the top edge of a monopitch roof and an adjacent wall above. Here is one suggestion. DESIGN RIGHT BY ALIDE ELKINK, FREELANCE TECHNICAL WRITER, WELLINGTON DESIGN DETAIL FOR JUNCTION BETWEEN A MONOPITCH ROOF AND AN ADJACENT WALL ABOVE WE CONTINUE the Build series on roof-to-wall junction details not included in Acceptable Solution E2/AS1 to the New Zealand Building Code clause E2 External moisture. This detail occurs at the junction between the top edge of a monopitch roof and an adjacent wall above (see Figure 1). Steps for installation Figures 2–5 illustrate the steps of the construc- tion sequence for the detail with a sheet cladding material over a drained and vented cavity. Step 1: Install roof and wall underlay over framing. Turn the roof underlay up under adjacent wall underlay (1a) and overlap the lower wall underlay (1b). Step 2: Fit a self-adhesive, flexible flashing membrane over the junction. Cut and fold a section of the membrane across the roof underlay turn-down. Step 3: Install apron flashing over the roofing with upstand over upper wall underlay. Apron flashing to have at least the minimum upstand height and roof cover required by E2/AS1. Step 4: Lap an additional layer of wall underlay or fix self-adhesive, flexible flashing tape over the apron flashing upstand. Step 5: Install cavity battens to lower wall. Step 6: Install internal corner wall flashing over cavity battens on the lower wall. The corner flashing must end behind the barge flashing. Step 7: Install lower wall cladding over cavity battens and then install fascia board. Junction detail location. Figure 1 2-storey fall single storey junction at top edge of monopitch roof and adjacent wall above
4
Embed
DESIGN DETAIL FOR JUNCTION BETWEEN A MONOPITCH ROOF … · 2018-06-06 · 32 — April/May 2018 — Build 165 Figure 3 Steps 3–4 – Roof/wall junction construction sequence. Figure
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Build 165 — April/May 2018 — 31
Steps 1–2 – Roof/wall junction construction sequence.Figure 2
wall framing (insulation omitted for clarity)
upper wall underlay lapped over upturned roof underlay
Step 2 – self-adhesive flexible flashing membrane fitted around junction and folded across the roof underlay turn-down
lower wall underlay
Step 1b – roof underlay turned down over lower wall underlay
wall framing (insulation omitted for clarity)
purlin
roofing
Step 1a – roof underlay turned up under upper wall underlay
Roof-to-wall junction detailThe BRANZ helpline has been asked recently about how best to detail the tricky junction between the top edge of a monopitch roof and an adjacent wall above. Here is one suggestion.
DESIGNRIGHT
BY ALIDE ELKINK, FREELANCE TECHNICAL WRITER, WELLINGTON
DESIGN DETAIL FOR JUNCTION BETWEEN A MONOPITCH ROOF AND AN ADJACENT WALL ABOVE
WE CONTINUE the Build series on roof-to-wall
junction details not included in Acceptable
Solution E2/AS1 to the New Zealand Building
Code clause E2 External moisture.
This detail occurs at the junction between
the top edge of a monopitch roof and an
adjacent wall above (see Figure 1).
Steps for installationFigures 2–5 illustrate the steps of the construc-
tion sequence for the detail with a sheet cladding
material over a drained and vented cavity.
Step 1: Install roof and wall underlay over
framing. Turn the roof underlay up under adjacent
wall underlay (1a) and overlap the lower wall
underlay (1b).
Step 2: Fit a self-adhesive, flexible flashing
membrane over the junction. Cut and fold a section of
the membrane across the roof underlay turn-down.
Step 3: Install apron flashing over the roofing
with upstand over upper wall underlay. Apron
flashing to have at least the minimum upstand
height and roof cover required by E2/AS1.
Step 4: Lap an additional layer of wall
underlay or fix self-adhesive, flexible flashing
tape over the apron flashing upstand.
Step 5: Install cavity battens to lower wall.
Step 6: Install internal corner wall flashing
over cavity battens on the lower wall. The corner
flashing must end behind the barge flashing.
Step 7: Install lower wall cladding over cavity
battens and then install fascia board.
Junction detail location.Figure 1
2-storey
fall single storey
junction at top edge of monopitch roof and adjacent wall above
The Strand range from Laminex New Zealand® includes solutions for structural flooring, roof sarking, building, furniture and joinery applications. Strandfloor, StrandfloorH3.1, Strandboard and Strandsarking are all Declare Red List Free products. The whole range is manufactured in our own backyard from the strands of New Zealand Radiata Pine.
Build the complete Red List Free picture.
OVER AROUND
UNDER
Strandsarking®
High density panels speci�cally formulated for use as a roof sarking substrate. BRANZ appraised.
Strandboard®
Versatile panel for use in a wide range of interior
applications.
Strand�oor®
Structural �ooring panels including an H3.1 option and a 50 year warranty. BRANZ appraised.
Another trade essential from Laminex New Zealand®
J005
753
For more information visit www.laminexnewzealand.co.nz or call 0800 303 606
Note: All flashing dimensions (turn-ups and laps) to meet requirements of Acceptable Solution E2/AS1.
Step 10 – install cavity closer
upper wall underlay
Step 9 – install barge flashing over roofing and fold down over fascia board
fascia board
Step 7 – install lower wall cladding over cavity and then install fascia board
Step 11 – install cavity battens to upper wall
150 mm
150 mm
75 mm
75 mm
75 mm
fabricated corner flashing fitted over apron flashing before barge flashing installed
Build 165 — April/May 2018 — 33
Step 8: Install fabricated corner flashing over
apron flashing and fascia.
Step 9: Install the barge flashing over the
roofing and fascia board.
Step 10: Install cavity closer above apron
flashing maintaining the minimum gap required
by E2/AS1 (generally 35 mm).
Step 11: Install cavity battens to upper wall.
Step 12: Install cladding over the cavity
battens cutting the cladding to fit around the
apron flashing as required.
Some specifics from E2/AS1Specific requirements in Acceptable Solution
E2/AS1 include that there must be:
● a 75 mm minimum wall cladding cover over
the upstand
● a gap between the wall cladding and the
roofing as given in E2/AS1 Table 7
● roof flashing cover over the roofing as per
E2/AS1 Table 7, depending on wind zone and
roof pitch. Step 12 – Roof/wall junction construction sequence.Figure 5
wall cladding
Step 12 – wall cladding cut around apron flashing as required
seal flashing to fascia and cladding
8 — June/July 2018 — Build 166
For smart technology, trade quality and cost-effective materials, check out what’s in the Bunnings Solutions Studio. You’ll find cutting edge products for your next build that not only look incredible but perform at the highest levels.You will also find a great team with hands-on industry experience, so you can be sure that you’ll get the advice you need for the project you’re planning.
To find out more about these products or to arrange an appointment to view the solutions studio call the Bunnings SupportCentre on (09) 978-2200 and ask to speak to the Trade Team, or talk with your local Bunnings Account Manager.
HydrapanelIntended primarily for use in wet areas such as bathrooms and kitchens, Hydrapanel’s unique composition also creates a high performing alternative wall lining for other areas like laundries and garages. It’s easy to clean, resistant to water, steam and abrasion.
Beyond TilesBeyond Tiles are another great alternative to wall tiling. They are waterproofed wall panels that are installed directly onto framing. With no need for stoppers, water proofers or tilers, installation is faster than tiling. They also come in 6 different collections.
KaboodleNo matter what kind of kitchen you’re looking to create, small or large, Kaboodle offers a great range to fit your space. They also have the ability to provide alternative joinery solutions too.
BUNNINGS SOLUTIONS STUDIOHAS THE LATEST TRADE INNOVATIONS
I am writing to point out a technical defect in the article Roof-to-wall junction detail (Build 165, pages 31–33). As drawn, the details do not close off the cavity to water entry blown by wind up the slope of the roof on the apron flashing.
The fabricated corner flashing needs a stop-end, with the stop-end 35 mm minimum high up to the bottom of the cladding, then cut back to also close off the cavity up to the top of the flashings. The cladding cavity closer would then butt into the stop-end, or the stop-end could be 50 mm high and the cavity closer could pass over the top of it. The cladding
beyond the roof would then be sealed to the stop-end and the corner flashing at the vertical joint between the two.
The junctions are very complicated, and it is important to get them right! LEIGH MARSHALL : AUCKLAND
BRANZ comment Thank you for your feedback. Adding a stop-end as you suggest is a good idea to add another layer of protection.
It is important that adding a stop-end does not introduce additional weak points, such as needing to notch in a cladding or other mate-rial to accommodate it. Our revised fabricated saddle flashing incorporates a simple stop-end to stop water passing over the top of the detail while not impacting on the cladding above.