Top Banner
Design, Construction, Installation and first Commissioning Results of the LHC Cryogenic System Serge Claudet (CERN, Geneva) On behalf of the “Cryogenics for Accelerator” group and the hundreds of people involved
34

Design, Construction, Installation and first Commissioning ...

Nov 20, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Design, Construction, Installation and first Commissioning ...

Design, Construction, Installation and first

Commissioning Resultsof the

LHC Cryogenic SystemSerge Claudet (CERN, Geneva)

On behalf of the “Cryogenics for Accelerator” groupand the hundreds of people involved

Page 2: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Thanks to contributors

• A. Ballarino• Ch. Balle• J. Casas• J-P. Delahaye• G. Ferlin• Ph. Gayet• Ph. Lebrun• F. Millet

• C. Parente• G. Riddone• L. Serio• L. Tavian• R. Van Weelderen• B. Vullierme• U. Wagner

Page 3: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Content

• Introduction• Design challenges and R&D outcome• Procurement, Construction & Installation• First commissioning experience• Main problems encountered• Considerations for new projects• Conclusion

90ies

‘02 - ‘06‘98 - ‘06

Page 4: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

LHC accelerator

24 km of superconducting magnets @1.8 K, 8.33 T

p-p collision 1034 cm-2.s-1, 14 TeV, 0.5 GJ stored energy

Early requirements for

the LHCcryogenic system

Page 5: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Layout of cryogenics

Pt 3

Pt 4

Pt 5

Pt 6

Pt 7

Pt 8

Pt 1

Pt 2

Pt 1.8

Cryoplant DistributionPresent Version

Cryogenic plant

8 x 18kW @ 4.5 K

1’800 sc magnets

24 km & 20 kW @ 1.8 K

36’000 t @ 1.9K

100 t He inventory

Page 6: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Cryogenic architecture

Warm CompressorStation

Upper Cold Box

Interconnection Box

Cold Box

Warm CompressorStation

Lower Cold Box

Distribution Line Distribution Line

Magnet Cryostats Magnet Cryostats

Cold Compressorbox

Warm CompressorStation

Cold Compressorbox

Warm CompressorStation

Shaft

Surfa

ceC

aver

nTu

nnel

LHC Sector (3.3 km) LHC Sector (3.3 km)

1.8 K Refrigeration Unit New 4.5 K Refrigerator Ex-LEP 4.5 K refrigerator 1.8 K Refrigeration Unit

Typical LHC even point

Page 7: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

0

20

40

60

80

100

120

140

160

180

1960 1980 2000

Year

OMEGA,BEBC,

ISR Low-Beta

ALEPH,DELPHI,

LEP Low-Beta

LEP2

LHC, ATLAS, CMS

LEP2+

LHC

: 14

4 kW

LHCCooling capacity

How does it compare ?

Tevatron, RHIC,Jlab, SNS, HERA,

Tristan, …

ITER

0

50

100

150

200

250

300

Tevatr

on

HERA

CEBAF

RHIC

LEP2

LHC

(SSC)

[tonn

es]

VirtualLiquidGas @ 2 MPa

Helium Inventory

Unprecedented !

1

10

100

1000

10000

1 10

T [K]

P [k

Pa]

SOLID

HeII HeI

CRITICAL POINT

GAS

λ line

Saturated He II

Pressurized He II

1

10

100

1000

10000

1 10

T [K]

P [k

Pa]

SOLID

HeII HeI

CRITICAL POINT

GAS

λ line

Saturated He II

Pressurized He II

Superfluid Helium 1.8 K

Page 8: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Design

• Site constraints and general concerns

• Early heat load inventory and follow-up, periodic update of cryogenic architecture

• Components and system R&D:– Early industry involvement– Dedicated tests facilities

Page 9: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Magnet cooling scheme

1

10

100

1000

10000

1 10

T [K]

P [k

Pa]

SOLID

HeII HeI

CRITICAL POINT

GAS

λ line

Saturated He II

Pressurized He II

1

10

100

1000

10000

1 10

T [K]

P [k

Pa]

SOLID

HeII HeI

CRITICAL POINT

GAS

λ line

Saturated He II

Pressurized He II

Thermo-hydraulics of two-phase flow

in He II

(and limitations!)

(≈ 1W/m)

Page 10: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

1.8 K issues

CC:- 3D wheels- Bearings (300K)HX:- Very Low Pressure

CC

CC

CC

LHe

Sub-atmosphericcompressor

4.5

K re

frige

rato

r

Heat load

HP

MP

LP

1

2

3

“Mixed” Compression P ratio ≈ 80

HX Stainless Steel Plate

Axial-centrifugalImpeller (3D)

Fixed-vanediffuser

3-phase inductionElectrical motor(rotational speed: 200 to 700 Hz)

Activemagneticbearings

300

K un

der

atm

osph

ere

Cold

und

erva

cuum

Inlet

Outlet

Pressure ratio2 to 4

Spiral volute

200 to 800 Hz)

Cold Compressor

Page 11: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Thermometry6’000 units, +/- 10 mK @ 2K in LHC radiation conditions

From ‘sensor’ to ‘thermometer’ with signal processing

Page 12: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Other R&D examples

• HTS current leadsTotal: 3.4 MA

1200 units600-6000-13000 A

BSCCO 2223

• Thermal design:– Low temperature insulation– Heat intercept techniques

20 l/m @ 1.9 K 100 m3 @ 20 K 2000 m3@ 300 K

• Safe cryo-magnets resistive transition:– Cascade: cryostat - cold recovery header - MP tanks– Specific cold safety relief valves

Page 13: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

LHC test string

More than 20’000 hours of operation of the LHC Test Strings

1.7

1.75

1.8

1.85

1.9

1.95

2

10:50 11:00 11:10 11:20 11:30 11:400

2

4

6

8

10

12[kA], W/m[K]

0.2 W/m 0.3 W/m - 0.6 nOhm

T stability duringMagnet powering

0

5

10

15

20

25

30

35

0 20 40 60 80 100 120 140 160 180

time,s

[K],

[bar

], [V

]

0

2

4

6

8

10

12

QV9202SIQV920

Quench MB5 , 37s

Quench MB6 , 72s

pressureT MB5

T MB6

T MB4

T MB1, MB2, MB3

P evolution during quench at 13’000 kA

Page 14: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Procurement• Sub-systems by type of functionality:

– CERN to define interfaces and required performance

• Great majority procured from industry:– Competitive performance based tendering

– Detailed studies, manufacturing, site installation, commissioning, performance assessment

• Separate management of general services:– Interconnecting piping, controls

Page 15: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Construction phase• Industry available products:

(storage tanks, piping, 4.5K refrigerators)– Functional technical specifications adapted (tests)

• Extension of existing products(1.8K units, cryogenic lines, electrical feed boxes)– Complex performance & possible impacts– CERN add. design & support to fabrication

• Totally new products(Rad. tol. cryo thermometry - superconducting links)– CERN with full responsibility for developments and

“built to print” fabrication contracts

Projects

OP

Page 16: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Industrial fabrication sites

European abrication sites for LHC Cryogenics

And from USA, Russia, Japan, …

Main distribution line:Dedicated assembly sites to cope with ’’relative’’ modularity

215 standardpipe elements

30 fixed points & vacuum barriers

17 special service mod. + 1 return mod.

18 standardservice modules

2 double-jumper service module

30 special pipe elements

2 steps 6 elbows 1 test module

Important issues:Qualification, procedures, supply

chain, follow-up, Quality assurance

Page 17: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Electrical feed boxes

Assembly of current leads cartridges

Final assembly and tests

Assembly of DFBM, DFBL, LCM

Assembly of DFBA HCM

Components

Assembly of the busbar bundles

Assembly of the Arc Termination Module (ATM)

Final assembly + tests

CL cartridges assembly area

CL modules assembly stands

Global leak test of DFBMPressure test area for DFBAs

Assembly of DFBA shuffling boxes

DFBA busbar bundles lambda plates

AT-ACR

IHEP / AT-ACR

TS-MME

ICS / AT

Towards an integrated factory !

Mechanics - Electricity - Cryogenics

Page 18: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Installation phases

Helium storage tanks

Compressors

Cold Box close to access shaft

Powering sub-station

Cooling towers

Important issues: logistics, handling, co-activity, quality

Page 19: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Installation & tests

Cryoplants

Interconnection box

MP storage< 20 bar

Purge line

TunnelCavernsSurface

Warm Recovery Line (WRL)

Vent

Lin

e (V

L) To atmosphere

B

E

D

C

F

QRL & Machine

Cold He with HPWarm He with HPWarm He with LPAir

Cold compressor box

PT

Equipment under installation already connected to cryogenic equipment under operation or commissioning …

- Tappings

- Two valves in series

- Padlocks

Page 20: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Commissioning• Commissioning of each sub-system:

– Mechanical pressure test, helium leak test– Input/output signal tests– Operational tests to demonstrate all functions– Performance measurements (ref. capacity, thermal losses)

• Subsequent commissioning in cascade:– Potential problems identified early and clearly– Possible actions before it becomes critical

• Global LHC Hardware Commissioning:– A Crucial test for many systems, incl. cryogenics– Project wide coordination efforts, incl cryogenics

Projects

OP

Page 21: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Magnet cold tests

Page 22: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Cryogenic sub-systems

Point 8Storage

Sector 7-8 Sector 8-1

Surf

ace

Cav

ern

QSCA QSCB

QSRB

QURC

QUIC

QURA

Shaf

t

QSCC QSCC

Tunnel

QURC

QSRA

Page 23: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

18 kW @ 4.5 K Refrigerators33 kW @ 50 K to 75 K - 23 kW @ 4.6 K to 20 K - 41 g/s liquefaction

Pinput : 4.2 MW

Carnot Limit

COP

250 W/W

Page 24: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

2400 W @ 1.8K units

1.8K refrigeration units1st Pump-down in final LHC configuration

0.000.05

0.100.15

0.200.250.30

0.350.40

0.450.50

7:12 8:24 9:36 10:48 12:00

Time

0

500

1000

1500

2000

2500

Coo

ling

Pow

er [

W]

Suction Pressure

Set point

1.8K Cooling Power

P8 - 7 April 2005

Installed mode 2400 W @ 1.8 K

Pump-down 15 mbar

0

10

20

30

40

50

60

70

80

1985 1993 2000Year of construction

Isen

tropi

c ef

ficie

ncy

[%]

Tore SupraCEBAF

LHC

Diam: 250mm

Page 25: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Main cryogenic line

634 +/- 50 (~0.2 W/m)

593

B+C+D (4-20 K)

9000 +/- 400 (~ 2.8 W/m)

Measured

9850Calculated

E+F (50-75 K)

Heat inleaks [W]

Page 26: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Cryogenics P&F diagram

A large and complex fluid distribution system

More than 100 PIDcontrol loops

Towards modern predictive controls …

Page 27: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Progress overview

Staggered progress by ‘‘LHC Point’’ then by sub-system

Page 28: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Main problems !• Very specific “troubles” not even mentioned

• Design & sub-system concerns– Cryogenic lines ( x 3 )– Electrical heaters for cryogenic flows ( x 2 )– Impurities (dust) remaining from fabrication– Controls– Coordination for “built to print” sub-systems ( x 2 )

• General concerns– 3D models, transport items to place, QA tools– “Time is contingency” to “Keep on schedule” takes time!

Page 29: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Main cryogenic line (1/2)E

F

BD

C

E

F

BD

C

Φ= 650 mmE-F= 50-75 B,C,D = 4-20 K

Weak mechanical approach and quality assurance

Page 30: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Main cryogenic line (2/2)“C” type interconnections

“A” type interconnections

Special interconnections

2nd start has been the

good one, after

complements by CERN

Double sourcing ?

Page 31: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Electrical heaters

Combination of heat exchange, flow patterns, electrical and

integration analysis

New design

Chicane Filler piece

Thermal screens

600 kW ElectricalHeater

D ≈ 500 mmL ≈ 3.5 m

Page 32: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

SH6

US IP6

SUH6

QURA-1

QSCA-1/2

QURCa-1

QSA(a)

QURCb-1

QSCCb

QSCB

QUI

QSDN

Ethernet backbone (IT-CS)

Ethernet surface Infrastucture (IT-CS)

Comp 4.5KComp 1.8K Comp 1.8K Comp 4.5K Main Dryer

QURCa-2

QURCb-2

QURA-2

QSRB-1/2Cold Box 4.5K LN2 BufferGhe Buffer

CB 1.8KCB 1.8K

LCB4.5K

ConnectionBox

SHM6 SD6

QSRA-1/2UCB 4.5K

Ethernet underground Infrastucture (IT-CS)

QSKAQSA(b)QSCCa QSV

Main Dryer

SCADA data servers

LHCALHCCa

LHCCb

LHCB

Ethernet local connection (LHC-IAS/IT CS)

1.8K 1.8K4.5K 4.5K

DS1 DS2

OS1OS2

OS3OS4

EW1

EW2230v

Alcove AlcoveUS IP5(b)

DFB

AlcoveAlcove US IP7(a)

DFB

Sector DFB

DFB

Sector

OS1OS2

OS3OS48 x 30 PLC’s

8 x 10’000 I/O

Controls

Industrial PLC’s, Ethernet based communications and object

oriented sofware:High potential, reliability being

improved

Page 33: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Considerations for new projects

• LHC public documentation:• Each new project has its own constraints!

Identification of boundary conditions and technological evolution since last project:– Partnership: an efficient way to catch faster– If necessary, R&D and components validation

• For design & installation: solid referencescompleted by flexibility

• Take advantage of experienced teams while they exist!

www.cern.ch/lhc> LHC Design Report > Cryogenics> LHC Project Reports : Papers

Page 34: Design, Construction, Installation and first Commissioning ...

S. Claudet - EPAC'06 Edinburgh LHC Cryogenic system: 1st experience

Conclusion

• Installation of various cryogenic sub-systems and cold tests of LHC cryo-magnets will be mostly completed by end of 2006

• All cryogenic sub-systems commissioned so farfulfil their requirements

• First LHC sector cool-down and commissioning end 2006:

Confident, and aware that it represents an enormous challenge with learning process, efforts and surprises!