Top Banner
DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA
27
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

DESIGN BUILD

NATIONAL PERSPECTIVE

byDwight Horne

FHWA

Page 2: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

WHAT IS DESIGN-BUILD ??

• PROCUREMENT METHOD

• RISK SHARING TECHNIQUE

• INNOVATION

• QUALITY BASED SELECTION

• WARRANTY OPTIONS

• FINANCING OPTIONS

Page 3: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Design-Build - Why is it Experimental?

Design-Build

23 USC 112 (b)(1)Competitively Bid(Low bid)Construction Contracts

23 USC 112(b)(2)Qualifications basedSelection, Engineering /Design Services

Page 4: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Capitol Outlay

0

10000

20000

30000

40000

50000

60000

1950

1952

1954

1956

1958

1960

1962

1964

1966

1968

1970

1972

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

Year

$ (m

illio

ns)

Local

State

Federal

Page 5: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

STATE DOT CHALLENGES

• FEWER STATE DOT EMPLOYEES

• MORE $$• HIGHER PUBLIC

EXPECTATIONS– MORE CUSTOMER

FOCUS

– MORE INNOVATIVE CONTRACTING

Page 6: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Design / Build

• NOT “IF”

• NOT “WHEN”

• “HOW”

Page 7: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Design-Build Selection Procedures

• Low Bid

• Modified Design-build

• Adjusted Bid

• Highest Composite Score

• Best Value

• Best Value / Fixed Budget

Page 8: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Procurement StrategyProcurement Strategy

Page 9: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Advantages of Design-Build (from Owner Perspective)

• Single Point of Responsibility

• Quality / Innovation

• Potential Time or Cost Savings

• Improved Risk Management

• Earlier Knowledge of Firm Costs

• Lower Incidence of Claims

• Reduced Project Administration

Page 10: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Advantages of Design-Buildto Industry

• INNOVATION• CONSTRUCTABILITY• DESIGN TO STRENGTHS• BETTER SCHEDULING• MORE COST AWARENESS• SHORTER DECISION TIME

Page 11: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

DESIGN / BUILD

• State & Local Governments

• Private Companies

• Federal Agencies

Page 12: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

FHWA Design-Build Philosophy

• Give same Flexibility & Protection offered by FEDERAL ACQUISITION REGS.

• Allow D-B contracting techniques allowed under STATE LAW

• Comply with other Federal-aid Provisions• Preserve the NEPA process• Determine best entity to manage risk• Protect the Public $$

– Competition - Best Value - Quality

Page 13: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

States Currently Using Design-Build

Page 14: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

SEP-14 Design-Build Contract Amounts

15

18

24

710685

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

> $100 M$ 50 - 100M$20 - 50 M$ 10 - 20 M$ 5 - 10 M$ 2 - 5 M$ 1 - 2 M$ 0 - 1 M

Page 15: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

TEA-21 Design-Build LegislationSection 1307

• By June 2001 FHWA must develop regulations • It will allow states to use D/B without HQ approval for :

– ITS projects > $ 5 million

– Other projects > $50 million

• Existing SEP-14 will be used in the transition period• SEP-14 will continue for smaller projects

Page 16: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

ISSUES• For Consideration when Structuring Procurement

•For FHWA Consideration in Rulemaking

Page 17: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

NEPA COMPLIANCE?RFP Release?

Issue• When should the RFP

be released relative to the conclusion of NEPA?

• Public perception - bias for build/preferred alternate if RFP prior to ROD

• Contingencies• Federal investment / risk • Trade-off - time vs. risk of

increased costs

Page 18: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Procurement Issues

Issue• Basis of evaluation

and award

• Low-Bid• Two-Phase Process• Best Value

Decision based on %, design complete, risk, project uniqueness

Page 19: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Procurement Issues - Weight of Price

Issue• Weight of price in the

selection process

• Relative weight• How to compare• Consideration of other

factors

Page 20: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Standardized Changed Condition Clauses

Issue• For traditional Federal-

aid construction projects, 23 CFR 635.109 applies.

• However, TEA-21 Section 1307(b) indicates SCCC are not necessary for design-build.

• Owner delays• Differing site

conditions• Significant changes

in character

Page 21: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

FHWA Authorization / Approvals

Issue• Timing of

authorization• Involvement in project

approvals

• Timing relative to NEPA

• Prior to release of RFQ, RFP, Concurrence in award

• Existing stewardship agreements

• “Clean Air” Implications

Page 22: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Conflict of Interest

Issue• Owner’s consultant?• Owner’s

subconsultants?• Same consultant /

different teams• post award team

changes /enhancement

• Competition• Unfair

advantage• Bid shopping?• Minimum

team requirements/ enhancement?

Page 23: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Owner Oversight

Issue• What is the

appropriate level of owner oversight?

• Owner’s role• Verification• Applicability of 23

CFR 637 (acceptance testing, IA testing)

• Warranties

Page 24: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Time Table

• NPRM - Fall ‘00/Early Winter Published in Federal Register

• Final Rule - Spring of ‘01 Published in Federal Register

• + 30 Days - Effective

Page 25: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

Additional Resources on SEP-14 Design-Build Projects

• FHWA HIPA-30 web page– http://www.fhwa.dot.gov/infrastructure/progadmin/

contracts/d_build.htm

• Utah State University web page– http://www.utaht2.usu.edu/projects/innovativecontracting/

ICSearchpage.html

– Run query for design-build projects

• WSDOT Design-Build Process for Highway Projects– http://www.wsdot.wa.gov/designbuild/db/index.htm#Stake

Page 26: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.

GIVE US YOUR COMMENTS

• On THESE and OTHER DESIGN/BUILD ISSUES Important to you

• IN WRITING– as an Association

– as a Company

– as an Individual

• TO FHWA 400 SEVENTH STREET WASH. DC 20590

Page 27: DESIGN BUILD NATIONAL PERSPECTIVE by Dwight Horne FHWA.