Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e
35

Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Mar 26, 2015

Download

Documents

Aiden Parker
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Demonstration Problem

Chapter 15 – Exercise 5

Direct Labor Variances – Solving for Unknowns

AccountingWhat the Numbers Mean 9e

Page 2: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Problem Definition

• Ackerman’s Garage uses standards to plan and control labor time and expense. The standard time for an engine tune-up is 3 hours, and the standard labor rate is $25 per hour. Last week, 42 tune-ups were completed. The labor efficiency variance was 14 hours unfavorable, and the labor rate variance totaled $140 favorable.

Page 3: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Problem Requirements

a. Calculate the actual direct labor hourly rate paid for tune-up work last week.

b. Calculate the dollar amount of the labor efficiency variance.

c. What is the most likely explanation for these two variances? Is this a good trade-off for the management of the garage to make? Explain your answer.

Page 4: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Problem Solution

a. Calculate the actual direct labor hourly rate paid for tune-up work last week.

First:

Set up the general model for analyzing labor variances and enter all known amounts.

Page 5: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR

Note:• AH = Actual labor hours used

• AR = Actual labor rate per hour

Page 6: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR

Note:• AH = Actual labor hours used

• AR = Actual labor rate per hour

• SR = Standard labor rate per hour

Page 7: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR

Note:• AH = Actual labor hours used

• AR = Actual labor rate per hour

• SR = Standard labor rate per hour

Labor Rate Variance

Page 8: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Note:• AH = Actual labor hours used

• AR = Actual labor rate per hour

• SR = Standard labor rate per hour

• SH = Standard labor hours allowed for the actual number of units produced

Labor Rate Variance

Page 9: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Note:• AH = Actual labor hours used

• AR = Actual labor rate per hour

• SR = Standard labor rate per hour

• SH = Standard labor hours allowed for the actual number of units produced

Labor Rate Variance

Labor Efficiency Variance

Page 10: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

Next:Enter known amounts from the problem information into the general model for analyzing labor variances.

Page 11: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Solution steps:• Step 1 – Enter standard labor rate into the general model.

Labor Rate Variance

Labor Efficiency Variance

Page 12: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

$25 $25

Solution steps:• Step 1 – Enter standard labor rate into the general model.

Labor Rate Variance

Labor Efficiency Variance

Calculation:

$25 standard rate amount was given

Page 13: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

$25 $25

Solution steps:• Step 2 – Calculate the standard hours allowed for the actual number

of units produced. Standard time for an engine tune-up is 3 hours.

Labor Rate Variance

Labor Efficiency Variance

Page 14: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

$25 126 hrs x $25

Solution steps:• Step 2 – Calculate the standard hours allowed for the actual number of

units produced. Standard time for an engine tune-up is 3 hours.

Labor Rate Variance

Labor Efficiency Variance

Calculation:

3 standard hours x 42 tune-ups

Page 15: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

$25 126 hrs x $25

Solution steps:• Step 3 – Calculate the actual hours used for the units produced. The

labor efficiency variance was 14 hours unfavorable.

Labor Rate Variance

Labor Efficiency Variance

Page 16: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

140 hrs x $25 126 hrs x $25

Solution steps:• Step 3 – Calculate the actual hours used for the units produced. The labor

efficiency variance was 14 hours unfavorable.

Labor Rate Variance

Labor Efficiency Variance

Calculation:

126 standard hours + 14 unfavorable efficiency

variance hours

140 hrs

Page 17: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Solution steps:• Step 4 – Calculate the actual hours x the standard rate.

Labor Rate Variance

Labor Efficiency Variance

140 hrs x 140 hrs x $25 126 hrs x $25

Page 18: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x 140 hrs x $25 126 hrs x $25

Calculation:

140 actual hours x $25 standard rate per hour

$ 3,500

Solution steps:• Step 4 – Calculate the actual hours x the standard rate.

Page 19: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x 140 hrs x $25 126 hrs x $25$ 3,500

Solution steps:• Step 5 – Enter the labor rate variance into the general model.

Page 20: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x 140 hrs x $25 126 hrs x $25$ 3,500

Solution steps:• Step 5 – Enter the labor rate variance into the general model.

Calculation:

The $140 favorable labor rate variance was

given

$140 F

Page 21: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x 140 hrs x $25 126 hrs x $25$ 3,500

Solution steps:• Step 6 – Use the actual hours x the standard rate and the favorable

labor rate variance to compute the total actual cost of labor.

$140 F

Page 22: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x 140 hrs x $25 126 hrs x $25$ 3,500

Solution steps:• Step 6 – Use the actual hours x the standard rate and the favorable labor

rate variance to compute the total actual cost of labor.

$140 F Calculation:

$3,500 - $140 favorable labor rate variance

$ 3,360

Page 23: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $25 126 hrs x $25$ 3,500

Solution steps:• Final Step – Compute the actual hourly rate of direct labor.

$140 F

$ 3,360

140 hrs x

Page 24: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $25 126 hrs x $25$ 3,500

Solution steps:• Final Step – Compute the actual hourly rate of direct labor.

$140 F

$ 3,360

140 hrs x $24

Calculation:

$3,360 / 140 direct labor hours

Page 25: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $25 126 hrs x $25$ 3,500

Solution:• The actual direct labor hourly rate paid for tune-up

work last week = $24 per hour.

$140 F

$ 3,360

140 hrs x $24

Page 26: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Problem Requirements

a. Calculate the actual direct labor hourly rate paid for tune-up work last week.

b. Calculate the dollar amount of the labor efficiency variance.

c. What is the most likely explanation for these two variances? Is this a good trade-off for the management of the garage to make? Explain your answer.

Page 27: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Problem Solution

a. Calculate the actual direct labor hourly rate paid for tune-up work last week.

b. Calculate the dollar amount of the labor efficiency variance.

Continue to complete the general model for analyzing labor variances by entering all

remaining amounts.

Page 28: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Solution steps:• Step 1 – Calculate the total standard cost of labor.

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $24 140 hrs x $25 126 hrs x $25$ 3,360 $ 3,500

$140 F

Page 29: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Solution steps:• Step 1 – Calculate the total standard cost of labor.

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $24 140 hrs x $25 126 hrs x $25$ 3,360 $ 3,500

$140 F

$ 3,150

Calculation:

126 standard hours x $25 standard rate

per hour

Page 30: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Solution steps:• Final Step – Calculate the labor efficiency variance.

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $24 140 hrs x $25 126 hrs x $25$ 3,360 $ 3,500

$140 F

$ 3,150

Page 31: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $24 140 hrs x $25 126 hrs x $25$ 3,360 $ 3,500

$140 F

$ 3,150

$ 350 U

Calculation:

$3,500 (AH x SR) - $3,150 (SH x SR)or

14 hours unfavorable efficiency variance x $25 standard rate

Page 32: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

• General model for analyzing labor variances:

Problem Solution

AH x AR AH x SR SH x SR

Labor Rate Variance

Labor Efficiency Variance

140 hrs x $24 140 hrs x $25 126 hrs x $25$ 3,360 $ 3,500

$140 F

$ 3,150

$ 350 U

Solution:• The direct labor efficiency variance = $350 unfavorable.

Page 33: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Problem Requirements

a. Calculate the actual direct labor hourly rate paid for tune-up work last week.

b. Calculate the dollar amount of the labor efficiency variance.

c. What is the most likely explanation for these two variances? Is this a good trade-off for the management of the garage to make? Explain your answer.

Page 34: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

Problem Solution

Less skilled, lower paid workers took longer than standard to get the work

done. The net variance is $210U ($350U - $140F). This was not a good trade-off based on the variance. From

a qualitative viewpoint, less skilled workers may not do as good of a job.

Page 35: Demonstration Problem Chapter 15 – Exercise 5 Direct Labor Variances – Solving for Unknowns Accounting What the Numbers Mean 9e.

AccountingWhat the Numbers Mean 9e

David H. MarshallWayne W. McManus

Daniel F. Viele

You should now have a better understanding ofdirect labor variance information.

Remember that there is a demonstration problem for each chapter that is here for your learning benefit.