Genesis Centre Educational Facility • Clients: SWRDA and Learning and Skills Council • Showcase sustainable construction • Integrates cutting edge and contrasting sustainable building techniques with mainstream methods • Sustainable features include • Building materials – timber frame, clay block, straw bale construction, green roofs • Energy and water efficiency - solar panels, PVs, SUDs system, innotherm insulation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Genesis Centre Educational Facility
• Clients: SWRDA and Learning and Skills Council
• Showcase sustainable construction• Integrates cutting edge and contrasting
sustainable building techniques with mainstream methods
• Sustainable features include• Building materials – timber frame, clay
block, straw bale construction, green roofs
• Energy and water efficiency - solar panels, PVs, SUDs system, innotherm insulation
M25 J1b-3 Widening • Client: Highways Agency• Contractor: Costain• Scheme to reduce congestion at the
A2/M25 Junction• Procured using the Early Contractor
Involvement (ECI) method which encouraged a collaborative and innovative working environment
• Innovative engineering solutions (such as QMB) enabled them to reduce traffic management on the A2 by around 6 months - leading to huge cost/time savings
• ECI enabled more focus on sustainability issues leading to reduced waste, less vehicle movements and lower carbon emissions
St Paul’s Square
• Client: English Cities Fund• Contractor: Shepherd Construction• Construction of a 14000m2 office
block, apartment block and a 336-space multi-storey car park at St Pauls Square, Liverpool
• At tender stage they found the programme required 105 weeks and two cranes which would take them over time and budget
• Collaboration with their supply chain partner led to a new product (Bi steel cores) being employed on the project which brought it back within the client’s required timeframe and budget
• The project completed in 84 weeks using only one crane
MoD Andover North Site • Client: MoD• Consultant: Rider Levett Bucknall (RLB) • £35m, 35 acre site including offices, sports
facilities, live-in quarters, etc • The combined construction / compliance
contract meant whole life value was a primary consideration at the design stage
• Adoption of collaborative working across the team (particularly co-location) really drove the projects success
• Sustainability was a key consideration of the project (SUDs ,etc)
• Overall the project has saved 44% on actual costs compared to the target/budget which equates to £500,000
Redlands Primary School • Client: Nottinghamshire County Council• Contractor: Willmott Dixon• Keystage 2 extension to a primary school
and construction of a New Opportunities Funded (NOF) Table Tennis Centre
• Collaborative and integrated working helped to develop relationships across the team and bring the project in on time and budget
• Sustainable Features include• Rainwater harvestings• Power generated from wind turbine• Passive ventilation • Minimised waste & improved recycling
BAe • Client: Airbus• Contractor: Laing O’Rourke• Factory constructed to supply the
manufacturing programme for the Airbus A-380
• To achieve the tight construction timeframe, a partnering oriented process based on Prime Contracting was adopted
• Early involvement of the team helped to generate advice on buildability, cost and programming issues
• Collaboration - the team were engaged in dialogue and co-operation throughout the project
• All key completion dates were achieved
The Academy of St Francis of Assisi
• Client: Kensington Academy Trust• Contractor: Birse Build• The building was required to facilitate
environmental education, model good environmental design practice and offer itself as an educational resource
• The finished building has had a on huge impact on pupils’ achievement• In 2007 44% of the Year 11 students
gained five or more A* to C passes at GCSE, in 2008 this figure rose to 57%
• In “value-added” league tables the Academy was the top school in the UK
Cadishead Way Stage2 Bypass • Client/s: Salford City Council & Urban
Vision Partnership• Contractor: Birse Civils Ltd• New build road • ECI to develop the design, buildability and
cost of the scheme• Partnering approach led to significant
‘Value Engineering’ ideas being developed and adopted on the scheme, including;• Innovative approach to embankment
excavation to avoid major temporary works
• Redesign of retaining wall to minimise construction and financial risk
• The Bypass opened approx 16 weeks ahead of schedule and within budget
Barts and London Hospitals • Client: Barts and The London NHS Trust• Contractor: Skanska• Britain’s largest hospital programme –
refurbishment project over £1billion• Huge challenges to keep both hospitals
100% operational throughout the works• Early consideration of issues allowed
room for innovation solutions• Innovations – use of a large acoustic
screen to absorb sound and vibration • The Appointment of Sustainability
Champions was a real success• 50k tonnes of waste diverted from
landfill• 99.6% of demolition waste recycled
Wolseley Sustainable Building Center
• Client: Wolseley Uk Ltd• Contractor: Sol Construction Ltd• The center is a sustainability showcase
featuring sustainable building materials and water conservation products
• Wolseley fulfilled dual roles of both client and supplier on the project
• Adopted strategic partnering to drive the project and establish the sustainable product range
• 170 types of products feature in the center including: PVs, Micro wind, a sedum roof, Biomass boiler, etc
• The project completed on time & budget • Site waste was segregated and recycled
Heathrow Terminal 5 • Client: BAA• Contractor: Laing O’Rourke• Construction of a new Terminal and
associated facilities• Adopted the principles of standardisation
in design, pre fabrication and modularisation to reduce waste
• Use of products with a high recycled content
• Less waste sent to landfill - reducing vehicle movements, leading to lower carbon emissions
• Over 97% of waste material recycled or recovered
• 300,000 tonnes of waste crushed and reused on site
Silk Stream Flood Alleviation Scheme
• Client: Environment Agency • Contractor: Jackson Civil Engineering • The scheme involved the development of
an area for controlled flooding• Sustainability and health and safety were
identified as key project drivers• Committed team working to develop the
most appropriate solution• Integration of engineering, health and
safety and environmental aspects was integral to providing the most sustainable solution
• Use of recycled road materials led to a £19k cost saving
Liverpool South Parkway
• Client: Merseytravel• Contractors: BAM Construction / BAM
Nuttal• Close team integration was vital to
ensure they met strict delivery deadlines • Environmental / sustainability features
include; Rainwater Harvesting, Solar Panels, Sustainable Timber, etc
• Achieved a ‘Very Good’ rating in a specially designed BREEAM assessment
• Achieved targets set for Health & Safety and Environmental KPIs
• No lost time accidents throughout the course of the works
SLAM (Single Living
Accommodation Modernisation) • Client: MoD• Main Contractor: Debut• A £1billion project comprising the
modernisation of 18,000 Army bedspaces across the UK
• An Integrated Project Team (IPT) was established at the start of the project to ensure delivery
• Since year 1 the team have over-delivered year on year and are ahead of programme
• During Phase 1 a 9% cost saving on the building only element of the programme was delivered
• The project is currently running at 2% below Target Cost
John Perryn School• Client: London Borough of Ealing• Contractor: Willmott Dixon • The school was re-developed as part of
an £8.4m Government Pathfinder scheme - to show how failing schools can be transformed by new facilities
• Employed collaborative and integrated working to deliver an innovative school to a tight timetable
• Pushed the boundaries of sustainable design and achieved an air tightness rating below PassiveHaus standards (1.99m³ per m² per hour)
• Since the pupils moved in, the school has been taken off special measures
St Helens and Knowsley PFI Hospitals Project
• Client: NewHospitals • Contractor: Taylor Woodrow• £338m PFI project concerning the
redevelopment of two major hospital sites• Adoption of a single team collaborative
approach to achieve an innovative patient- focused design solution
• A ‘design for manufacture’ approach enabled them to deliver 20-25% of the prime cost manufactured offsite
• Time spent at the planning stage, together with repeatability, offsite construction, early stage planning and investment helped deliver the construction phase ahead of schedule
Olympic Stadium• Client: Olympic Delivery Authority (ODA)• Contractor: Sir Robert McAlpine• Adoption of collaborative working principles
to deliver this unique £496m public sector funded project
• The team are performing well against their overall sustainability targets• 30% of the external white steel work is
reused• The roof is 100% recyclable• 99% of all waste has been segregated
and recycled• Team Stadium have exceeded their 3%
apprentices target and have increased the target to 4.5%