Rigless P&A of Subsea wells in Norwegian and Danish Waters - 2009-2014 Decom North Sea Lunch and Learn November 12 th 2014 Øystein Kanestrøm
21

Decom North Sea Lunch and Learn

Jan 03, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Decom North Sea Lunch and Learn

Rigless P&A of Subsea wells in Norwegian and Danish Waters - 2009-2014

Decom North Sea Lunch and Learn

November 12th 2014

Øystein Kanestrøm

Page 2: Decom North Sea Lunch and Learn

2

Oceaneering

Page 3: Decom North Sea Lunch and Learn

HSE

3

Oceaneering Safety

Page 4: Decom North Sea Lunch and Learn

4

Oceaneering Safety

Page 5: Decom North Sea Lunch and Learn

5

Oceaneering Life of Field

Page 6: Decom North Sea Lunch and Learn

2009 – The year it started

• Client: Det norske

• Scope: Wellhead removal and survey

Page 7: Decom North Sea Lunch and Learn

2010 – Wellhead removal & X-mas tree recovery

• Client: Det norske, Premier,

Nexen

• Scope: 5 wellhead removals,

X-mas trees recovery (for

resuse), survey

Page 8: Decom North Sea Lunch and Learn

2011 – Wellhead removal & CAN recovery

• Client: Det norske, Petro Canada (Suncor), Premier,

• Scope: 7 wellhead removals, cement flushing, survey, and 1 spud CAN

Page 9: Decom North Sea Lunch and Learn

2012 – Wellhead removal & CAN recovery

• Client: Det norske, Statoil, Total,

Noreco, Centrica

• Scope: 5 wellheads, hydrate

washing, fishing of WF cutting

tool, recovery of dropped

drillpipe, CAN recovery and

survey, rescue fishing vessel

Page 10: Decom North Sea Lunch and Learn

2014 – Rig Chase

• Client: Det norske /GDF Suez,

Statoil, Total, Talisman

• Scope: 6 wellheads,

Page 11: Decom North Sea Lunch and Learn

• Offshore campaign divided in 4

Phases– Phase 1 – Access to wells

– Phase 2 – Remove TA caps and

Top up cement

– Phase 3 – Cut wells below seabed,

– Phase 4 - Clear seabed and final

survey

• 9 wells finally abandoned in 2013

• survey of 4 wells for 2014 scope

(15 wells planned for 2014)

Island Valiant Pipe Handling System

2013 – Mærsk Oil and Gas P&A of Suspended Subsea wells

Page 12: Decom North Sea Lunch and Learn

• Offshore campaign divided in 5

Phases– Phase 1 – Access to wells

– Phase 2 – Remove TA caps /

Wireline operations / scraping

– Phase 3 – Cut and recover casing

– Phase 4 - Cementing

– Phase 5 - Cut and recover wells and

clear seabed (2015)

• 14 wells

2014 – Mærsk Oil and Gas P&A of Suspended Subsea wells

Page 13: Decom North Sea Lunch and Learn

Phase 1

Access the wells

Phase 2

TA caps / scraping

Phase 3

Cut and pull casing Phase 4

Cementing

Phase 5

WH cut and recovery

Page 14: Decom North Sea Lunch and Learn

2014 – Phase 1- Access to wells

Flushing 500m^3 /min@8 bars - vessel ballast

pumps

Jetting 5-8m^3/min@300-500 bars - cement pumps

Jetting 1m^3/min@1000 bars HP pumps

Downhole video cameras

Various type of flushing heads and jetting nozzles

Page 15: Decom North Sea Lunch and Learn

2014 – Phase 2 - TA caps recovery and wireline operations

Wireline operations:

- Lubricator

- Slickline jar (prong

recovery)

- CBL and CCL

logging

- Bridge plug setting

Page 16: Decom North Sea Lunch and Learn
Page 17: Decom North Sea Lunch and Learn

2014 – Phase 3 - Casing, scraping, cutting and recovery

Scraping the wells

Page 18: Decom North Sea Lunch and Learn

• Pump and pull - hose and cement stinger

• Flush back to 35ft BML

• Weight test

• Batchwork

2014 – Phase 4 - Cementing the wells

Page 19: Decom North Sea Lunch and Learn
Page 20: Decom North Sea Lunch and Learn

Client reference list

12

Oceaneering – Well abandonments