Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

Jul 17, 2015

Download

Jonathan Hansen
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Using&Cost&of&

Delay&to&

Understand&your&

Customer’s&Real&

Priorities

Deadlines vs. Sad-lines

Page 2: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

About Me

Jonathan Hansen

Thumbtack Technology

NYC Kanban Meetup

Page 3: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Some Project Challenges

• Delayed&Start&

• Wrong&Thing&Started&

• Premature&Op>miza>on

Problems&that&Happen&Some>mes

Root Cause: Misunderstood Cost of Delay

Page 4: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

About Cost of Delay

•What&it&is&

•∩&Queues&

•Using&it

Page 5: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cupcakes!An&Example

Page 6: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cost of DelayAn&Example

Page 7: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cost of DelayA&New&Fad

Page 8: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cost of DelayA&Market&Saturates

Page 9: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cupcake Market LifecycleAn&Example

Cupcake&Episode

Page 10: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cupcake Market LifecycleAn&Example

Realized(Value

Poten/al(Value

Cupcake&Episode

Compe>tor&starts&selling

Page 11: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cupcake Market LifecycleAn&Example

Realized(Value

Poten/al(Value

Cupcake&Episode

Compe>tor&starts&selling

Cost%of%Delay

Page 12: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Typical Project Start

• Monthly&Release&Cycle&

• Desired&Feature&List&

• Budget:&$4000

“What&can&we&have&this&month?”

Page 13: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Estimated Delivery Costs

Feature Story%Points T&M%Cost%($)

1 1 $500

2 3 $1500

3 3 $1500

4 10 $5000

Page 14: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Capacity + BudgetCustomer’s&Backlog

Feature Story%Points T&M%Cost%($)

1 1 $500

2 3 $1500

3 3 $1500

4 10 $5000

Capacity: ≤8 points

Below Budget: $3500

Page 15: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

What About Cost of Delay?Customer’s&Backlog

Feature Story%Points T&M%Cost%($)

Added%Revenue%per%

month%($)

Value%aGer%6%months%($)

1 1 $500 $800 $4,300

2 3 $1500 $500 $1,500

3 3 $1500 $5,000 $28,500

4 10 $5000 $60,000 $355,000

Page 16: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Customer’s&Backlog

Feature Story%Points T&M%Cost%($)

Added%Revenue%per%

month%($)

Value%aGer%6%months%($)

1 1 $500 $800 $4,300

2 3 $1500 $500 $1,500

3 3 $1500 $5,000 $28,500

4 10 $5000 $60,000 $355,000

What About Cost of Delay?Actual Value:

$33,880

Page 17: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Customer’s&Backlog

Feature Story%Points T&M%Cost%($)

Added%Revenue%per%

month%($)

Value%aGer%6%months%($)

1 1 $500 $800 $4,300

2 3 $1500 $500 $1,500

3 3 $1500 $5,000 $28,500

4 10 $5000 $60,000 $355,000

Potential Value WastedActual Value:

$33,880

Potential Value

Page 18: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

About Cost of Delay

•What&it&is&

•∩&Queues&

•Using&it

Page 19: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Tracking a Feature’s CostsCoD&for&“Feature&I”

Worth&$20,000/week&once&released

Page 20: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Tracking a Feature’s CostsCoD&for&“Feature&I”

Worth&$20,000/week&once&released

Dev+QA&es>mate:&$4,000

Development&Costs

Page 21: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Tracking a Feature’s CostsCoD&for&“Feature&I”

Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Value%Added

Wait

Idea&Captured

Dev&&&QA

UATDeployed

Si\ng&in&Backlog

Wai>ng&for&UAT

Wai>ng&for&Deployment

Page 22: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Tracking a Feature’s CostsCoD&for&“Feature&I”

Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Value%Added

Wait

Idea&Captured

Dev&&&QA

UATDeployed

Si\ng&in&Backlog

Wai>ng&for&UAT

Wai>ng&for&Deployment

$4,000&(development&cost)+&$260,000&(13&weeks&Opportunity&Cost)=&$264,000

Page 23: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Tracking a Feature’s CostsDrop&Everything&for&“Feature&I”?

Page 24: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Tracking a Feature’s CostsDrop&Everything&for&“Feature&I”?

Everything&has&a&

Different&Cost&of&Delay

Page 25: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

About Cost of Delay

•What&it&is&

•∩&Queues&

•Using&it

Page 26: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

What&feature&should&we&work&on&first?

Prioritizing with CoD

Page 27: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Value

Value&=&Revenue&g&Cost

Page 28: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

1. Increase&Revenue&2. Protect&Revenue&3. Reduce&Costs&4. Avoid&Costs

Ways to Increase Value

Page 29: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Kinds of Cost

• Development&

• Opportunity

Page 30: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Prioritizing with CoD

1. CoD&already&known&2. Quan>ta>ve&Es>ma>on&3. Qualita>ve&Es>ma>on

Depends&on&What&You&Have&to&Work&With

Page 31: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Prioritizing with Known CoD

Weighted&Shortest&Job&First&(WSJF)

Page 32: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Weighted&Shortest&Job&First

Project DuraQon Cost%of%Delay

Weight%=%CoD%/%

DuraQon1 1 10 102 3 3 13 10 1 0.1

Prioritizing with Known CoD

Source:%%The$Principles$of$Product$Development$Flow

Page 33: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Cost(of(Delay(($)

Time

High&Weight&First

Project DuraQon Cost%of%Delay

Weight%=%CoD%/%

DuraQon

1 1 10 10

2 3 3 1

3 10 1 0.11

2

3

Weighted Shortest Job First

Source:%%The$Principles$of$Product$Development$Flow

Page 34: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Low&Weight&First

Cost(of(Delay(($)

Time

1

2

3

Project DuraQon Cost%of%Delay

Weight%=%CoD%/%

DuraQon

1 1 10 10

2 3 3 1

3 10 1 0.1

By contrast, this is horrible

Source:%%The$Principles$of$Product$Development$Flow

Page 35: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Quantitative Estimation

What&if&nobody&knows&Cost&of&Delay?&

Page 36: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Sample Feature Value CardTitle:&Replace(Sign>Up(Process(with(Google(Accounts(Integra/on

What&kind(s)&of&value&is&this&feature&adding?

☑Add(Revenue&

☐Protect(Revenue

☑Lower(Costs(

☐Avoid(Costs

About&how&much&value&do&you&think&this&will&add/month?

☐<($500(

☒$500(>($999(

☐$1,000(>($9,999

☐$10,000(>($49,999(

☐$50,000(>($99,999(

☐>($100,000

How&will&it&add&those&kinds&of&Value?

The$current$sign-up$system$is$slow$and$10%$of$poten:al$users$abandon$the$process$3$pages$into$it.$Signing$up$with$Google$Accounts$will$take$fewer$than$3$clicks$and$is$projected$to$reduce$abandonment$by$40%.$Also,$we$will$no$longer$need$to$maintain$the$old$sign-up$module.

Complexity: 5$points

Weight: 150

WSJF&again

Page 37: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Qualitative Estimation

What&if&nobody&can&es>mate&value?

Page 38: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Define Work Item Types

Standard Expedite Fixed Date Intangible

Page 39: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Hunting for Clues

Page 40: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Qualitative EstimationClues&in&the&Language

A.“It(is(becoming(increasingly&urgent(for(us(to(release(an(Android(

version”(

B.“We’re(losing(customers(—(we(need(an(Android(version(now!”(

C.“The(founda/onal(API(for(our(Android(app(will(be(shut&down&

on&March&15(so(we(need(to(replace(it(by(then.”(

D.“Maybe(we(should(think(about(wri/ng(an(Android(app(

some>me.”

Page 41: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: Standard WorkTypical&Cost&of&Delay&Graph

“It(is(becoming(

increasingly&urgent(for(us(to(release(an(

Android(

version”

Cos

t of

Del

ay (

$)

Time

Page 42: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: Standard WorkTrigger&Words

“increasingly&urgent”

“worth&$X&per&year”

“recurring&savings”

“compound&growth”

“compe>>ve&advantage”

“a&priority”

Page 43: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: ExpediteTypical&Cost&of&Delay&Graph

“We’re(losing(

customers(—(

we(need(an(

Android(

version(now!”

Cos

t of

Del

ay (

$)

Time

Page 44: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: ExpediteTrigger&Words

“right&away”

“drop&everything”

“NOW”

“we&are&bleeding&cash”

“customers&are&screaming”

Page 45: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: Fixed DateTypical&Cost&of&Delay&Graph

“The(founda/onal(

API(for(our(

Android(app(will(

be(shut&down&on&March&15(so(we(need(to(replace(it(

by(then.”

Cos

t of

Del

ay (

$)

Time

Page 46: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: Fixed DateTrigger&Words

“on&November&15”“next&Friday”

“Quarter&End” “seasonal&opportunity”

Page 47: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: IntangibleTypical&Cost&of&Delay&Graph

“Maybe(we(

should(think(

about(wri/ng(

an(Android(

app(

some>me.”

Cos

t of

Del

ay (

$)

Time

?

Page 48: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item: IntangibleTrigger&Words

“seems&important”

“need&to&refactor”

“in&my&opinion” “probably&useful”

“would&be&nice”

Page 49: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Work Item Types

Standard Expedite Fixed Date Intangible

Page 50: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Use Kanban to BalanceWork&in&Progress&Limits&by&Class&of&Service

3 2 2

1 1 1

1 1 1

Page 51: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

ConclusionWhat,&Why,&What&to&do

1.Invisible&Lost&Money&2.Queues&Increase&it&3.Bener&Priori>za>on

Page 52: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Shameless Plug

Next NYC Lean Coffee: Wednesday 7pm @ Spotify

Page 53: Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Real Priorities

@jonathansen

Read More