Top Banner
Dale Even, PE Lunda Construction Company Jason Block - Ames Construction, Inc.
91

Dale Even, PE Lunda Construction Company Jason Block ...

Jan 29, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 2: Dale Even, PE Lunda Construction Company Jason Block ...

Project Area

WisconsinMinnesota

Page 3: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Contracts

Pile Load Test Contract – 2012 $3.5 million

Early Foundation Contract – 2013 $37 Million

Minnesota approach roadway - 2012 $55 million• Ames/Lunda Joint Venture

Superstructure Contract – 2014 to 2017 $332 million• Lunda/Ames Joint Venture

Wisconsin roadway – 2013 to 2017 $27 Million

Page 4: Dale Even, PE Lunda Construction Company Jason Block ...

Bridge Project Schedule

St. Croix Crossing Project Schedule

2012 2013 2014 2015 2016 2017Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Final Design

Early Fnd Design

Pile Load Test contract

Early Fnd Contract

Superstructure Contract

Page 5: Dale Even, PE Lunda Construction Company Jason Block ...

Project Labor and Subcontractors

• Lunda/Ames Joint Venture Prime Contractor• Self Performed 67% of the

work• Up to 400 trades persons at peak

• Multiple Shifts• DBE Goal 15.3%• Workforce goals

• Minority 22%• Female 6%

• 25 subcontractors• Rebar/PT labor• Electrical• Painting• Stay Cables

Page 6: Dale Even, PE Lunda Construction Company Jason Block ...

Project Partnering

• Quarterly Partnering Meetings• Facilitator• Project Management• Executive Management

• Project Charter• Safety• Environment• Quality• Schedule• Budget• Public Relations• Issue Resolution• DBE Goal

Page 7: Dale Even, PE Lunda Construction Company Jason Block ...

MnOSHA Project Partnership

• 120 OSHA Site Evaluation's

• 780 Safety and Environmental Orientations

• LAJV Project Specific Site Safety Plans

• Multiple Project Safety Professionals

• All parties believe it is a Successful Program

Page 8: Dale Even, PE Lunda Construction Company Jason Block ...

Quality Program

• Hybrid of MnDOTDB and DBB

• Limited 3rd Party QC

• Roles of QC vs. QA• 992 Segments only

1 rejected.• National recruiting

of technical people to support the work.

Page 9: Dale Even, PE Lunda Construction Company Jason Block ...

St Croix Crossing Bridge

• Extradosed Bridge Design• Hybrid Cable Stay and Concrete Box Girder

• Total Bridge Length 5,079’• Total Bridge Area 13.5 Acres.• 100 Year Design Life

Page 10: Dale Even, PE Lunda Construction Company Jason Block ...

Major Materials

• 140,000 C.Y. of Concrete• 20 different mix designs (plastic up

to 180 minutes)• 4,000 to 9,000 PSI• 2 suppliers

• 40,000,000 pounds of Reinforcing• Epoxy Coated and Stainless

• 8,000,000 pounds of Post Tensioning Steel

• 160 Stay Cable – 76 Strands each

• 20,000 gallons of paint

Page 11: Dale Even, PE Lunda Construction Company Jason Block ...

Environmental Commitments

Regulatory/Oversight• MnDOT• WisDOT• USACE • USCG• MPCA • Water shed District• USFW • DNR (Mn and WI)• Over 70 site specific

plans developed• Full time ECO

Page 12: Dale Even, PE Lunda Construction Company Jason Block ...

Approach Bridges Construction

Minn. Mainline Approach Spans• Two parallel 1700-ft.

sections of bridge – Two units• Pre-cast balanced cantilever/

CIP on falsework

Off-Ramp – On-Ramp Spans• 960-ft. and 630-ft. structures• Pre-cast balanced cantilever/

CIP on falsework

Page 13: Dale Even, PE Lunda Construction Company Jason Block ...

On-site Casting Yard

Page 14: Dale Even, PE Lunda Construction Company Jason Block ...

On-Site Casting Yard

• Construction:• 342 pre-cast

concrete segments • 3 castings beds• Completed casting

7/13/16

• Segment dimensions:• 43 ft. wide• 10-14 ft. tall• Up to 90 tons each

Page 15: Dale Even, PE Lunda Construction Company Jason Block ...

Construct and Transport Rebar Cage

• 3 Pre-tie Jigs• Adjustable Jig• Cage weight approximately

7000 pounds

Page 16: Dale Even, PE Lunda Construction Company Jason Block ...

Match Casting

• Previously cast segment used a bulk head for casting the next segment

• Geometry of the structure controlled by rotating the match cast segment vertically and horizontally.

• As cast surveys allow for adjustments as segments are cast.

Page 17: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erection – Approach Structure

• Unit 1 Segments• First Segments Erected

May 2015• Balance Cantilever

Method• SPMT transport on site• Crane based erecting• 300 to 440 ton cranes

Page 18: Dale Even, PE Lunda Construction Company Jason Block ...

Approach Segment Erecting

Unit 1 Segments• 13 Pre-Cast Spans• Span lengths 180’ to 290’• Spans over

• Wetlands• Multiple Rail Lines• Roadways

Page 19: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erection -Approach Structures

Unit 1 Segments• Up to 80 above existing grade

Page 20: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erection -Approach Structures

Unit 1 Segments• Last Segment Erected October 2016

Page 21: Dale Even, PE Lunda Construction Company Jason Block ...

Approach Bridge Cast-In-Place Spans

Cast-In-Place Bridges• Br. 82048 On Ramp• Unit 2 Gore Area • Br. 82047 Off Ramp

Span 1

Page 22: Dale Even, PE Lunda Construction Company Jason Block ...

Cast In Place Falsework

• 80 Feet above grade• 12 Million pounds of

False-work

Page 23: Dale Even, PE Lunda Construction Company Jason Block ...

Cast In Place– Falsework and Formwork

• Outsourced FW Design• Pile Foundations• Pipe Columns (27,000 lf)

• LAJV Formwork Design

Page 24: Dale Even, PE Lunda Construction Company Jason Block ...

Cast-In-Place Box Girder Construction

• Variable Depth• Variable Width

Page 25: Dale Even, PE Lunda Construction Company Jason Block ...

Cast In Place – Falsework and Formwork

• No standardized shapes

• Hand formed in place• VE to simply shapes

denied due to aesthetic concerns

Page 26: Dale Even, PE Lunda Construction Company Jason Block ...

Cast-In-Place Box Girder Construction

• Cold Weather Work

Page 27: Dale Even, PE Lunda Construction Company Jason Block ...

Cast in Place on Falsework

Page 28: Dale Even, PE Lunda Construction Company Jason Block ...

River Bridge Construction

Page 29: Dale Even, PE Lunda Construction Company Jason Block ...

Cold Weather Construction

Page 30: Dale Even, PE Lunda Construction Company Jason Block ...

Pier Blades

Page 31: Dale Even, PE Lunda Construction Company Jason Block ...

Aesthetic Construction Details

Page 32: Dale Even, PE Lunda Construction Company Jason Block ...

Crossbeam Falsework and Formwork

Page 33: Dale Even, PE Lunda Construction Company Jason Block ...

Rebar, PT Duct and Headed Rebar Installation – Crossbeams

Page 34: Dale Even, PE Lunda Construction Company Jason Block ...

3D Model of Knuckle Joint

• The owner developed a 3D Model Pre-Bid• Contactor developed ISD’s• Bid Item to Build a Mock up to sort out

Constructability Issues• Mock-Up and ISD’s identified several conflicts in

the design

Page 35: Dale Even, PE Lunda Construction Company Jason Block ...

Crossbeam Construction - Concrete

Page 36: Dale Even, PE Lunda Construction Company Jason Block ...

Crossbeam Construction

Page 37: Dale Even, PE Lunda Construction Company Jason Block ...

Pier Tower Construction

Pier Tower Climbing Formwork • Custom Forms• Poured in 22 Foot Lifts• Tower Boxes • 67’ above deck

Page 38: Dale Even, PE Lunda Construction Company Jason Block ...

Pier Tower Construction

Page 39: Dale Even, PE Lunda Construction Company Jason Block ...

Tower Construction

Page 40: Dale Even, PE Lunda Construction Company Jason Block ...

Typical River Span Deck Section

• 18‘ deep twin three cell box

• CIP center closure link

• 4-0.6“ φ transverse PT tendons at approx 2-6" c/c

30 m

6 m

Page 41: Dale Even, PE Lunda Construction Company Jason Block ...

Grey Cloud Casting Yard

Page 42: Dale Even, PE Lunda Construction Company Jason Block ...

Grey Cloud Segment Casting

• 5 casting beds• 3 OH Cranes• 5 Pre-tie beds• Storage for up to 400

Segments• Cast 650 segments

Page 43: Dale Even, PE Lunda Construction Company Jason Block ...

Grey Cloud Island Casting Yard

River bridge segments

• 18 ft. deep

• 10 ft. long

• 48 ft. wide

• 180 tons

• Casting September 2014 to August 2016

Page 44: Dale Even, PE Lunda Construction Company Jason Block ...

Pre-Fab of Rebar

• 35,000Lbs

Page 45: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Transport

• Barged 33 miles on Mississippi and St. Croix rivers to project site

• Up to 10 Segments per barge

• Pass through Lock and Dam #2

• 96 Hours outside the St Croix pool.

Page 46: Dale Even, PE Lunda Construction Company Jason Block ...

River Bridge Construction Staging

Page 47: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 48: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 49: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 50: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 51: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 52: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 53: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 54: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 55: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 56: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 57: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 58: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 59: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 60: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 61: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 62: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 63: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 64: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 65: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 66: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 67: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 68: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 69: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 70: Dale Even, PE Lunda Construction Company Jason Block ...

Construction Sequence

Page 71: Dale Even, PE Lunda Construction Company Jason Block ...

Geometry Control

• Methods to control Geometry

• Wet joints

• Shims

• Adjust PT bar forces

Page 72: Dale Even, PE Lunda Construction Company Jason Block ...

Erecting Equipment

Segment Lifters• Design, Fabrication,

Procurement 10 months• Load Test to 125%• 3 Pairs of lifters

Page 73: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erection

Page 74: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erection

Page 75: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erection

Piers 8 and 12• Hoist off of Barge• Walking Frame to

transport

Page 76: Dale Even, PE Lunda Construction Company Jason Block ...

Erecting Equipment

660 Ton Ringer Cranes• 1- Barge Mounted• 1 – Land Based

Page 77: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erection - Segment Epoxy

• 3 temperature ranges

• 40°F - 115°F • Revised to

28°F - 115°F for cold weather then Rescinded.

Page 78: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erecting – Post Tensioning

Post-tensioning steel bars

Post-tensioning stressing 25 strands 0.6” φ

Page 79: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Erecting -Longitudinal Closure Link

Closure Link• Connects EB and WB• Install Rebar/PT• Pour Concrete• Stress PT• Completed to advance

erection

Page 80: Dale Even, PE Lunda Construction Company Jason Block ...

Typical Deck SegmentAt Stay Anchorage

• External transverse tendons at stays

• Hoist Strut into place

• Install Rebar/Cast Concrete

• PT Transverse Tendon Before Stays

Page 81: Dale Even, PE Lunda Construction Company Jason Block ...

Transverse Struts

Page 82: Dale Even, PE Lunda Construction Company Jason Block ...

Stay Cables

• 32 Cables/Pier• 76 Strands/each• 2.4 Million Lbs of

force• Installed Strand by

Strand• 400 miles of cable

Page 83: Dale Even, PE Lunda Construction Company Jason Block ...

Stay Cables

Each of the 76 strands is installed and stressed separately in a 10” diameter duct

Page 84: Dale Even, PE Lunda Construction Company Jason Block ...

Stay Cables – Inside Anchor Box

Page 85: Dale Even, PE Lunda Construction Company Jason Block ...

Stay Cables

After each strand is installed, crews pull it tight using a hydraulic jack. It applies 33,000 lbs of force.

Page 86: Dale Even, PE Lunda Construction Company Jason Block ...

Span 14 Trestle

• Top Down Construction• Tree Clearing Allowed 10 feet

beyond drip line• Highly Erodible soils• Steep Terrain

Page 87: Dale Even, PE Lunda Construction Company Jason Block ...

Span 14 Erecting

• Hoist segments onto cart

• Winch segments into place

• Install Temporary PT Bars

• Repeat

Page 88: Dale Even, PE Lunda Construction Company Jason Block ...

Span 14 Erection

Page 89: Dale Even, PE Lunda Construction Company Jason Block ...

Span 14 Erection

Page 90: Dale Even, PE Lunda Construction Company Jason Block ...

Segment Construction Update

Completed Erecting October 5th, 2016• 2015 – 282 segments erected• 2016 – 710 segments erected

Page 91: Dale Even, PE Lunda Construction Company Jason Block ...

Questions