DAKSHIN HARYANA BIJLI VITRAN NIGAM SALES INSTRUCTION No. 42/2006 From GM/Commercial, DHBVN. Hisar. To All CEs (OP)/SEs (OP)/Xens/SDOs/OP., JEs-I, Incharge in DHBVN. Memo No. Ch- 42 /SE/Comml/R-17/48/2006 Dated:- 17.7.2006 Subject:- HERC regulations on duty to supply electricity on request— Self execution of works. Para 3 & 4 of Haryana Electricity Regulatory Commission Regulation No.HERC/12/05 dated 26.7.2005 (copy enclosed as Annexure-I) provides the detailed method on “Duty to Supply Electricity on Request” for the Distribution Licensee. Under the said Regulation the consumer may opt either for self execution of work or for carrying out the work through the licensee on paying of expenditure where the supply of electricity requires extension of distribution system. The consumer may opt any one of the alternatives. The Nigam has decided that for self execution of the work the following guide-lines will be followed:- GUIDE LINES WHERE EXTENTION OF LINE/DISTRIBUTION SYSTEM IS REQUIRED:- i) The consumer applies as usual. ii) On receipt of written application from the consumer, the SDO will visit the site, prepare the detailed estimate as per formula prescribed by HERC which is attached along-with. (Annexure-A). iii) SDO shall send the estimate and detailed list of various items of material to the consumer and ask for his option – whether he would like to do the work himself or get it done through DHBVN/Licensee. iv) If consumer opts for self execution, then he shall be given written permission to proceed along-with copy of estimate and list of items and specifications. SDO will ask the consumer for submitting an undertaking also to the effect that:- a. He will arrange the required material as per Nigam specifications. b. He will get the work executed through licensed contractor. c. He will bear the supervision charges @ 1.5% of the estimated cost. d. He will deposit the requisite charges for clearance from the Chief Electrical Inspector to Government of Haryana. v) The applicant will provide all items of material required for execution of works as per Nigam’s specifications. The Nigam specifications can be down loaded from the Nigam Web site (www.dhbvn.com ) or from the O/O SE/Operation concerned). The list of latest suppliers of the Nigam
15
Embed
DAKSHIN HARYANA BIJLI VITRAN · PDF fileDAKSHIN HARYANA BIJLI VITRAN NIGAM ... M/s Vijai Electricals Ltd. 6-3-648/1 & 2, ... Somajiguda, Hyderabad. 2. M/s Nucon Power Control Pvt.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
DAKSHIN HARYANA BIJLI VITRAN NIGAM
SALES INSTRUCTION No. 42/2006 From GM/Commercial, DHBVN. Hisar. To
All CEs (OP)/SEs (OP)/Xens/SDOs/OP., JEs-I, Incharge in DHBVN. Memo No. Ch- 42 /SE/Comml/R-17/48/2006 Dated:- 17.7.2006
Subject:- HERC regulations on duty to supply electricity on request—Self execution of works.
Para 3 & 4 of Haryana Electricity Regulatory Commission
Regulation No.HERC/12/05 dated 26.7.2005 (copy enclosed as Annexure-I)
provides the detailed method on “Duty to Supply Electricity on Request” for the
Distribution Licensee. Under the said Regulation the consumer may opt either
for self execution of work or for carrying out the work through the licensee on
paying of expenditure where the supply of electricity requires extension of
distribution system. The consumer may opt any one of the alternatives.
The Nigam has decided that for self execution of the work the
following guide-lines will be followed:-
GUIDE LINES WHERE EXTENTION OF LINE/DISTRIBUTION SYSTEM IS REQUIRED:-
i) The consumer applies as usual.
ii) On receipt of written application from the consumer, the SDO will visit
the site, prepare the detailed estimate as per formula prescribed by
HERC which is attached along-with. (Annexure-A).
iii) SDO shall send the estimate and detailed list of various items of
material to the consumer and ask for his option – whether he would
like to do the work himself or get it done through DHBVN/Licensee.
iv) If consumer opts for self execution, then he shall be given written
permission to proceed along-with copy of estimate and list of items and
specifications. SDO will ask the consumer for submitting an
undertaking also to the effect that:-
a. He will arrange the required material as per Nigam specifications.
b. He will get the work executed through licensed contractor.
c. He will bear the supervision charges @ 1.5% of the estimated cost.
d. He will deposit the requisite charges for clearance from the Chief
Electrical Inspector to Government of Haryana.
v) The applicant will provide all items of material required for execution of
works as per Nigam’s specifications. The Nigam specifications can be
down loaded from the Nigam Web site (www.dhbvn.com) or from the
O/O SE/Operation concerned). The list of latest suppliers of the Nigam
of major items is attached as Annexure-II. The detail of PO’s is also
available at the web site.
vi) The material so arranged by the applicant shall be inspected by the
SDO M&P wing, who will record a certificate to the effect that the
material conforms to the Nigam specifications.
vii) The consumer may be advised to take the list of approved contractors
of the District from the office of CEI/representative of CEI.
viii) The work will be got executed with the inspected material through Ist
class licensed contractor by the consumer himself.
ix) The completed work shall be inspected by the Xen/SDO M&P who will
also certify the quality of material used and execution of work as per
Nigam specification. The copy of the certificate issued by M&P shall
be handed over to the consumer and a copy shall be sent to SDO
concerned for placing in the consumer case file.
x) The applicant will deposit supervision charges @ 1.5% of the
estimated cost.
xi) The inspection of material before execution of the work and after
execution of the work shall be carried out by Xen.(OP) concerned if the
cost of the work is less than Rs. 50,000/-.
xii) On execution of work, consumer shall deposit the inspection charges
of CEI in the bank and inform the SDO in writing who in turn shall issue
the service connection order within 15 days from the date of receipt of
intimation from the consumer and connection will be released within
next 30 days.
xiii) The consumer opting for the self execution of work shall be exempted
from levy of development charges.
xiv) These instructions shall be applicable for all categories of consumers
including AP tubewell connections.
Additional guide lines for AP consumers. The AP consumer who opts for self execution of the work will have to
follow the additional guide-lines as under:-
i. The A.P. consumers who have already deposited the money under
Sales Circular No.D/80/2001, but have not been given connection so
far, are also eligible for self execution of work.
ii. In case the consumer opts for self execution of the work, the non
refundable amount of Rs.7000/- per span of HT/LT line shall be
refunded on receipt of option.
iii. Over riding priority shall be given for releasing connection in
chronological order on the basis of date and time of option received. A
separate seniority list shall be maintained for such connections.
iv. A.P. tubewell connection shall be released on 11 KV only as per
instructions issued vide Sales circular No.D-42/2005.
v. All procedures prescribed above shall also be followed.
vi. After energization of the new electrical system, this will become the
property of the Nigam and an undertaking in this regard shall be taken
from the consumer.
vii. Upkeep and maintenance of the system beyond warranty period e.g.
replacement of damaged D.T. after two years, shall be carried out by
the Nigam.
The above instructions may be brought to the notice of all concerned
for meticulous and careful compliance.
DA/As above -sd-
SE / Commercial For G.M/Commercial, D.H.B.V.N., Hisar
DAKSHIN HARYANA BIJLI VITRAN NIGAM ANNEXURE - II
List of empanelled Suppliers for Distribution Transformers. Sr. No. Name and address of firm 1. M/s Vijai Electricals Ltd. 6-3-648/1 & 2, Off Raj Bhawan Raod. Somajiguda, Hyderabad. 2. M/s Nucon Power Control Pvt. Ltd., D-46, Phase –V , Focal Point, Ludhina. 3. M/s Jay Bee Industries, 7A/3, Friends Colony (west), New Delhi. 4. M/s Akal Electricals Pvt. Ltd., 2657, Gurudev Nagar, Ludhiana 5. M/s Maha Shakti Conductors Pvt. Ltd., a-8 , New Focal point, Dabwali Road, Bathinda. 6. M/s P.P. Industries, C-5 , New Focal Point, Dabwli Road, Bathinda 7. M/s Sangrur Industrial Corp. Ltd., Sangrur 8. M/s Punjab Transformers & Electronics Ltd. , Sangrur 9. M/s Shiv Shakti Electricals, G.T.Road, Nangal Bhoor, The Pathankot, Distt. Gurdaspur. 10. M/s J.R. Industries Focal Point, (New) , Dabwali Road, Bathinda 11. M/s Saraf Electricals (P) Ltd. , Bathinda Road, Rampuraphool
ACSR CONDUCTORS
1 M/s Dynamic Engineering F-260, Road No-13, Vishkarma Industrial Area Jaipur-302013