DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review
18

DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

Jan 11, 2016

Download

Documents

August George
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

DaISy – Datacast Information System

Group: SotanorsuCustomer: Digita Oy

7.4.2004

T-76.115 Final Demonstration and Review

Page 2: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

2

T-76.115 Final demonstrationT-76.115 Final demonstration

Agenda

Product presentation (5 min) Demonstration (15 min) Project evaluation (15 min) Questions and comments (5 min)

Page 3: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

3

T-76.115 Final demonstrationT-76.115 Final demonstration

DaISy – Datacast Information System

Future: DigiTVInternet (DVB-T)

• Upload pictures and movies

• Create slide shows

• Attach PDA content

• Manage displaying content based on location

• View location based slide shows and movies (e.g. advertisements)

• Browse internet and extra content using PDA

CoDSyDB

Bluetooth CoDSy

GPS

CoMSy DB

HTTP

WWW

CoMSy

Page 4: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

4

T-76.115 Final demonstrationT-76.115 Final demonstration

Product Demonstration

Page 5: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

5

T-76.115 Final demonstrationT-76.115 Final demonstration

Project Evaluation

Page 6: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

6

T-76.115 Final demonstrationT-76.115 Final demonstration

Team Sotanorsu

Aleksi Ahtiainen (AA) – Project management 2004, Quality Control, Documentation, Development

Jussi Koponen (JK) – Architecture, Development

Kirsi Louhisuo (KL) – Requirement engineering, Configuration management, Development

Simo Neuvonen (SN) – Project management 2003, Infrastructure, Development

Esa Puttonen (EP) – User Interface, Development

Eiri Valanto (EVa) – Risk management, Development

Essi Vehmersalo (EVe) – Testing, Peer Testing, Development

Page 7: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

7

T-76.115 Final demonstrationT-76.115 Final demonstration

Project Progress [1/4]

In total: 1412 hours Documentation, meetings and project

management took 52% of total work Many hours of programming still in DE

phase (minor improvements and unexpected bugs)

0

50

100

150

200

250

300

350

PP I1 I2 I3 DE

Hours by worktype

Documentation

Testing

Programming

Design

Comp. Maintenance

Lectures

Studying

Proj.Management

Meetings

Meetings22 %

Design8 %

Programming26 %

Testing6 %

Documentation12 %

Comp. Maintenance

4 %

Studying3 %

Lectures1 %

Proj.Management18 %

Page 8: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

8

T-76.115 Final demonstrationT-76.115 Final demonstration

Project Progress [2/4]PP Iteration – Meetings and requirement

design Work practices documented Requirements specified and prioritized with the

customer Infrastructure built (TWiki collaboration

platform, mailing list, IRC channel) Problem: Bugs in Trapoli system -> Own hour

reporting practice using CVSI1 Iteration – Design and basic features Architecture designed 11 more requirements implemented and tested Problem: Bugzilla had no module division ->

Own bug reporting within Twiki Problem: Work hour estimates exceeded ->

Had to decrease hours from plans in following iterations

Problem: Some hardware was delayed -> Had to concentrate on other issues

0

10

20

30

40

50

60

AA EP EVa EVe JK KL SN

PP phase personal hours

PP planned

PP actual

0

10

20

30

40

50

60

AA EP EVa EVe JK KL SN

I1 phase personal hours

I1 planned

I1 actual

Page 9: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

9

T-76.115 Final demonstrationT-76.115 Final demonstration

Project Progress [3/4]I2 Iteration – Programming Lot of programming More focus on demonstrational use in meeting room

-> DVB-T internet in moving vehicle dropped 17 more requirements implemented and tested Problem: Work hours underrun -> Had to increase

work share for some members in I3 and DE Problem: Unit testing not working as planned -> Did

code review and increased weight of system testing Problem: GPS module and DVB-T cards not

functioning -> Had to delay implementation Problem: Too heavy risk management practice ->

specified a lighter oneI3 Iteration – Concentrating on requirements for

final configuration 26 more requirements implemented and tested Group and customer thought more about final

demonstrational use: some new requirements specified and implemented for

easier demonstrational use visualization of moving vehicle (GPS) -> demo

preparation took time had to drop specification of large system issues

0

10

20

30

40

50

60

70

AA EP EVa EVe JK KL SN

I2 phase personal hours

I2 planned

I2 actual

0

10

20

30

40

50

60

70

AA EP EVa EVe JK KL SN

I3 phase personal hours

I3 planned

I3 actual

Page 10: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

10

T-76.115 Final demonstrationT-76.115 Final demonstration

Project Progress [4/4]

DE Iteration – Finalization 6 more requirements implemented and tested Attainment of goals and project practices

analyzed with the customer and within the Sotanorsu team

Problem: Contract not signed, decided on postponing physical delivery to after easter -> easier to run final demonstrations. Customer has been able to test system through internet

Problem: More bugs found than expected, major problem in exception situation handling as well -> Some minor and trivial bug fixes after the preplanned final code freeze on Sun 28th March, major bugs well documented. The system was retested after these.

0

10

20

30

40

50

60

70

AA EP EVa EVe JK KL SN

DE phase personal hours

DE planned

DE actual

Page 11: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

11

T-76.115 Final demonstrationT-76.115 Final demonstration

Goal attainment Out of the original 10 customer goals:

4 were reached: Using GPS information WWW interface for management Scalable architecture Easily extendable (some refactoring needed, though)

4 were dropped in I2: Use of DVB-T internet Well adapted for DVB-T internet use External internet connection on PDA Automatic content transfer (user triggered now in demonstration

environment) 2 low priority goals were not reached:

The system is not error-prone and can recover from errors The system is secure

Page 12: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

12

T-76.115 Final demonstrationT-76.115 Final demonstration

Work share between team members

Project management: AA and SN managers, EVa and KL created demonstration content

Design: JK responsible for architecture design Programming: EP and JK did the most Documentation: AA did most of the project plan and reports, KL responsible for user

guide and requirements document AA: Did plenty of implementation work during the fall 2003, not as many hours left for

project management in the spring. Spent a lot of time managing the techinical aspects of the project in addition to secretarial management.

0

50

100

150

200

250

300

AA EP EVa EVe JK KL SN

Worktype share of team members

Documentation

Testing

Programming

Design

Comp. Mgmt

Lectures

Studying

Project mgmt

Meetings

Page 13: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

13

T-76.115 Final demonstrationT-76.115 Final demonstration

Software size

Total: 103 requirements, of which 60 implemented

Line count is not very good estimation method, but:

Total: 9100 NCLOC, 4900 COM Would have been average size

on 2002-2003 course Well commented (1/3 of lines

in comments)

0

10

20

30

40

50

60

PP I1 I2 I3 DE

Number of requirements across iterations

High priority reqs

Implemented High priority reqs

Medium priority reqs

Implemented medium priority reqs

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

PP I1 I2 I3 DE

Software size in lines of code

SQL code lines

JSP code lines

Java code lines

Page 14: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

14

T-76.115 Final demonstrationT-76.115 Final demonstration

Quality assuranceRequirements and testcases

0

20

40

60

80

100

120

PP I1 I2 I3 DE

Implemented requirements

Testcases

0

10

20

30

40

50

60

70

PP I1 I2 I3 DE

Cumulative number of found bugs by severity

Blocker

Critical

Major

Minor

Trivial

0

5

10

15

20

25

30

Trivial Minor Major Critical Blocker

Total bugs by severity

Open

Closed

In addition: 182 code review issues, of which 156 fixed

remaining ones are related to bug below and also some non-prioritized unit test class issues

1 major bug remains in exception situation handling

Wasn’t noticed well enough until DE iteration code review. This second code review should have been done in I3 instead.

Not a problem in proof-of-concept demonstration environment

Page 15: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

15

T-76.115 Final demonstrationT-76.115 Final demonstration

Evaluation of used practices Good at all other process related

issues instead of risk management Most critical about implementation

related practices. Speculation: Built-in perfectionism in every

technology-oriented computer science student?

Easy for coders to think that it is their fault, that even one bug remains in the software, although that might have originally been caused by some trouble in the process

Our use of practice

0,00 1,00 2,00 3,00 4,00 5,00

Unit testing

User interface planning

Risk management

Static methods

Assessment of architecture

Architectural planning

Bug management

Refactoring

System testing

Coding convention

Communication within the group

Use cases

Communication with the mentor

Meeting practices

Requirements prioritization

Team organization

Hour reporting

Project reviews

Scheduling

Requirement management

Communication with the customer

Version control

Iteration planning

Iterative development process

Documentation

Page 16: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

16

T-76.115 Final demonstrationT-76.115 Final demonstration

Evaluation of used tools Good tools to keep in mind in the future:

CVS TWiki collaboration platform

Not so fun tools to work with: WWW user interface, but I guess in our place and time we just have to live with it…

Page 17: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

17

T-76.115 Final demonstrationT-76.115 Final demonstration

Lessons learned Great introduction to iterative software development process It was very helpful to plan the work practices in the beginning of the project instead of just starting

to write code Good experience in making work estimates It takes a lot of work to both lead the people and manage the technical issues of the project in this

course’s setting

If only... If final code review had been done already in I3, no major problems would remain in the software The user interface and especially it’s architectural connection to the software should have been

planned better A person with more visual skills and enthusiasim would probably have gotten our final product

prettier Maybe a clearly a separate person being responsible for leading and managing technical details

would have made the process more efficient and taken some of the stress out of the project manager

A separate server at the customer premises would have made it possible for the customer to test software on site instead of over the network

Course feedback Couple surprise mentor visits per iteration to the team meetings, customer meetings and computer

classrooms might give mentors better inside information in the process. Progress reports and reviews are only the showcase

Arranging 4 demonstrations of the software, when it is not totally physically movable, takes a lot of effort. Maybe demonstrations at the actual production or development environment?

The calendar time of 7 months is long for this process and makes it very difficult and also more unrealistic to control. Maybe the course could be done in a single spring term?

Page 18: DaISy – Datacast Information System Group: Sotanorsu Customer: Digita Oy 7.4.2004 T-76.115 Final Demonstration and Review.

Thank you for listening!

Questions?Answers?