METHOD STATEMENT
Urban infrastructure Construction for THT Newtown Project Method
Statement
For Technical Trench DAEWOOP1-MS-TT-A1-EN
CONTENTS1. General
---------- 22. Scope of Work
---------- 23. Construction Schedule ---------- 2
4. Site Organization Chart
---------- 25. Material
---------- 36. Equipment and Tools
---------- 37. Construction Procedure
---------- 48. Quality Control
---------- 129. Safety Control
---------- 1410. Environmental Control
---------- 14APPENDIXAppendix - Technical Trench - Construction
shop drawing (File Attached)1. GeneralThis Method Statement is to
describe the work procedures for the construction of Technical
Trench. This work item shall be done in accordance with the
contract and Chapter 16 of the Specifications. 2. Scope of work
This method statement shall apply to Technical Trench work
activities in construction of Urban infrastructure Construction for
THT Newtown Project are as follows:Technical
TrenchNoFunctionDimensionLength (m)Remark
BxH (m)Phase I (m)
1Technical Trench Type 10.8 x 1.41422
2Technical Trench Type 20.8 x 1.65143
The above quantities are only for reference. The design quantity
will be made from approved shop drawings. The actual construction
quantity will be shown on As-built Drawing.
3. Construction ScheduleConstruction Schedule shall be referred
to Latest Overall Schedule. In addition, Technical Trench work
shall be indicated and updated in monthly and weekly schedule. For
each location, Detail Schedule shall be submitted together with
working drawing.4. Site Organization ChartSite Organization Chart
shall be referred to final approved The Site Organization Chart and
Emergency Communication Flowchart.5. MaterialList of required
material for construction is shown below:
When stored at site, materials such as rebar and Angle must be
kept off the ground and shall be covered by vinyl sheet. Other
materials used for backfilling shall be timely transported to the
site.Nominal diameter and permissible deviation are specified in
table below:
No.Internal diameterSpecified thickness
BxH (mm)Permissible deviation (mm)Specified thickness
(mm)Permissible deviation (mm)
1800x140010150+5
2800x165010150+5
6. Equipment and ToolsList of required equipment and tools for
construction is shown below:
7. Construction ProcedureWork Sequence for Technical Trench
SHAPE \* MERGEFORMAT
All Material shall be divided into several segments (as
indicated on approved shop drawing) and each segment shall be
constructed one by one. The description of each segment work item
is shown as follows:7.1 Preparatory Works
Construction of Technical Trench shall be commenced after shop
drawing, method statement and working drawing have been approved
from the Engineer.
Confirmation of approval for working drawings and preparation of
working area shall be carried out before execution of work. Survey
line marking and layout for Technical Trench shall be established.
Mobilize all necessary materials and equipment before execution of
work.Survey works has been carried out follow the benchmark, that
was approved by Engineer. 7.2 Excavation, Trimming Works, Lean
Concrete a) Excavation and trimming works shall be carried out
based on approved Working Drawing. After excavation must be
inspected by the Engineer, and the Excavation shall be cleaned and
ensure safety and protect the slope.
Before carring out excavation work, Contractor must make sure
cleaning for site. Excavation work: Construction and acceptance
follow TCVN 4447-2012: Earth works Construction, check and
acceptance.b)Survey marking shall be established prior for placing
and casting lean concrete for foundation of Technical Trench and
Manhole. Lean concrete shall be placed and casted as indicated in
the Approved Shop Drawings. Mix Trucks tank must be rotated during
transportation and concrete slump and temprature shall be checked
at site prior to concreting. Placing concrete shall be carried out
either by direct pouring, using excavator or crane and concrete
bucket.7.3 Installation of Reinforcement Bara) Survey marking
layout shall be carried out prior to rebar and formwork
installation for concrete base.b) Rebar used for structures shall
be in accordance with Specification of the Project and approved by
the Engineer. Rebar manufacturing and testing follow TCVN
1651-2:2008 Steel for the reinforcement of concrete Part 2: Ribbed
bars.c) Rebar, before and after fabrication, shall not be placed
directly to the ground but firmly chocked and covered by nylon
canvas to minimize all the external effects.d) Rebar shall be
fabricated by cutting and bending machine at fabrication yard and
shall be transported to construction site.
e) Rebars shall be installed and fixed with wires in workmanship
manner based on Approved Shop Drawings. Rebar protection thickness
shall be ensured by installation of pre-cast concrete spacer and
follow Specification and Shop drawing.f) Starting rebars for next
segment shall be installed and carefully protected from
corrosion.g) After installation, rebar must be inspected by the
Engineer. 7.4 Installation of Formwork7.4.1) Formwork shall include
all temporary mould for forming the concrete. Falsework shall
include all temporary constructions required such moulds, the
weight of the concrete and all other applied loads.
7.4.2) Falsework shall be capable of with standing temperature
changes without causing damage to the concrete.7.4.3) Falsework and
centering shall be designed and construced to provide the necessary
rigidity to support all loads placed upon it without undue
settlement or deformation. 7.4.4) Falsework columns shall be
supported on bases not on any part of the structure, except the
permanent foundations.7.4.5) The forms shall conform to the shape
and dimension of the structures shown in the issued for
construction drawings and will be tight at joints in order to
prevent leakage of cement paste.7.4.6) Form support and bracings
shall be installed and properly fixed. Formwork and supporting
system shall be ensured so that formwork is even without distortion
and deformation during concreting.
7.4.7) Installed formwork shall even and tighten to avoid water
leakage during concreting which may influence the quality and
appearance of the structure. So that the gaps on form joint shall
be treated and filled by cleat.7.4.8) Prior to concrete, entire
surface of formwork shall be oily coated for easy dismantling in
the next stage.7.4.9) Scaffolding, temporary staging and access
ladders will be provided whenever necessary in order to access and
egress work areas. And its shall be installed prior to install
rebar and formwork.7.4.10) After installation, form alignment shall
be carefully checked by survey works.7.4.11) Openings for the
inspection and cleaning of the inside of formwork shall be
formedand constructed so that they can be conveniently closed and
properly sealed before placing of concrete.7.4.12) The work of
striking (dismantling) the formwork will only be carried out undern
the personal supervision of a competent foreman.
7.4.13) Formworks shall be removed after the concrete has
achieved 80% of the designed concrete strength.
7.4.14) After removal of the formwork, all fins and projecting
edges shall be cleaned from the concrete faces, which are to be
exposed in the permanent works.7.4.15) Construction joint shall be
chipped by steel brush and water to ensure loose concrete shall be
removed until sound aggregate is exposed. 7.4.16) Curing procedures
shall be initiated immediately after removal of formwork and
completion of finishing work.7.5 Casting Concrete.
7.5.1) Prior to casting concrete, the below items shall be
strictly followed:- Concrete casting by handle by manpowers.
Plastic hose shall be provided and attached on the tip of mobile
pump pipe to avoid the concrete segregation during casting.-
Cleaning inside the form and water shall be sprayed on construction
joint.
- Resources of materials shall be checked such as supply of
concrete and equipments.
- Concrete casting equipment shall be set-up and check its
condition before casting concrete. -Placing of concrete shall not
be commenced until the engineer has inspected and passed the
formwork or other area to receive concrete and any reinforcement,
cast in fixings etc., against which the concrete is to be
placed.-When all elements and procedures meet the requirements,
concrete is then ordered.-Concrete shall be mixed at plant and
shall be transported to site by concrete mixer trucks. Mixer Trucks
tank must be rotated during transportation so that concrete shall
not be segregated.
-When concrete arrives at site, immediately a quality control
inspection such as grade, slump, temperature, time of batch, and
time of arrival at site will be done, before placing is done to
ensure that it is as per the specifications.- Pouring guide level
shall be established for finishing. Pouring guide level shall be
placed at the centerline transversely and a maximum distance of 2
meter longitudinally.7.5.2) During casting, the below items shall
be strictly followed- Vibrators shall be used in workmanship manner
in order to consolidate and compact the concrete properly. Vibrator
shall be applied to area of concreting on a vertical position at 5
to10 sec at one place.
-The vibrator will be inserted systematically in a regular grid
with spacing of insertion points depending on mix characteristics
equipment. The grid spacing will be selected to ensure adequate
compaction of all parts ofthe concrete, without over-compacting it.
The spacing of insertion ofr normal area is n x d ( n=10,
d=diameter of vibrator head)
- The poker vibrator would not be inserted closer to the form
side than 3 times its diameter, and it must not be inserted in the
cover layer (between the reinforcement and the form) The vibrator
will be immersed vertically in its full length and through the
entire thickness of the concrete layer. A sloped immersion will be
madeonly if the thickness of concrete is less than the length of
the vibrator.
- Regularly check the verticality of forms and necessary
adjustment shall be made immediately if displacement or movement on
forms is found.
- Discharging concrete shall be done layer by layer with a
maximum I = (0.6 ~ 0.8) x S.
-The layer thickness would not be less than 0.5 x S to protect
the vibrator.
Prior to casting of the next lift, the previously cast concrete
top surface must be covered with a pure cement mortar layer. -
Concrete supply shall be closely monitored to avoid cold joint.
- Tightness of the formworks shall be inspected regularly by the
pouring guards to make sure that there is no deformation or
displacement of forms and rebar and leaks at the formworks. During
concreting, formworks and supporting system shall be always
supervised to prevent problems if any. If displacements occur,
immediate adjustment shall be done to reposition the forms or rebar
before concrete placing continues.
7.5.3) Finishing. -Finishing on concrete surfaces will be done
as per specified on the drawings.
-Appropriate tools and equipment such as straight edge brush,
timber float, steeltrowel will be used at site to achieve proper
finish.
After the water sheen has disappeared, the surface will be
floated with a finishing machine using vinyl sheet. Trowel is to be
done twice as minimum to avoid early shrinkage on the top of
concrete. The water spray should be used during finishing
operations and curing shall be started as soon as the surface of
the fresh concrete is sufficiently hard to permit it without
damage.7.6 Concrete Curing and Treatment of Construction Joint
7.6.1) Curing shall be done after concrete surface start dry.
Concrete surface shall be covered by wet burlap or vinyl sheets.
These burlaps or vinyl sheets shall be kept moisture during curing
period. Curing shall be at least 7 days from finishing
concrete.
.
7.6.2) Formwork removal can only be done at least 1 day after
completion of concrete casting for vertical structure. After remove
forms, concrete shall be covered by vinyl sheet for curing. 7.6.3)
Construction joint shall be chipped by steel brush and water to
ensure loose concrete shall be removed until sound aggregate is
exposed.
7.7 Backfilling and Compaction 7.7.1 Backfilling and compaction
shall be carry out layer by layer with material approved by the
Engineer. 7.7.2) Each layer of backfilling shall be compacted until
density of not less than requirements of that determined by TCVN
9436:2012 Highway embankments and cuttings Construction and quality
control.7.7.3) Material placing and compacting
- The embanking/backfilling materials shall be black sand. The
material shall be in accordance with TCVN 9436-2012.
Before making use of material the Contractor shall submit test
results as required by the Engineer approval, showing exact
locations and hauling distances of embanking/backfilling.-
Embankment materials shall be placed continuously and horizontally
with a thickness not exceeding thirty (30) cm before compaction.
Compaction shall be done for each stratum in line with the
conditions stated herein or as instructed by the Engineer.-
Reference standards:
No.SpecificationsDescription
1TCVN 9436 : 2012Emankment work. Construction procedures and
inspection.
222TCN 346-06Field density test sand cone replacement method
322TCN 333-06Max density of materials in laboratory
422TCN 332-06Determinate CBR index in laboratory
7.8) Cleaning Up SiteAll excess materials and rubbish shall be
removed and disposed leaving the site neat, tidy and acceptable to
the Engineer. 7.9) In Case of Emergency7.9.1) If it is necessary to
stop placing concrete before a casting is completed, make the
surface flat until the last available batch of concrete, and make
proper construction joint. In case of rainfall, pooling water shall
be removed from concrete surface before making the surface
flat.
7.9.2) Extra specimens for concrete compression test shall be
taken from emergency stopped concreting area in order to confirm
the strength of concrete at the corresponding section.
7.9.3) In case of rainfall, all areas of concreting shall be
covered by plastic vinyl sheet.7.9.4) If casting equipment
breakdown, a standby casting equipment shall be utilized for
concrete casting. Casting concrete shall follow the direction
initially poured.8. Quality ControlThe whole procedure shall be
thoroughly checked by the Engineer in charge for operation. Quality
control shall be carried out in accordance with this Method
Statement and other applicable specifications. Inspection and Test
Plan and Inspection Checklist are attached as Appendix 2.
Inspection and Test Plan and Inspection Checklist are subject to
revision in accordance with the instruction by the Engineer.8.1)
Tolerance for Concrete Structures The temperature and slump of
concrete shall control quality as below table:
ItemsTemperatureSlump
Lean concrete 32C52.5 cm
Concrete Grade C1 32C102.5cm
8.2) Tolerance for Concrete Structures
Tolerance for concrete structure is shown as below table:
8.3) Testing frequency of materials for concrete shall be
complied with chapter 10 of Specifications.8.4) Necessary tools
shall be used such as level bar for controlling the elevation of
concrete top surface during casting concrete. 8.5) Sampling of
concrete for compressive strength test shall be in accordance with
Inspection and Test Plan. 8.6) Slump test and temperature check
shall be done on each concrete mixer truck delivered to site. The
slump tests shall be carried out in accordance with TCVN 4453:1995
Monlithic concrete and reinforced concrete structures Codes for
construction. Check and acceptance.9. Safety Control Safety control
shall conform to Approved -HSE PROGRAM and that method shall be
part of this Method Statement. Prior to start the construction
work, the following particular matters are to be through to all
members working in the construction site in order to complete the
Drainage System and construction efficiently without any accident
or casualty.
The Contractor proposed an adequate measures to ensure safety,
security and environment during construction process in accordance
with Decision 55/2009/QD-UBND date 17/03/2009 on Establishing
Regulation for Security, Safety and Eviromental Sanitation during
Construction works in Ha Noi City.9.1) Joint MeetingPrior to start
any activity, a joint meeting with relevant staffs shall be held
for the purpose of general explanation on the whole contents of
works as well as the method for the implementation of efficient
work in accordance with this Method Statement.
9.2) Instruction All workers shall wear Personal Protective
Equipment (PPE) at all times, such as hardhat (helmet), safety
shoes and working uniform.9.3) Prevention of Accident by Heavy
MachineOnly skilled operator shall be allowed to operate equipment
on site. In case of new operators, a test of skill shall be
conducted first prior to his acceptance to the job. Preventive
maintenance check shall be done regularly at equipment working at
site prior to full operation. Stability of working area and
foundation of equipment shall be checked particularly at locations
of outrigger and track pad of cranes.9.4) Prevention of Accident of
the Falling Object
During handling of materials and equipment, it shall be tied up
properly to prevent from falling. Lifting wire ropes shall have
designed capacity for heavy lifting. Lifting wire of lifting
equipment such as crane shall be carefully checked.9.5) Prevention
of Accident of ElectrocutionElectric generating equipment shall be
properly protected and properly installed with earth connection.
Electric wires shall be connected with electrical tapes to prevent
electric leakage. Only skilled operator shall be allowed to operate
equipment on site.
9.6) Prevention of Accident in Night Shift Works
Sufficient quantity of lighting system shall be provided for
night shift works especially installed at working platforms. If
necessary all of the surrounding working area shall be lighted
up.9.7) Existing FacilitiesExisting facilities especially existing
overhead electric line, water line, telecommunication line and
other important facilities at surrounding area shall be taken with
care not to damage. 9.8) Working platform
Working platform and access ladder shall be provided for work
efficiency and safety as well.10. Environmental Control
Environmental control shall conform to the approved - HSE PROGRAM.
That Method Statement and shall be part of this method statement.
Responsibility for surrounding environment during construction work
and shall comply with the Condition of Contract and Vietnams
National Law on Protection of Environment and other relevant
legislation such as: Decision 55/2009/QD-UBND date 17/03/2009 on
Establishing Regulation for Security, Safety and Eviromental
Sanitation during Construction works in Ha Noi City.If any other
problems occurred in the site, applicable counter measures or
prevention action shall be considered immediately and executed as
soon as possible.
APPENDIX Technical Trench - Construction Shop drawing title(File
attached) EMBED Excel.Sheet.8
EMBED Excel.Sheet.8
Backfill and Cleaning up Site
Survey
(Location & Line marking)
Form Removal and Site Cleaning
Casting conerete Wall and Top Slab
Install Top Slab
Rebar and Form Assembly
(wall)
Install Cable Support & Grounding
Cast in Bottom Slab
Cast in lean concrete
Rebar and Form Assembly
(Bottom slab)
Survey
(Alignment + Level)
Excavation Work
PAGE Revision A1, 15th April, 2010page 1
_1384235592.dwg
_1468648696.xlsSheet1
No.Material forDescriptionDetailQuantityRemarks
Blinding Stone
?1BackfillExcavated Soil /SandConform to Chapter 7varies
?2Lean ConcreteClass E - Unreinforced Conc.
?3ConcreteClass C1Strength - M200 - Conform to Chapter 10
?4Reinforcing Steel barGrade 300, Grade 400Conform to Chapter
11
?5Angle Steel 80x80x7L80x80x7
_1468817273.xlsSheet1
No.NameDescriptionUse forRemarks
ExcavationBackfillingBox CulvertBlinding StoneConcreting
?1Excavator0.70 m306 ea
?2Dump Truck15 m306 ea
?3Bulldozer16 ton03 ea
?4Mini Compactor1 ton12 eaincl. Base compaction
?5Submersible Water Pump4 inches06 eaDewatering
?6Diesel Generator50 KVA03 eaLighting for nightwork
?7Lighting System03 lotNightwork
?8Survey Equipment03 ea
?9Minor Tools06 lotincl. Joint sealing
?10Concrete VibratorDia.(25~60mm)06 eaincl. spare
?11Formwork06 lotSteel form panel
?12Bending Machine03 ea
?13Cutting Machine03 ea