DDWhat will it take to get data out of the
CFT?*
Don LincolnCFT Commissioning Czar
Fermilab
Run II MeetingMay 12, Y2K
* that’s John’s title, not mine........
D. Lincoln Run II MTG May 12, Y2K
DD What will it take to get data out of the CFT?
Work
Lots and Lots of Work
D. Lincoln Run II MTG May 12, Y2K
DD Central Fiber Tracker Status
8 layers Outer 6
2.52 m Inner 2
1.66 m r - .2 to .51 m Axial readout to
south VLPC Readout Waveguide system
8-11.5 m “Pipes” light from
detector to VLPCs
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Done Stuff
Fiber Ribbons (roughly 400 ribbons)
VLPC Characterization 17,000 chips tested, 15,500 OK
VLPC Recovery 2,200 tested, 1,100 recovered So total useful chips 16,600
D. Lincoln Run II MTG May 12, Y2K
DD
(r)measured - (r)predicted
Cylinder 4 axial, r (incl. correct.) and res. slopes
0100200300400500600
-0.01 -0.005 0 0.005 0.01 0.015 0.02
MeanRMS
0.4723E-04 0.1188E-02
Constant 501.8Mean 0.5674E-04Sigma 0.1149E-02
inch
d(r)/dz correction0
0.250.5
0.751
1.251.5
1.752
2.252.5
-10 -8 -6 -4 -2 0 2 4 6 8 10mil/100in
RM 1=RM 1.5=RM 2=
2.02367 mil2.23837 mil2.4196 mil
CFT Status - Ribbon Mounting
30 m rms
50 m e-e offset
Going Very Well - To Spec
Last cylinder (1) getting stereo ribbons attached now
Project Tomorrow completion
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Nesting
Cylinders 8,7,6,5,4 & 3 nested
CFT Completion - 5/19/00Delivered to DAB by
6/15/00
Global precision 15 m (Measured vs Desired)
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Waveguides
Waveguide Production CPS complete (IU) Fiber pulling/sheathing at ND
75% complete for CFT Fiber sorted
– Best (attn.L from Kuraray) - longest runs [8-11.5m]
FPS at IU CFT WG Connectorization
At ND + Fermilab + IU 50 with curved end connectors
Expect to complete production in August (100+ July 15)
CFT Hookup and commissioning complete by 9/1/00
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Readout System
VLPC Characterization/test/sort now complete
Cassette Assignment
As shown (includes cassettes 1-10)
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Readout System II
Cassette production Approximately 50%
of sub-component complete
All components in-house except Flex circuit
Flex Circuit Production deliveries
starting 600 of 2000 in hand 100/week
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Readout III
Cassette Test - Going Well
Noise low (Stereo Board) Good uniformity
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Cryo
Fabrication delayed by delivery of top plates
Now in house To spec
Making up some time
Welding going well
Final Cryo Operational in June
D. Lincoln Run II MTG May 12, Y2K
DD CFT Status - Conclusions
CFT construction is going well Mechanical assembly is to specification Complete in mid-May
VLPC + Cryo VLPC characterization/selection complete 1024 channel cassettes working well Cassette production assembly underway
Subcomponents 50% complete First 10 (11?) production cassettes assembled All cassettes leaving factory have met specifications
CFT wave guide production Fiber pulling/sheathing going well (far along) Connectorization underway
D. Lincoln Run II MTG May 12, Y2K
DD Major Installation Activities During Next 3 Months
April May June July
Install/align CFT
Platform moves: pick
up EF north/south
Install VLPC cryostats in
platform
Collision Wall down – Hi Bay full
Rework EF shielding pieces
End detectors installed (FPS, ICD, L0)
Install N/S A-layer MDTs
Install both
EF shields
Install gas/cooling lines in Collision Hall
Rework/reassemble
shielding mid-pieces
Collision Wall back up
Install CFT cable ductwork in platform
Collision Wall down
Stage/survey N/S shielding
Solenoid Test
Install N/S A-layer pixels
Install EMC-S MDTs and pixels • Crane needed
• Platform occupied• ICR occupied• CF closed; no cal preamp access
survey
survey
survey
survey
survey
survey
survey
Survey east PDTssurvey
Install South truss in Hi Bay, re-weld arms
Forward Muon Installation
Disassemble EMC-S for
move to sidewalk
to July 15
D. Lincoln Run II MTG May 12, Y2K
DD DO TimelineVersion N
2000 2001 J F M A M J J A S O N D J F M
D
Install silicon front-end
CFT install/hookup
1/2 VLPCs installed
1st CFT crate operational
Waveguide production
All VLPCs installed
Cosmic Ray CommissioningPhase I: Central
muon, DAQ, RECO, trigger, silicon front-end
Phase II: Tracker
Commissioning (CFT, SMT, PS), VLPCs, Forward
Muon
Phase III: Full Cosmic
Ray Run (add CAL, full TRIG & SMT)
Run II begins:
Mar 1, 2001
Roll in detecto
r
Remove shield wall
Beam-ready
Install final CFT electronics
Platform moves
No Services
No Services
Install/hookup/checkout SMT
South half North half
ICDFPSLum (L0)
D. Lincoln Run II MTG May 12, Y2K
DD Commissioning Plan
CFT arrives DAB mid-June, install and survey (Gaston) Cryostat install and hookup through mid June, testing
cooldown followed by cassette insertion, end of June (Russ)
As waveguides hooked up (CPS, 8, 7, etc.), testing is needed
Current plan: 2 people/crew, 2 crews/shift, 2 shifts/day, 2 LG/crew/shift 8 lightguides/day. (300 CFT light guides 8 weeks)
Initial test, LED pulsers on the ribbons, secondary electrical.
Verify light continuity. Verify photoelectron noise consistent with temperature and
voltage Electrical noise.
D. Lincoln Run II MTG May 12, Y2K
DD Needed Components
CFT cylinders: In DAB mid-late June Cryostat: Operational late-June Cassettes: In DAB June/July (30-ish, 11 in hand now) LHe: Tested already, hiatus early July (end iron) Lightguides: In DAB June/July, all CPS, 100 CFT (7/8 S/A) Cables: In house (AFE sequencer VRB) DAQ: Running now Unpacking: SVX unpacking done, some mapping
remains. Examines: Available now, will need tweaking for commissioning Cosmics: Piggyback on muon trigger Tracking: Cosmic tracking mostly OK, minor technical fixes Event Display: Ready in some form
D. Lincoln Run II MTG May 12, Y2K
DD Front End Electronics:
AFE not available, use stereo board, limited availability LED Electronics:
Two components, small card (300-ish), large driver/control card (10-ish) Small cards available early June Large controller cards maybe available mid-August...Gack!
Sequencer VRB cable pull late July Silicon uses same cables, need splitter, not available Can pull the small number of CFT fiber optic cables first
CFT Online guru: CFT Calibration guru: Not yet filled Control/Download guru:
Needed Components
}
D. Lincoln Run II MTG May 12, Y2K
DD Summary
Much of the required components are in place for mid-July hookup/commissioning
Some aren’t
They will be